Where to assign GL Account to cost center?

Hello Friends,
Actually in MIGO T.C , I  am issuing the material against the cost center.Now in MIGO T.C ,  in Account Assignment tab i give the cost center and other requied data and save.And in display mode when i check that document than by default system takes the GL Account.Now my question is where we assign the G/L Account to cost center?In FS00 T.C i checked in Edit cost element for that account, there in Default account assignment , no cost center is maintained.So from where system is picking this G/L Account?
Thanks and Regards,
Jitendra Dilip Chauhan

Hi Jitendra,
This setting is made in OBYC. This actually MM & FI integration.
You check this in OBYC.
1.First check your valuation class in material master.
2.Then goto OBYC.
3. Double click on GBB transaction key
4.This will pop up chart of account.Maintain chart of account & enter.
5.Here you will see that GL account for combination of Genral modification VBR & Valuation class.
VBR: for internal goods issues (for example, for cost center)
That means whenever you do Goods issue of material  for cost center which having same valuation class,this GL account will be automatically assigned.
Hope this clear you.
Regards,
Raja.
Edited by: Raja on May 8, 2009 9:46 AM

Similar Messages

  • Not updating G/L account and cost center with BAPI BAPI_PO_CREATE1

    Hello Friends,
    The two fields G/L ACCOUNT and Cost Center is not updated using BAPI BAPI_PO_CREATE1. I am unable to understand why? This is what i am passing to account assignment structure( POACCOUNT). Filled POACCOUNTX structre as well. I have passed company code at the header level.
    PO_ITEM = 00010
    SERIAL_NO = 01
    CREAT_DATE = sy-datum
    GL_ACCOUNT = 621000
    COSTCENTER = 1000
    CO_AREA = 4000
    Please let me know why it is not updating anything i missed while passing?
    2>I need to update GR quantity but this field is not available in the BAPI ..Please let me know how to update this field.
    Any help is highly appreciated.
    Regards,
    Raj

    Hi, I have a problem I use the bapi BAPI_PO_CREATE1, I pass the table pt_poaccount in the parameter poaccount but the bapi when register my purchase order doesn't register correctly the values KOSTL, AUFNR, PS_PSP_PNR, NPLNR of the tablepoaccount and register the default values of the contract. Please i need help with this.
    CLEAR s_poaccount.
         s_poaccount-po_item     = <fs_datos>-ebelp.
         s_poaccount-serial_no   = w_serial.
         s_poaccount-costcenter  = <fs_datos>-kostl.
         s_poaccount-orderid     = <fs_datos>-aufnr.
         s_poaccount-wbs_element = <fs_datos>-ps_psp_pnr.
         s_poaccount-network     = <fs_datos>-nplnr.
         s_poaccount-activity    = <fs_datos>-vornr.
         s_poaccount-quantity    = <fs_datos>-menge.
         s_poaccount-net_value   = <fs_datos>-brtwr.
         s_poaccount-creat_date  = sy-datum.          
         s_poaccount-itm_number  = <fs_datos>-ebelp.  
         s_poaccount-co_area = '1001'.               
         APPEND s_poaccount TO pt_poaccount.
    CLEAR s_poaccountx.
         s_poaccountx-po_item     = <fs_datos>-ebelp.
         s_poaccountx-serial_no   = w_serial.
         s_poaccountx-po_itemx = 'X'.
         s_poaccountx-serial_nox = 'X'.
         s_poaccountx-creat_date = 'X'.
         s_poaccountx-itm_number = 'X'.
         s_poaccountx-co_area = 'X'.
         s_poaccountx-costcenter = 'X'.
         s_poaccountx-orderid = 'X'.
         s_poaccountx-wbs_element = 'X'.
         s_poaccountx-network = 'X'.
         s_poaccountx-activity = 'X'.
         s_poaccountx-quantity = 'X'.
         s_poaccountx-net_value = 'X'.
         APPEND s_poaccountx TO  pt_poaccountx.
    CALL FUNCTION 'BAPI_PO_CREATE1'
         EXPORTING
           poheader          = pe_poheader
           poheaderx         = pe_poheaderx
         IMPORTING
           exppurchaseorder  = pi_exppurchaseorder
         TABLES
           return             = pt_return
           poitem           = pt_poitem
           poitemx         = pt_poitemx
           poschedule    = pt_poschedule
           poschedulex  = pt_poschedulex
           poaccount      = pt_poaccount
           poaccountx    = pt_poaccountx
           poservices     = pt_poservices
           posrvaccessvalues = pt_posrvaccessvalues.
    The BAPI is register with these values as default however i pass other values in table
    pt_poaccount

  • No functional area derived from GL account and cost center ccombination sel

    Hi,
    When doing a goods issue for a delivery, am getting this error. Hope somebody could advice.
    "No functional area derived from GL account and cost center combination selected."

