WBS Element Name Change

Hi,
User wants to change the WBS element Name, but the field is greyed out.
User has the access to CJ02 but only the long text is open to change but WBS Element Name / ID field is freezed and can not be changed.
The current status of WBS element is released.
In Quality system I am able to change the WBS element Name / ID.
Please let me know what can be the reason for WBS Element name field being greyed out.
Thanks
Satish

Hi,
I agree with Nitin.
You can not open any version witht he old name if they are already created and in at table level internal number is stored. When you change external number will get changed but not the internal number.
So for any report purpose or in any developments you are taking internal number and thru conversion exit converting it to external number then it will return old value not new value.
It will create lot of inconsistency in data once such volume of such instances grew.
If possible , set deletion indicator to that WBSE and create new one with desired name afresh.
Thanks
Saikishore.Ganga

Similar Messages

  • Checking WBS elements when changing WBS element group

    Dear Gurus,
    Well I am a technical consultant, I use to dwell in the ABAP forum, so maybe I am going to say things without much sense, if so please tell me.
    I have a problem. One of our customers uses transaction KJH2 to change WBS elements groups and they have asked us to check the WBS elements that the users can put in the transaction.
    If a user adds a new WBS range both the WBS elements have to exist in the system, we have to check it somehow, probably using a user-exit or a BADI.
    The problem is that I have been looking for a BADI or a USER-EXIT for many hours and I have been unable to find one which allows us to check this, same when the user inputs the WBS element as when we save the changes.
    Somebody has some help? Any advice would be apreciated.
    In the while I will keep trying to find it and if I succeed I will post it here anyhow.
    So long I have put a break-point in the 'CL_EXITHANDLER' class and I have checked the BADIs that can be used when I make the process, none can be useful I think. I have tried to find a USER-EXIT and I have foud none.
    Thanks in advance to everyone.

    Hi Ayan,
    Maybe you are right and we can't use a BADI for this. But we have a customer which has requested us to code this data check so I have to try.
    I agree that this is master data but it is a simple data check without many consecuences (at least it seems so to me), maybe there is a way to do this.
    Right now I think I am going to stop this until Monday as the FI consultant is now on vacation.
    Thanks a lot for your reply.

  • WBS Elements - Cannot change status

    Hi Guys,
    When we are trying to change the status of a WBS element to " CLSD " , it is giving us the following error message
    " There are still open down payments for WBS XXXXXX ".
    Please advise as to how these down payments for the WBS be tracked and cleared.
    Our intention is to change the status of the WBS to " CLSD ".
    Thanks..
    Kris...

    Please check below reports
    S_ALR_87100191 - Receipts/Expenditures in Fiscal Year
    S_ALR_87013575 - Receipts
    S_ALR_87013574 - Expenses
    S_ALR_87013573 - Receipts/Expenditures for all Fiscal Years
    With Regards
    Nitin P.

  • Changes in a field of any of the WBS element should change in all WBSelemnt

    Dear All ,
    I have a requirement in CJ20N transaction where if i am changing in any of the field under a certain WBS element then it should change automatically for all the WBS elements of that project automatically.
    Now it is changing only in that particular WBS elemnt.
    Do anybody knows the BADI/exit for the same/how to make it possible if there is a way.
    Regards
    Rajendra

    Hey experts its much required , can u do some thing on this.

  • Wbs element number changing in easy cost planning

    Hi ps guies
    I m facing a strange problem in ps.
    I create a structure in project bulider.after that when switch to easy cost palnning ,the top wbs number changes to another number which i dont know from where it is coming.
    This happens only with top wbs ,rest of the numbers are same as i created.
    it is happining in only easy cost planning ,and in rest of the transactions it is fine.
    please suggest ur thoughts
    regards
    shashank

    Hi...
    what about..using item category E :Internal Activity.
    You need to have defined activity types per Person ex T1000 for John W1,  T1001 for Mike W2 etc.
    Also you need to have defined planned rates in KP26 for each one of the activity types.
    This way you can use ECP for each activity type (therefore employee) and use their own rates.
    Hope it helps
    Pan

