Why Doesn't MS Project use all of a resource's availability when resource levelling is applied?
Hi,
We are using MSProject 2010 and Project Server 2010 with Enterprise resources. All resources on all projects in the enterprise are shared resources. We are finding that after resource levelling is applied to the project some resources are only
being assigned a fraction of their total availability, and in some cases Project will assign 0 hours to a resource for several consecutive weeks even though the resource has capacity for the week the task is scheduled to start.
For example: Let's say we have a task that is scheduled to start on 1-20-14. The task is a 112 hours of effort with no constraints and one resource assigned to it. The resource is available 40 hours per week for the next 4 weeks. After resource
levelling I would expect Project to assign the resource as follows: 40 hours in week 1, 40 hours the next week and 32 hours the next week, for a total of 112 hours. Instead, Project does not assign the resource to the task until week 4 (even
though the resource has capacity on the start date of the task) and pushes the finish date out. In some weeks the resource has 0h hours showing in the timephased grid on the Resource Usage sheet. We have experimented with the levelling settings and it
does not seem to matter which boxes are checked, but following is our preferred settings:
1. Levelling Calculations set to Manual
2. Look for overallocations on a day by day basis
3. Clear levelling values before levelling is CHECKED
4. Level entire project is selected.
5. Levelling order is Priority,Standard
6. Level only within available slack is CHECKED
7. Levelling can adjust individual assignments on a task is CHECKED
8. Levelling can create splits in remaining work is UNCHECKED
9. Level resources with the proposed booking type is UNCHECKED
10. Level manually scheduled tasks is CHECKED.
Does anyone have any ideas about why Project is not using the resource's available capacity?
Thanks, Judy
Judy Washington
Hi Judy,
The resource leveling command is not a resource optimization tool. It's only job is to resolve resource overallocations by delaying tasks. It will not:
Change resource assignment units to tasks.
Ensure the resource is "fully" utilized.
For example:
Resource with max units of 100% (the default).
Task A starts on 20 January until 22 January and the resource is assigned at 75%.
Task B starts on 21 January until 23 January and the resource is assigned at 50%
The resource is overallocated on Tuesday (peak = 125%) and Wednesday (peak = 125%).
Leveling produces this result:
Project did not drop the assignment to Task B to 25% to allow it to continue while Task A was going on -- it simply delayed B (at 50%) until A was scheduled to finish.
Similar Messages
-
Why doesn't my MB Air connect automatically to my TC right when it turns on?
Why doesn't my MB Air connect automatically to my TC right when it turns on? I have my iPhoto Library stored there and I use a picture as a background but when the computer starts, the volume doesn appear to exist so therefore iPhoto doesn't find the library and doesnt show the background.
(I'm sorry for my English, but it's not my native laguage).Don't apologize for your English, I am quite certain I would be far worse in your native language, whatever it is. The drive does not connect because access privileges are connected to the user that is logging on and OS X doesn't have that information until your account has fully logged on.
-
Why doesn't my iPad recognize an update to iOS 7? When I try to update, it says, "iOS 5.1.1 Your software is up to date."
Because you have a 1st generation iPad and iOS 5.1.1 is the last update for it.
It will not get any further iOS updates beyond 5.1.1
iOS 7 requires at least an iPad 2 -
Why isn't my iMac using all of my RAM
Hi,
I've recently upgraded the RAM in my iMac (System details below) from 4GB to 12GB as it was running a little slow, I have found this has made no difference and at times seems even slower.
I was doing some work with video files and was converting a video using MPEG Streamclip and so this would be quite a memory intensive task. As it was progressing very slowly I checked my Activity Monitor and it was only using 4.49GB of the memory overall and of that only 97MB seemed to be dedicated to the MPEG Streamclip task.
Does anyone know why the system isn't using the rest of the RAM that is installed?
The highest usage process is 'kernal_task' with 838.9MB but I don't know what that is, There are a lot of items in the process list but I don't know how to remove them or even if I can or should remove them?
