WBS status locked - system allows consumption

Dear Experts ,
I need expert opinion on the following two points.
1. My WBS status is locked. But the system allows consumption of materail (ie 261 movement) against production order assigned  to the WBS
2. My WBS status is locked. But the system allows to create schedule lines against the scheduled agrrement assigned to the WBS.
Due to the above two phenomeneon , the system is allowing comitment & incurrence to happen even for closed WBS.
Are the functionality described above are part of standrad PS process.
If yes, then how to tackle these points. If no, then is there any PS configuration for providing checks.
Thanks & Regards,
Vishal Murmoo

Hi Khader Sir/ PSR
Thanks for the reply .
As suggested by PSR , the user status should be used to prohibit business transcation . In my case for Order Confirmation , Goods Receipts & Schedule delivery .
I made the configuration chnages for user status ( locked), which prohibits all the above mentioned transcation. This user status is mainatined for the concerned WBS .
But still i found that it is actaully not working .The system allows  Order Confirmation , Goods Receipts & Schedule delivery .
against WBS having user staus locked.
Is it that i have missed some configuration.
Need experts suggestions on this matter
Regards,
Vishal

Similar Messages

  • COOIS system status field doest allow drop down list

    hi,
    In COOIS my user is unable to view the drop down list for SYSTEM STATUS. it doesnot allow to see the drop down list with F4 and drop down click.
    Whome do i refer to?
    Regards,
    Sameer Jalal

    Dear,
    I read mentioned note and there are following text under solution:
    Implement the source code corrections as described in the correction instructions.
    when i click on Correction Instruction 771905
    Note :  0001257156 Order information system: Selection according to sys. status
    Correction: 0120031469 1  0000681041
    but there is no text in correction instruction(0000681041).
    FYI... the SP SAPKH60016 is mention in this note while our system have SP SAPKH60020.
    Regards,
    Sameer Jalal

  • About wbs status check ----GR/IR balance check

    hi,dear all
    When I set wbs to "clsd",can system check the purchment order's gi/ir balance of the wbs?(the account assignment of the po is the wbs,the po's goods receive is completed,all commitment is close ,but invoice has been done partially, not complete,the gi/ir balance is not zero.)
    If it can not ,is there any else method can do this?
    thank you!
    maojian

    Hi Jian,
    Since the project is not fully complete, you can use the Status "TECO". This will ensure that no fresh commitments will be allowed. If required you can even use "lock" in the WBS to lock Master data /Account assignment or "all"
    Please follow the following link for various aspects of Status management in Help.sap.com
    Project system --Structure ---Status management ---System Status in WBS.
    Warm regards,
    Srinivas Potluri

  • WBS gets locked

    Hi all,
    I have one Z-program which posts accounting document using function module "BAPI_ACC_DOCUMENT_POST". Program posts no. of documents.
    Also before calling this bapi I am using function module 'STATUS_READ' to read the System Statuses for the WBS element.
    When the program executes WBS gets locked for whole duration of the program.
    For any project management posting screen – for example releasing or changing budgets [CJ30 / CJ32] – people get an error message telling them that person X is already processing the WBS. This message stays in force until the Program finishes.
    Any idea why WBS gets locked? How can we avoid it?
    Regards,
    Umesh

    Hi Umesh,
    Please try BAPI_TRANSACTION_COMMIT and pass WAIT = 'X'. This should solve the issue.
    Thanks
    Anand

  • XML failure with ASN no Process DELIVERY_INFO_GR for ASN in status is not allowed

    Hi All,
    In production , we are having many XML failures while sending inbound delivery to SNC from ECC.
    In SXMB_Moni,  ASN XXXX: Process DELIVERY_INFO_GR for ASN in status is not allowed. Becasue ASN is not exist in SNC but in ECC GR status is complete.
    Please help to resolve the same.
    Regards,
    Sheetal

    Hi,
    Please go the tcode CO02 and click on functions and select the restrict processingand click on unlock
    the reason may be tht some might have locked the produvtion order ,
    hopw it wud have answered ur question.
    rewards if it is useful
    Shawn

  • Change WBS status

    Hello
    I am trying to migrate some statuses from one project to another.
    I am using  BAPI_BUS2054_GET_STATUS for reading the old wbs status and BAPI_BUS2054_SET_STATUS to set the status to the new wbs
    My Problem is that i have several old WBS that have for ex the status REL  AALK RESA SETC  .This result is beeing return in form of 4 lines in the system  status table :
    WBS1   REL
    WBS1   AALK
    WBS1   RESA
    WBS1   SETC
    and when i try to give these 4 lines as parameter to the   BAPI_BUS2054_SET_STATUS  bapi, i get the error that :
    "WBS Element SP/10000XX appears more than once"
    How can i set this status to the new WBS?
    thank you

    Hi,
    you can process only one WBS in each LUW. So you have to call COMMIT after each WBS element not after each WBS element and status.
    Here is a quote from BAPI documentation
    You can call up the BAPI as often as you like until a Logical Unit of
    Work (LUW) is closed with the BAPI BAPI_PS_PRECOMMIT and BAPI COMMIT
    WORK.
    Only one project or WBS element from a project can be processed in a
    LUW.
    Cheers