  • Changing WBS element in PO

    Hi
    In my Purchase Order, earlier it was account assigned to a WBS element A. When we ran CJI3, it showed the same. But now the account assignment of WBS element was changed to B. I have no idea how this got changed. I only can check from the Purchase Order history and found that "Profit center has been changed for the item".
    How this could have happened? Any info reg this will be helpful. Thanks.
    Reagrds
    Ram

    Hi,
    You can check the same in item >envoirnment-> changes.
    Also if your PO is made wrt PR & some one has changed the wbs in PO only then it will not show correct commitment values in PS reports.
    If you want your data to be correct then you give authroization only to your Planning team to change the WBS element. You can ask your consultant to make these fields as grey when PR is converted to PO.
    regards,
    Vinay

  • Change in WBS element in a PO

    Hi
    In my Purchase Order, earlier it was account assigned to a WBS element A. When we ran CJI3, it showed the same. But now the account assignment of WBS element was changed to B. I have no idea how this got changed. I only can check from the Purchase Order history and founf that "Profit center has been changed for the item".
    How this could have happened? Any info reg this will be helpful. Thanks.

    do you hav any substitution rules in PO
    where did you change the profit centre
    in std sap this should not be an issue

  • BAPI for finding child WBS elements under a Parent WBS element

    Hi friends,
    I am working on the transaction ZIOS02 transaction. On releasing the Parent or Main WBS element in ZIOS02 transaction I need to copy some data from ZIOS to PRPS based on WBS element.
    I have a Bapi for retrieving all the WBS elements based on Project Definition (BAPI_PROJECT_GETINFO) but i want to know whether is there any BAPI for finding the child WBS elements when we give a Parent WBS elemnts as Input to BAPI.
    Could any one please help me in the query ASAP.

    Hi friends,
    I have got the answer for finding the child WBS elements.
    In Function module BAPI_Project_get_info.
    Use parameter subtree = 'X' and give the WBS element name in tables section under I_wbs_element. You will get all the child WBS elements which are under Main WBS element.
    Thanks
    Satish Raju

  • WBS Element Editable

    Hi Gurus..
    Our client wants to have WBS Element in change PO (ME22N) transction in display mode.
    Please suggest.
    Thanks in Advance
    Rohan

    Is it MRP generated or manually created? If it is MRP generated it is not possible. If it is manual you have option to change. Go to T.code OME9. select your account assignment category. Tick on acct.assg.changeable. It will work for you
    Regards
    Antony

  • Exit for replacing WBS element characters while copying from Project

    Hi All,
    While copying a Project from other Project/template in CJ01, we are getting only first 10 letters of a WBS element are getting replaced.
    The requirement is to have replacement of letters even after 10th character in WBS element.
    The SAP Note 502322 suggests to have user specific (custom) replacement logic in the user exit CNEX0033.
    Anyone has worked around such requirements?? If so can you share it,,,?????
    Regards
    Pavan

    Hi,
    While creating a Project in CJ01 by giving a template, the new Project will get created with all WBS elements from the template Project.
    In standard system, the WBS Element which has more than 10 characters will get copied till 10th character only.
    Now we need to work on user exit CNEX0033, so that entire WBS element name should get copied in the new Project.
    Anyone has worked on such requirement???
    When i create new Project in CJ01, the exit CNEXX0033 will trigger..
    If so can you suggest me how to move further??
    Regards
    Pavan

  • Change WBS element from Sales order

    Hi...
    I have created one sales order with WBS element assignment then I have created billing document and released to accountingu2026.
    Accounting and controlling documents are fineu2026
    After creation of accounting document system is allowing to change or delete the WBS element at sales order item levelu2026same time profit centre field does not allow to change or delete
    We donu2019t want to user to change WBS element after creation of accounting documentu2026that field should be shown in greyu2026
    Please help me to solve this issueu2026
    Thanks,
    Raj

    Hi,
    You can create a Transaction Variant for the transaction VA02 in which you have to maintain the WBS Element field as output only.
    1. Go to SHD0, enter VA02 in Transaction & give a name to the transaction variant and press Create.
    2. Enter an order no., go to the item "Account Assignment" tab.
    3. Check "Output Only" against WBS Element in the screen listing all the tabstrips & Fields.
    4. Exit & Save.
    You will be returned to the SHD0 screen.
    Select the "Standard Variants" Tab under "Standard Vriants" tab. Press activate to activate the Transaction Variant.
    Go to VA02 to test the variant. You will get the WBS Element disabled.
    Revert in case of any doubts.
    Regards,
    Vijay

