What Project Server 2010 and 2013 make possible in terms of timesheeting, "freezing" timesheets and expenses.

We have recently gone live on a Timesheeting system based on Project Server 2007.
I now want to know how the system could be improved using 2010 or 2013.
But first you would need to know our requirements and what we did in 2007 ...
We needed the GUI of My Timesheets and the Admin tasks but approvals based on what project/task it was. Ie PM approval not line management approval.
We managed it by entering timesheets in My Timesheets, importing to My Tasks and then regularly picking up published Task Updates in the Table EPMAssignmentByDay and capturing them in an added table in the Reporting database. We had a few key requirements
which required some customisation:
Need to capture the timestamp of when approved. to nearest hour. plus approver ID (ie status manager) and the cost centre at that time of the resource (they can move sometimes)
Need to be able to freeze approved records - so that after that point they can't be changed. And financial reports can run and know the data won't change.
2 - is a headache for us. There is no mechanism to stop a user from trying to update frozen records. We currently have to just ignore the updates
We also wanted expenses - but that wasn't possible in 2007.
The new "Single Entry" mode looks like it will make life easier for the users.
But:
Is there any concept of timestamping the approvals?
Is there any concept of freezing the approved data?
The new Timesheet user-defined fields. Could these be used to add an expense amount and comment?
I now know my way around the 2007 Reporting Database (at least parts of it) - but haven't found documentation to tell me what changed at the level need to answer the questions above.
Thank you
MikeCro
MikeCro

One of my colleagues pointed me to the MSFT paper "Managing timesheets in Microsoft Office Project Server 2007"
It tells me that there is a field called "Processed" in the timesheet tables in 2007.
It also says "This block is designed to indicate when a timesheet has been transferred to a third-party system. 
Customers may also use this field to block the timesheet from being recalled." - which feels like MSFT are trying to give the hooks I need. This could enable me to close off changes - at least at timesheet level if not timesheet line level.
But which field is it in which database table?
I also notice that there is a tantalising comment for one value of the enumeration TimesheetEnum.Status in EPM 2013:
PendingSubmit: Value=5. Pending submission; used when one or more timesheet lines are pending approval after a timesheet is submitted and project manager coordination is required.
This sounds very like it would support what we want: each of the lines in a timesheet week to be approved by the different approvers and then lock the timesheet.  (Even better would be to lock a row after PM has approved and a weekly processing
day reached)
Can anyone point me to this level of detail of what is in project Server 2013. or is this in 2010 as well.
MikeCro
MikeCro

Similar Messages

  • Upgrading from Project Server 2010 to 2013 ConvertTo-SPProjectDatabase gives error (Convertto-SPProjectDatabase : Action 15.0.38.0 of Microsoft.Office.Project.Server.Upgrade.PublishedDatabaseSequence)

    Getting the error on subject line when I try to upgrade from Project 2010 to 2013

    Hi,
    Do you get and error when the command is executed or when you try to start the execution (the command is not valid)?
    If you get the error when you try to start the execution, I would suggest re-typing the command and make sure all parameters are valid.
    Please give us the error details if you get the error when the command is running
    Paul

  • Error when navigating to the PWA root site for Project Server 2010

    I received a nice Happy New Year from my Project Server 2010 today. I tried to navigate to the root site and received the following error.
    Error
    The base type 'Microsoft.Office.Project.PWA.PJBaseWebPartPage' is not allowed for this page. The type is
    not registered as safe.
    Troubleshoot
    issues with Microsoft SharePoint Foundation.
    Correlation ID: b1898d3e-5d41-4ed4-9466-1d7775714293
    Date and Time: 1/3/2012 10:54:53 AM
    I did some searching and found that it could be one of 2 things
    1.      
    App Pool security
    2.      
    Custom Master page.
    All the sub-sites seem to work fine, so I went with option 2. I changed the Master page of the root site back to v4.master and everything works fine again.
    So far the only solution I found to allow for using a Custom master page is to modify the web.config as suggested here:
    http://jimecox.wordpress.com/2011/05/03/project-server-2010-changing-master-page/
    My custom master was working fine for the past 6 months, so I’m not sure why I need to make this new update.
    Anyone else run into this recently with another fix? The changes seem to be opening the security on the Project web app a bit or am I wrong?
    Thank you in Advance!

