WBS for two company codes

Dear Experts,
This requirement is for an IT service project.
The process is - I have two company codes Comp code 1 & Comp code 2, In which Project is created in company code 1. Employees are assigned to project to onsite & offshore from company code 2. This means the employees are created in the company code 2. But working for the project in Comp.code 1. Comp code 2 get revenue thru intercompany billing based on number of hours/days the employee worked in the project created by the com. code 1. The employee books the timesheet in comp code 1 against the project id.
To acheive this
1)  i need to maintain same project for two company codes?
2) Or same project, one wbs for one company code & other wbs for another company code?
Will the above two possible to work in SAP? or
anyother we i can workaround this
Please advise
Regards,
Deepu Pillai

Hi,
This is possible through Resouce Related billing in PS.
For e.g. Consider business scenario, where we have created T-10006 as a customer project.
Now this project is mapped using a work breakdown structure that contains activities.
The activities define the flow of the project and form a quantity structure for determining costs and payment data automatically.
The project cost plan is used to create quotations.
When the sales order is received, it is assigned to the project. This means that it can be used to plan revenue and then post this revenue.
Actual costs are entered when activities are confirmed, components are purchased and when invoices are assigned. Actual revenue is posted to the project by means of milestone billing.
Two companies are responsible for executing project T-10006.
Company 'A' is mapped using company code 1000 and performs all services except for those planned in WBS element T-10006.1.2.
Comapny 'B' is mapped using company code 2000 and performs some of the engineering services. (WBS element T-10006.1.2).
Here Comapny 'B'  bills its services to Company 'A' on a resource-related basis.
A results analysis is carried out for the billing elements T-10006 und T-10006.1.2 in the project.
The results analysis values are settled to the profitability segment.
Regards
Tushar

Similar Messages

  • Different Bank charges GL account for two company codes with same COA

    Hi,
    While configuring OBXK ( Automatic GL account for bank charges)  , I see there is provision to enter only one GL account per chart of accounts.
    We have two company codes using same chart of accounts but different bank charges GL account. Please tell me how to configure this.
    Thanks,
    suresh

    Hi,
    Thanks Krishnan and Chandra.
    I agree with you it could be the same GL account for bank charges, but the business requirement is such that in one of the two company codes, bank charges are required to be tracked separately to be subsequently transferred to the other company code. This means two separate GL accounts are required for two company codes which needs to be configured in OBXK.
    Hope this clarifies my query further.
    thanks,
    suresh

  • Can I create a single PO for two company codes

    Hi
    Can I create a single PO for two company codes. Though I know that Company code is assigned at header level but still I know there is a setting in controlling which when activated two company codes under same controlling area can procure the goods under the same PO.But i forget from where to activate that message or control in config.
    Thanks

    Hi Lekhram,
    I'm just beginner so maybe I got the wrong end of the stick.
    If you order something that something must belong to a definite company > plant. How could possess two company the same thing at the same time (totally)?
    (companies are at the same organisational level - none of them is subject to the other).
    Maybe I'm mistaken.
    So I <b>guess</b> you can use only one company code for one PO.
    Controlling area & company code
    http://help.sap.com/saphelp_46c/helpdata/en/e5/077a704acd11d182b90000e829fbfe/frameset.htm
    http://help.sap.com/saphelp_46c/helpdata/en/08/513f4b43b511d182b30000e829fbfe/frameset.htm
    Purchasing & organisation
    http://help.sap.com/saphelp_46c/helpdata/en/75/ee0a9555c811d189900000e8322d00/frameset.htm
    All the best
    Csaba

  • One vendor for two company codes

    Hi Frds,
    I have two company codes and i create a vendor which is applicable to both the company code.Is it required for me to create separate Payable reconciliation GL account  for each company codes or creation of one common recco  account is enuf.
    Please elaborate on this as am new to this..
    Thanks,
    Rashmi Ravi

    Dear all,
    SAP allows You to create a customer / vendor master data that contains information that is valid for all the Company code --> into General data.
    Then there is a part, Company Code data, where You can define specific details for each Company Code.
    The transaction is the same FD01 or FK01.
    I hope this helps You.
    Mauri

  • Operating concern for two company code with different currency

    Hi,
    We are merging two company code into one SAP server.
    We decide to use on chart of account, and to use one operating concern.
    For company code A: the currency is CNY, for company code B: the currency is TWD.  The operating concern currency is:CNY.
    So i need to in KEA0(maintain operating concern) active company code currency, right?
    So every posting in company code B will be posted in TWD and CNY to COPA same item, right?
    In KE30 report, where to add characters: Currency type that i can show company code B report in TWD?
    Thanks.

