Views and Base unit of Measure is not coming in Chines Lang

HI All
Plz Help me.
I log-In Chines Server, during MM01 the views are coming in English language instead of chines.
and  during PO creation The Base unit of Measure is not Coming in Chines Language it is displaying Some number??
I have maintained Source and taget lag in CUnI..but still Im getting this problem..
How to solve this plz help..
Thanks and regards
Ramesh reddy

Hi
Please maintain the translation in the Following Configuration
Logistics - General->Material Master->Configuring the Material Master->Define Structure of Data Screens for Each Screen Sequence
Select the Specific Screen Sequence & Maintain the languages
Similarly please maintain the Translations in the Transaction CUNI for the Base UOM in respective languages
I hope currently in your system only Language EN is maintained
Thanks
Madhav

Similar Messages

  • Base unit of measure can not be changed since EAN is already assigned.

    Hi,
    We would like to change the UOM from EA to SET .In order to tag MM # as BOM Header and ZCEN (Serial number profile)but the error massage appears as below print screensystem is not allowing to do so ,throwing following error message:
    "Base unit of measure can not be changed since EAN is already assigned."
    Could you help to resolve the same.
    Thanks,
    Amit

    Hi,
    Thats correct you must be getting Error message M3 341 ,
    EAN international article number is tied with material number in basic data view with EAN Category and seperate number range
    EAN is a standardized unit that uniquely identifies a material relating to a unit of measure or type of packaging.
    The International Article Number (EAN) is assigned by the manufacturer of the material. In this case, the EAN identifies the
    manufacturer uniquely. A company can assign EANs using "in-store" numbering techniques known only to the company.
    If you still want to change UOM you need to first remove the EAN assigned..please explore further if you have internal number range
    for EAN or external ..etc
    Thanks
    Diwakar

  • How to maintain space between value and base unit of measure in sapscript

    Hi Guys,
    I am working on an upgradtion project, i have problem like while upgrading from 4.6b to 5.0. i need to main a space between value and base unit of measure. can anyone letme know how to maintain in the form. I mean in sapscript.
    Thanks,
    Yogesh

    There are a couple of ways to handle this,  if you need a bigger space between, you can use tabs in the paragraph format.  Or you can just write the space in between the fields like so.
    ZA  &MSEG-MENGE& &MSEG-MEINS&
    Regards,
    RIch Heilman

  • Material Master MATMAS IDOC and base unit of measurement

    Hi
    We are using SAP standard material master IDOC type MATMAS05 to trigger IDOC. Our material master is having base unit of measure as "G". We are not using ISO unit of measurement. But Material master IDOC, segment E1MARM is populating base unit of meaurement (MEINS) as "GRM".
    Any idea why IDOC is picking ISO unit of measurement instead of material master base unit of measurement.
    Any idea how to send base unit of measurememt as "G" instead of "GRM" in DOC segment.
    Thanks
    Nilesh

    There are ISO codes for country keys, currency keys, units of measure and shipping instructions. According to SAP design guidelines, you should use ISO codes for an IDoc if they are available. When you set up the IDoc, the SAP codes have to be replaced by ISO codes.
    http://help.sap.com/printdocu/core/Print46c/en/data/pdf/BCMIDALEPRO/BCMIDALEPRO.pdf

  • How to correct CIF error Base unit of measure does not exist?

    Dear experts,
    I'm trying to cif a location product with base unit of measure KG in R/3 and alternative unit of measure well maintained.
    it gives me a CIF queue saying that
    "Base unit of measure ZXX does not exist (Product 0000000000000XXXXXX has not been created)"
    I do not understand why, the unit ZXX does not exist in the alternative unit of measure for any of the materials managed
    I also checked CUNI table and ZXX is not there neither in R/3 or APO,
    Thanks for your help
    E

    Looks like the Alternate UOM --Zxx is not maintained in APO.
    2 ways to do this:
    (1) program- RSIMPCUST
    Re transfer all your UOM settings from R3 to APO
    (2) Manual Maintenance in APO:
    SPRO>SAP NETWEAVER>GENERAL SETTIGNS>Check UNits of Measurement
    Thanks
    Kumar

  • Base unit of measure values  not loading into the cube.