    Looks like I fixed this by changing the Master page back to the OOTB version v4.master here:
    https://<pwa url>/_Layouts/ChangeSiteMasterPage.aspx
    Then I navigated to the PWA root site.
    https://<pwa url>/default.aspx
    Finally changed the master page back to my custom one. Error gone!

  • Project Server 2010 - Assigned tasks not visible in PWA

    Hi,
    When I enter an issue on a project site, the assigned issue is not visible in the PWA under Issues & Risks.
    Based on this link (http://social.technet.microsoft.com/Forums/en-US/f5abd024-3c9a-47f8-a7cb-7743fafebf2b/project-server-2010-cannot-see-assigned-issues-and-risks) I have tried to solve it however without success.
    In the queue jobs I have the following error details:
    General
    Reporting Wss list sync failed:
    ReportingWssSyncListFailed (24018) - 1100. Details: id='24018' name='ReportingWssSyncListFailed' uid='6c8a0779-3c9f-4d25-a81c-04d69d6fce1d' SPListType='2136b7a0-03b9-4547-8b2d-c66497accd08' Error='1100'. 
    ReportingWssSyncListFailed (24018) - 1101. Details: id='24018' name='ReportingWssSyncListFailed' uid='1573855e-b176-44cc-bf92-8959d167f8fe' SPListType='2136b7a0-03b9-4547-8b2d-c66497accd08' Error='1101'.....................................
    Reporting message processor failed:
    ReportingWSSSyncMessageFailed (24016) - RDS failed while trying to sync one or more SP lists. The RDS queue message will be retried.. Details: id='24016' name='ReportingWSSSyncMessageFailed' uid='839ed0b8-6b8c-4bd5-bfbe-540349c1f27a' QueueMessageBody='ProjectUID='2136b7a0-03b9-4547-8b2d-c66497accd08'.
    ForceFullSync='False'. SynchronizationType='All'' Error='RDS failed while trying to sync one or more SP lists. The RDS queue message will be retried.'. 
    ReportingWSSSyncMessageFailed (24016) - RDS failed while trying to sync one or more SP lists. The RDS queue message will be retried.. Details: id='24016' name='ReportingWSSSyncMessageFailed' uid='b0e773af-5cc3-4965-85b3-a4d8050e86f5' QueueMessageBody='ProjectUID='2136b7a0-03b9-4547-8b2d-c66497accd08'.
    ForceFullSync='False'. SynchronizationType='All'' Error='RDS failed while trying to sync one or more SP lists. The RDS queue message will be retried.'............................................
    Queue:
    GeneralQueueJobFailed (26000) - ReportingWSSSync.WSSSyncMessageEx. Details: id='26000' name='GeneralQueueJobFailed' uid='07edaa28-647c-4dee-974e-06f47e4b4e40' JobUID='899bd048-2c19-4176-bd6c-1b45b8379a40' ComputerName='NLHGOL7FPR' GroupType='ReportingWSSSync'
    MessageType='WSSSyncMessageEx' MessageId='1' Stage=''. For more details, check the ULS logs on machine NLHGOL7FPR for entries with JobUID 899bd048-2c19-4176-bd6c-1b45b8379a40.
    As I understand this error could be due to a mismatch between the fields that are 'standard' in the project server and fields that are op the project site.
    If the reporting database could not sync, will consequently also the issues not be visible on the PWA??
    Any suggestions how to solve this?
    Regards,
    Dirk