Any help would be greatly appreciated
Thanks
Dan
System Details:
iMac (21.5-inch, Mid 2010)
Processor - 3.06 GHz Intel Core i3
Memory - 12 GB 1333 MHz DDR3
OSX - Yosemite 10.10.2Thanks for the help:
Problem description:
I checked my Activity Monitor and it was only using 4.49GB of the 12GB memory overall
EtreCheck version: 2.1.8 (121)
Report generated 14 April 2015 23:08:13 BST
Download EtreCheck from http://etresoft.com/etrecheck
Click the [Click for support] links for help with non-Apple products.
Click the [Click for details] links for more information about that line.
Click the [Adware! - Remove] links for help removing adware.
Hardware Information: ℹ️
iMac (21.5-inch, Mid 2010) (Technical Specifications)
iMac - model: iMac11,2
1 3.06 GHz Intel Core i3 CPU: 2-core
12 GB RAM Upgradeable
BANK 0/DIMM0
4 GB DDR3 1333 MHz ok
BANK 1/DIMM0
4 GB DDR3 1333 MHz ok
BANK 0/DIMM1
2 GB DDR3 1333 MHz ok
BANK 1/DIMM1
2 GB DDR3 1333 MHz ok
Bluetooth: Old - Handoff/Airdrop2 not supported
Wireless: en1: 802.11 a/b/g/n
Video Information: ℹ️
ATI Radeon HD 4670 - VRAM: 256 MB
iMac 1920 x 1080
System Software: ℹ️
OS X 10.10.2 (14C109) - Time since boot: 3:48:23
Disk Information: ℹ️
ST3500418AS disk0 : (500.11 GB)
EFI (disk0s1) <not mounted> : 210 MB
Macintosh HD (disk0s2) / [Startup]: 499.25 GB (15.36 GB free) (Low!)
Recovery HD (disk0s3) <not mounted> [Recovery]: 650 MB
HL-DT-STDVDRW GA32N
USB Information: ℹ️
PI-239 USB 2.0 Drive 500.11 GB
EFI (disk2s1) <not mounted> : 210 MB
Windows (disk2s2) /Volumes/Windows : 499.76 GB (75.63 GB free)
Apple Inc. Built-in iSight
Apple Computer, Inc. IR Receiver
Samsung D3 Station 2 TB
EFI (disk1s1) <not mounted> : 210 MB
Time Machine (disk1s2) /Volumes/Time Machine : 2.00 TB (1.07 TB free)
Apple Internal Memory Card Reader
Apple Inc. BRCM2046 Hub
Apple Inc. Bluetooth USB Host Controller
Gatekeeper: ℹ️
Anywhere
Adware: ℹ️
Geneio [Adware! - Remove]
Kernel Extensions: ℹ️
/Applications/Parallels Desktop.app
[not loaded] com.parallels.kext.hidhook (9.0 24172.951362) [Click for support]
[not loaded] com.parallels.kext.hypervisor (9.0 24172.951362) [Click for support]
[not loaded] com.parallels.kext.netbridge (9.0 24172.951362) [Click for support]
[not loaded] com.parallels.kext.usbconnect (9.0 24172.951362) [Click for support]
[not loaded] com.parallels.kext.vnic (9.0 24172.951362) [Click for support]
/System/Library/Extensions
[loaded] com.Cycling74.driver.Soundflower (1.6.6 - SDK 10.6) [Click for support]
[not loaded] com.NCHSoftware.driver.SoundTapVirtualAudioDevice (1.0.0d1) [Click for support]
[loaded] com.delantis.kext.tcpblocknke (2.2.6 - SDK 10.6) [Click for support]
[loaded] com.logmein.driver.LogMeInSoundDriver (1.0.3 - SDK 10.5) [Click for support]
[not loaded] com.mice.driver.Wireless360Controller (1.0.0d12 - SDK 10.8) [Click for support]
[not loaded] com.mice.driver.WirelessGamingReceiver (1.0.0d12 - SDK 10.8) [Click for support]
[not loaded] com.mice.driver.Xbox360Controller (1.0.0d12 - SDK 10.8) [Click for support]
Launch Agents: ℹ️
[not loaded] com.adobe.AAM.Updater-1.0.plist [Click for support]
[loaded] com.adobe.CS5ServiceManager.plist [Click for support]
[loaded] com.google.keystone.agent.plist [Click for support]
[failed] com.logmein.LMILaunchAgentFixer.plist [Click for support] [Click for details]
[not loaded] com.logmein.logmeingui.plist [Click for support]
[not loaded] com.logmein.logmeinguiagent.plist [Click for support]
[not loaded] com.logmein.logmeinguiagentatlogin.plist [Click for support]