    HI Xperts,
    i have created a generic data source and in that i took unit as base_uom and one quantity keyfigure and in my cube i have taken 0base_uom and a quantity key figure infoobject.
    in transformation i mapped the  base_uom(source) to 0base_uom (target)and soures quantity KF infoobject to targer keyfigure infoobject.
    after loading the data into my cube..i am getting the values for quantity keyfiure infoobject but for  unit (CS,IT) i am not getting any value in my cube.
    so in my report also the for a specific quantity unit value is showing ERR.which is wrong.it should show me as CS or IT(10CS or 15 IT etc).
    Can any one help me on this?
    Regards,
    satihs

    > in transformation i mapped the base_uom(source) to 0base_uom (target)and soures quantity KF infoobject to targer keyfigure infoobject.
    This is not how you map Key Figure and Currency in cube..
    First check in RSD5 whether you have Unit Infoobjet assigned to the key figure.
    in Type/Unit tab ..you have to assign 0BASE_UOM to your Key Figure.
    Then in transformation from DataSource to Cube  : connect both the Unit and Key ( in source) figure to target KF.
    In Rule Detail you have to select .
    Target Unit = 0BASE_UOM
    Unit  = From Source
    Source Unit = Your source field name for unit
    Let me know after doing all these whether are getting unit field in cube
    Regards
    Anindya

  • Base Unit of Measure - Day & Hours

    Hi All,
    We are facing a unique problem. We created a material with Base Unit of Measure as "DAY". At the time of MIGO, the FI Document also got posted with Quanity 5.00 and Base Unit of Measure as "DAY".
    However, when we go to the Report Painter Reports in Controlling and see the Quantity; we see 120.00 Hours rather than 5.00 Days and we are unable to figure out because of which settings, system is behaving like this.
    We checked the configuration of Unit of Measure through T. Code CUNI and found everything OK.
    Kindly request you to throw some light on this.
    Thanks,
    Shalin

    i day = 24hrs, system has calculated the 5days and converted into 120hrs.
    please check the Order unit used in PO
    also check the stock keeping unit/issue unit in master
    also check the info record

  • QM_Change of base unit of measure not possible

    Dear QM Experts,
    Scenario is,
    1.     Material master created with QM view activation.
    2.     The Base Unit of Measure kept as EA
    3.     Inspection plan prepared for material with usage 5 and status 4.
    4.     Material has not undergone any purchase order / production order / routing or any other transactions except inspection plan.
    5.     No movements have done and the stock is zero
    6.     The requirement is to change Base Unit of Measure from EA to KG
    When tried through MM02 system throws an error message as The base unit of measure cannot be changed; choose "Display errors" Message no. M3189
    When viewed through log another information gets displayed as Routings already exist that are assigned to the material. Task list type Q.
    I tried through trial and error method. First material assignment was deleted from task list, problem did not resolve. Thereafter deletion flag put to task list. No impact. At last entire task list deleted. Still system does not allow changing unit.
    Has anybody faced the same problem ever? Whether deletion of task list (By T-Code QSR6) from data base will server the purpose? What are the obligations that one must follow while execution QSR6?
    Or if there is any other solution to this requirement?
    Thanks in advance
    Best Regards,
    Anand Rao

    Hi
    *What are the obligations that one must follow while execution QSR6?*
    By this T code  Deletion is very much possible provided that
    If there are no stocks of the material in the current period and in the previous period
    If there are stocks in the previous period, you can clear them as follows:
    a) Post the stock in the previous period to the current period (for example, using movement type 561) so that the stock for the previous period is the same as the stock for the current period.
    b) Clear the stock with the posting date in the previous period (for example, using movement type 562).
    If no purchase requisitions, purchase orders, or scheduling agreements exist for the material
    Material Is used in any task list/Rauting.
    Now as per your schenario I hope you have checked Inspection lot & PR,PO.
    Error showing Q type of task list.
    Go to PLKO & MAPL table for this material & group & Gr counter check the entry.
    Check deletion Indicator in both the tables. If it has status "X" then this task list is very much possible to delete through QSR6.
    I hope this will add some value to your Execuation.
    Regards
    Sujit

  • Base and alternate unit of measure  - Per PO conversion

    Hi,
    Here is my problem :
    I buy let's say 100 M of Configurable Material A, the weight  Stock unit (KG) is expected 50 .
    Now buy another 100 M of Configurable Material A, the weight  Stock unit (KG) is expected 100 . because of a slightly configuration change.
    I which I can change the conversion between Buying Unit and Stock Unit on the PO itself ( UMREN - UMREZ ) depending on the user input or config changes (feg dependency like we do on sales).
    I didn't find the right zone to unlock these two fields  in the "SPRO  ... Define screen layout at doc level" , and I am not sure it is the right way to reach my goal.