    Hello,
    Yes, if the Issues & Risks are not being synchronised to the Reporting database then this will impact the issues & risks appearing on the PWA homepage reminders web part. See this post on how the data gets to the Reminders web part in Project
    Server 2010:
    http://pwmather.wordpress.com/2012/07/13/projectserver-active-issues-and-risks-on-pwa-reminders-web-part-ps2010-sp2010-sharepoint/
    The error you are seeing is probably caused by the default Issue or Risks columns being edited or removed from the Issues or Risks lists. It might be worth taking a look at this post:
    http://pwmather.wordpress.com/2011/06/20/project-server-2010-project-site-default-fields/
    Paul
    Paul Mather | Twitter |
    http://pwmather.wordpress.com | CPS

  • Project server 2010 What are the number of Custom fields and views allowed?

    How many customizations are permitted in Project Server 2010?
    Thanks in advance

    Hi
    new findings on that issue...
    There is an article for Project Online that speaks about limits for reporting: https://support.office.com/en-US/Article/Project-Online-software-boundaries-and-limits-5a09dbce-1e68-4a7b-b099-d5f1b21ba489?ui=en-US&rs=en-US&ad=US
    Apart from that you will have an issue if you like to upgrade to Project Server 2013. When trying to convert the 2010 databases to a 2013 database a SQL stored procedure will fail if you have more custom fields than fit into the UserViews.
    Error message will be something like this:
    System.Data.SqlClient.SqlException (0x80131904): INIT METADATA ERROR!  At least one mismatch found between SQL schema for view MSP_EpmProject_UserView and reporting metadata.  Call to MSP_Epm_CheckIntrinsicAttributes failed for Projects  INIT
    METADATA ERROR.    
     at System.Data.SqlClient.SqlConnection.OnError(SqlException exception, Boolean breakConnection, Action`1 wrapCloseInAction)    
     at System.Data.SqlClient.TdsParser.ThrowExceptionAndWarning(TdsParserStateObject stateObj, Boolean callerHasConnectionLock, Boolean asyncClose)    
     at System.Data.SqlClient.TdsParser.TryRun(RunBehavior runBehavior, SqlCommand cmdHandler, SqlDataReader dataStream, BulkCopySimpleResultSet bulkCopyHandler, TdsParserStateObject stateObj, Boolean& dataReady)    
     at System.Data.SqlClient.SqlCommand.FinishExecuteReader(SqlDataReader ds, RunBehavior runBehavior, String resetOptionsString)    
     at System.Data.SqlClient.SqlCommand.RunExecuteReaderTds(CommandBehavior cmdBehavior, RunBehavior runBehavior, Boolean returnStream, Boolean async, Int32 timeout, Task& task, Boolean asyncWrite)    
     at System.Data.SqlClient.SqlCommand.RunExecuteReader(CommandBehavior cmdBehavior, RunBehavior runBehavior, Boolean returnStream, String method, TaskCompletionSource`1 completion, Int32 timeout, Task& task, Boolean asyncWrite)    
     at System.Data.SqlClient.SqlCommand.InternalExecuteNonQuery(TaskCompletionSource`1 completion, String methodName, Boolean sendToPipe, Int32 timeout, Boolean asyncWrite)    
     at System.Data.SqlClient.SqlCommand.ExecuteNonQuery()    
     at Microsoft.Office.Project.Server.Data.SqlSession.ExecuteNonQuery(SqlCommand command)  ClientConnectionId:21f11abd-7388-48a0-a029-b5161fcb2dc8
    Workaround for the issue (UNSUPPORTED !!!!!!)
    Execute the Convertto-SPProjectDatabase script. Now you need to be fast or well prepared. You need to find the MSP_Epm_CheckIntrinsicAttributes stored procedure. Execute an ALTER statement for it and change the last lines of code to something like this:
    LblError:
       PRINT @ErrorMessage
        --changed RETURN code if an error occurs to be able to proceed with migration 
        --RETURN 1
         RETURN 0
    END
    I hope that helps someone out there - when I came across the issue last night, a google query returned nothing for INIT METADATA ERROR....
    Regards
    Christoph
    Christoph Muelder | Senior Consultant, MCTS, MCSE | SOLVIN information management GmbH, Germany