    Hi,
    Go to FS00 and specify the functional area for the gl account. Go cost center change mode specify the functional area. Define the f area in Tcode OKBD, FSP2,KA02,KS12,
    Hope this is clear, if yes assign points
    Regards,
    Sankar

  • Control G/L account and Cost Center for movement type 251

    Dear Friends,
    I would like to use mov. type 251 for GI for sale and like to control over G/L account and Cost center.
    The G/L account is by default from the valuation class of the the material and if the user will enter wrong G/L
    we had done the customising in OMJJ movement type 251 - Account grouping - Unchecked the check box of column
    "Check account assignment" - Impact is " the system always uses the G/L accounts or account assignments determined automatically"
    I also made default cost center for G/L account and plant wise through OKB9.
    Now I would like to suppress/dispaly the G/L account and cost center - for same I had done Setting in Entry control menu of OMJJ for 251 of field Account control - Value  - "-" field is suppressed. But it is not working.
    Please advise to solve this situation.
    Thanks & Regards
    Rajan

    Dear Rajan
    Yes, I have checked in MB1A earlier. We have separate node for Field seletion layout for Enjoy transaction MIGO for mvt type in which the G/L account (KONTO) an Cost center (KOSTL) have only optional or required entry selection.
    warm regards
    Ramakrishna.

  • How to assign activity type to cost center

    hi Gurus,
    Sir i have got error during the T.Code: CRC1.  in which i have to assign Activity type to cost center. which is as follow: ( I have also made tickmark in cotrolling area for Activity type)
    ( Error :No activity type assigned to cost center #1301,Controlling area ABCD on 01.02.2008)
    Pls provide me the solution where the activity type should be assign to cost center.
    Than'x & Regards,
    Dhananjay

    Hi,
    Planning at KP26 for Activities itself is integration between Activity and Cost center.
    Once you do this, your problems is solved.
    Assigned points suitably
    Best Regards
    surya

  • GL account and cost center field appearing for Goods issue movt type 201

    Hi SAP Gurus
    We are trying to post goods issue in ecc6 . The problem is that the GL Account and cost center fields are available fields .The cost center field is logical but why the GL account field is avaiable .
    How we can grey out the same field as it is going to be picked up from the valuation class setting in GBB - VBR ? Any ideas
    Regards
    Hitesh

    Hi Ravi
    You think that its ok we have to input the cost center .
    But if you allow the users to input the GL then you are overriding the whole purpose of defining the valuation class and offsetting entries ? What is your opinion ?When you input the material in the goods issue screen the offsetting entry needs to be picked from the GBB -VBR .Although even if you do not enter the GL the system posts the Godds issue document .But from the control perspective this needs to be suppressed .
    What do you think ?
    I have also posted the same in Logistics forum .
    Once  again many thanks for your help .In case you find some solution this would be of great help
    Regards

  • G/L Account & the Cost Center not updating in BAPI_PO_CREATE1

    Hi,
    We are using BAPI_PO_CREATE1 for Service PO Creation.
    The System is creating the Purchase Order, but it is not updating the G/L Account & the Cost Center.
    We are passing the following parameters:
                    wa_poaccount-PO_ITEM  = '00010'.
                    wa_poaccount-SERIAL_NO   = '01'.
                    wA_poaccount-quantity   = '100.000'.
                    wa_poaccount-GL_ACCOUNT  = '0058120000'.
                    wa_poaccount-COSTCENTER  = '1000-LSG'.
                    wa_poaccount-itm_number  = '000010'.
                    wa_poaccount-CO_AREA     = '1000'.
                    append wa_poaccount to it_poaccount.
                    clear wa_poaccount.
                    wa_poaccountx-PO_ITEM = '00010'.
                    wa_poaccountx-SERIAL_NO   = '01'.
                    wA_poaccountx-quantity   = 'X'.
                    wa_poaccountx-GL_ACCOUNT = 'X'.
                    wa_poaccountx-COSTCENTER = 'X'.
                    wa_poaccountx-CO_AREA     =  'X'.
                    wa_poaccountx-itm_number  = 'X'.
                    append wa_poaccountx to it_poaccountx.
                    clear wa_poaccountx.
    Please guide how to correct the error.
    Regards,
    PK