    Hi,
    BASE UOM is the unit of measure which will be used by business to calculate the weight of the goods or rather the Unit of measure in which stocks of the material are managed.
    Say for example I create one bulb. The base UOM is PCE or Piece.
    It means that the Bulb will be referred to as 1 Piece irrespective of its weight.
    So if in the sales order i put 10 PCE of Bulb it means 10 individual unit of the bulb.
    Alternative UOM is the Unit of measure in which quantities can be entered alternatively to the base unit of measure / stockkeeping unit.
    Say for example in our cases; we are selling these bulbs in boxes.
    I BOX = 10 PCE .
    So BOX becomes your alternate UOM.
    The relation is maintained in MARM table via the additional view in the Material Master (MM01/ MM02/ MM03 transaction)
    The relation 1 : 10 is managed by the UMREN UMREZ fields in MARM.
    I hope this is useful for you.
    Regards,
    Ankur Parab

  • Base and alternate unit of measure

    HI,
    can anyone please tell me
    1) what is base unit of measure and alternate unit of measure.
    2) what is the relationship between these two.
    i have one program which currently calculates base unit of measure for all the unit costs and now i need to calculate the alternate unit of measure for all the unit cost
    I heard that relationship of these two will be found in MARM table but i couldnt find it
    Please tell me how do i do achieve it.
    Thanks,
    Ahmed.

    Hi,
    BASE UOM is the unit of measure which will be used by business to calculate the weight of the goods or rather the Unit of measure in which stocks of the material are managed.
    Say for example I create one bulb. The base UOM is PCE or Piece.
    It means that the Bulb will be referred to as 1 Piece irrespective of its weight.
    So if in the sales order i put 10 PCE of Bulb it means 10 individual unit of the bulb.
    Alternative UOM is the Unit of measure in which quantities can be entered alternatively to the base unit of measure / stockkeeping unit.
    Say for example in our cases; we are selling these bulbs in boxes.
    I BOX = 10 PCE .
    So BOX becomes your alternate UOM.
    The relation is maintained in MARM table via the additional view in the Material Master (MM01/ MM02/ MM03 transaction)
    The relation 1 : 10 is managed by the UMREN UMREZ fields in MARM.
    I hope this is useful for you.
    Regards,
    Ankur Parab

  • Follow up material with different base unit of measure

    Hi all,
    I have the BOM with material Mat1 as a component. The base unit of measure of Mat1 is KG.
    Is it possible to replace Mat1 with Mat 2 material in MRP once the Mat1 warehouse stock is depleted.
    The base unit of measure of Mat 2 is KGK.
    The required quantity of MAT1 should be recalculated from KG to KGK accordanly unit ratio.
    Please, expain, where does it maintain?
    Thanks,
    Peter

    Hello Peter,
    You can use follow-up setting (set Mat2 as follow-up of Mat1 in MRP 4 view of material master if this follow-up scenario is valid for all BOM) with discontinuation indicator '1', w/o effective-out date. In this case Mat1's stock will run out (no PldOrd, PR, etc) will be created, and from the date, when Mat1's stock runs out, MRP will calculate with Mat2.
    As I told you, according to my best knowledge, you cannot realize this with different base unit of measures. (you have to change the buom of one of the related material masters or create a new material master if you cannot cope with buom-change).
    Follow-up group scenario can also be used but I guess different buoms will be a problem in that case as well.
    Maybe there are better solution but I'm not aware of it...
    BR
    Csaba

  • Base Unit Of Measurement error

    Dear Sir \ Mam,
    Our some materials base unit of measurement is in KG, and we want to make bills, excise RG1 entry in KG for milligram sales or material transfer. How to go for such transaction, system is not allowing for such transactions.
    Pls Note : We can't create two separate materials code for these UOM issue materials.
    Requesting a help.
    Regards,
    Randhir Padwal