  • Need solution to make changes in existing project sites in Project Server 2010 environment

    Dear Folks,
    Hope you all are doing good and ready to give a way for this requirement. :)
    In project server 2010 environment, I am using InfoPath documents library, Issues, Risks etc in each and every project sites.
    Say, after creation of 100 projects/project sites, I have got a requirement to make some changes in the InfoPath document library and in Issues, Risks list, so I have decided to use the following solution which is actually weird:
    Make the changes in InfoPath document library, Issues/Risks list for 1 of the project site and save that site as template and associate it with running EPT.
    Then, delete the existing project sites (after taking backup) and start recreating it from PWA/Server Settings/ Operational Policies/ Project Sites, so that it will take the latest template. But, seems like it is time taking and handy and actually it's not
    working for some of the projects.
    Request all of you to provide some solution for this.
    Ask more, if my explanation is not clear.
    Regards,
    Shravan

    Hello,
    Regarding mass deleting and recreating Project Sites via the PSI, firstly delete the project sites then run the following PowerShell script to bulk create project sites:
    https://gallery.technet.microsoft.com/Bulk-create-Server-Sites-784f7b29
    I have got a script that bulk deletes projects but this is not published as this could be a dangerous script to run if you did know what to update etc. To give you an idea of how to delete project sites via the PSI see a code snippet below:
    $EPMTYGUID = [system.guid]::empty
    $projectOwnerID = 'd6a0a720-12ac-e211-93f9-00155d153dd4'
    $ProjectList = $svcPSProxy.ReadProjectStatus("$EPMTYGUID","PublishedStore","", "0").Project | format-table proj_uid -hidetableheaders | out-string -stream
    foreach ($projectUid in $projectList)
    if ($projectUid -ne "")
    $projectsforDeletions = $svcPSProxy.ReadProject($projectUid, "PublishedStore").Project | where {$_.projectOwnerID -eq $projectOwnerID} | format-table proj_uid -hidetableheaders | out-string -stream
    foreach ($projUid in $projectsforDeletions)
    if ($projUid -ne "")
    $svcWSSProxy.DeleteWSSSite($projUid)
    Write-host 'Project UID for deleted site' $projUID
    That particular example deletes the project sites for a particular project owner, you could easily modify that to remove the project owner filter if needed.
    Regarding your query about having to delete the project sites to get the changes to take affect, there is no easy option to get the issues and risks list changes to filter though, this would either be manual on each existing site or using code to iterate
    through each existing site and apply the changes programmatically. Depending on if you used site collection content types to set up the Issues and Risks lists, it might be simple to add a new column etc. as you could do this centrally and it will cascade
    down. If you didn't use content types and or its view changes etc. this is a per site change that can be manual or programmatically done. The same applies to the document library, if this was set up using a site collection content type, the changes can
    be modified on the content type and cascaded down. If the library was set up with just a library that used local columns / templates then it will be a per site change - the same as the issues and risks.
    The company I work for (CPS) does have a site sync tool that will programmatically update existing sites based on a specified site so I know it is all possible to do in code!
    Paul
    Paul Mather | Twitter |
    http://pwmather.wordpress.com | CPS |
    MVP

  • Project Server 2010 compatibility with IE11 and Windows 8.1

    Hi All!
    Maybe a silly question since compatibility is always asked about older versions, but here is my question:
    Is Project Server 2010 compatible with IE11 and Windows 8.1?
    I personnaly tested with IE11 and it seems to be ok. All views and pages can be opened with IE11.
    But what about windows 8.1? 
    Has Microsoft done any communication about this?
    Thanks in advance for your helps.
    Guillaume.
    Guillaume Rouyre - MBA, MCP, MCTS

    I am seeing a minor issue with the timesheet grid after users are upgraded from IE8 to IE11.
    We are using Project Server 2010 with SP1 and Oct 2013 CU.
    When some users (using IE11) switches between filters or views in the Timesheet page, the grid shrinks making to content un readable.  The only way to get it back is to refresh the page. After a refresh, the grid returns to normal size, but the pane
    divider is too far to the left and always must be dragged to the right in order to see the task names in the left grid. 

