Want to change my existing Release strategy for - PR, PO & Service Entry

Hallow Experts ,
Here i have a requirement to change the existing Release strategy for Purchase Requisitions, Purchase Order and Service Entry sheet. Already There are unreleased Purchase Requisitions and Purchase Orders in Production system with the existing Release strategy.
1. My Query is Before making change in Existing release strategy, should I need to release all PR and PO with unreleased status.
2. In PO scenario is like this, we have 4 purchacing groups and 4 document types(ZLOC,ZIMP,ZSER,NB) in release strategy, we need to add one more purchasing group that is to be aplicable to my  service PO(ZSER) only . so should I need to creat another stretegy for the same, or I can add in the same strategy
thanks in advance.
regards
vb

Dear Vikrant,
1. My Query is Before making change in Existing release strategy, should I need to release all PR and PO with unreleased status.
Sol:  Not  Required but , doing it is recomandaed
2. In PO scenario is like this, we have 4 purchacing groups and 4 document types(ZLOC,ZIMP,ZSER,NB) in release strategy, we need to add one more purchasing group that is to be aplicable to my service PO(ZSER) only . so should I need to creat another stretegy for the same, or I can add in the same strategy
thanks in advance.
Sol: No Only thing you have to  do is that   go to your class 32 and   chek what is the charaterstic define for the purchasing group  copy it
2 Now go to  Tr.code: CT04, give that charaterstic and go to change mode and give the additional Purchasing group there, and save it
3 Now go to Release strategy where you want to add that Purchasing group, go to classification tab and tik that new purchase group ,  that  group will now in fact of release Strategy

Similar Messages

  • Release strategy for PO and Service Entry Sheet

    Hi
    I maintain characteristics- Plant, Doc Type , Order Value & Purchasing Group for PO release strategy.
    should I maintain the same characteristics for service entry sheet ?
    the approval will be the same for both

    Hi,
    The Po reselase strategy can be set up separately from the entry sheet release strategy, so you can use even different characteristics for your entry sheet release strategy. These are not connected!
    Please read note 672719 question 5 - How can I set up a release procedure for service entry sheets?
    Note: The release strategy must be based on the structure CESSR.
    The PO release strategy is based on the structure CEKKO.
    For the SEs release strategy you must create a different class.
    Regards,
    Edit

  • Sub: Our Client wants to change the existing Release procedure.

    Dear Friends,
    Requirement:
    Our requirement is to remove one of the Release Code from the existing release sequences, with out affecting the old Purchase Orders.(including Released and Partially Released)
    Changes we done:
    Once we remove the specific release Code and found that it affects all the Purchase Orders (both Released and Partially Released) which are relevant to this removed code.
    Is there any other way to do this changes with out affecting the old Purchase orders (we don't have Work flow in the Release Strategy).
    Regards,
    Dhan

    Hi,
    If you want to change the release code, then what are the open order which or not released and in process make sure those PO's are released then you can change the release code.
    Else System wouldnt allow you to process further, then you need to create new PO's, So avoiding this first release all the open PO's and partial release PO's then you do change the release code.
    Thanks & Regards,
    Dhanush.

  • Release Strategy for Sales Order-IMP

    Hi Gurus,
    I want to know regarding <b>Release Strategy for sales orders</b>. I want to know the detailed step-wise procedure for SO and not for PO. My understanding is that standard SAP does not support Release Strategy for SO in SD Module. Please l want the following queries to be answered
    1) Is my understanding on Release Strategy for SO correct as mentioned above?
    2) What are the other alternatives and the steps of configuration step-wise.?
    Kindly help me post this information as it is required urgently. Suitable full Reward Points will be given to all answers.
    Many Thanks,
    Pankaj Mishra
    E-Mail : [email protected]

    Pankaj,
    There is no release strategy for sales order.
    You can try it doing Authorisation /Status  profile with your BASIS person...
    REWARD IF U FINDS THIS AS USEFUL...
    Regds
    MM

  • Reset Release Strategy for any change in the Purchase Order

    Hi,
    Is it possible in SAP standards to reset release strategy for even minor changes in the Purchase Order irrespective of whether it is value change or any change in the text or Purchasing group change or whatever it is?
    If so, where do we need to make the configurations.
    I have seen in some thread about resetting the release strategy for decrease in Purchase Order value.Even that was possible through some BAPI.
    Thanks in Advance.
    S.Raghavan

    hi sandesh,
    sorry, i know it's too late.
    i tried your suggestion, it works blocking the purchase order after release strategies are setted.
    sandesh, raghavan:
    i need to reset the strategies after to make any change in the po. i'll appreciate your help if you can give it.
    regards
    f

  • Release strategy for Release POs

    Hi Every one,
    We have a requirement.
    A contract is created and approved as per the regular strategy.
    The releases (POs) are created against it and sent directly to the vendor.
    As the Contract is already approved, standard SAP does not apply the release strategy for the POs created for the contract.
    But the business wants the PO releases too to follow the release strategy.
    Can you please look in to this and let me what changes we need to make this happen.
    Regards
    Pavan

    As the Contract is already approved, standard SAP does not apply the release strategy for the POs created for the contract
    This statement is not correct, it's upto you to use or Not to use Release Process for release Orders (PO) created w.r.to Contract.
    As the table & fields are Common for both Contract & PO release ..you need to choose the PO relevant fields & values in the Release Strategy..
    So that the Release Process is applicable to PO's created w.r.to Contract also..
    For ex: if you use the field purchase Doc category as a Character  in  the Release , it differentiates whether it is PO or Contract..
    So that you can define different Release Strategy for PO & Contract
    Or  if you maintain the Doc type of PO in the Contract Release Strategy in CL20N / CL24N trxn code..
    then the release strategy applies to PO also..