[loaded] com.oracle.java.Java-Updater.plist [Click for support]
[failed] com.trusteer.rapport.rapportd.plist [Click for support] [Click for details]
[loaded] org.macosforge.xquartz.startx.plist [Click for support]
Launch Daemons: ℹ️
[loaded] com.adobe.fpsaud.plist [Click for support]
[loaded] com.adobe.SwitchBoard.plist [Click for support]
[loaded] com.delantis.tcbblocknke_load_kext.plist [Click for support]
[not loaded] com.delantis.TCPBlock.plist [Click for support]
[loaded] com.google.keystone.daemon.plist [Click for support]
[not loaded] com.logmein.logmeinblanker.plist [Click for support]
[not loaded] com.logmein.logmeinserver.plist [Click for support]
[loaded] com.logmein.raupdate.plist [Click for support]
[running] com.mice.360Daemon.plist [Click for support]
[loaded] com.microsoft.office.licensing.helper.plist [Click for support]
[loaded] com.oracle.java.Helper-Tool.plist [Click for support]
[running] com.trusteer.rooks.rooksd.plist [Click for support]
[loaded] net.sourceforge.MonolingualHelper.plist [Click for support]
[loaded] org.macosforge.xquartz.privileged_startx.plist [Click for support]
User Launch Agents: ℹ️
[loaded] com.adobe.ARM.[...].plist [Click for support]
[failed] com.apple.CSConfigDotMacCert-[...]@me.com-SharedServices.Agent.plist [Click for details]
[loaded] com.divx.agent.postinstall.plist [Click for support]
[loaded] com.genieo.completer.download.plist [Adware! - Remove]
[loaded] com.genieo.completer.ltvbit.plist [Adware! - Remove]
[running] com.genieo.completer.update.plist [Adware! - Remove]
[loaded] com.valvesoftware.steamclean.plist [Click for support]
User Login Items: ℹ️
Dropbox Application (/Applications/Dropbox.app)
AdobeResourceSynchronizer Application (/Applications/Adobe/Adobe Reader.app/Contents/Support/AdobeResourceSynchronizer.app)
AirServer UNKNOWN (missing value)
Internet Plug-ins: ℹ️
GameFacePlugin: Version: GameFacePlugin 1.8.0.1 - SDK 10.5 [Click for support]
OVSHelper: Version: 1.1 [Click for support]
Default Browser: Version: 600 - SDK 10.10
Flip4Mac WMV Plugin: Version: 2.4.4.2 [Click for support]
OfficeLiveBrowserPlugin: Version: 12.3.1 [Click for support]
Unity Web Player: Version: UnityPlayer version 4.6.1f1 - SDK 10.6 [Click for support]
AdobePDFViewerNPAPI: Version: 10.1.12 [Click for support]
FlashPlayer-10.6: Version: 17.0.0.169 - SDK 10.6 [Click for support]
DivXBrowserPlugin: Version: 2.2 [Click for support]
LogMeIn: Version: 1.0.935 - SDK 10.7 [Click for support]
Flash Player: Version: 17.0.0.169 - SDK 10.6 [Click for support]
LogMeInSafari32: Version: 1.0.935 - SDK 10.7 [Click for support]
iPhotoPhotocast: Version: 7.0
OnLiveGameClientDetector: Version: OnLiveGameClientDetector 1.0.0 [Click for support]
AdobePDFViewer: Version: 10.1.12 [Click for support]
QuickTime Plugin: Version: 7.7.3
SharePointBrowserPlugin: Version: 14.3.4 - SDK 10.6 [Click for support]
Silverlight: Version: 5.1.30514.0 - SDK 10.6 [Click for support]
JavaAppletPlugin: Version: Java 8 Update 25 Check version
User internet Plug-ins: ℹ️
Google Earth Web Plug-in: Version: 7.1 [Click for support]
Safari Extensions: ℹ️
Open in Internet Explorer
DivX Plus Web Player HTML5 <video>
Omnibar [Adware! - Remove]
Ebay Shopping Assistant [Adware! - Remove]
Slick Savings [Adware! - Remove]
Amazon Shopping Assistant [Adware! - Remove]
Searchme [Adware! - Remove]
3rd Party Preference Panes: ℹ️
AirServer Preferences [Click for support]
Connect360 [Click for support]
DivX [Click for support]
Flash Player [Click for support]
Java [Click for support]
