Why the basic finish date is not adjusted in planned orders

Hi, all.
Can anybody help me to understand:
"Why the basic finish date is not adjusted in planned orders during
forward scheduling, but in production order basic finish date is adjusted?
It is look like non-coordination between groups of developers.
And lead to situation, when planner don't see in MD04 when he can really wait material receipt. He must go to planed order and check production data there, it's unusable."
Am I right, or SAP have it's own logic.

Hi,
Production orders are different story. Since production order is a constant element, they are not created in the course of MRP, basic dates can be adjusted. In production order basic finish date is adjusted, but you won't see for the upper level materials', basic dates of the planned orders adjusted according to the prodcution order you create. Production order is consistent within itself in terms of date and is not dependent to other elements of MRP, but planned orders are not like that.
MRP creates planned orders whose basic finish dates are calculated by subtracting goods receipt time from production start date of the source of requirement. MRP works backwards without changing directions. Meanwhile if any production finish date is calculated different than the basic finish date due to forward scheduling, in order not to violate the alignment between the basic finish date and source of requirement's start date, basic finish date is not adjusted. If it was, dates of all the planned orders calculated so far at the upper levels of the BOMs had to be recalculated, otherwise all the consistency of all the dates is violated. This cannot be done because changes in any level affects all lower levels.

Similar Messages

  • Need to count the number of times the Basic Finish data chages

    HI Expertes,
    I have a requirement I need to count number of times the Basic finish date chaged for PM work order. I went throug our forums I got some info like using a standard function module
    CHANGEDOCUMENT_READ_HDRS_ONLY
    CHANGEDOCUMENT_READ_HEADERS
    CHANGEDOCUMENT_READ_POSITIONS
    But all the above function module will not be suitable for my requirement since  CHANGEDOCUMENT_READ_HDRS_ONLY it gives whole changes but my requirement is just need number of changes occurred in Basic Finish date but CHANGEDOCUMENT_READ_POSITIONS can give the filed number which has been changed but still I need change id.
    So kindly suggest me wether there is any other Standard FM to get number of changes occurred in Basic Finish date?
    Thanks,
    Rajesh

    Hi Debbie,
         To count the number of groups please try the folling steps:
    1) Create a formula @reset and place this formula in the page header
        whileprintingrecords;
        numbervar i:=0;
    2) Create another formula @evalgroup place this in the group header where you want to count the values.
        whileprintingrecords;
        numbervar i:= i+1;
    3) Create another formula @display and place this in report footer.
        whileprintingrecords;
        numbervar i;
    In order to display the count of details which are printing in the detail section place the eval formula in the detail section and the @display formula in the group footer.
    Hope this helps!!!
    Regards,
    Vinay

  • Collective orders header order basic finish date is not changing

    Hai all,
    I am working on collective orders. The header order has Basic finish date as 17.05.2011 . Now i have changed this date to 10.05.2011 and re scheduled the order . But again system changing the Basic finish date to 17.05.2011. how to solve this.
    In the outline dates also i have given finish date 10.05.2011 it is remaining the same but order Basic finish date is not changing and schedulded dates are also not changing. can anybody help.

    Hi gurus,
    In a collective order suppose the lead order is having three child orders.  Kindl
    If one of the child order is partially confirmed is the entire collective order can be rescheduled.
    If one of the child order is Fully confirmed is the entire collective order can be rescheduled
    Can any body help me out

  • The Basic Finish date is a Day earlier than Planned date

    Dear Experts,
    I am getting a strange behaviour about Maintenance order Basic Finish Date when generated from Maintenance Plan. I have Customizing settings (TCode : OPU7) Adjust: "Adjust Basic dates, adjust dep reqmts to order start date" and scheduling type : Backwards in Time. For this setting Order Basic Finish Date is a day earlier than Planned date , but when Schduling type is Backwards instead of Backwards in Time, Basic Finish date is same as Planned date.
    Example: The start of cycle of a monthly plan is 14-Nov-2010, 1st Planned date is 14-Dec-2010. When Scheduling type is " Backwards in time" , the order generated is having Basic Finish Date as 13-Dec-2010 .And when Scheduling type is "Backwards" , Basic finish date is 14-Dec-2010.
    Thank you.
    -Malay-