  • Cannot reset release strategy for RFQ

    Dear SAP gurus,
    I set release procedure for RFQ. I set anyway that the changeability is 6, and the tolerance is zero. I expect that after it is released, whenever anyone is changing everything the release strategy will be reset.
    But this is not happening. In my case, the manager already approve the RFQ but the RFQ has not been sent yet. Then someone change the quantity of the RFQ, and the release strategy is not reset. When I check again I realize that changeability 6 means the release will be reset if the value is changed; while in RFQ there is no value mentioned anywhere, it means that the release strategy for RFQ will never be reset.
    Do i miss something? Is there any way to make sure that the release for RFQ is reset if someone change anything in the RFQ?
    Best regards,
    John.

    Why are you having a value based release in RFQ? And more important, why do you need release for RFQ?
    However, if you still want to go ahead with release, then you need to use the user exit for purchasing document release to achieve your objective. Please search for my earlier posts on how to reset release even on decrease of PO value. You can use the same logic for RFQ also.
    Lakshman

  • Release strategy for Future validity period- (Outline agreements)

    Dear All,
    I want to create release strategy for Scheduling agreement.But I am creating the SA for furure validity period.In this case how the release strategy will triger.
    E.g Today 09.03.09 I create a Sceduling agreement and the validity period I maintain is from 01.06.09 to 31.12.09 and Amount say 100 Rs.
    I am using Characteristics Doct type and Amount.. The system checks the rate as on date (i.e on 09.03.09) and since it doesnt find any value the Release strategy is not trigeering.
    How to set up release strategy in the above case.
    Thanks in Advance.
    Regards
    Amar

    Hi Amar,
    1) if you maintain a target value (EKKO-KTWRT) in the header of the            
    contract this value is the basis for the determination of the release          
    strategy. If the target value is 0, the system will cumulate the               
    values of the items and will use this value for the determination.                                                                               
    2) So if the target value is 0 and you change the price of a condition         
    with a validity period in the future the system will react in the              
    following way:                                                                               
    Example:                                                                       
       the contract contains one item with quantity = 100 and a net price          
    of EUR 5,-.                                                                    
       all contracts with a target value from EUR 0 - 1.000,- should be            
    subject of a release strategy                                                  
       the contract is created and released on October the 1st                     
       ME32K -> October the 2nd you define a new price of EUR 7,- with a           
    validity period from 03.10.09 - 30-10.09 -> you save the contract              
    -> the release strategy is not reset, as the start date is not                 
    reached yet (system date < startdate of validity period)                       
       ME32K October the 3rd you change a field in the contract -> the             
    release strategy is reset                                                                               
    This is system design that a release strategy can only be reset through        
    an action by the user. The determination of the release strategy can't         
    be triggered automatically in the background.      
    If you create a document which is subject of an overall release strategy      
    (e.g. p.o., contract) the determination of the release strategy takes         
    place when the user hits the 'save' button or chooses the 'check'             
    function.                                                                     
    So there must be a kind of event that tells the system that something         
    has changed.                                                                               
    Regards,
    Edit

  • Release strategy for auto created PO's

    Hi Guys,
    I have a requirement to implement release strategy for automatically created PO's.
    PR's are created automatically and we have a program which create PO's automatically.
    we would want to release them before generating output to vendor.
    could anyone please have any inputs here.
    regards
    mittu

    Hi!
    You may use your existing release strategy or create a new one (depending on your requirement). You just have to add/ use the document type you used for your auto-generated POs.
    Hope this helps! =)

  • Release strategy for manual reservations

    hi!
    Is it possible to have a Release strategy for manual reservations ? how?
    Regards,
    Rajiv Kane

    Dear,
    There is no release procedure exists for Reservations in SAP.
    1. Either remove authorizations for MB21 to the low level employees and give authorizations for CREATE / CHANGE / DELETE reservation trans to management only.
    2. Or else instruct inventory people to only make movements (issues) against the printed signed copy of reservation from the concerned manager. Only the user brings the reservation print with manager sign or seal, then only the material can be issued.
    Meantime, instruct the management to time follow goods issues reference to reservations timely.
    Regards,
    Syed Hussain.