    Dear David,
    Yes. If you have different compancy codes within one controlling area, you have to maintain currency type with 10-Company code currecny and while maintaining the operating concern also you have to choose the company code currency only.  Then only you will get the reports with respect of your company code currecny level. This will be basing on your company code-sales organisation, plants and other charcters assignment basis in your configuration.
    All the best,
    Dharma Rao. Yekula.

  • Exchange Rate Maintenance for two company codes..

    Friends,
    My client is having two company codes
    X = India
    Y = USD
    US Company code is live for the last few years and India Company code is created recently and the same is live now.
    Now when the US company code creates Purchase Orders /  Scheduling agreements, the following error is encountered.
    "Enter rate INR/EUR rate type M for 31.07.2008 in the system settings.:"
    Now my question to the forum is that
    1. If we maintain the exchange rates in OB08 will there any other effect ?
    2. Is this error because One more company code is added to the same client which is operating in INR ?
    3. When US Company code is not all transacting with India Company Code why is this error encountered.
    Appreciate if some one can explain the pros and cons of this please. I am basically an MM consultant and I would also like to know the FI impact in this scenario, hence posted this question in FI forum.
    Regards

    Hi,
    At the time of initial installation SAP would make EUR as base currency, so any new company code you create needs to have an exchange rate defined to the base currency EUR.
    In your case you can define exchange rate to EUR and process PO, as per my knowledge there will not be any impact of this.
    Thanks,
    Ramesh.

  • One payments for two company codes

    i would like to inform you how to post incoming payment when i have received amounts for differents company codes
    regards

    Guess you are trying to use F-28 (or something similar) to post the incoming payment. That will not allow what you want to do - split the incoming payment across two company codes.
    Try the generic FI txn - F-02 (or something similar), and simply choose a different company code for the credit line items.
    Dr Incoming Cash                            100
    .   Cr Customer 1 in Co Code A          80
    .   Cr Customer 2 in Co Code B          20
    The obvious complication here is that you won't be able to pick open invoices for the customers. You might have to knock off the open invoice items against these credit line items in a separate txn (F-32).
    Try it out and see if this suffices.
    Rgds
    Gulshan

  • Clear incoming payment for two company codes

    dear all
    i received an incoming payment but it concerns two company codes how to clear it

    hi
    what do you mean by concerning two company codes?
    1. the payment is made by one company code to another company code, both of which are in your system?
    2. same payment, part of which for one company code, remaining for another one?
    3. centre ar collection, one company code collects money for another compay code?
    please clarify
    best regards, Lawrence

  • Two same ERP # for 2 company codes

    Hi!
    I noticed that someone set up same ERP # for two different company codes for a same client.
    What kind of issues this can bring from account receivables cycle perspective?
    Would someone recommend to make different ERPs for different company codes?
    Thank you.
    Let me know if need more precision.

    Hi,
    If you want to use same COA for two company codes, you need to assign the same COA to those company codes with Tcode OB62.
    Create all your GL accounts centrally with Tcode FS00.(COA level as well as first company code level), then copy all the GL accounts to the other company code with Tcode FS15.
    Hope this will enough for this issue.
    Thanks,
    Srinu

  • One PO for multiple company code

    Hi,
       I have one scenario,  we have two company code   X and Y,  now we want to purchase the UPS qty 1  and Battery qty 10, which will use by both the company now can we create one PO for both compnay code  on the vendor and the Cost should be divide between both the company code , and how to do the further Finance process like invocie verification giveinng payment to vendor etc.
       regards,
        zafar

    Hi,
    I have one scenario, we have two company code X and Y, now we want to purchase the UPS qty 1 and Battery qty 10, which will use by both the company now can we create one PO for both compnay code on the vendor and the Cost should be divide between both the company code , and how to do the further Finance process like invocie verification giveinng payment to vendor etc.
    Hi Zafar
    What I think is that you cannot make one PO for two company codes. Yes you can make two different PO for two company codes.
    As per the cosrt conern in a PO you can further divide it to as per Distribution i.e. Single account assignment, distribution on Qty & Distribution on %age and than you can define different-2 Cost centres and than invoice them as per rules.
    Please tell me if any doubt in this.
    Regards
    SS

  • Creation of referenc BP in SD for different company code from IS-U system

    Dear Friends,
    I have two company codes called 2000 and 3000 in my IS-U system. I would like to create SD ref customer with reference to BP created in the IS-U system.
    I created SD reference customer with 2000 company code along with sales data's and assigned it to MKK role in IS-U, but for the second company code 3000, I can't assign the SD reference customer in IS-U MKK role, because the MKK role has been assigned it to the SD ref customer of company code 2000.
    Now the problem is, I need to create SD reference customer for two company codes (2000 and 3000) with two different sales org. details through IS-U.

    Try creating your SD reference customer in both the company codes (2000 & 3000) with their respective Sales Org data in XD01. Specify this reference customer while defining the parameters for automatic creation of SD customers for BP in IS-U.
    Regards,
    Rajini.

