WIP Discrete Job status

Hi Experts,
Is it possible to add a custom Discrete job status? We would like to use it to mass
close jobs.
Thanks.
Gregg

Right now users are manually updating the status to Complete(irrespective of quantity complete of not). They want this process to be automated for the jobs after three days from scheduled start date, since they have so many in a day. For automation is there any available functionality or If write a custom program to update the status what other tables do i have to update other than wip_discrete_jobs?
Any ideas, appereciate your help.
Thanks.

Similar Messages

  • Serialization Control in WIP Discrete JOB

    Hi everybody,
    I want perform a Discrete job which consists of 7 operations.10, 30, 50 and 70 are with Count Point & Auto Charge options and the 20, 40, 60 operations are without Count Point and without Auto Charge. In the 30th operation the Serial Numbers will be generated for the Final assembly.
    In routings i have specified the operating sequnce number i.e 30 in routing details window.
    If we specify any Item as under Serial Control (Predefined) in Inventory then Serial Numbers button will be enabled in the WIP Discrete JOBS window. There we can assign the Serial Numbers to the JOB quantity.
    But I am not able to perform neither Move Transactions nor Material Transactions in WIP even though my job is in Released status.My JOB name is not available in Move Transactions window.
    Please help me to solve this problem.
    regards,
    VAS

    hai,
    user guide says you can perform serialized move trans through oracle mobile supply chain applications using a mobile device,for further details you can refer metalink Is Serial Number Association Functionality Only Available Using Supply Chain Mobile Applications? doc:-note:265512.1,if you want to track serial numbers thro desktop appl then you will have have start serial tracking from the first operation itself but in your case it doesn't happen like that so i think you will have to use mobile device,once the serialization start operation number appears when you release a discrete job ,you cannot transct thro desktop appl,hope you are clear,post your feedback

  • Serial control in wip discrete jobs

    Hi gurus,
    i had created a discrete job with serial control enabled for components.
    but when trying to query for job im unable to get it.
    so whats the mistake i did?
    when going thru oracle white papers they mentioned to change profile option
    TP:WIP Operation backflush setup to online processing mode.(for having serial control in job)
    but i cant able to get the profile option in wip responsibilty.
    will u pls guide what are mandatory steps for building discrete jobs with serial control and to perfor move transactions?
    waiting for solution pls.

    Dear Mr.Riccardo
    I would like to bring to your notice a document from Metalink. It says that we cannot do move transaction of Serial controlled Items in Desktop forms.....
    Subject: Is Serial Number Association Functionality Only Available Using Supply Chain Mobile Applications?
    Doc ID: Note:265512.1 Type: HOWTO
    Last Revision Date: 01-APR-2004 Status: PUBLISHED
    The information in this article applies to:
    Oracle Work in Process - Version: 11.5.9
    This problem can occur on any platform.
    Goal
    Is the new functionality of Serial Number Association only available through Mobile Applications?
    Fix
    This functionality provides support for standard discrete jobs with or without a routing.
    The User Interface for this functionality is via Mobile Applications
    Serialization can be activated within a job...this can be for entire job or beginning at
    a specified operation.This new feature is optional. It is defaulted by org parameter and controlled at the job level. The user will need to define the default to steps for the moves.
    When turned on, then when Jobs are created automatically ...via CTO or Planning, the serial will be turned on.
    The current functionality of serial number generation and uniqueness is used. Auto-generation and association at the time of job creation via Mass Load is added with this functionality. Also import of serials from 3rd party systems is supported.
    The serial association can occur anytime during or after job creation. Users can use pre-generated or on-the-fly serial numbers. This association is also not tied to job quantity and is changeable until assigned to a specific unit.
    Once the job is 'Serialized', you cannot transact this job through any of the Desktop forms. A new Menu structure is added in the Mobile Applications called 'Serialized Assembly and Material Transaction'.
    Users utilize the mobile pages under this menu to perform serialized move or completiontransactions.
    These assembly items for which the serial numbers are associated at the time of creating the wip job itself can be transacted only through Mobile Supply Chain Applications (MSCA) .

