What are the additional steps for SRM refresh as compared to ECC refresh? (Windows and MS SQL)

Hi,
I need to know if there are any additional pre steps or post steps for SAP SRM system refresh as compared to SAP ECC refresh? Windows/MS SQL

Hello Rajat,
You have to change all the data on the middleware configuration tables to point to your new ECC system. I don't remember exactly which tables are but you can take a look to this:
http://www.sdn.sap.com/irj/scn/go/portal/prtroot/docs/library/uuid/309258e9-0da2-2d10-b598-bf27edb56a31?overridelayout=t…
It explains how to do the Middleware Configuration between SRM and ECC. You should also do a master data transfer from ECC to SRM.
Best regards.

Similar Messages

  • What are the config steps for contract mass change and quota arrangement?

    Hi friends
    what are the config steps for contract mass change and quota arrangement?
    Regards
    Raj Kumar

    Process Flow
    The mass change process consists of four steps. You navigate between these steps by choosing the Next and Back buttons located at the bottom right-hand corner of the screens.
           1.      Search for contracts
    You search for and select the contracts or the contract hierarchy that you want to change.
    Contracts that have the status Closed cannot be changed.
           2.      Define mass changes
    You specify the changes you want to make.
    You make changes at header data level and at item data level by choosing the relevant change methods. A green tick appears next to each change parameter so that you can see where changes are already active.
    Once you enter this step, the documents you have selected to be changed are locked so that other users cannot make changes to them until you are finished with this process.
           3.      Simulate mass changes
    Here you can perform a trial run of your mass changes. This simulation step is optional.
    We recommend that you perform this step so that you can check how the change methods you have chosen will be processed by the system.
    You receive status messages about the change methods for each contract and can quickly see whether any errors arise in connection with the proposed changes at this stage. From this step, it is easier for you to go back and correct the error than after applying the changes.
    Background processing
    The system processes the changes in the background.
    If there are a large number of contracts to be processed, this step could take some time to complete. In this case, you can leave the transaction so that you can, for example, carry out other tasks in the meantime.
    The system sends you an e-mail once the simulation step is complete. The e-mail contains a link to the relevant screen in the application so that you can return to it when it is convenient for you to do so. If you have left the SRM application, you can only return via this link.
    Here you can see the status of the changes and, if necessary, you can correct any errors by going back to the Define mass changes step.
    The messages that you receive in the simulation step are not confirmation that a change has been performed. They simulate the messages you get after you apply the changes. You must complete the final step of the mass change process and apply the changes before they take effect.
           4.      Carry out mass changes
    Here you apply the changes to the contracts.
    You cannot reverse this step, which is why we advise you to perform the simulation step beforehand.

  • What are the config steps for contract hierarchies and vendor hierarchies?

    Hi friends
    what are the config steps for contract hierarchies and vendor hierarchies?
    Regards
    Raj Kumar

    Contract hierarchies
    A function that enables users authorized to create a purchasing contract to define relationships between super- and subordinate contracts.
    A contract hierarchy consists of one or multiple contracts and is subject to the following rules:
    The top node of the hierarchy cannot have a superordinate contract
    Every contract except for the top node has exactly one superordinate contract
    Every contract can have none, one, or multiple subordinate contract(s)
    A contract can be part of no hierarchy or exactly one hierarchy
    Note:Contract hierarchies are only available for purchasing contracts. They are not available for global outline agreements.
    You can activate this from SRM Server> Cross application settings>Activate Hierarchies for Product Categories, Vendors, and Contracts.
    Note:
    These hierarchy functions should not be reset once they have been activated.
    Similiarly you can do this for Vendor Hirerachies.
    Please visit link for more details: http://help.sap.com/saphelp_srm50/helpdata/en/43/2022b83fbc2be8e10000000a11466f/content.htm
    Thanks

  • What are the basic steps for creating a content repository?