    Hi there,
    Please check the primilinairy buffer in your strategy package. This field have an effect on your order start date.
    But I agree on Pete, you should use a forward planning.
    Regards,
    Johan
    Edited by: Johan Zeeman on Dec 17, 2010 11:29 AM

  • Why the time and date is not correct when I save a waveform in txt format, using Labview 6.1?

    I am using Labview 6.1 and my operation system is Windows 98. The date/time properties is configured in the Windows (time and date in the control panel is correct). I generated a waveform using Basic Function Generator.vi and saved this using the Export Waveforms to Spreadsheet File.vi. When I opened this file the date and time was wrong. Only the delta t was correct and it did not show the date neither the time, only a float number. How can I adjust the correct time?

    Actually, the date/time is correct, it is expressed as seconds since January 01, 1904.
    In order to print the string version of the date/time from your file, you will need to write a utility that converts the date/time to a string or series of strings in whatever format you wish. This can be done by reading the first line (I assume that is the line with the time on it), formatting the date/time into a string, and writing over this information in the file.
    The waveform VIs were meant to be used internally to read and write waveform data. Any use beyond that should require you to add formatting and other information/data as necessary.

  • Why the "basic" authentication template is used?

    Dear all,
    I created an EJB and expose its only business method as a web service. The web service configuration named "Config1" has no security settings at all. Transport protocol is "HTTP" and authentication mechanism is "NONE". But in the visual administration, under the "Security Provider" service, the authentication templeat is "basic" and the login module is "BasicPasswordLoginModule". Can anybody tell me what's the reason?
    Thanks + Best Regards
    Jerome

    Hi,
    Production orders are different story. Since production order is a constant element, they are not created in the course of MRP, basic dates can be adjusted. In production order basic finish date is adjusted, but you won't see for the upper level materials', basic dates of the planned orders adjusted according to the prodcution order you create. Production order is consistent within itself in terms of date and is not dependent to other elements of MRP, but planned orders are not like that.
    MRP creates planned orders whose basic finish dates are calculated by subtracting goods receipt time from production start date of the source of requirement. MRP works backwards without changing directions. Meanwhile if any production finish date is calculated different than the basic finish date due to forward scheduling, in order not to violate the alignment between the basic finish date and source of requirement's start date, basic finish date is not adjusted. If it was, dates of all the planned orders calculated so far at the upper levels of the BOMs had to be recalculated, otherwise all the consistency of all the dates is violated. This cannot be done because changes in any level affects all lower levels.

  • Want last date of the month as default basic finish date for the Proc order

    For forward scheduling type in process order, irrespective of the start date i want last date of the month as my  basic finish date.
    Ex start date can be 01/10/2009 or 15/10/2009, but the basic finish date should be 31/10/2009.

    Hi Sam,
    sorry to say , its not possible in standard SAP.
    1) If, on order creation, a planned order exists for the production order/ process order, the basic dates are copied from the planned order.
    2)If no planned order exists on order creation, you must specify at least one basic date.
    The scheduling type determines the basic dates that you must specify. and it useses timings from routings for scheduling.
    so may be you need some work around.
    explain your requirement why do you want to fix it for the last day of month and other constraints, may be we can find some way.
    Regards
    Ritesh

  • Basic start date and basic finish date in the maintenance sub-order

    Hi guys,
    when I create a maintenance sub-order by the transaction IW36 are the Basic start date and the Basic finish date taken,inherited from the principal Maintenance order?And if it is in this way,is there the possibility to put these two dates as a current day only on the  maintenance sub-order ?Thanks in advance...
    Maximilian