  • Same material in two company codes

    Hi all,
       I want to use the same material code (A1 - reynolds pen) for two company codes 1000 & 2000 what are all the implications i vl get in future,,,
    plz any guide me,,,
    regards,
    urendra

    Hi
    You will not get any implications for this.
    All your transactions are made effect on your valuation area.
    which may be company code or plant.
    In mm01 you are maintaing that material for plant level.
    So data related to this material is stored for perticular plant if you are valn area is plant.
    Also for stock transfer order you will have to maintain this material for both plants or company codes.
    regards
    rb

  • One Legal entity two company code - pros & cons

    Hi SAP GURUS,
    We are having one legal entity with multiple products. I want each plant  to be a profit center. But i am loosing plant wise profitability when we are transferring the same product from different plants, in a common depot. This is because we are not having batch & hence profitabilty for plant is lost when it is sent to depot for sale.
    In this case I am thinking to  go for two company code. One manufacturing & Other selling. What will be the pros & cons in this case.
    Thanks
    CHEERS

    Yes ! kishore You are obsolutly correct !
    Hi Nitin,
    As per my understanding your issue seems profit cannot be determined while sending goods sending plant to another palnt. For that SAP suggested to use Transfer pricing in Prrofit centre accouting & your valuation must be profit centre valuation not company code to get internal reports.
    Rgds
    ManiSuma

  • One controlling area  with two company codes assigned with one CoA

    Hi,
    I   am having one controlling area  with two company codes assigned , i am using the same  gl for two company codes  as cost element , when i am positng the  miro for vendor purpose  it posted the error  , to avoid the  price difference purpose , i have given  one cost center  of  first company code in OKB9 , and  overcome the error , entries posted, when i am posting new entry for MIRO   in secod  company codes with same cost  element ,  price difference of that account should go to the other cost center  which specifically created for second company code,  in the OBK9 i have given  cost center first company code   of the same GL  account , now this is another new entry in the second company code with other cost center in the second company code  since the price difference  account should sit in the other cost center of second company code,  how to  over come  this problem, pls help me
    Thanks and regards
    Murugesan

    Hi,
    First, remove the default cost center in the cost element. Then, for the system to derive the correct cost center for each company codes, define one cost center for each compny codes in OKB9 just like this:
    Co Code   Cost Element   Cost Center
    1000          1000000              A
    2000          1000000              B
    So during MIRO, the system will derive these values you maintain in OKB9.
    Regards,

  • How to prevent WBS element for other Company code to be used in WO

    Hi,
    I am new to this forum and want to try this out.
    This thread is regarding: Area: plant maintenance, create/change work order, message control in wbselement in tab "Addit data"
    Detailed explanation:
    In our SAP system we have the functionality that when a user enters a wbs element in a Work order (Addit.Data Tab) he gets an error message CJ065 if the WBS element is from another Controlling area.
    We want in addition the functionality: show error message CJ 066 when the WBS element is for another Company code.
    I have searched in message control within PM, but here is only allowed to enter messages for application area IW.
    I have also tried to search for other message classes without finding where in customizing to maintain message class CJ.
    Please help
    Best Regards
    Ellen

    Thanks for your feedback Narendra,
    I have thought of that solution (using customer exit at save), but hoping maybe there was a setting in Customicing eather in CO or in PM to make message CJ066 appear. When looking at the source code it looks tlike there is a setting in customizing to be triggered, but I cannot find out where..
    BR
    Ellen
    Edited by: Ellen Ødegaard on Apr 29, 2008 2:08 PM

Maybe you are looking for

  • How can I display all album art of my library in iTunes

    All my music tracks in my library contain the respective album art within their ID3-tags and it is perfectly displayed in the lower left corner window when I select or play a track. What I really would like to do is to browse through my library using

  • Data Import defaulting Null date to system date

    I am trying to import Campaigns using Data Import, and when End Date is NULL it defaults to system date. Is there any way to avoid this default? Even when I don't "map" the End Date, it still defaults it. Thanks!

  • Opening a pdf file in a relative link / local

    Maybe this sounds simple. But I get used to AS2 code to open  a pdf file like the code below: getURL("pdfDocuments/pdfname.pdf","_blank") As I search uncle Google I'm stuck to this as equivalent to getURL in AS2. btn.addEventListener(MouseEvent.CLICK

  • How do you display Roles?

    In the old Enterprise Console, it was possible to display Roles, and see what privileges had been granted to each, and what users had been linked to an individual role. Is it possible to do something similar in SQL Developer? I can write my own queri

  • NAS - wakeonlan?

    I've got a NAS that stays off. My PCs can wake it up automatically on boot-up with a utility. My linux box can wake it up by manually sending a wakeonlan command. Does anyone know if something like wakeonlan or an automatic utility exists for iPad? M