  • Error  " RFC Status :-  Lock table overflow "in event trace  ( SWEL )

    Hi experts ,
    I will not mention this post as URGENT but you guys can understand the importance as I am in PRD Support of my workflows .
    My Workflow is throughing error in SWEL  , as below   and after error its getting deactivated .
    The workflow is triigering based on the  BO : DRAW and event CREATED .
    Error :  RFC Status           Lock table overflow
    In feedback after error the message is : A system error has occurred in lock management .
    I have resolved the deactivation problem after error  , but   can any body please suggest me  what is the root cause of this error , so that i can try to avoid that error .
    Regards
    Prabhudutta
    Edited by: Prabhudutta Behera on Nov 20, 2008 5:58 AM

    This error I have not faced. i will suggest you to check SWU3 transaction Code and check everything is configured. Also check SM12 and SM58. Also I will ask you to contact the Basis Guys related to this issue. Also check WF-BATCH is having all the authorization required. Try to replicate this from the system where Workflow is working.
    Thanks
    Arghadip

  • Bypassing work status lock in FX Restatement

    Hi,
    We have a requirement to bypass the work status lock when we run an FX Restatement as part of our budgeting process.  I was hoping to achieve this by writing my own BPC Process Type and piggy-backing off standard code.  However, hereu2019s my problem:
    1.  The currency conversion is part of the main consolidation program logic.
    2.  This program calls the main WRITE BACK logic to write the data back to the application once the conversions have been performed.
    3.  The WRITE BACK logic (method cl_ujr_write_back->write_back_int) has a parameter (I_BYPASS_LOCK) which, when set to TRUE, allows the work status locks to be bypassed.
    4.  However, the consolidation program calls the WRITE_BACK in such a way that the parameter is not set, which means the default value is taken, which is FALSE, which means the locks are respected:
    So, from what I can see, my only options are:
    A.  Implement the WRITE_BACK BAdI and use it to bypass the lock in the special circumstance that a currency conversion is being performed (Iu2019m not even sure this is possible u2013 will need to check).
    B.  Create my own version of the Consolidation and Currency Conversion program by inheriting from CL_UJP_CURR_CONVERSION (annoyingly itu2019s a FINAL class) and redefining the method that calls the write back.  The problem with this will be how to get the script logic parser to call my class, instead of the standard class.
    Has anyone faced the same problem and found a solution?
    Thanks,
    Tristan

    Hi Tristan,
    I may be confirming what you already know that it is not possible to bypass the work status in NW version. At one of our implementations, where the customer had OLS 4.2, had a keyword which is used then in a script logic to check the work status code along with the script.
    We had a solution which worked in our case as we have opened up the DM method in work status code 'Submitted' where the managers could run the packages. Not sure if this would also be applicable in your scenario.
    Thanks,
    Sreeni

  • Disable processing status "Locked" for tempaltes

    A template in cProjects has these processing statuses:
    - created
    - released
    - locked
    - obsolete
    I would to deactivate the status "locked".
    Is this possible? If yes, is it also possible if there are already templates that are "locked", or should i "unlock" then before.

    Hi Daniel,
    You can achive this through transaction BS12.
    Select object type DX1 (Project Template). Then Go to Allowed business transaction from the menu bar.
    Untick the business transactions DX07 and DX08.
    The above mentioned steps will decativate lock and unlock status for cProject templates.
    Regards
    Amit

  • How Can I know, Material status does not allow purchase??

    Hi Experts,
    Pls. clarify me that, How Can I know/track the follwoing things? Which tables I hv to see?
    I hv a list of materials, some r good , some r bad. So, I hv to trace out the bad materials depending on the criteria, So, pls. let me know Which tbls I hv to look?
    1) Material does not exist in plant 1500
    2) Material status does not allow purchase
    3) Decimal places on the quantity may not be supported by unit of measure
    thanq

    thanq
    MATNR status:
    In our system the values for MARC-BESKZ are
    E     In-house production
    F     External procurement
         No procurement
    X     Both procurement types
    My requirement: I need to trace the MATNR from matnr_list for Material status does not allow purchase
    So, am thinking to write IF condn as,
    IF my_itab-matnr <> 'F' or my_itab-matnr <> 'X'.
    --> this matnr is Material status does not allow purchase
    ENDIF.
    Am I correct?
    3) Decimal places on the quantity may not be supported by unit of measure
    This can be retrieved from table T006
    I hv seen but, DO NOT UNDERSTAMD THIS TABLE entries, bcoz, there r values of 0 & 1 for the DECIMAL PLACES filed, partcularly for EA unit - devciaml places value is 0?
    pls. clarify,
    thanq

  • Error in budget transfer - wbs is locked

    hi experts, need advise on how to check error exists during budget transfer in CJ34 from level 1 wbs to level 3, error message occured sender wbs  is locked. then when I looked in CJ20n for this wbs status, this is not locked.