    I am trying to create a document store on a file system (fsdb) that will hold files that are ftp's to that location. Is this possible using KM? If so, what are the basic steps for creating a file system repository and using it through KM? I have found stuff on help.sap.com but that only tells you what each component does not what actual steps need to be taken to setup KM, such as user rights , creating an entry point, so that all of KM is not visible, etc...
    If anyone knows of any guides that show a step by step process that would be great too.
    Thanks
    Paul

    Hi Paul
    First of all you need to create a new repository
    Suppose you want to add all the documents under folder Paul under C: Drive
    (Even you can put whole documents of C: drive into Paul)
    Navigate to System Admin -> System Configuration -> Knowledge management -> Content Management -> Repository Manager -> File System Repository
    There you can create a new directory by clicking on button New
    Give the parameters as follows :-
    Name               :           Anything you like
    Description       :           Anything you want
    Prefix (must start with /)  :  Probably same as your repository name like \Paul
    Lookup mode : caseless
    Root Directory   :  C:\Paul
    NOTE:  This is the trick. You need to give the proper path means folder path which you want use as repository)
    Repository Services  :  Any services you want
    Property Search : Managercom.sapportals.wcm.repository.manager.generic.search.SimplePropertySearchManager
    Security Manager         :           AclSecurityManager
    ACL Manager Cache   :           ca_cm_rep_acl
    The save it
    Now see whether the same repository is coming under KM Content or not, if not may be after restart it will come.
    I think the above information will help you. If still you have problem, please feel free to contect me.
    Regards,
    Chamkaur

  • What are the installation steps for Oracle Fusion HCM

    Hi all
    I will like to ask, what are the installation steps for Oracle Fusion HCM as well as can it work on Windows or only on virtual machine?
    Thanks

    If you're looking to install Fusion HCM, your best bet is to install on linux, eg, Oracle Enterprise Linux. It's up to you whether you put that in a Virtual Machine or not. I don't think Windows is an available platform for Fusion Apps at the moment, although am prepared to be corrected if you find anything to the contrary!
    If you're looking to do an install on your own PC/laptop, you're probably out of luck - you'll be needing around 128GB of RAM. Check out this post:
    http://onlineappsdba.com/index.php/2011/11/02/fusion-applications-128-gb-memory-and-500-gb-disk-space-are-you-ready/
    Atul has also posted some good stuff on installing:
    http://onlineappsdba.com/index.php/2011/06/15/install-oracle-fusion-applications-in-10-steps/

  • What are the correct steps for installing Oracle Entitlement Server SSM?

    Can somebody explain what are the correct steps to install OES SSM 10.1.4.3? I have installed OES admin 10.1.4.3 and applied the CP2 patch. it is allowing me to open Entitlement Administration, where I can define the policy.
    Is it sufficient to have this Entitlement Admin to call the policy from BPM? Do I need a SSM ?
    When I try to configure Java SSM using ConfigTool.bat -process myssm_config.properties I am getting the following error
    Is Admin in the same BEA-HOME as SSM: [default: Yes]:
    Give the location of the Admin: c:\bea\ales32-admin
    Enter the identity directory name which will be used: [default: CoESSM_dir]:
    Enter the root node which will be used to create resources: [default: //app/policy/CoESSM_app]:
    Checking if default ARME port is free: 8000
    Generating policy files based on templates ...
    Checking if SSM instance already present
    Checking to see if SSM ARME port is free.
    Checking JDBC parameters...
    Checking to see if asipassword was run...
    2010-03-15 18:06:59,295 [Main Thread] ERROR com.bea.security.SsmConfigTool.AlesConfig - You need to run asipassword first
    2010-03-15 18:06:59,295 [Main Thread] ERROR com.bea.security.SsmConfigTool.ConfigurationTool - Error making changes: You need to run asipassword first
    I have tried running the asipassword utility, but still it gives the same error. Please let me know what am I doing wrong?

