Which release procedure will pick?

Can any body help?
We have a requirement that ,for same material (ABC)  but belongs to different plant,
we have two release strategies R1,R2
R1:-in this strategy two codes assigned
This release strategy will effect when net value=50000
& plant "X"
R2:-in this strategy three codes assigned
This release strategy will effect when net value=50000
& plant "y"
i will create PO with two line items,                                                                                in one line material is ABC & plant X
in other line item material is ABC, Plant Y
net value =50000
my question is which strategy&releases procedure will effect to this scenario
plz do needful

These are the communication structures
CEBAN
CEKKO
CESSR
Customizing Tables
Release strategy without classification
u2022     T161I  as described above.
u2022     T161E Release code and Description
u2022     T161S Release indicator
u2022     T161G Assignment to release indicator
u2022     T161F Prerequisites
Release strategy with classification
u2022     T16FG, T16FS as described above.
u2022     T16FH description of the release group
u2022     T16FT description of the release strategy
u2022     T16FC Release code
u2022     T16FD Description of the release code
u2022     T16FV Prerequisites and actions
u2022     T16FK Assignment to release indicator
u2022     T16FB (purchasing documents), T161S(Purchase requisitions), T16FL(Service Entry sheet) is the release indicator
u2022     T161U(requisition), T16FE(purchasing document),  T16FM(service entry sheet) are the descriptions of the release indicator

Similar Messages

  • PR release procedure problem

    We are using SAP 4.7 EE Version.
    Regarding PR release procedure, I have created PR release procedure by using characteristics with Plant, Total value of the item, document type, creation indicator and account assignment category.
    Created class PR_RELEASE with above-mentioned characteristics. The same is used in PR release procedure.
    When I am creating PR, the release procedure not picking up for standard procurement (stock material) account assignment category.
    We have identified the problem with account assignment category u2018 u2018 (Standard) while creating PR. For other account assignment categories (K, U, X, A), it is working fine.
    Recommend any SAP note numbers if you have or known.
    Points will be rewarded.
    Thanks,
    SK
    Edited by: s k on Jun 9, 2008 2:11 PM
    Edited by: s k on Jun 9, 2008 2:12 PM

    Hi
    Blank Account assignment does not work, as you cannot create a chracteristic Value as Blank.
    You need to create a new release strategy without the account assignment category chracter.
    Or remove the account assignment Chracterisitc from the release strategy
    Thanks & Regards
    Kishore

  • Release Procedure For Contract

    Dear Gurus,
                                 I have created a release procedure for Purchase Order.Now i created a Contract , it also asking for release.I dont know y its happening??
                                Is ter any link between Po release and Contract Release??
    Plz Explain ....
    Thanks in advance...........

    Hi,
    Whatever document types you give in release procedure will undergo Approval process.
    Since you have given MK & WK, your contract has been blocked for release. Unless it is released, it cannot be used for further transactions, say creation of PO.
    Tcode to release contract is ME35K.
    Release it using your release group & release codes, Afterwhich you will be able to create PO with contract reference.
    If you donot want contract to undergo release procedure, please do not mention WK or MK in values for doc characteristics. Give the document type of PO alone. Say NB (standard PO)
    Regards,
    Divya

  • How to find that which release is set to the plant

    Hi,
    I am having the plant name, but i don't have any other details. how to find the which release procedure is set for that one.Hpw to reach that link.
    Regards,
    Sydanna

    Hey you can go to the release strategy in SAP SPRO>MM>PO->Release->Release startegy and can check for the PO class what is the release strategy and can check for plant as a charactestic what are the diffrent values for other parameters are maintained.
    Dont forget to award points for the same.
    Lekhram

  • I would like to know when the slow motion video recording will come in 5c. in which update u will release it.

    Dear sir ,
    i would like to know when the slow motion video recording will come in 5c. in which update u will release it.

    I'm afraid the processor in the iPhone 5c does not support that feature. Since you can't change the hardware setup inside the phone, this will probably not be introduced at all for this model.

  • Which availability check procedure will be approprite for Pharma industries

    Hello All,
    I am working with a Pharma client.
    Please suggest me which availability check procedure will be approprite for Pharma industries.
    Depending ATP or On Product Allocation.
    Thanking you in anticipation.
    Regards
    Venkat

    Hi,
    ATP is a basic availability check which have limited functionality. GATP is a more dynamic checking which is suitable for real-time availability check, which is more appropriate for pharmaceutical industry.
    The basic differences between the two checking systems are:
    APO GATP:
    - Check for several Online Transaction Processing (OLTP)
    - Uses Live Cache Technology
    - Advanced Basic method
    - No restriction for combination of basic methods
    - Rules-based substitution
    - ATP check in several locations ("global")
    - Advanced backorder processing
    - Call of production possible
    ERP ATP:
    - Check possible only in an ERP system
    - Uses database tables or shared buffer (ERP server)
    - Basic methods
    - Restriction for combinations of basic methods
    - Standard substitutions
    - Check only in one location
    - Restricted backorder processing
    - No call of production possible
    This topic has been discussed before in the forum.
    You may find the following thread relevant to you:
    GATP
    Thanks.