TCPBlock [Click for support]
XBox 360 Controllers [Click for support]
Time Machine: ℹ️
Skip System Files: NO
Auto backup: YES
Volumes being backed up:
Macintosh HD: Disk size: 499.25 GB Disk used: 483.89 GB
Destinations:
SAMSUNG [Local]
Total size: 2.00 TB
Total number of backups: 33
Oldest backup: 2015-01-22 01:17:29 +0000
Last backup: 2015-04-14 20:57:20 +0000
Size of backup disk: Excellent
Backup size 2.00 TB > (Disk size 499.25 GB X 3)
Top Processes by CPU: ℹ️
119% MPEG Streamclip
17% mds
4% WindowServer
3% syncdefaultsd
1% backupd
Top Processes by Memory: ℹ️
477 MB softwareupdated
180 MB Google Chrome
142 MB Finder
134 MB Google Chrome Helper
129 MB MPEG Streamclip
Virtual Memory Information: ℹ️
7.60 GB Free RAM
3.48 GB Active RAM
749 MB Inactive RAM
1.06 GB Wired RAM
10.42 GB Page-ins
377 KB Page-outs
Diagnostics Information: ℹ️
Apr 14, 2015, 08:29:49 PM /Library/Logs/DiagnosticReports/fm_2015-04-14-202949_[redacted].cpu_resource.di ag [Click for details]
Apr 14, 2015, 08:03:58 PM /Library/Logs/DiagnosticReports/Final Cut Express_2015-04-14-200358_[redacted].cpu_resource.diag [Click for details]
Apr 14, 2015, 07:21:54 PM /Users/[redacted]/Library/Logs/DiagnosticReports/rapportd_2015-04-14-192154_[re dacted].crash
Apr 14, 2015, 07:17:33 PM Self test - passed
Apr 13, 2015, 08:10:27 PM /Library/Logs/DiagnosticReports/Adobe Photoshop Elements_2015-04-13-201027_[redacted].cpu_resource.diag [Click for details]
Apr 12, 2015, 11:36:09 PM /Users/[redacted]/Library/Logs/DiagnosticReports/rapportd_2015-04-12-233609_[re dacted].crash
Apr 12, 2015, 07:43:45 PM /Library/Logs/DiagnosticReports/Final Cut Express_2015-04-12-194345_[redacted].cpu_resource.diag [Click for details]
Apr 12, 2015, 07:39:28 PM /Users/[redacted]/Library/Logs/DiagnosticReports/rapportd_2015-04-12-193928_[re dacted].crash
Apr 12, 2015, 07:21:05 PM /Library/Logs/DiagnosticReports/Final Cut Express_2015-04-12-192105_[redacted].cpu_resource.diag [Click for details]
Apr 12, 2015, 06:29:56 PM /Library/Logs/DiagnosticReports/MPEG Streamclip_2015-04-12-182956_[redacted].cpu_resource.diag [Click for details]
Apr 12, 2015, 05:29:30 PM /Library/Logs/DiagnosticReports/Final Cut Express_2015-04-12-172930_[redacted].cpu_resource.diag [Click for details]
Apr 12, 2015, 04:17:13 PM /Library/Logs/DiagnosticReports/Adobe Photoshop Elements_2015-04-12-161713_[redacted].cpu_resource.diag [Click for details]
Apr 12, 2015, 12:36:19 PM /Library/Logs/DiagnosticReports/Mp4Split_2015-04-12-123619_[redacted].cpu_resou rce.diag [Click for details]
Apr 12, 2015, 11:38:28 AM /Library/Logs/DiagnosticReports/HandBrake_2015-04-12-113828_[redacted].cpu_reso urce.diag [Click for details]
Apr 12, 2015, 11:04:39 AM /Users/[redacted]/Library/Logs/DiagnosticReports/rapportd_2015-04-12-110439_[re dacted].crash
Apr 13, 2015, 11:19:51 PM /Library/Logs/DiagnosticReports/OnyX_2015-04-13-231951_[redacted].hang
Apr 14, 2015, 10:17:30 PM /Library/Logs/DiagnosticReports/MPEG Streamclip_2015-04-14-221730_[redacted].cpu_resource.diag [Click for details]
Apr 12, 2015, 11:35:09 AM /Users/[redacted]/Library/Logs/DiagnosticReports/garcon_2015-04-12-113509_[reda cted].crash -
SAP job not using all dialog processes that are available for parallel processing
He Experts,
The customer is running a job which is not using all the dialog processes that are available for parallel processing. It appears to use up the parallel processes (60) for the first 4-5 minutes of the job and then maxes out about 3-5 processes for the remainder of the job.