    Yes I have explored this pdf...but it doesn't tell how to use the policy from the BPM. My question is if I want to use the policies from BPM, then do I need to install the SSM ?
    If yes, what are the correct steps of installation ?
    I am getting the errors while configuring the Java SSM.
    Is Admin in the same BEA-HOME as SSM: [default: Yes]:
    Give the location of the Admin: c:\bea\ales32-admin
    Enter the identity directory name which will be used: [default: CoESSM_dir]:
    Enter the root node which will be used to create resources: [default: //app/policy/CoESSM_app]:
    Checking if default ARME port is free: 8000
    Generating policy files based on templates ...
    Checking if SSM instance already present
    Checking to see if SSM ARME port is free.
    Checking JDBC parameters...
    Checking to see if asipassword was run...
    2010-03-15 18:06:59,295 [Main Thread] ERROR com.bea.security.SsmConfigTool.AlesConfig - You need to run asipassword first
    2010-03-15 18:06:59,295 [Main Thread] ERROR com.bea.security.SsmConfigTool.ConfigurationTool - Error making changes: You need to run asipassword first
    I have tried running the asipassword utility, but still it gives the same error. Please let me know what am I doing wrong?

  • What are the highlevel steps for changing to a new R/3 backend in SRM 7.0?

    Hi,
    I need confirmation of the highlevel steps required for changing to a new R/3 backend system in a SRM 7.0 server?
    Our scenario is that we want to switch from an old R/3 backend to a new R/3 backend (both ECC 6.0). From what I can read from SAP Note 995771 the following steps would have to be conducted, only I don't know if all are valid or complete for SRM 7.0 as well?
    1. Create new RFC connection for new R/3 backend system in SM59 ( in SRM system.)
    2. Create new RFC connection for SRM system in SM59 (in new R/3 backend system).
    3. Define Logical System for the new R/3 backend system (in SRM system).
    4. Define Logical System for the SRM server (in new R/3 backend system)
    5. Define System Landscape for new Logical System and RFC connection (in SRM system).
    6. Adjust settings in Define Backend system for Product Category. (in SRM system)
    6. Run BDLSS (in SRM system)
    7. Run BDLSS (in new R/3 backend system).
    8. Control BDLSS results via report ZSCAN_LOGSYS (in SRM system)
    9. Control BDLSS results via report ZSCAN_LOGSYS (in new R/3 backend system)
    10. Maintain ALE-Distribution Model and Distribute Views for new R/3 backend. (in SRM System)
    11. Verify ALE-Distribution Model and Distributed view for SRM system (in new R/3 backend system)
    12. Generate/Control Partner functions in WE20 for IDOC processing (in SRM System)
    13. Generate/Control Partner functions in WE20 for IDOC processing (in new R/3 backend system)
    14.Adjust the site attributes in transaction SMOEAC (in SRM System)
    15. Adjust Table CRMRFCPAR (in new R/3 backend system)
    16. Adjust Table CRMCONSUM (in new R/3 backend system)
    17. Adjust Table CRMSUBTAB (in new R/3 backend system)
    18. Adjust Table CRMPAROLTP (in new R/3 backend system)
    19. Adjust Table SMOFPARSFA (in SRM system)
    20. Run report RHOMATTRIBUTES_REPLACE to replace attributes still having the old logical system assigned in the organization model.
    Are there any relevant steps missing? (I will of course take care of master data, number ranges etc)
    Thanks in advance for your responses,
    BR Jakob

    Hi,
    Solution Manager has some documents. or check help.sap.com.
    http://help.sap.com/saphelp_nw70/helpdata/en/39/a1bb5c4c0d4ab4a417e87ef35f1efa/frameset.htm
    When you create a custom task, you should add the task ID to the UWL configuration.
    Portal, Administration -> System configuration -> UWL Administration -> Click to Manage Item Types and View Definitions. Select Configuration "com.sap.pct.srm.core"; and download the configuration. Edit the configuration copy the task block and add new task ID. Upload the configuration.
    Regards,
    Masa

  • What are the configuration steps for cheque process

    hi,
    sap gurus,
    what are the steps for cheque process if our customer wanted to pay by the mode of cheque.
    regards,
    balaji.t
    09990019711.