  • Project Server 2010 - Modification date and name of the person who made the last change in the project

    Hello everybody
    I'm with a doubt.
    I got in the business
    environment Project Server 2010 and
    would like to get the publication date,modification
    date and name
    of the person who made
    the last change in
    the project. It is possible
    to doby the native
    resources or is
    there any query in
    SQL Server to perform a
    query of this information.
    Thank you.
    Obrigado por contactar o fórum Microsoft Technet!

    Hi Hezequias,
    You can get the ProjectModifiedDate column in MSP_EPMProject_userView in the Reporting DB where you can
    get the data based on the projectUID. 
    The "last saved" date in the draft DB (be aware that querying in the draft DB is not supported by MS).
    For the "last modified by", I think it is not stored in any place.
    But you can develop custom code upon publishing the project (Event BeforePublish), writing the current
    date and username automatically into a custom enterprise field.
    Hope this helps,
    Guillaume Rouyre, MBA, MCP, MCTS |

  • Project Server 2010 - Error 20010 with a master project and 3 sub-projects during publication

    Hi,
    Here is the situation :
    One master project with three sub projects.
    Sub projects are really similar (Same ressources and nearly same tasks but only the first contain real work for now).
    Sub projects got no sub projects nor links between projects.
    The owner of the master project got read rights through projects permissions on sub projects.
    Sub projects are link in "read only".
    We applied Project Server 2010 SP2 last week end and the issue appeared monday.
    Here are the symptoms :
    When we link only one sub project (Doesn't matter which one), the owner can publish, no problems.
    With 2 sub projects, the error may occur.
    With 3 sub projects, the error always occurs.
    With admin rights, the error doesn't occur.
    Here is the error :
    ID : 20010 (0x4E2A)
    Description : You don't have required permissions to perform the action (Average traduction)
    Detail : <detail><errinfo><general><class name="Project"><error id="20010" name="GeneralSecurityAccessDenied" uid="19515c1d-2624-466f-953a-b7fc67337b81"/></class></general></errinfo></detail>
    I'm unable to determine which sub project is the culprit, if there is one, as it's working when I link only one of them.
    Thanks for your time !

    Fylim --
    If the project manager in question does not need to edit any of the three projects, the PM does not need to have Read/Write access to any of the three projects.  Because you said that the PM needs to set links in all three projects, this means that
    the PM will be editing all three projects.  In order to edit the three projects, the PM must have Read/Write access to all three.  Setting cross-project links constitutes editing of the projects, which is why the PM must have Read/Write permission. 
    Make sense?
    Regarding SP2, I am not aware that this would change anything, but I could be wrong.  The reality is that regardless of which SP you have applied to Microsoft Project and Project Server 2010, the PM in this situation MUST have Read/Write access to the
    projects that he/she needs to edit with cross-project links.  Hope this helps.
    Dale A. Howard [MVP]

  • I want to break inheritence and create unique permissions in a Project Server 2010 project site list/library.

    Some Project Managers want to restrict permissions on certain lists or libraries in their Project Server 2010 project site. However, when I have done this for them, by breaking inheritence to the parent site and then removing/adding users with unique
    sharepoint permissions, it seems that when the project schedule is published, some of the newly created permissions are lost.
    I have tried creating a SharePoint group at the project site level and then applied it with specific permissions (eg. Contribute) to the list/library and this seems to work better but I haven't been able to confirm yet if this will work in the
    longer term.
    Does anyone know what is the best method to break inheritence and set up unique permissions on a list in a Project Server 2010 project site that will not be lost when the project schedule is published?
    Thanks
    Peter