  • Change of WBS Element

    Hi,
    i am checking the all tabs of  WBS Element in CJ20N, while checking unfortunately one character of WBS Element was missed & saved accordingly.
    Old :   09/ITS/CN/IT/T09
    New:    9/ITS/CN/IT/T09
    Now user is trying to settle 09/ITS/CN/IT/T09 in CJ88, it showing the error as WBS does not exist.
    again i tried to change as  09/ITS/CN/IT/T09 in CJ20N. but it is showing the error as below.
    WBS element 09/ITS/CN/IT/T09 version RELEASED already exists
    Message no. CJ026
    Diagnosis
    A WBS element with the name 09/ITS/CN/IT/T09 already exists in version RELEASED.
    System Response
    Processing stopped.
    Procedure
    Enter another name for the WBS element.
    now how can i replace the correct WBS Element, Please suggest me any solution is possible.
    Regards,
    Shekar

    Hi Shekar,
    There are other options available to you, to resolve this issue.
    Firstly, you can manually delete the WBS Element from the table
    VSPRPS_CN. There is no report to remove individual records from this
    table.
    Alternatively, please review note 616732.
    This report renames the WBS Element within the table VSPRPS_CN. You
    could rename this WBS Element in VSPRPS_CN allowing you to recreate the
    operative WBS Element.
    Again customers are advised to contact regional support when running the
    report ZVERSION_UPDATE to be informed of the following.
    Thanks a lot and kind regards,
    Enrique Sosa

  • What is the BAPI Name to chg status of Project def/WBS element.

    HI ALL,
    Can anybody tell me is there any BAPI which will change the
    status of Project Definition or WBS element and  also update
    JCDS table data?
    for eg. TECO(technically comlpited)-> CLSD(closed)
    I want to do this by any FM instead of BDC.
    can anybody help me inthis regard?
    Thanks,
    MM

    Hi Deepak,
    We have tried the given BAPI, but it is only used at WBS level.
    our requiremnet is that when Project definitions system status is changed, then it should chg the system status of WBS as well as Network..  We got the BAPI for this named"
    BAPI_BUS2001_GET_STATUS.. this is used to chg the status of Project and corresponding WBS but does not chg the Network. but in this BAPI also we are passing following
    project but we are getting error  like
    Project _def: 40co-9001937
    undo_system_status: DLFL
    when execute, it given error like Error in processing FM was not executed.
    can any one tell me why i am getting this kind of error
    and also other BAPI name which will chg the status at all 3 levels like Pro Def, WBS and Network..
    Regards,
    MM

  • Cannot change Status of WBS Elements

    Hi Guys,
    I am trying to change the status of a WBS element. When i try to change the status of the WBS element, I get the message that " THere are still open down payments for the WBS ". What does this actually mean??
    I found the downpayment GL and looked for the open items. In the open items i was able to find a line item to which this WBS is attached. Then i tried to go to the document, in which this line item exists. Now in order to clear the open line item with the WBS, how should i clear that line item?? I want to know how to clear the down payment for this WBS or the found out line item.
    Thanks.
    Kris..

    Hi,
    Run the report S_ALR_87013536 - Plan/Actual/Down Payment as Expense for the particular WBSE that was showing in the error. Here you would see the value of down payment against the WBSE.
    Run FBL3N for the down payment G\L by selecting the WBSE from dynamic selection. Here you can get the open line items with WBSE and relavent PO.
    For clearing the down payment discuss with your concern MM  and FI dept.
    Hope this could help you.
    Regards,
    Nag.

  • Change WBS's statistical WBS element

    Hello;
    We use the SAP PS module. I create the WBS and WBS's statistical WBS element (XSTAT) set the true.
    I need the change WBS's statistical WBS element and set the false. But WBS's statistical WBS element read only on the screen.
    How is change WBS's statistical WBS element?
    Thanks.

    Hello
    Set a substitution rule for a particilar proj profile/type, to set the WBS as statistical on saving.
    Sarang