  • Operation 10 ToMove in Discrete Job status

    Hi,
    Does anyone knows why some DJ in the status of operation 10 ToMove has components assigned to, while some DJ has the same status don't have components.
    Thanks,
    AKM

    Are you comparing the DJ for the same assembly?
    The components for the standard DJ are copied from the referred BOM (primary/alternate) during job creation.
    The material requirement operation will decide that on which routing step the material should be available
    If the jobs under discussion are non standard make sure that both refer the same BOM

  • Join wip discrete job with sales order

    I need to develop a report and
    I've to tie wip_discrete_jobs to the sales order that caused their creation.
    the sales order line is for an ato item which has a few subassemblies under it.
    Can someone please let me know the tables involved...?

    Hi;
    Please check below thread which could be helpful for your issue:
    http://forums.oracle.com/forums/thread.jspa?messageID=9155702
    Regard
    Helios

  • Closed WIP job status change

    how to change closed WIP job status to released.
    Thanks
    Vijay

    If you are in the same period as you closed the job then go to Discrete Jobs>>Close Discrete Jobs Form>> Tools>> Unclose.
    Once unclosed then you can change it to released.
    If you are not in the same period, you cannot change the status.

  • Discrete job is finishing with status 'Complete-No Charges'

    Hi,
    Some of our discrete jobs are getting completed with no charges. I wanted to know the name of API/Package which is changing/updating the status of job as 'Completed-No Charges'.
    Regards,
    Jaspreet Singh

    Hi Jaspreet,
    Normally once all the activities on the job were done, then the job status will get changed to complete. As per my knowledge, there is no API for changing the job status to "Complete-No changes". If you want this to be analyzed, please generate the FND logs by setting the following profile options and then try to re-produce the issue . Once the log is generated, then we can analyze the log.
    1.Enable the INV and WIP profiles for debugging.
    FND: Debug Log Filename = (Make sure this is null)
    FND: Debug Log Enabled = Yes
    FND: Debug Log Level = Statement
    FND: Debug Log Module = WIP%
    2. run the below query and take a note of the output
         select max(log_sequence) from fnd_log_messages;
    3. Finish the job
    4. Once completed run the following sql script:
         select message_text from fnd_log_messages where log_sequence> '&Log_seq received from step 2';
    5. Upload the the SQL output (which you got from setp4) generated from the above sql script
    Edited by: 813411 on Mar 28, 2012 7:43 PM

  • ESYU: Canceled 상태의 WIP Work order나 Discrete job을 purge 할 수 있는 방법

    Purpose
    Oracle Work in Process - Version: 11.5.2 to 11.5.10
    WIP 사용자 중 Canceled status의 Discrete Jobs이나 WIP Work Orders를 purge
    하길 원하는 user가 있다.
    하지만 standard form은 closed discrete jobs만을 purge 할 수 있다.
    WIP user manual에 따르면 현재 closed 된 accounting period 안에서 closed 된
    discrete jobs에 대한 정보만을 purge 할 수 있다고 되어 있다.
    다음은 이에 대한 work around 이다.
    Solution
    Work Around:
    1. WIP: Discrete> Close Discrete Jobs> Close Discrete Jobs(Form)으로 이동한다.
    2. Find Discrete Jobs parameter에 아래와 같이 입력한다.
    From Job = Close를 원하는 Job
    To Job = Close를 원하는 Job
    Status = Canceled
    3. Tools menu에서 Close 1을 선택한다.
    Close 1을 선택하면 canceled Discrete Job이 closed 가 된다.
    이 때 job number를 기억하고 note 해 둔다.
    4. GL과 Inventory Accounting periods가 close가 될 때, canceled discrete jobs
    (현재는 closed 상태)를 Purge Job form을 이용하여 purge 할 수 있다.
    WIP: Discrete> Purge Discrete Jobs> Purge Discrete Josb from or SRS
    Reference
    Note 429489.1

  • How to create a discrete job on condition that build-in-wip attribute is No.

    two or three times a year, jobs are created in the Discrete Job  form although build in wip attribute is No. (never created from MRP)
    i have no idea how the job could be created... i tried several times at same condition, but i couldn't.
    does anyone experience like this??