    Hi
    " Sender and receiver are in the same hierarchy branch".
    Since you are trying to transfer funds between objects assigned to the same branch of the hierarchy. This not possible with CJ34 t.code.
    Budget updates between objects in the same hierarchy branch are carried out by means of a supplement using CJ37 t.code or a return using CJ38 t.code.
    Try this
    Thanks
    S.Murali

  • SYSTEM ALLOWING TO ENTER WRONG CODING MASK

    Dear Gurus,
    I have created a project ID WITH 2 LEVELS OF wbs AS BELOW
    P/AT11
    P/AT11-LAND
    P/AT11-LAND-CV
    P/AT11-LAND-ME
    But if i later change the 2nd Level WBS from  P/AT11-LAND TO  P/AT11-LNBL and tried to save, the system allowed it to save, where as the 3rd level WBS are still  P/AT11-LAND-CV,
    Finally there is mismatch in 2nd level and 3rd level WBS so system should not allow, is there any setting for this pls guide.

    Kindly check the following thread:
    Making project defination non editable
    Regards,
    Syed Ammar Zaheer

  • EWM - Unable to convert inbound delivery to goods receipt- status 'locked'

    Hello EWM gurus,
    We have configured ECC 6.0 with EWM 5.1. We created a delivery and distributed it to SCM 5.1.
    We are able to convert the delivery notification to inbound delivery. However when we try to convert the inbound delivery to goods receipt we receive the following error message
    "Delivery xxx has status locked( not possible to post)" Message no. /SCWM/GOODS_MOVEMENT026
    Could you please let us know how to resolve this issue
    Thank you,
    Ganesh

    Hello Amit,
    Many thanks for your response. I was able to overcome the above issue after I realized I needed to setup the staging area. Now I have run into a new issue. Below is the error message that I am now receiving. WHSE is the warehouse setup in SCM and so is 300015 which is the party entitled to dispose and F1 is the stock type ( unrestricted putaway). All these are in SCM. Not sure where this is to be mapped in ERP
    Regards
    Ganesh
    Could not determine ERP stock data for: WHSE 0000300015 F1
    Message no. /SCWM/ERPINTEGRATION105
    Diagnosis
    The transaction you executed causes a stock posting in the ERP system. For this, the system must determine the stock data for the ERP system (such as material, plant, storage location) from the EWM data (such as material, party entitled to dispose, stock type).
    For the following field, the system could not determine any ERP data: WHSE 0000300015 F1

  • WBS status 'REL' & 'BUDG'

    Hello,
    The requirement is not to release level 1 WBS until it has been budgeted. How this can be achieved?
    Regards,

    Hi,
    I implemented the same requirement:
    Create a user status that is set automatically at creation of the WBS.
    Add the next control steps for the newly created user status:
    - The user status must prevent the business transaction for releasing the WBS.
    - The user status must be reset automatically when the WBS is budgetted (system status BUDG at WBS).
    Now the WBS element can only be released if a budget is maintained for the WBS.
    Regards,
    Paul

  • WBS status -ISBD Insufficient budgeting

    Dear All,
    Please explain WBS status. "ISBD Insufficient budgeting"
    Regards,
    Vishal

    Dear Nitin,
    In our case of Insufficient budgeting  we have transcation as
    Collective Entry of Confirmations  &
    Goods Withdrawal
    Could you explain what does this mean.
    Does it mean that the cost booking during these two transcation has exceeded the alloted budget of the corcerned WBS.
    If it means that only, then being Availability control active in the system, how has this default occured.
    Please suggest .
    Regards,
    Vishal

Maybe you are looking for

  • Paguei o Adobe muse CC, mas não passo da tela de Avaliação

    Eu paguei uma assinatura do adobe muse CC, mas quando eu abrir o programa ele diz que a licença gratuita expirou. Eu clico em LICENCIAR ESTE SOFTWARE, aparece a mensagem parabéns por comprar, mas depois volta para a tela de AVALIAÇÃO, como se o meu s

  • ACCEPT

    Hi everybody! Does the ACCEPT command work in a stored procedure or in a compiled PL/SQL procedure??? URGENT!!!! Hope ur able to help me! thomas

  • Need Unlock code for 5230 3G

    Hi,           My friend has gifted me Noika 5230 3G bought from UK. Problem its locked. My IMEI No.: Can you please assist me in this matter. Appreciate your response. Thanks, Kayshap Moderator's Note Post Editted PM Sent to user "Please be informed

  • Create test env from production system

    Hi, Please sorry, I am new in this area of Oracle Applications 11.5.10 and I need help in couple of questions. We have production system with Oracle Applications 11.5.10, APPS tier on 32bit Red Hat Linux EE 4 server, and 10.2.0.3 DB tier on 64bit Red

  • Seeking a good quality Slide show application recommendation!

    I am seeking a good slide show application that has really nice additions like transitions, Ken Burns effect that will then export the finished slide show to a Quicktime movie. As always thanks in advance for reading and replying to my post, Sebastia