How do I analyze the job to find out the issue from a Basis perspective?
Thanks,
ZahraHi Daniel,
Thanks for replying!
I don't believe its a standard job.
I was thinking of starting a trace using ST05 before the job. What do you think?
Thanks,
Zahra -
why doesn't my imac tell me what is being dowloaded when i can see that my modem is downloading something?
There are many reasons for the activity light on your cable or DSL modem to be flashing. Your Mac could be checking for or downloading updates in the background. It could be checking e-mail. It could be syncing a cloud service like iCloud, Dropbox, etc.
If your Mac isn't the only thing on the network, then the light could be flashing due to some other device on the network downloading an update, syncing something, etc.
And, of course, it's always possible your network is under attack by an automated botnet or something. You'd be surprised how often a device exposed to the internet directly - as a modem like this is - will be hit with attempted attacks, in an attempt to find things that are vulnerable. -
Why doesn't V8.01 keep all of the favicons next to web pages as previous version did?
A lot or maybe most of my bookmarks are lacking the web sites favicon even after double clicking on the bookmark. All that is visible is a small black rectangle whee the favicon should be, and then the usual web info.
Thanks,
TomThanks for your help
I installed the first addon only. I can't tell if it is doing anything yet or not.
Even clicking on my list of bookmarks only helps a little.
But more importantly, why is Firefox getting worse as they upgrade?
Chrome works sooo much better it just doesn't have the addons yet to use it full time.
3.??? was soo much better then 5 was ok 6 was worse now 8 seems even worse but I've just had it installed for 2 days.
Maybe other people have a different plan of attack.
See you,
Tom -
Why doesn't Premiere Pro use my GPU when rendering?
Hello all,
I bought two GTX 770s for the purpose of rendering super fast with premiere's wonderful Mecrury Playback Engine. The issue I'm having is, I'm rendering a project right now, but it's not making any use of my GPUs whatsoever. My CPU is hovering at 55-80% usage, so I was just wondering what was going on.
Just kind of upsetting that my investment has gone to waste. Thanks!Tweakers Page - Exporting Style
From that article:
The video card and hardware MPE is not the holy grail. It helps in some circumstances to improve performance and rather significantly, but in other instances it does not help at all, as is indicated in the link above. People often think that installing a super fast video card will reduce export times by a significant amount of time. That is not true. It only helps in a limited number of situations. -
Why doesn't Twitter & Facebook use the sounds you set in your sound settings?
When Twitter send a notification, its uses the Apple message sound, instead of the "Tweet" sound that is the default sound in your sound settings. For Facebook, it either sends the same Apple sound, or no sound at. Facebook is supposed to use the "Swish" sound. Does anyone know how to fix or configure that correctly? I did log in both apps through my settings instead of just using the apps.
Hi Judy,
The resource leveling command is not a resource optimization tool. It's only job is to resolve resource overallocations by delaying tasks. It will not:
Change resource assignment units to tasks.
Ensure the resource is "fully" utilized.
For example:
Resource with max units of 100% (the default).
Task A starts on 20 January until 22 January and the resource is assigned at 75%.
Task B starts on 21 January until 23 January and the resource is assigned at 50%
The resource is overallocated on Tuesday (peak = 125%) and Wednesday (peak = 125%).
Leveling produces this result:
Project did not drop the assignment to Task B to 25% to allow it to continue while Task A was going on -- it simply delayed B (at 50%) until A was scheduled to finish. -
Why doesn't Garage Band use wav files?