    Hi,
    Kindly go to OVFD where in you will have to create a new payment procedure if it's not there in standard SAP. Then, you will have to assign this new payment guarantee procedure in customer in sales area data>billing document screen. As far as standard SAP is concerned you will be able to assign the payement by cards in customer master, but for DD process I think you will have to create it.
    Hrishikesh

  • What are the different steps for  costing related to repetitive manufacturi

    Hi PP guys
    can any one explain the different steps for costing in repetitive scenario as compared to discrete scenario what is the major difference
    thanks
    shaik

    Dear Michel,
    !.In REM scenario Product cost collector is required for all the products for which production booking is
    to be done.
    2.For each production version created a product cost collector will be created in KKF6N.
    3.Without a product cost collector production confirmation can not be done in MFBF.
    4.Product cost collector is the cost object in REM scenario.
    5.Once after creating material master,BOM,work center,rate routing,aproduction version the next steps
    is creating product cost collector.
    6.While creating the PCC,the system creates a preliminary cost estimate nothing bu the sum up of the
    BOM and dare routing cost.
    7.Either a prelimnary cost or a standard cost estimate can be used for doing the production
    confirmation in MFBF as per the REM profile assigned.
    8.Standard cost estimate can be done in CK40N and this costs gets updated in the material master.
    9.For every production confirmation made in MFBF the costs gets accumulated in the respective PCC.
    10.the variances can be settled periodically as per the business requirement.
    Regards
    Mangalraj.S

  • What are post installation steps for SOA 10.1.3.5 patchset on Windows

    Hi all ,
    what are the post installation steps in windows after applying SOA patchset 10.1.3.5 on 10.1.3.1
    Thanks,
    Durga

    Hi 924979,
    may I ask cause I have same exactly this issue on solaris 10 and what do you mean with :
    edit the (two) opmnctl scripts to change "tr" to "/usr/xpg4/bin/tr"   ?
    Need your suggestion since I change PATH environment variable but still error and The installer cannot find the system application ascontrol ("opmnctl status -app") in the OC4J instance. All system applications should be present even if they are in a stopped or non-routable state. This is generally due to a situation where OPMN has been shutdown ... bla bla  bla .. (stop in 83%)
    need advise
    Regards,
    Thanks

  • What are the Major Step for Completely Avoiding the Server Problem?

    Like Ora-01033,Ora-12514.

    leen wrote:
    Ora-12514 : is listener error you need to make sure is running up and no error in listener.log
    any database error can be avoided by monitor your database everyday .
    It's possible to check daily that listener is running properly. Please, Don't mind can you provide the steps.The steps for what? Checking your listener? Just try to make a connection that uses it. For example.
    sqlplus scott/tiger@orclBut believe me, once your listener and clients are configured, the listener will 'just run' and NOT be a problem. I've been an Oracle DBA since 1995 and I've only seen ONE listener failure. And that was only when a friend at another company called to ask about a problem HE was having.

  • What are the correct steps for installing SP1 over Sharepoint 2010

    Hi,
    I have SharePoint 2010 (Release To Manufacturing) environment and am planning to to upgrade it to SP1. May I please know the correct steps
    to install SP1 on to my environment(2WFE + 2APP servers & 64 bit OS).

    SP2 provides key updates and fixes across our servers, services and applications including security,
    stability, and performance enhancements and provides better compatibility with Windows 8, Internet Explorer 10, Office 2013, and SharePoint 2013.
    also your Sharepoint is upto date version, you will get all the functionality which
    you will losing since you are prior to SP1.
    i.e Site Recycle bin,
    Content Deployment fixes, . you can go throw all the kB articles which will tell you what fixes in it.
    http://blogs.technet.com/b/stefan_gossner/
    Please remember to mark your question as answered &Vote helpful,if this solves/helps your problem. ****************************************************************************************** Thanks -WS MCITP(SharePoint 2010, 2013) Blog: http://wscheema.com/blog

  • What are the pre requisites for SAP SRM7.0  DB Rrefresh?

