When to schedule the  RPTARQPOST  report

Hi experts,
                  We are using the workflow ws12300111 for leave approval process.Everything works fine.But I want to update the 2001 infotype.For this i think we have to schedule the  RPTARQPOST  report.When we have to schedule this report .How to schedule this report .In th e same way we have to send a mail using the report RPTARQEMAIL.How to schedule this report.
Thanx and Regards
rajesh

Mostly it is scheduled everyday night.
This completely depends on total number of leave requests received daily (higher the number longer time its gonna take) so you might prefer to schedule in night when no other (payroll etc) program is going to lock master data(otherwise update will fail) .
Also if this is business critical for you to update immediately so that reports come correctly then you might like to run program every 3 hour. Basically this is completely a trade off between immediate reflection (all the time) and system Performance.
Hope this helps.
Rgds

Similar Messages

  • I am not Getting emails when i schedule the Report.

    Hi All,
    When i Schedule the Report in obiee 11g i am Getting Alerts Successfully but am not getting Mail.
    When i Schedule the Publisher i am getting mails.
    ERROR Details:
    Eventually succeeded, but encountered and resolved errors...
    Number of skipped recipients: 2 of 3
    AgentID: /users/administrator/Agents/latest test
    [nQSError: 75005] Failed to send AUTH command. SMTP server does not support any authentication mechanisms. Remove email credentials, or use a server which supports authentication. AgentID: /users/administrator/Agents/latest test
    ...Trying SMTP Delivery loop again... Sleeping for 3 seconds. AgentID: /users/administrator/Agents/latest test
    [nQSError: 75005] Failed to send AUTH command. SMTP server does not support any authentication mechanisms. Remove email credentials, or use a server which supports authentication. AgentID: /users/administrator/Agents/latest test
    ...Trying SMTP Delivery loop again... Sleeping for 5 seconds. AgentID: /users/administrator/Agents/latest test
    [nQSError: 75005] Failed to send AUTH command. SMTP server does not support any authentication mechanisms. Remove email credentials, or use a server which supports authentication. AgentID: /users/administrator/Agents/latest test
    ...Trying SMTP Delivery loop again... Sleeping for 8 seconds. AgentID: /users/administrator/Agents/latest test
    [nQSError: 75005] Failed to send AUTH command. SMTP server does not support any authentication mechanisms. Remove email credentials, or use a server which supports authentication. AgentID: /users/administrator/Agents/latest test
    Exceeded number of SMTP delivery retries.
    Thanks and Regards
    Kiran Kumar

    Hi All,
    I got the answer and it worked for me:-
    1. If the BI Scheduler cannot ping the mail server specified in the scheduler configuration, check the correct server is specified. If it is, check that it is up and running.
    2. If the user name and password are specified in the scheduler configuration, log in to Enterprise Manager and navigate to:
    Weblogic Domain
    Right click on bifoundation_domain > Security > Credentials
    Expand oracle.bi.enterprise
    Highlight mail.server and delete the user name and password..
    Thanks & regards
    Nitin Aggarwal

  • Firefox crashes when opening and the crash report I get is Firefox 3.6.3 Crash Report [@ strlen | nspr4.dll@0x15f9f ].

    == Issue
    ==
    Firefox is crashing or closing unexpectedly
    == Description
    ==
    Firefox 3.6.3 crashes when opening and the Crash Report [[@ strlen nspr4.dll@0x15f9f ]. It was working perfectly fine and the last three days, I am having difficulty in opening firefox. It crashes with the above crash report every time I open. I came across the bad image error and did a clean reinstall multiple times and that did not help. I have firebug and firecookies as an addon.
    == Crash ID(s)
    ==
    bp-5972b384-791f-4667-b3cb-051812100504
    == Firefox version
    ==
    3.6
    == Operating system
    ==
    windows XP
    == User Agent
    ==
    Mozilla/5.0 (Windows; U; Windows NT 5.1; en-US) AppleWebKit/532.5 (KHTML, like Gecko) Chrome/4.1.249.1064 Safari/532.5
    == Plugins installed
    ==
    firebug and firecookie

    Usually doesn't immediately crash, although that happens also. Usually hangs, then crashes.
    Addons are WHY I use Firefox when it works. I am NOT on the bleeding edge any longer. I could go back to boring, boring, Chrome.

  • Is there any way to schedule the webi report as body of the mail

    Hi All,
             I have a bit different requirement. I need to schedule the webi reports to BlackBerry Mobile .
    The report should be displayed not as an attachment or URL but should be the body of the mail.
    Is there any Trick or Tip to do that.
    Thanks in Advance

    You could schedule the reports to run as an Excel or PDF document and the destination as a folder on a server.  Then after the reports are sent to the destination, you could use the Program Job Server to run a script which parses the files line-by-line and creates an email.  It's not the most elegant solution but in theory it should work.