I would like to use Garage Band to edit wav files I have, but it won't recognize them - only seems to work with songs I imported from cassette tapes. Why?
Thanks for the suggestion. I do have the option to use Total Recorder in Windows which I also have on my Mac. That is also free and I used it a lot when I had PC. So guess that is the route I will take. Just thought I would see if I could do it in Garage Band as the sound view is bigger than in TR, and also I wouldn't have to switch over to Windows. By the way, does Audacity take up a lot of space on the hard drive? I don't want to clog it up with too much stuff.
-
Why doesn't my account use the Mavericks unlock screen?
I have a 2007 MacBook Pro. I have upgraded it through every version of OS X released since I purchased it, currently running Mavericks. I noticed on Lion that my user account does not use the new screensaver unlock dialog - the lock screen has not changed. Any new account I create on my computer uses the new lock screen dialog. Just not my account. I've asked on StackExchange, no answers. I've tried every option in System Preferences related to lock screen or screensaver. I've tried deleting every plist I could find that seemed remotely related. No luck. When my screensaver is triggered, the password dialog I see is this:
This is a direct screen capture of my lock screen. My user account name is automatically filled in (grayed out here). This is not supposed to be the way it works. Every other Lion+ machine we have in our lab group shows user icon and a password field, NOT what I see above. The screen I see when first starting the computer is correct - list of users, with icons and password fields. The issue I am reporting has NOTHING to do with the main login screen, just the screensaver unlock dialog. This is relatively minor, but it is driving me absolutely batty: Why does my account, and my account ONLY, display this behavior?In Settings>General>Restrictions is the Camera turned off?
Matt -
After a recent OS update, Clamshell mode quit working. I couldn't find any Apple documentation
that would help. So many people were stabbing around in the dark, until I finally found the following information
that is lacking from any Apple documentation that I've been able to find.
Here's what I found to be the most helpful:
Forcing a MacBook to use the External Monitor:
I tried about everything: Rebooting, switching off completely, removing and inserting the Thunderbolt->HDMI adapter etc.
The only thing that finally worked was the following:
1. Take it out of the dock and connect to Power and HDMI to the TV.
Shut down the Mac. Turn it on and close the lid. It will now boot up on the external screen.
Log onto the Mac, and put it in sleep mode (Option-Command-Eject).
Put it back into the dock and wake it up with the spacebar.
It should be OK now... until the next update...
Note: One indication that you’re going to have extreme trouble with this is when (occasionally and without reason) the Mirroring Options icon shows up on the top icon bar.
Other useful commands:
“Command + F1” puts PC in Two-Screen MIRROR mode.
If it’s REALLY being stubborn, do the following (Clamshell Must be open
to see the arrangement tab.):
In System Preferences > Display on the MacBook screen there should be an Arrangement tab when you have the MacBook hooked up to the TV and both screens working. When you click the Arrangement tab do you see two monitors side by side? One of them will have a Menu Bar at the top. Just click on the Menu Bar and drag it to the second monitor (Yes, I know, it’s hard to grab ahold of it...) That will make your EXTERNAL monitor your main screen.
You can now use your MacBook in Clamshell Mode with a wired or Bluetooth keyboard and mouse. http://support.apple.com/kb/HT3131 When you disconnect from the TV, make sure it’s asleep (Option+Command+Eject buttons) or your Menu Bar will automatically change back to the MacBook.After a recent OS update, Clamshell mode quit working. I couldn't find any Apple documentation
that would help. So many people were stabbing around in the dark, until I finally found the following information
that is lacking from any Apple documentation that I've been able to find.
Here's what I found to be the most helpful:
Forcing a MacBook to use the External Monitor:
I tried about everything: Rebooting, switching off completely, removing and inserting the Thunderbolt->HDMI adapter etc.
The only thing that finally worked was the following:
1. Take it out of the dock and connect to Power and HDMI to the TV.
Shut down the Mac. Turn it on and close the lid. It will now boot up on the external screen.
Log onto the Mac, and put it in sleep mode (Option-Command-Eject).
Put it back into the dock and wake it up with the spacebar.
It should be OK now... until the next update...
Note: One indication that you’re going to have extreme trouble with this is when (occasionally and without reason) the Mirroring Options icon shows up on the top icon bar.