  • How to release  PRs through workflows without setting release procedures?

    Dear all,
             I am involved in overall purchase requisition workflow.I have copied standard workflow WS20000077.
             For overall PR release,I will be using the standard task TS20000159 which uses BOR as BUS2105 and method SINGLERELEASE.This method is defined with RELEASECODE as mandatory parameter.
             My functional consultant wants me to get release codes from ztable based on plant and PR value without setting release groups and release code in SPRO transaction.
             So,I have created an entry in ztable for release code with data element FRGCO as in T16FC standard table with SAP log on id of agent ,plant and PR values.I have created a custom background method to pick the appropriate release code from ztable based on PR value and plant.The picked release code now can be passed to he above standard task.Is this a right procedure for PR release?Please correct me if I am wrong ,as this is the first time I am involved in release workflows, for which I will be grateful.
    Thanks and regards,
    S.Suresh

    Dear Swaminathan,
                     Thank you so much for your reply.
                     I will get back shortly once this is done.
    Thanks and regards,
    S.Suresh

  • Release procedure for PR

    Hi,
    I need to upgrade the existing release procedure for Purchase requistion.
    I have created new release groups, release codes and strategies.
    I have created new characteristics and have added that to the existing class which was being used.
    Now i am not able to see the purchase requistions getting picked up for release, both the new release and the existing release are not working now.
    I need my release at the header level and i am working on the release procedure with classification.
    Let me know what is going wrong or do i have to any thing further.
    Thanks,
    Regards
    Raghavendra

    Hi Raghavendra,
    IMG>MM>Purchasing>Purchase Requisition>Release Procedure>Procedure with classification>Check Release Strategies
    Here all the nodes must be in green color then ur release strategies will be fine.
    For more check the following link for Release Procedure.
    http://www.sap123.com/showthread.php?t=59
    Regards,
    Nani.

  • Use of Release Procedure  / status in Condition Table

    What is the purpose of Release Procedure / Release status when creating condition tables ?

    Hi
    Release procedures are used in condition tables to control whether the condition types for these condition tables have to be read during pricing condition determination or not.
    If the condition table status is released then only the condition types will be read during pricing determination. If the status is not released, then they can be used for information purposes or for simulation of pricing.
    The release status is controlled by processing status too, which can be seen in condition record creation screen.
    So in crux, the processing status with Release status help in simulation of pricing, blockign the condition records from being read during pricing etc.
    For more information an F1 help on the following path will give you some more information.
    SPROSD-BF-PRICING-DEFINE PROCESSING STATUS----Here read the documentation meant for this link. You will get some more clarity on this.
    Rwd point if it helps.
    Reward points if it helps.

  • PR release procedure no longer working-error MEPO 822

    I've raised a message previously regarding PR release problem. Now i've found something that need expert helps to clarify on this.
    Situation :
    One of my client(ABC) implemented release procedure for PR which is not assign to value limit. It is by document type. They had 2 document types; NB and RNB.
      NB = NOT subject to release
      RNB = SUBJECT to release.
    So when they :
    create a PR with document type RNB - it will goes for approval.
    create a PR with document type NB - it will not go to approval.
    It was working fine until after they created a new document type which copied from NB, called ZTP.
      ZTP = NOT subject to release.
    They did not touch anything on PR release configuration. However, the release has no longer working. Means, when they create PR with document type RNB, it will NOT go for approval as it suppose to. I've check in configuration, all are fine.
    Findings:
    I've created a PR, and go to ME45N to release it but system prompt me an error message
    "Purchase requisition 10000066 cannot be released". I check on the message data,  the error coming from MEPO, message number 822.
    So i check in OSS and found a note which is similar to this case.
    Note 939371 - Overall release PR using ME54N gives error MEPO 822
    Link : https://websmp230.sap-ag.de/sap(bD1lbiZjPTAwMQ==)/bc/bsp/spn/sapnotes/index2.htm?numm=939371#Text
    But my question is,is it also applied to ME51N and without external application as per my client's case?
    Please anyone help.
    Thanks.