  • How will schedule the BW report in the Background ?

    Hi
    Small query, i have one management report in the BI, which should be run early morning and send mail to the GM,
    We can schedule the ABAP report but no the BW !!!!
    How will schedule the BW report in the Background ?
    How the mail send to the GM ?
    Please advise us
    REgards
    Anwer Waseem
    SAP BASIS

    Reporting Agent will be only supported in the 3.X runtime in 2004s,start using Bex Broadcaster.Reporting agent is going to be obsolete or is would say.
    All the new functionalities will be implemented in Broadcaster only.
    Advantage -The old Reporting Agent in BW 3.x could pre-calculate the data of a template and access it through the URL . It could not broadcast queries, workbooks or web templates by email or to KM folders.
    https://websmp203.sap-ag.de/~sapdownload/011000358700004219392005E/ERQA_INFOBROADCASTING.PDF
    http://csc-studentweb.lrc.edu/swp/Berg/articles/Reporting_Analytics_2006_Broadcasting_v10.ppt
    Note 760775 - Settings for Information Broadcasting
    Hope it Helps
    Chetan
    @CP..

  • Scheduling the crystal Reports

    Hi all,
    What is the use of Scheduling the Crystal Report?
    In the document I saw the use of scheduling is to run the object automatically at specified times.
    I want to Schedule that Crystal Report. For that I followed the following Steps.
    Login into CMCApp.
    Select the required rpt file. and clicked the Schedule.
    It opens the Schedule Screen.
    In that I have specified the Recurrence Parameter and Scheduled For.
    It refreshes the data,only if I press the Refresh button manually. Otherwise data is not refreshed.
    The status of corresponding object is Success, while seeing the History of the Object.If I click the View Latest Instance in CMCApp, It shows the updated data(Refreshed Data).
    Whether I am following the Correct Steps? Other than this What I have to do for scheduling?
    How can i retrieve the data from View Latest Instance?
    Thanks & regards,
    Hemalatha J

    Hello Hemalatha,
    You can schedule Crystal Reports only in an BO Enterprise environment (BOE).
    Documentation on how to schedule documents you can find in the BusinessObjects Enterprise Administrator's Guide [here|http://help.sap.com/businessobject/product_guides/].
    I also recommend to post this query to the [BusinessObjects Enterprise Administration|BI Platform; forum.
    This forum is dedicated to topics related to administration and configuration of BusinessObjects Enterprise, BusinessObjects Edge, and Crystal Reports Server.
    It is monitored by qualified technicians and you will get a faster response there.
    Also, all BOE Administration queries remain in one place and thus can be easily searched in one place.
    Best regards,
    Falk

  • How to schedule the webi report based on data changes in the report data

    Hello,
    I want  to schedule a webi report based on data change in a column in the report.
    The scenario is something like below:
    1. If a data of a particular column changes from 2 to 3 than I would like to schedule this report and sent it to users mail box.
    I know how to apply alerts or schedule a report or data tracking for capturing changes in the report but I dont know how to schedule the report only for data changes.
    Anybody done this before.
    Thanks
    Gaurav

    Hi,
    May be these links can help you:
    http://devnet.magicsoftware.com/en/library?book=en/iBOLT/&page=SAP_R_3_Master_Data_Distribution_Defining_Change_Pointers.htm
    SEM-BCS: Load from data stream schedule
    Attribute Change Run

  • How do I schedule the Oracle Reports to run only weekdays (Mon - Fri)?

    I am using the Oracle Reports Server to schedule the report.
    I have successfully been able to schedule my report to run every day (Monday - Sunday), but the customer does not want it creating an empty report on Saturdays and Sundays. I have tried at least 50 different &schedule= commands and none of them work.
    Someone here suggested that to use WEEKDAYS that the DBAs have to set something up in the Oracle Report Server, however our DBAs do not know of anything that they have to do.

    If you have monday to friday these would be 5 weekly jobs for every day.

  • Password is lost when I save the Crystal Report

    We use Crystal Reports v. 11.5.3.417, and our users access the crystal Reports using InfoView (Web Portal)
    We store the username and password inside the different Repor so the end-users of these reports don't have to know our database passwords in order to run the reports. (Oracle DB)
    We have 2 problems with our Crystal Reports
    1) Every time I change and the Save a report, the Password is lost, and I have to remember to go into the "Manage Object" and Process->Database and enter it again. It's really annoying to have to remember this every time we change a report.. Is there an option somewhere to avoid this?
    2) The password and username are occationly failing. When the users (accessing Crystal Reports through the Web Portal / Infoview) get an error message "Incorrect logon parameters..." The funny thing (actually not that funny) is that if I try to open the report like 10-15 times, just by clicking on the Crystal Report in the Infoview, it usually starts to work again. Some times after 5 clickes, and other times after 10-15 clicks. Its just not logical. Also when it starts working in my web-browser, it also start to work on our users browser as well.
    Every week I have to tell a couple of users to try like 10-15 times, but its not that funny to say this to a user.