    Here is my code
      DATA : lv_date_diff TYPE i.
      lv_date_diff =  caufvd_imp-gltrp - caufvd_imp-gstrp.
      caufvd_exp-gstrp = sy-datum.
      caufvd_exp-gltrp = sy-datum + lv_date_diff.
    This is a 4 year old answered message. Please open a thread for your specific query.
    -Paul
    Moderator
    Edited by: Paul Meehan on Nov 24, 2011 8:42 AM

  • Change of Basic Finish Date for a Maintenance Order

    Hi Experts,
    I have a requirement where I need to change the Basic Finish Date of an order. Currently in config for order type and plant combination, scheduling parameters are set as:
    Adjust to Basic Finish Dates
    Automatic Scheduling.
    If in an order, I remove the tick for Automatic Scheduling, I am able to change that but I am not supposed to do that.
    Can you suggest me how thisissue can be resolved. Remember, changing the Config is not an option.
    Regards...

    hi
    Since you have done the adjust basic dates ,kindly change the operation dates ,which will automatically change the dates specified in the operation dates
    regards
    thyagarajan

  • Basic Finish Date in Service Order

    Hi Gurus,
      I want to change the Basic Finish date in the service order. The
    system is allowing me to change it in the change mode of service order
    (IW32), but after saving when I come back and see the order again, it is
    showing the old date only. I want to change the Basic Finish date as
    10.09.2007. Could anybody please guide?
      Prassee

    Hi Thyagarajan,
    Thanks, I have already checked the same. For the order type and palanning plant, the date adjustments set as " Adjust basic date.......", but still it is not allowing me to change the basic date.
    Prasanth
    > hi prasanth
    >
    > check for you order what scheduling parameters are
    > you maintained.if the Adjust shchduling is set as" DO
    > not adjust basic dates:, then i think your problem
    > will occur.
    >
    > regards
    > thyagarajan

  • IW31 - Modify Basic Finish Date

    Hi Gurus,
    I'm looking for a badi or user exit that allows me to modify the Basic Finish Date in the IW31/IW32 transactions just before saving.
    I've tried the following ways without any succes:
    - IWO10009 - Function Module --> EXIT_SAPLCOIH_009
    This user exit is treggered before saving (as I would like to) but I'm not able to modify any field. It is used to active the automatic order release when saving the order.
    - IWO10012 - Function Module --> EXIT_SAPLCOIH_012
    It allows me to modify the CAUFVD-GLUZP, CAUFVD-GLTRP fields, but this user exits is triggered when the priority field is modified.
    - BAdi WORKORDER_UPDATE --> I've tried to implement this BAdi but all parameters in the methods AT_SAVE, BEFORE_UPDATE are type = IMPORTING so SAP does not allow to modify them. I've tried it using field symbols but I thing that I've done something wrong.
    Is there another way to do it?
    Thanks and regards,
    Sergi.
    P.D.: I've looked for it in the forum threads but I could not find any valid answer.

    You can use function module CO_IH_SET_HEADER in user-exit IWO10009 (at save).
    Search for more details using "CO_IH_SET_HEADER"
    Be very careful when using this technique as it caould cause data inconsistencies.
    PeteA

  • MO basic finish date how to compute

    Hi, i create a MO, qty = 42000, basic start date 200/12/01, the system automatic calculation basic finish date 2009/02/19, Can you tell me the basic finish date how to compute?
    our system setting:
    standard margin key = 000
    scheduling type = Forward

    Hi,
        it will consider your processing time if u have made a production order based on standard value & base qty u have given in routing. plz check them.
       In case of Planned order creation generally it will take ur in house production time but if u have maintained base qty & setup time, processing time etc in work scheduling view then it will take finish time according to that & it will not consider in house production time.
    Regards
    Rakesh

  • Changing basic finish date in Preventive maintenance orders

    Hi Experts,
    My requirement is to block PP work centre when maintenance schedule the equipment for preventive maintenance. I am making system condition as zero in generated preventive maintenance order but basic finish date is not changing in the order automatically. Can anybody please explain how to bring this? Finally my requirement is system should change basic finish date and time as time given in operation of task list.
    Thanks in advance.
    best regards,
    Srinivas M