Other useful commands:
“Command + F1” puts PC in Two-Screen MIRROR mode.
If it’s REALLY being stubborn, do the following (Clamshell Must be open
to see the arrangement tab.):
In System Preferences > Display on the MacBook screen there should be an Arrangement tab when you have the MacBook hooked up to the TV and both screens working. When you click the Arrangement tab do you see two monitors side by side? One of them will have a Menu Bar at the top. Just click on the Menu Bar and drag it to the second monitor (Yes, I know, it’s hard to grab ahold of it...) That will make your EXTERNAL monitor your main screen.
You can now use your MacBook in Clamshell Mode with a wired or Bluetooth keyboard and mouse. http://support.apple.com/kb/HT3131 When you disconnect from the TV, make sure it’s asleep (Option+Command+Eject buttons) or your Menu Bar will automatically change back to the MacBook. -
I keep getting a message that I have "used 100% of the data in my prorated plan." However, when I check I still have over 3 GB left in my regular plan, but the full promotional 1GB is used up. I hope that the promotional data is not just a way to give me an overage charge.
The txt indicates that you have prorated data - suggesting that you made some type of change mid-cycle - resulting in you only have a percentage of your data available for the remainder of your bill cycle. For example, if you make a change 3 wks into your 4 wk cycle you then have 25% of your data available for the remaining 1 wk. If that 25% is 500MB and you USE 501+MB during that 1 wk - you have then used 100% of the prorated (25%) data.
-
Why is adobe reader XI using all my resources and keeps locking up?
Win8,dual core2.5ghz,6gig mem, Fire fox. Can't use a product that preforms like this.
Using what resources?
Locking up how; standalone Reader, or browser plugin? In what browser? -
alright.
made it a couple times. no problem. but for right now either i have a problem with my mac or here are some nervewrecking coincidences going on to make my life just that more complicated:
as in every youtube-tutorial about how to get pictures into imovie and in lots of macusers logic to get a photo into imovie you do this with the function of the mediacenter at the center-right. so you go there click on the iphoto and to fast forward everything go for the searchbar and look for the photo you want, drag it to the upper left side or if you changed setting bottom left side and then, what comes next... yep... right... you drop it.... well yeah, if there would be the possibility => i got no possibility to drop my pictures.
however, this is no problem for me with my videos, with my audio but for some random reason photos are unpossible for me to drag there.
somebody an advice? something with the setting? it's normal jpeg, it's imovie from the year 2009 which is version 8alright, you guys, forget about what i just said... i know why it's not working, it is a file that is not as a quadratic picture but one that is just cut out of a quadratic picture. so it's probably that's why it is not working....
so let's take this thing to a different level:
how can i get things that i cut out from editors like gimp and made a jpeg file out of it get into imovie when they are not quadratic?
My idea is to make a video and add in the foreground some little pictures. something like a logo that i can't make with the writing software of imovie. So hoy can i add such a thing or is it even possible?
Maybe you are looking for
-
Trying to output to a Samsung 40" LCD TV correctly.
Problem: I have hooked my macbook up to my Sony 40" LCD TV model LN-S4041D via an apple (Mini-DVI to DVI adapter) and then a (DVI to HDMI cable). My TV does not have a DVI input just HDMI and all of the other analog inputs. When I hook it up my i get
-
How to maintain inspection type at the time of material creation using LSMW
Hi All, I have a differnet Issue. I am using a std. LSMW to create the materials. But now using same LSMW i have to maintain Inspection types(ART-RMQAM) for the materials to be created. How this can be done. This filed is not found in any structures
-
I am unable to launch Dreamweaver Trial version
I am unable to launch Dreamweaver Trial version which I have just downloaded. I am running Mac OS X 10.6.8 and have also performed a software update. Can anyone advise? When launching the application, I get the following error: Adobe Dreamweaver CC 2
-
hi can I have a reply to above question: I just upgraded my old versionj 3 of photoshop elements to v13 when I import photos they are not imported in the same order they are mixeds up
-
How can i check PPAPI status of Flash Plugin in Chrome using JavaScript
Hi, Can anybody help me to get PPAPI details of Flash Plugin installed in Chrome using JavaScript ? Thanks in advance. Regards, Pawan