    Thanks Lynda
    I am aware that I can disengage the entire permissions sychronisation using that setting but that is not what I want to do.  I just want to be able to break the inherited permissions on individual document libraries or lists on specific Project Sites
    so that I can restrict access to nominated people.
    My issue is that when I do this, I find that some of the amended permissions disappear from time to time.  It seems to be related to when the schedule is published.  They
    don't revert to the inherited permissions, just some of the people who I have given direct access to no longer have access.
    Im just trying to find out the best way to manage setting non-automated permissions on a single list or library in a Project Server project sites so the changes stick.
    Peter

  • How to change the look and feel for Heading of quick launch menu in project server 2010

    Hi
    can someone tell me how to change the look and feel of Header names in quick launch.
    I want the header to be displayed in Bold with Underline to it.
    could this be possible for just header in quick launch in project server 2010. 

    Hi Rohan
    It does not work this way. You have to use a content editor webpart.
    See references below that might help you starting with this customisation:
    Http://go4answers.webhost4life.com/Example/sharepoint-2010-quick-launch-look-feel-78379.aspx
    Http://m.sharepointpromag.com/sharepoint/four-ways-add-or-remove-quick-launch-menu-control
    Hope this helps.
    Guillaume Rouyre - MBA, MCP, MCTS

  • Is it possible to create a formula that converts a resource hours into full time units in project server 2010

    Hi
    Is it possible to create a formula that converts a resource available hours into full time equivalent units in project server 2010? Say a resource has 160 available hours for any given month this will translate into 1 FTE for this month. If it is 80 hours
    for that month then it will be 0.5 FTE and so on and so forth.
    Thanks,
    -Maurizio

    Maurizio,
    It's a bit late, but there are two OLAP cubes that can provide you with this information in a pivot table in Project Server 2010.
    "MSP_Portfolio_Analyzer" and "Resource Timephased" contains capacity measures that be used to provide calculated measures when the cube database is generated. You change OLAP cube configuration in "Server Settings -> Database Administration -> OLAP
    Database Management". In either of the aforementioned cubes, use "Calculated Measures" to create two measures:
    Member Name
    MDX Expression
    Available (FTE)
    ([capacity]-[work])/[capacity]
    Work (FTE)
    [Work]/[Capacity]
    These two fields will appear in the pivot table field list as "Values", and when combined with a "Time" column, can give you a picture of FTE usage and availability.
    I prefer the portfolio version since it contains project/assignment data and resource data, letting you see just  how resources are being utilized.
    One thing I have not been able to get around is getting ""Maximum Units" for a resource factored into the measure. A common practice is to allocate more that "100%" to generic resources to represent teams for planning purposes. The OLAP measures will show
    only 0.0 to 1.0 FTE for any resource, even if a resource represents more than one body.
    If you have an SSRS query you could share, I would appreciated it!
    Hope this helps!
    JTC
    JAckson T. Cole, PMP, MCITP

  • Project Server 2013 reporting database change in Schema from Project Server 2010

    I have a current Project Server 2010 implementation, I am planning to migrate to Project Online.
    We have Customized Reports that consume from the PS 2010 Reporting DB.
    Are there differences in the Reporting DB schema  between PS 2010 and Project Online?
    My Question is: if we migrated to Project Online, will the reports crash?
    Another question is that, is PS 2013 Reporting DB schema the same as Project Online?

    Hi Atia,
    IN project server 2013 we have only one database instead of 4, it means draft, archive, published and reporting with in one database.Project Server 2013 reporting database schema tool that can be downloaded.
    http://blogs.msdn.com/b/project_programmability/archive/2013/01/28/project-server-2013-reporting-database-rdb-schema-reference.aspx
    There are differences in reporting of on-premises vs. Project Online
    The Project Server 2013 reporting schema includes three new tables, 27 new views, and a total of 33 tables and views that include new fields.
    Answer-1 : Yes there are some differences between PS 2010 and project Online.
    Answer-2 : Reports will crash as In Project Online you have to use ODATA to create report. You can not query project online data for reporting directly you have to have use ODATA. 
    http://msdn.microsoft.com/en-us/library/jj163015.aspx
    Answer-3 : NO, PS 2013 Schema and Project online Schema is different. 
    kirtesh

  • How to : Configure Project Server 2010 to work with Exchange Server 2013

    Hi everybody. I have a problem. I did integration success project server 2010 with exchange server 2010. But now my customer use exchange server 2013. So my question is "Have a way to integration project server 2010 with exchange server 2013 ?"