    Hi guys!
    Wants to share something. I had a problem to release my PR. When i want to release PR via ME54N, system give me error message "Purchase requisition 10000066 cannot be released". When i checked message data, it is coming from MEPO Messafe 822. So i asked SAP, they said this one is caused by different issue. Here's the reply from SAP.
    Here's the reply from SAP :
    Purchase requisition 10000066 cannot be released
    Message no. MEPO822
    Now click the other requisition button and let say
    choose Purchase requisition 10000068,
    Execute ME54N again:
    Purchase requisition 10000068 cannot be released
    Message no. MEPO822
    Comment/explanation:
    The log incidence seems not having problem with release
    strategy as it was ok but it was the last PR was called
    everytime ME54N was called. This same as it works in enjoy
    transaction ME21N/ME22N or ME51N/ME52N.
    For example, When using ME21n or ME22n to create or change PO,
    after saving the PO. There are 2 ways to exit the transaction,
    1, enter another T-code or use /n to exit directly.
    2, use 'F3' or the 'green tick' to exit ME21n (or ME22n)
    Then you can access ME23n to see the difference.
    For the 1st way, ME23n won't display the last PO created in ME21n
    For the 2nd way, ME23n will display the last PO just created!!!
    Please see attached consulting note 595627 that explains a new
    functionality as of release 470:
    Due to performance problem, a decision had to be taken about the way to
    use transactions. If you leave transaction ME21N/ME22N via the
    exit button (F3), the expected PO will be displayed next time you use
    these transactions. But if you quit abruptly (/nXXX) the PO number
    won't be saved for the next transaction ME2?N.
    As SAP note is the official document to explain system behavior,
    this document is provided by SAP developement to explain this system
    behavior to customers.
    In your case, you had used ME54N and this was same as you use ME53N.
    The last PO always display. You may try to view Purchase requisition
    with release strategy, for example Release group R1, Rel. strategy
    R1, then after this execute transaction ME54N again, the message
    MEPO822 will not be there anymore.
    Hope this will help you guys if you're having the same problem in future.
    Thanks,
    Crystal.

  • Release strategy will not be effected when reduce in amount or when item de

    Hi All,
    I have created the PO with three line Items out of 3 items 2 items got GR and Invoce done and 3rd is open NO GR and Invoice
    Whenever I delete the 3rd item ,PO is again going for release.Our Client wants that whenever Item will be deleted or PO price will be reduced to the 5%  actual amount Po should not go into Release.
    Fields I have used in strategy is Purchasing group,Purchasing document category,Total net order value,USRC1,USRN1 and EKORG.
    Release Indicator used for this is 2    6 Changeable, new rel. if new strat. or value change/outputted with 5%
    Could you guide me What Configuration I need to change to PO shoud not go into release when PO item is deleted or net order value will be minus after release.
    Thanks in advance
    Best Regards
    Katta

    Hi
    YOu need to do SPRO setting
    SPRO > Materials Management >  Purchasing > Purchase Order > Release Process for Purchase Orders > Define Release Procedure for Purchase Order
    Execute it, new pop up will come ..
    then go to Release Indicator
    Changeability                  Short Description
    1                                        Cannot be changed
    2                                        Changeable, no new determination of strategy
    3                                        Changeable, new release in case of new strategy
    4                                        Changeable, new release in case of new strat. or val. change
    5                                        Changeable, new release if new strategy/outputted
    6                                       Changeable, new rel. if new strat. or value change/outputted
                                            Changeable, new release in case of new strategy
    There is another field Know and % Change you can use of that
    Tolerance for Value Changes During Release
    Specifies the percentage by which the value of the requisition may be increased (as a result of a change to the requisition) after the release procedure has begun.
    Use
    By specifying a percentage for changes in value, you can ensure that a requisition cannot be changed significantly after having been released.
    If the requisition is then changed, and the new value exceeds the old value by more than the percentage entered, the system issues an error message.
    The user can:
    Adjust the amount of the change so that the percentage value is not exceeded
    The release procedure continues from its current point.
    Leave the change as it is (disregarding the system message)
    The release procedure is re-started from the beginning.
    Dependencies
    The system only checks changes in the value of a requisition if the Changeability indicator is set to "4 - Changeable, new release procedure if strategy or value changed" for the release indicator Customizing.
    Hope things will help to resolve the issue.

  • Service Entry Sheet Release Procedure

    Dear all,
    I want to assign a new Plant to an existing service entry release strategy. In CL20N for Class Type 032 and maintaining the Release Group and Release Strategy I want, I hit ENTER and the Class SERVICE_RELEASE is displayed, which is correct (it is a service entry release procedure).
    Selecting the item and displaying the values for the Class, I have Plant, Order Type and Cost Centre. I added a new row, include a new Plant and hit Save. I get the message "Saving changes to assignments" and then I exit the screen.
    However, to double check that the object has been assigned to the class, I check in SPRO>Materials Mgt>External Services Mgt>Define Rel. Procedure for Service Entry Sheet> Release Strategies to confirm that the object was created in the classification for service entry release procedure. BUT IS NOT THERE!
    However, if I performed the assignment in Classification in SPRO for the release strategy, and check in CL20N, IT IS THERE!!
    How come I have created in CL20N and it is not displayed in SPRO for the same release strategy? The object assignment was successful with no error msg. It is not possible that you have done it in CL20N and you have to do the same in SPRO, right? Doesn't serve the purpose..
    Pls help.
    Thank you.