    Hi,
    Thanks for the reply.
    We are passing the following parameter in POITEM.
                      clear wa_poitem.
                      wa_POITEM-PO_ITEM = '00010'.
                      wa_POITEM-PLANT = '1003'.
                      wa_POITEM-TAX_CODE = 'S1'.
                      wa_poitem-MATL_GROUP = 'SER04'.
                      wa_POITEM-ACCTASSCAT = 'K'.
                      wa_poitem-ITEM_CAT   = 'D'.
                      wa_poitem-pckg_no    = '0000000001'.
                      wa_POITEM-SHORT_TEXT = 'Freight Service'.
                      append wa_POITEM to it_POITEM.
                      clear wa_poitemX.
                      wa_POITEMX-PO_ITEM = '00010'.
                      wa_POITEMX-PLANT = 'X'.
                      wa_POITEMX-TAX_CODE = 'X'.
                      wa_poitemx-MATL_GROUP = 'X'.
                      wa_poitemx-short_Text = 'X'.
                      wa_POITEMX-ACCTASSCAT = 'X'.
                      wa_poitemx-ITEM_CAT   = 'X'.
                      wa_poitemX-pckg_no    = 'X'.
                      append wa_POITEMX to it_POITEMX.
    Please guide.
    Regards,
    PK

  • G/L Accounts and cost center

    i would like to find the list of valid G/l Accounts and cost center for a input company code. Is there any good tables for getting this information. ?

    I don't think there is such a thing. If a GL is valid for a company code and a cost center is valid for the corresponding controlling area, then the transaction should post. A relationship between controlling area and company code is in table A059 (Controlling Area/Company Code). This table is empty in our system, so I don't think that checks will be made.
    Rob

  • Can I get  Vendor Account Group & Cost center from PAYEXT Message Type?

    Hi Everybody,
    I am getting all the IDOC's of message type "PAYEXT" fro EDIDC & EDID4 tables. But will these IDOC's will contain Vendor Account Group & Cost Center ? If so could you please let me know the Segment & corresponding fields.
    Thanks & Regards,
    Nagaraju Maddi

    Hi
    You can find the all related IDOC fields in the SDATA field of EDID4 table
    Yhis is a 1000 CHAR field which stores all the Segments data by concatenating into a string
    have to search for the required field by looking into the related segment..
    <b>Reward points for useful Answers</b>
    Regards
    Anji

  • Messg-AAPO189 :Account object Cost Center differs from that in asset master

    At the time of Asset Acquisition in T-Code F-90 using Internal order, the system throws the following error:
    Message-AAPO189  :Account object Cost Center differs from that in asset master
    But in Asset Master data and Internal Order Master data's Cost Centers are same. 
    And we are not facing this problem for all Assets (only for few asset class only we are facing this error).
    Please guide on this.
    Note:
    We are not using Joint Venture Accounting.
    Regards
    JS
    Edited by: JS on Aug 12, 2009 7:14 PM

    Closed

  • What is the different between account assignment P Project & K Cost center?

    Hi ,
    I need to raise a PR and PO for repairing damge of our Project's Product.
    In this stituation, I should create PR with account assigment P (Project) or K (Cost center)?
    Thanks

    Hi,
    Material are procured as stock or non-stock materials. When you procure material which can be used in production of finished product ,stock is maintained.
    Account assignment category describes how the procured material is being used (for eg: Cost Center, Sales Order, etc). It also determines how the accounting entries made when a GR document or IR document is posted.
    When you use the Account Assignment Category "K", it means the material is allocated to a cost center for consumption. The Materials is accounted to the particular cost center.
    Account Assignment Category "P" is used for materials that are required for the project related.
    Hope it helps.
    Regards,
    Bijoy Kumar

  • Account assignment category Asset to Cost Center in po items

    Hey,
    We have a Question how to handle this Exception:
    We have purchase order items with the account assignment category "A - Asset" and we have created Asset master data. Later, this assignment category is changed to "K - Cost Center". But the Asset Master Data is still there.
    How to handle this in the future? Do we have to delete the purchase order items with the account assignment category "A - Asset" and have to create new items with assignment category "K - Cost Center"?
    Thanks!