    Hi   Roy Ingar Hansen,
    If  you think not to provide the password for your End user then we can  do that go into the "Manage Object" and Process->Database  enter the password  and Enable the option in :
    When viewing report:
    Use same database logon as when report is run.
    For the first time you need to enter the logon credentials and enable the option and click on update.
    It wont prompt for the password and it will not show password to your user's.
    If you have problems with Original database logon , then try with Custom database logon and update the option.
    Try with this...
    Regards,
    Naveen.

  • Getting a error when clicked on the EWA report

    Hi All,
    I am getting the below error when i click on the EWA report.
    Error: &EA1000000002570&: Attribute not found: &TEXTPARAM& &check_244_comment&, Program SAPLDSVAS_PROC, Include LDSVAS_PROCERI, Row 48

    hi
    pls refer the thread
    [Ealry watch alert report is not displayed in solution_manager|Ealry watch alert report is not displayed in solution_manager]
    and
    [Re: EWA report is not displayed in solution_manager|Re: EWA report is not displayed in solution_manager]
    jansi

  • Scheduling the Webi report based on the current date

    Hi ,
    Can I schedule the report to give the results of the previous day (report Daily) and other one to give the results of the previous month (report Monthly)? How can I do it?
    Thanks in advance.

    Hi Peter,
    Well for yesterday, you can use something like:
    CAST(CONVERT(VARCHAR, T_GVQSTATCG1_HOUR.DATE_YYYYMMDD, 110) AS DATETIME) = DATEADD(dd,-1,(select T_GVQSTATCG1_HOUR.DATE_YYYYMMDD from YourTable where Current_Day_Ind = 'Y'))
    We have a date table in our data warehouse with a Current Day Indicator field. If you don't have something like that, then you should be able to just use:
    CAST(CONVERT(VARCHAR, DateAdd(dd,-1, GetDate()), 110) AS DATETIME)
    You would use something similar for previous month, parsing out the month number from the date, and then subtracting 1, except of course for January, where you could just plug in a case statement to handle that.
    This is assuming you are on SQL Server. Syntax may be different in Universe for Oracle or other.
    Does that make sense?
    Thanks

  • To display subreport page header when included in the main report

    Hi, 
    I am designing  a  report  using SSRS 2005.The main report has a few subreports.Each subreport has header which serve as page and table header for the report content.When the subreport is run individually there is no problem where header is
    getting displayed for each page  but when main report is executed only subreport body content is displayed.Can someone please suggest if there is any workaround for displaying sub report header
    My subreport looks as shown in the image below.

    Place your Header contents at top of the body and footer contents at bottom of the body. Remove Header and footer from your subreport.
    Aftab Ansari

  • Incorrect indentation when using on-the-flying report generation and IF statement

    Reproduce steps:
    1. Use teststand version 4.2
    2. Turn ON on-the-fying report option.
    3. Report option -> INclude Step Results->Result Filtering Expression = Exclude Passed/Done/Skipped
    4. My simply code is
    For loop
       If something
          Do something
             If somethingmore
               Call Action and set Record Result = ON
            end if
      End IF
    End loop
    Issue:
        The test report generated for "Call Action" indents every new row. Because it is a long test, this make the test report very difficult to read. If there is a very long test, the test report is  become unreadable.
    Is there a solution for this issue?
    Thanks