  • Release Strategy for SA/Contract/PO

    Hi friends,
    Should we have different release groups and release codes in contracting/ SA/ PO.
    Because...
    I have maintained 4 characteristics in release strategy for PO _[ Comp Co, plant, porg, total net order value].
    But i want to maintan only 2 characteristics in release strategy for contract  [plant, total net order value]
    because the same is reflecting in contract config also.
    Is it possible..please help me frnds.
    Prabhu

    Hi Prabhu,
    Unfortunately you need to maintain characteristics of all possible values for company code and plant for contractsu2019 to subject the release.
    Wish that SAP would be more flexible with release of PO, Contract and RFQ but it does not.
    Regards

  • Release strategy for Schedule lines in SD

    Hello All
    Can we create a release strategy for Schedule Lines in Scheduling Agreement? If Yes How?
    I have already maintained a release strategy for Item Level... which I want to put it for Schedule line as well....
    Thanks in advance.

    Hello,
    I think you are in the wrong forum. Please choose the right forum category and post it there.
    Matthias

  • Release strategy for Scheduling Agreement(SA)

    Dear Forum,
    This issue is with regards to the release strategy for Scheduling Agreement(SA)
    Until now release has only been applicable to contracts at our client site. But we now plan to introduce it for SA as well. Such a feature is available in SAP but the problem is that with the given release strategy GR is not allowed until the release is affected. The system allows you to post the delivery schedule.
    Now what I want is that after making the SA the system should not allow to make delivery schedule if release is not affected.
    We also have MRP run at client site..Kindly suggest the procedure as, how to configure it.Are der any User Exit for the same,if so please discuss..
    Warm Regards
    Nainesh
    SAP ECC 6.0

    Hi,
    What's the SA Type that was created via MRP.
    If it's LP (without release document), release will not do anything BUT
    If it's LPA (release document), then you will not be able to Post the GR until release is affected.
    Thanks.
    Scheduling Agreement can be categories as
    1) LP (without release document) and
    2) LPA (with release document)
    If use LP, you can do GR without release but with LPA, you need to release the schedule line via ME38.
    Thanks.
    NanoSAP  
    Posts: 58
    Registered: 1/5/09
    Forum Points: 6 
       Re: release strategy for Scheduling Agreement(SA)  
    Posted: Jun 26, 2009 8:32 AM    in response to: sathish.kumar           Reply 
    Dear Mr.Satish,
    Thanks a lot for your earliest reply...But my point is i want the system should not allow to make delivery schedule if release is not affected...Though schedule lines are generating through MRP run...Is is possible,by any chance...??

  • HT204053 i want to change an existing icloud account to a new icloud account?

    I want to change an existing icloud account to a new icloud account

    If you want to create a new iCloud account and migrate your data to the new account, you'll have to delete the existing account, create the new account with a new ID, and then migrate your data to the new account.
    Before doing this, if you have any photos in photo stream that are not in your camera roll or backed up somewhere else save these to your camera roll or you will lose them.  To do this, open the my photo stream album, tap Edit, tap all the photos you want to save, tap Share, then tap Save to Camera Roll.
    Once this is done, go to Settings>iCloud, scroll to the bottom and tap Delete Account. When prompted about what to do with the iCloud data, be sure to select Keep On iPhone.  Next, set up a new iCloud account using a different Apple ID (if you don't have one, tap Get a Free Apple ID at the bottom).  Then turn iCloud data syncing for contacts, etc. back to On, and when prompted about merging with iCloud, choose Merge.  This will upload the data to the new account.

  • Release strategy for PR in Third party case

    Hi,
    We have this third party scenario where Purchase reqs are created at the time of Sales Order creation. A release strategy is attached to these purchase req by defining a custom field in MMaster, whenever qty goes up or equal to tht field release strategy is applied.
    The problem is, for the same material's PR, the release strategy is set in one case whereas for other PR (of different sales order) it is not set. Please help let me know what could have gone wrong.
    Thx.
    Amit

    Per your information you say that based on a custom field qty in material master release strategy is triggered. Do you have any charecteristic maintained for the Release strategy anything other than this parameter- because there must be some difference between the 2 Reqs.
    Or check the change history in Material master it may be possible that at the time of second sales order if the field value was changed so that release strategy was not triggered.
    Please give more details
    Thanks
    Deepak

Maybe you are looking for

  • Share youtube to facebook button doesn't work :(

    Hi,      just upgraded Safari to 5.1.4 running an iMac on 10.7.3, now the share button on youtube doesn't function. It's ok on Firefox, looks like I need to abandon Safari (Again!)

  • Comma or point in decimal number

    Hi, I wonder how to handle decimal number input from jsp page with comma or point. Is there a way to take care of this automatic so a comma get parsed to a point or vice versa. Thanks in advance.

  • [code] does not work correctly, cannot post code example.

    Hi, I tried to do a code example, but HTML tags inside java quoted strings were intereperted. Like the <IMG> tag and the <H1> tag.. How do I prevent this???? Re: How to post an audio file in JSP or servlet

  • Connecting TV and Monitors to your PC

    Hi I have seen this question asked several times on this forum. Here is the best video that I have seen. It is made by HP support. I don't understand why these threads can't be made stickies. It sure would save advisiors a lot of time. Dokie!!! http:

  • Upload data from flat file to OVKK  using BDC