    Hi
    Once you change the acct assnment category to K, then there is no need for asset master. You can take help of your FICO consultant for deleting the asset master. You changed acct assnment in PO?
    Thanks

  • Freight Costing - Problem of G/L account with Cost Center

    Dear Gurus,
    In VI02, I have the following u201CAccount Assignmentu201D message of error:
    u201CG/L account 60900000 cannot be used (please correct)u201D
    u201CComparison of the field selection strings from the G/L account 60900000 and the account assignment category K reveals that there is an incompatible combination of field selections for the field selection group 'Earmarked Funds'.u201D
    Questions:
    Bearing in mind that I am in the Shipment Cost cockpit, I need to mention that the system directly allocated me the following Account Assignment Category: u201CKu201D for u201CCost Centeru201D.
    1-     I could there either way create another Account Assignment Category for Shipping instead of Cost Center
    2-     The system tells me about an incompatible combination of field selection, how can I change that field selection to make it compatible? There are so many possibilities that I get bogged down in choosing the right combination.
    I have been to OME9 and OB14 to try to maintain fields, however those fields have different values or names.
    My aim here is to coordinate a G/L account group with a Cost Center for Freight Costing
    Can anyone help?
    Thanks
    Chris

    Dear Zafar,
    If you desire you maintain two different cost centers for the two company and you need to have both of them posted on the same G/L account and Cost element, I would advice you to:
    - create a Z table where by controlling area you define where the specific cost center need to get posted
    - include this validation check in the exit for validation for controlling
    - include this validation check in the exit for validation for finance
    - include this validation check also in the sales order user exit
    Standard SAP seems do not have direct link between cost centers & cost elements. For this reason ideal solution is to generate a table where you may define you needed structure.
    E.g.: some ideas on the table you may create
    Controlling area
    Cost element from
    Cost element to
    Cost center from
    Cost center to
    I hope this suggestion may answer to your need.
    Regards,
    Viviana A.

  • Profit center accounting and cost center relationship

    Experts, in the future as we look to tie the PCA cube with the CO cube, the referential integrity will be important.  What I see as being important is capturing the profit center, cost center and account that was used at the transactional level and not from an arbitrary hierarchy.  As such, in the PCA cube, it would be optimal to have the cost center assigned to the transaction be available.  This assumes that the PCA totals are by profit center, cost center and account.  Furthermore, I will want to build a jump target from the PCA cube to the CO cube where we can see this data by cost center and cost element or vice versa.  There seems to be some uncertainty on if the PCA cube has the cost center informaiton, so how would I do this?

    I don know if i understood it correctly but If you assign you profit center in your cost center you should be able to get all that you need.
    Assign points if helpful

  • G/L account and cost center in Delivery

    Hi,
    When we create the deliveri, first in sales order user only enters and func center,  that fuind center comes in the deliveri goods movement document,  along with that when i check in MIGO document display along with fund center i can see the cost cenert and g/l account for which that document is posted, In our system we are using same chart of account for two compnay codes, and in OBYC  for GBB-VAX  we have maintain one G/L account 893011, and in cost element for this 893011 we have assign one cost center  for one compnay code that cost center is OK  but for othere one we want to assign different cost center,  by keeping the same account,  how we can do this.
    regards,
    zafar
    Edited by: zafar_karnalkar on Jan 6, 2011 6:36 AM

    Dear Zafar,
    If you desire you maintain two different cost centers for the two company and you need to have both of them posted on the same G/L account and Cost element, I would advice you to:
    - create a Z table where by controlling area you define where the specific cost center need to get posted
    - include this validation check in the exit for validation for controlling
    - include this validation check in the exit for validation for finance
    - include this validation check also in the sales order user exit
    Standard SAP seems do not have direct link between cost centers & cost elements. For this reason ideal solution is to generate a table where you may define you needed structure.
    E.g.: some ideas on the table you may create
    Controlling area
    Cost element from
    Cost element to
    Cost center from
    Cost center to
    I hope this suggestion may answer to your need.
    Regards,
    Viviana A.

Maybe you are looking for

  • How to use the class CL_PT_EMPLOYEE with GET PERNR?

    Hi, I saw this sample code on the forum. Is it more performant than using the "RP-PROVIDE-..." macros? Does the employee instance needs to be killed after each pass? How does it affects memory? start-of-selection. GET pernr. <b>* Create employee inst

  • How to find list box field from recording

    Dear All, My requirement is to close all POs whose delivery date is overdue by 6 months. this can be accomplished by setting the delivery indicator in ME22N. I want to do this by BDC. I have the list of all purchase doc numbers and item numbers whose

  • After itunes and q/time upgrade I get an error #63440

    after the itunes and q/time upgrade whenever I try to acsess anything via q/time i get an error #63440 quick time was not found even though it is on my machine and I have removed and re-installed.

  • The return numbers of XAI enquiry(CC&B 2.1)

    HI all: right now i am doing a Construction Detail Enquiry, and there are 72 Account Id in that Construction, but it's seems the most no. of records return of Account Id enquiry is 50, if i want to get all the Account Id at once, how could i do? and

  • XI 2.0 installation script for creating XI Sandbox Demo System

    Does any have a Windows2000 XI 2.0 installation script designed to create minimal XI Sandbox?  Brief installing instructions.