    Hi,
    What are the pre requisites for SRM DB Rrefresh?
    Thanks

    Hello Peter,
    When it comes to DB refresh you need to know what all the client dependent data which needs to be retained.
    For example you need  RFC connections, Variants, User master etc.
    As a pre task of Database refresh you may need to export the tables which are related to this so that once the database is refreshed you need to import them.
    Ensure the proper backup of production database is available. Also check all the STMS configurations which need to be retained again.
    Make sure that you need to have enough disk space which can accommodate your production data in to the pre production system.
    These are some of the general consideration one needs to have but again it depends on the environment on which one runs SAP systems.
    Regards
    Vivek

  • What are the main steps to be taken care while doing recording for LSMW

    Hi,
    I am facing problem in LSMW.
    Can anybody suggest me that What are the main steps to be taken care while doing recording for LSMW for recording mm01 ?
    thanks'
    naresh

    Hi,
    Recording in LSMW is similar as SHDB.
    in LSMW after you give Project-Subproject and Object.
    1)Go to-> Maintain Object Attributes -> double click
    2)Press Display/Change Button at top left to make editable mode.
    3)Select radiobuton -> Batch Input -> Give Recording name say Z_mm01
    4) Click the Recording Overview boton on right -> Give TCode which u want to record....
    Rest refer the Document link attached.
    Please find the links to various threads on the same.
    Re: LSMW - Using a BAPI
    BAPI, IDOC in LSMW
    Upload the data in LSMW using BAPI
    This one is the most complete document for the same
    http://sapabap.iespana.es/sapabap/manuales/pdf/lsmw.pdf
    http://service.sap.com/lsmw.
    Regards
    Kiran

  • Once I receive my Network Access Code(N.A.C.) for iphone 5 what are the next steps I follow to unlock my phone from vodafone to use on another network???

    Once I recieve my Network Access Code(NAC) for my iPhone 5, what are the next steps I follow to unlock it from vodafone to use on another network???
    I have my other nano sim ready and waiting to port my number to it, but im just waiting on vodafone to email me the NAC code, which i checked up that I was eligible for!!!

    Ok many thanks for telling me this BUT 1 last thing, once vodafone get back to me then is it just a matter of plugging my iphone into itunes and letting it sync? Like will a message be displayed or anything on screen letting me know or confirming that the phone has been unlocked...???

Maybe you are looking for

  • Stock Report for selected posting period!

    Dear All, Is there any standard program on Stock Report for selected posting period, which shows PRODUCT| UNITS| OPE.STOCK| PURCHASE| SALES| CLO.STOCK| I want report on this, anybody can help me out on the same. Or is there any standard report. Need

  • The privacy option doesn't work in 5.0: There's no notification given when multiple tabs are closed.

    The privacy option in 5.0 doesn't work. When exiting Firefox with multiple tabs open, no notification is given... How can I go back to Firefox 4? I had the google toolbar when I had firefox 4... I upgraded to 5.0 and it still works... My friend tried

  • KDE 4.2 and dual monitor setup

    Is there any way to make KDE 4.2 understand which monitor is my primary one? It acts like mye left monitor(my tv) is the default monitor, but my right monitor is the which is the primary one. Last edited by Roberth (2009-01-29 23:12:19)

  • Doubt on FILE to RFC & PROXYS

    Hi everybody,                     I'm able to solve most of my doubts by this forum, thankz to everybody who assisted me.Here are some simple doubts plz give solutions to them as many as possible               1.In my FILE to RFC scenario I'm using B

  • Reverse the confirmation

    Hi All, How can i change the specific Order Type for the purchase order as the default one. instead of the standard one given by sap , system should pick custum one as default. While tying to convert the PR to PO in the ME59 , system pick the sap sta