    I haven't seen any document with Project 2010 and Exchange 2013. You could still try the old document with Project 2010 and Exchange 2010.
    http://technet.microsoft.com/en-us/library/ff468700(v=office.14).aspx
    It might just work.
    Thanks Gaurav Wason MCITP, PMP

  • Error Project Server 2010, % Complete, Work and Actual Work

    Hi Everyone
    I have a Project Server 2010 SP2 Environment, The farm contains 3 Servers.
    1 WFE, 1WebApp, 1 BD. All servers in the farm are Windows Server 2008 R2 and the Data Base Server is SQL Server 2008 R2
    The Context:
    The Project Managers create the Project in Project Professional 2010 SP2 for support Annual Maintenance about a software, then the team members go to my tasks in PWA to create the task inside the stage in the project, then they put the actual work, then they
    send the progress to his project manager.
    So, the project manager goes to the approval page to approve two times, one, the task creation and two, the progress.
    So far all ok but when the project manager open the Gantt in Project Professional 2010 SP2 , the task that the team member has sent appear with a 100 percent complete, but the work with 0 hours and the actual work with 0 hours too, being that should appear
    with the hours the team member has sent, that is my problem.
    This occur only with this project manger and his team member, all of others project managers in the platform don't report this issue.
    I already have  re open the project and re publish too
    So , let me know if you have some idea about this issue.
    Erick Gutiérrez PMI Membership #ID 2089740 MTCS - Microsoft Project Server Managing Projects

    Only other ideas is to make sure the duration isn't 0, which would make it a milestone.
    Have the resources, recall the timesheets and resubmit.  Run it thru cycle again and see if they actual show up.
    Finally, you can run SQL query and see where the data may be. 
    1) Check if status manager is who you think it is
    2) Check if project shows actuals in sql.  Doesn't explain why not showing in schedule.
    cheers!
    Michael Wharton, MVP, MBA, PMP, MCT, MCTS, MCSD, MCSE+I, MCDBA
    Website http://www.WhartonComputer.com
    Blog http://MyProjectExpert.com contains my field notes and SQL queries

Maybe you are looking for

  • ? Office 2013 to support Excel 2003 (XLS) spreadsheets containing VBA CommandBars references

    Thanks in advance for reading this and offering any wisdom you have! I am not an expert in any of the following, so apologies if off base. The basic problem is: I need to use Excel 2013 to support Excel 2003 (XLS) spreadsheets containing VBA 'Command

  • How to find out the list of includes:

    Hi, I want to find out the list of includes, hw can I do that.. Suppose: ex: I want to know all the includes starting with zabc* hw can I do it, and one more question, where all the (total) includes will be stored. Akshitha.

  • TV Shows Season Pass New Episodes Gone from Check for Available Downloads

    I was informed today from iTunes Support that new episodes that become available will no longer come through the Store > Check for Available Downloads option in iTunes.  If you notice in your email alerts for the new episode's availability, it now sa

  • Converting a word 2000 file into pdf using Adobe Acrobat Standard X

    I reinstalled my Adobe Acrobat Standard X today, and tried to convert a *.doc word file into pdf, but the application could not open the word file and got stalled. I remembered that last time I installed the application the same probelm cropped up an

  • Po Pending

    how can i get the stock of po's lineitem wise? and po must open or pendding,.... if it help full then reward full. Message was edited by:         patel paresh