    Dear Sir,
    Go to CL02 give the Class and Class type, click on change icon
    Copy the characteristic of Plant from Char. Tab
    Then Go to CT04
    give characteristic which is copied from class and click on change icon.
    enter your new plant in Values tab, Save back
    Go to CL20N, give release group and release code for which you want to maintain the new plant.
    give the plant  and save enter.
    i hope this will help you.

  • Release procedure problem

    Hi Gurus,
              I created a release procedure for PO. i created a single chs based on total amount of PO and assigned it to a single class. then configured it for 5 release codes. all the simulation is working fine.
              But when I created the PO worth of 6 laks, which is above the level of last release code >=5 laks. when i go for release in ME29N or ME28 its giving an information message saying "document is not applicable for release procedure. in ME28 i am getting "message no documents found" for my release code and release group combination.
              Where should i have gone wrong. give me some suggestions.
    Thanks & Regards,
    Poorna.

    Hi,
    Your Maximum amount of PO which is applicable for release strategy is 5 Lakhs for your last release code.
    Now if you create the PO for 6 lakhs then how the system will consider the release strategy.
    Thats why you will not find the same in ME29N or ME28 to release the PO.
    So you need to change your Characteristics value for last release code from = 5 lakhs to >= 5lakhs.
    then system will consider the release str for any value above 5 lakhs for that last release code,
    rgds
    gsc

  • Effect of payment terms on release procedure

    Hi gurus,
    Will their be any impact of payment terms on release procedure of purchase order?
    As and when we change payment terms in a PO which is released earlier, the release procedure tab is getting disappeared
    I hope my question is clear
    Kindly reply soon
    regards,
    prasad

    Hi Prasad Sathya
    Be sure that Payment term in Po will not have any impact on release procedure. if u check the Table CEKKO throgh T code SE11 , there will not be any field for payment term. then how to create characteristic for the payment term.
    and it is not logic to create Release procedure based on the Payment terms
    friendly
    Manickss
    pl don't forget to reward if helpful

  • Regarding releasing procedure for p.o.

    hi sapgurus,
    the configuration for p.o. release procedure is working perfectly but whenever i go to me29n or me28 i am getting two step release procedure but in industry if the manager has given excess to me29n/me28 then himslef ca release the p.o by means of clicking both release steps, that means without general manager review the manager can release the p.o by means of clicking both. hence i am willing to restricate each user's acess to other stepd release procedure.
    examaple
    in me29n/me28 :-
    1) manager.
    2) general manager.
    in this case i want the manager to click on his resepctive release step and should not allow to acess the general manager's relase step's.
    thanking you
    praveer

    hi,
    please visit
    www.sap123.com
    there is a thread which  explain very clearly for the release procedure for PO.
    In PR (With classification0 there is only difference , you use CEBAN communication structure instead of CEKKO for PO)
    Regards,
    vijay

Maybe you are looking for

  • Which is better Lumia 720 or Lumia 820??????

    Lumia 820 has 1.5 ghz processor, 1gb ram bt doesn't look cool n around 6k more in price, n Lumia 720 has great look, better camera quality (both primary n secondary)  BUTTTTT jus 512 mb ram, 1 Ghz processor, so My question is- 1. Is Lumia 720 slow???

  • Querying many tables at once from a select statement for specific values

    Hi all, I'm very new to PL/SQL and have a daunting task ahead of me. I'm pretty sure our database normalization scheme is all out of whack, which I dont have the experience to fix yet, but this is the task ahead of me without getting to change or fix

  • Update for the X140e coming?

    I've been eyeing the X140e for some time, now I'm in need of a new small laptop for some tinkering, there's a 4-5 week wait before shipping (in Canada, at least). Is there a chance an updated version will be out soon, possibly with a newer CPU?

  • Spry menu doesn't appear in Yahoo! browser

    I built a spry menu into my website in dreamweaver. I then used the 'Check Page' function, and have checked it myself within Safari and Internet Explorer and the page seems to work fine. I have since found out though, that when accessing the website

  • How to use coherence snapshot feature

    Hi, Refer - http://wiki.tangosol.com/display/COH33UG/Overview+for+Implementors If long-term persistence of data is required, Coherence provides snapshot functionality to persist an image to disk. This is especially useful when the external data sourc