    Hi Biet,
    Unfortunately this is a known issue with TestStand, which is documented in the TestStand 4.2.x Known Issues. This occurs in situations where you are using HTML reports with On-The-Fly Reporting and a Result Filtering Expression. To avoid this situation, you can do one of a few things:
    Use a different report format
    Turn off On-The-Fly Reporting
    Not filter the results
    If you must filter results, you can modify the process model slightly to improve the situation. Though this is not a complete workaround, it can help.
    First, configue your Report Options so that you are reporting All
    Results, rather than filtering. Leave On the Fly reporting ON. Next, we
    need to make a modification to your process model. In the process model,
    open the ProcessModelPostResultListEntry sequence. In this sequence,
    select the Process Step Result step, and select the Properties tab. On
    that tab, select the Preconditions category. The text for the
    precondition should be the following by default:
    !Runstate.Root.Locals.ReportOptions.DisableReportGeneration &&
    Runstate.Root.Locals.ReportOptions.UseOnTheFlyReporting
    Now, we want to modify this to be as follows:
    !Runstate.Root.Locals.ReportOptions.DisableReportGeneration &&
    Runstate.Root.Locals.ReportOptions.UseOnTheFlyReporting &&
    Parameters.Result.Status != "Passed" &&
    Parameters.Result.Status != "Done" &&
    Parameters.Result.Status != "Skipped"
    This
    new precondition essentially implements our own filtering. In the
    condition that I have supplied, we will not add entries to the report
    where the status is "Passed", "Done", or "Skipped". (You can add
    additional lines to add additional statuses to filter.) The limitation
    here is that the bug provides incorrect indentation, so the results may still be grouped slightly differently than they would be without the bug.
    I hope this helps!
    John M
    National Instruments
    Applications Engineer

  • AR - Customer Statement - differences when compared with the Aging report

    I am running the customer statement (the Print Statement program) 'as of date' say 11-Jun-09, and found that the 'Total Amount Due' for a customer is not agreeing back to the balance displayed on the Aging Screen (Navigation: Collections -> Customer Accounts [Aging butto]) for the customer.
    The 'Total Amount Due' on the statement is greater than the balance on the aging report/screen.
    It appears that the statement is selecting more receivables transactions (invoices, credit note, payments etc...) than the aging report is looking at. Also the aging buckets on the statement does not tie back to that on the aging screen /report for example the '4 Bucket Aging Report'.
    My questions are:
    1, Is it possible for the 'Total Amout Due' on the statement to differ from the balance on the aging report/screen?
    2, What factors or reasons might cause the above senario to occur?
    3, How can one start to investigate this in order to account for such differences?
    Ideally what I would like to do is run a sql script that will show what is being selected for the statement 'as of' a particular date for a customer, and another sql that will show the same customer account balance and aging buckets at the same 'as of' date.
    And perhaps another sql that would show the same customer open receivable transactions.
    Thanks.

    Hello.
    This query will show you the customer open receivable transactions:
    select c.customer_name,
    decode(ps.class, 'PMT', 'Payment', 'INV', 'Invoice', 'DM', 'Debit Memo', 'CM', 'Credit Memo') Type,
    ps.trx_number,
    ps.trx_date "Inv Date",
    ps.due_date "Due Date",
    ps.acctd_amount_due_remaining "Amount Remaining"
    from ar_payment_schedules_all ps,
    ra_customers c
    where c.customer_id = ps.customer_id
    and ps.status = 'OP'
    and ps.org_id = &orgID
    and c.customer_number = &CustNumber
    Octavio

  • BO 4.0 : JCoException while scheduling the webi report

    Hi,
    We are in BO 4.2 patch 8.
    We have 35 webi reports. These report uses SAP BW as data source. We are using DF to fetch data from SAP BW.
    We have manually configured the RFC destination for JCO connection (as mentioned in SAP notes - 1638647).
    Reports are getting scheduled successfully. But sometimes some webi reports fails with the following error message.
    Database error: (CS) "Java Exception : java.lang.RuntimeException:com.sap.connectivity.cs.java.drivers.DBDError: [Data Federator Driver][Server] [Connector 'Sales_BO_New'] SAP NetWeaver BW has reported an exception: com.sap.conn.jco.JCoException: (112) RFC_ERROR_REQUEST_CANCELLED: connection with handle 3 closed
    after cancel (remote system is PBI|BILPBI)" . (IES 10901)
    This is in intermittent issue. If anybody faced this issue, then please let me know your feedback.
    Thanks,
    Ravi
    Edited by: Ravi Kirana Palla on Dec 9, 2011 7:38 AM
    Edited by: Ravi Kirana Palla on Dec 9, 2011 7:38 AM

    Hi,
    Personally, I haven't seen this before. To recap:
    - Manual refresh work fine
    - scheduling works most of the time
    - but sometimes it fails with << SAP NetWeaver BW has reported an exception: com.sap.conn.jco.JCoException: (112) RFC_ERROR_REQUEST_CANCELLED >>
    You might want see if you can isolate a particular document causing the problem, or determine if it's related to using certain refresh parameters
    According to http://help.sap.com/saphelp_nw70/helpdata/de/f6/daea401675752ae10000000a155106/content.htm
    it says Find out from the JAVA application or the JCo traces which JCo Server was cancelled and restart the server; in the J2EE Application Server context, JCo Servers are often started via the Service JCo RFC Provider
    but .. i don't know how helpful that is..
    Best of luck
    H