    Hi,
    As per my understanding you have base unit in KG and you want to material issue and sales in miligram unit. If this is requirement then you may try to assign "sales unit" for material master in "sales:sales org1" view. you have to also give the conversion rate from KG to miligram in additional data.
    for issuing you have to maintain issue unit "miligram" in material master view "Plant data/stor1"
    Regards,
    mukesh

  • Changing Base Unit Of Measure in Material Master

    Dear All,
                  We need to change the base unit of measure of certain materials who have been assigned inspection plan. We have deleted the material from Inspection Plan and later even the plan. But still the system not allowing to change the BASE UNIT OF MEASURE. The error thrown by the system is : Material is assigned to inspection Plan.
    Please guide in this regard as changing the material for us will be a very cumbersome act.
    Regards

    Hi Rohan,
    Please check 'display errors' in MM02 when you are trying to change the BUoM. It will say what prevents you from doing that.
    Please check:
    http://www.sap-img.com/materials/change-base-unit-of-measure.htm
    BR
    Csaba

  • Sale unit of measure is not copied into Delivery from MF60 staging

    Hello all,
    we are using MF60 for EWM staging. Component has base unit of measure as M2. For production purposes, issue unit of measure was set to KG.
    I managed to get KG in MF60 during staging, but Outbound delivery created contains however unit M2. This is unit of issue from sales org1 tab. I changed this to KG, but still M2 is coming.
    Please let me know if you know what is the problem.
    Thanks in advnace!
    Regards, Andrey.

    Hi Andrew,
    I think this issue is nothing to do with EWM. You can check with your SD consultant why sales UoM not getting copied into delivery. May be because of some delivery type or delivery item type settings.
    I had same issue for over delivery tolerance, which I raised with SAP and they advised to use the customized BAdi to get it done.
    Thanks,
    sandip

  • Error in BAPI_MATERIAL_SAVEDATA -  Unit of measure ****** is not defined;

    Hi,
    I am using the BAPI_MATERIAL_SAVEDATA to create material in the material master, I am passing
        ls_bapi_head-basic_view    = 'X'.
        ls_bapi_head-purchase_view = 'X'.
        ls_bapi_head-mrp_view      = 'X'.
        ls_bapi_head-storage_view  = 'X'.
        ls_bapi_head-quality_view  = 'X'.
        ls_bapi_head-account_view  = 'X'.
    these views, I am passing the necessary details to the BAPI . But it is giving me an error ' **Unit of measure ****** is not defined; check your entry**'. plz help me how to solv the problem.
    Thanks,
    shekar

    Hi Vinod,
    It was very usefull for me thanks,
    I have another problem i have  to pass Valuation Class - bklas and in quality view nspection Type - 'art', Inspection Type - Material Combination is Active - 'aktiv'.
    please let me know how to pass these values to FM
    thanks,
    shekar

Maybe you are looking for

  • How do you display a parameter form built from a report?

    Does anyone know how to display the parameter form from building a customized report, as a portlet on a page? Everytime I try, I get the report, which will return no records because it does not first ask for the query parameters. thanks! null

  • Attachment name problem

    Hi all, Scenario : sending ORDERS idoc from R3 to vendor as an attachment (named Untitled.xml) in mail through mail adapter. I've manage to rename attachment with adding module in communication channel : Processing sequence Module Name : localejbs/AF

  • LSO: Java errors when using Authoring Environment to check-in eLearning

    Have any users here encountered any of these Java errors when trying to check-in eLearning content to the Master Repository? reuseObj is null java.lang.NullPointerException: reuseObj is null      at com.sap.hcm.ls.shared.repository.exchange.DeltaVers

  • Duplex scan option missing on HP Officejet Pro 8500

    Moved to another board Although I am an HP employee, I am speaking for myself and not for HP. Twitter: @Ciara_B_HP

  • How to store Employee's working history ?

    Hi gurus, At present I've a problem with storing employee information for the following : 1. Working history for an employee ( At our company ) , For example : The employee has joined in how many projects , Time , Positions....... (How can I store th