    Hi Praveen,
    I have done all setting and tested but there is no change.
    My client requirement is like this - whenever maintenance plans are scheduled, for the scheduled dates, production capacity should not be considered by production. We could do this for breakdown orders but not happening for PM orders unless we change the finish date.
    The issue is to get the finish date automatically when scheduling maint.plans with respect to values given in operations. Please suggest how to get the  basic finish dates automatically.
    best regards,
    -Srinivas

  • Material Availability Date and Corresponding Basic finish date

    Hi experts,
    I have one requirement from my Business for updating Basic Finish date based on the Material availability date
    Requirement goes like this, When we enter a Component of 100 qty  in the service order , if stock is not available we get system status as MSPT and IWBK we can see how much quantity confirmed
    But i dont see any table or report which shows when this material can be available for further delivery. Based on the next available material date i have to change the basic finish date in the service Order
    Please let me know if you any report available for this or any standard approach. I want to know if any exist to leverage this functionality and logic how to get this accomplished
    thanks
    sarvan

    Sarvan,
    You would need to perform this check when saving the work order as there could be multiple components all with differing ATP dates.
    But a development could do something like:
    Read all active/open components/materials on the work order
    Determine the availability data for each component/material
    Determine the latest of the above dates
    Apply this date to the order Basic Finish Date
    You would need to ensure your scheduling parameters do not set this date back to its original value (OPU7).
    You could achiev the above through user-exit IWO10009 (SMOD) or BADI WORKORDER_UPDATE (SE18).
    PeteA

  • Basic finish date exit issue

    Hello Gurus
    I have a requirement to bring the basic finish date based on the priority calculation date from the maintenance plan for auto generated work orders. Since its defaults to the start date, I am trying to use the user exit : IWO10012 Maintenance order: Priority treatment on central header.
    I talked to developer and it seems like he is facing issues on and off using this exit.He cannot figure out when it gets called.  He has a debugging break point in the user exit which will take to the code of the exit whenever it is called.  It gets called in some circumstances, but not in othersu2026 and he cannot find any reason to it.  When it does get called, however, it does its job of updating the Basic Finish Date.
    So what could be the issue in this situation ?
    Mahee

    Mahee,
      On the order side, This exit will only be called during create.I dont think this will be called on change mode or when the priority is changed.
    Regards
    Narasimhan

Maybe you are looking for

  • Switch from classic to Extended Classic Scenario- Impact

    Hello, We are proposing to switch from Classic to Extended Classic Scenario. We are on SRM_SERVER 550,Sp7 and SAP 4.7 backend. We want to know if this is technically feasible to switch and have less/no impact on existing transactional data and master

  • Plz help for upgrading to new OS X Mavericks

    I purchased MacBook Pro in May'11 with Mac OS 10.6.6 installed. Few months back i downloaded DMG file elsewhere for upgrading to10.6.8 and successfully upgraded without loosing any file & other OS i.e. WINDOWS XP. Now i wish to upgrade to new OS X 10

  • Does Smartview 11.1.1.3 work on Windows 7?

    does Smartview 11.1.1.3 work on Windows 7? I think it is officially not supported. Anyone with luck using SV on windows 7 and office 2010? Office 2010 is very similar to Office 2007 (which is supported, I thijnk, by SV 11.1.1.3)

  • JSP page "cannot resolve symbol"

    Hi, I'm using j2sdk1.4.2_01 and tomcat-5.0.13. I'm developing within Eclipse 3.0.0 with the Tomcat plugin. In my project ("Agenda2") i only created one class ("Persona"), that is correctely compiled (%TOMCAT_HOME%\webapps\Agenda2\WEB-INF\src\Persona.

  • How do I get my Safari screen from 1/2 back to full page?

    I had opened calculator and must have inadvertently hit a key, because all of sudden my safari screen went to 1/2 a  page.  I tried some of the comments I found here, but nothing worked.  How do I get it back to full screen?