    Welcome to the forum.
    Oracle 9i is a database version from the previous century.
    But:
    You can read about DBMS_JOB in the 9i documentation here:
    http://www.oracle.com/pls/db92/homepage
    Or do some searches on http://asktom.oracle.com
    Anyway: if you want the job to run once, then omit the interval...
    Oh, and don't forget to read {message:id=9360002} from the SQL and Pl/SQL FAQ here:
    SQL and PL/SQL FAQ
    Edited by: Hoek on May 23, 2013 8:09 PM

  • WIP MASS LOAD를 이용한 DISCRETE JOB생성 방법

    제품 : MFG_WIP
    작성날짜 : 2004-05-21
    WIP MASS LOAD를 이용한 DISCRETE JOB생성 방법
    ====================================
    PURPOSE
    WIP Mass Load를 이용한 Discrete Job생성 방법을
    기술하고자 한다.
    Explanation
    (1) Interface Table 정보
    WIP_JOB_SCHEDULE_INTERFACE (Header level)
    WIP_JOB_DTLS_INTERFACE (Line Level)
    WIP_INTERFACE_ERRORS (WIP Mass Load의 Error발생시 참조)
    (2) 방법
    step1> 위에 언급한 Table에 정보를 Insert한다.
    step2> WIP Mass Load Program을 수행한다.
    WIP Mass Load 를 실행하면 , Interface table로부터 WIP Job을
    생성하게 된다.
    만약, 기존의 WIP Job에 대해 Detail한 사항을 수정하고자 할 경우,
    wip_job_schdeule_interface와 wip_job_dtls_interface를 모두
    작성해주어야 한다.
    이 때, wip_job_shedule_interface와 wip_job_dtls_interface는
    group_id, header_id가 동일하여야 한다.
    Example
    Reference Documents
    BUG1485375 , 1654237, 1663551

  • Discrete job History tab shows wrong completed qunatity

    Hi All
    We are facing an issue, When we perform the WIP completion trx thru mobile apps the completed quantity in discrete job history is not in sink with the transaction.Can any one comment on this issue.
    job qnty:256
    job status:Closed
    In history tab
    remaning qnty:135
    completed qnty:121
    Performed the WIP completion trx for qnty 135 and then for qnty 121 thru mobile apps
    Thanks

    Welcome to the Forum.
    First off if the job belongs to a open INV period, unclose the job (WIPUser>>Discrete>>Close Discrete Jobs>>Close Discrete Jobs (Form)>>Tools>>Unclose).
    Then check if there are any pending WIP completions from back end using
    peding LPN drop-
    SELECT *
    FROM apps.WIP_LPN_COMPLETIONS WLC,
    apps.WMS_LICENSE_PLATE_NUMBERS LPN
    WHERE WLC.ORGANIZATION_ID = 477
    AND WLC.LPN_ID = LPN.LPN_ID
    AND LPN.LPN_CONTEXT = 2
    AND WIP_ENTITY_ID = :P ---your WIP_entity_id
    -- Pending Material Transactions
    SELECT *
    FROM apps.MTL_MATERIAL_TRANSACTIONS_TEMP MMTT
    WHERE ORGANIZATION_ID = 477
    AND TRANSACTION_SOURCE_TYPE_ID = 5
    AND TRANSACTION_TYPE_ID = 44 ---WIP ASSY COMPLETION
    AND TRANSACTION_SOURCE_ID NOT IN
    (SELECT TXN_SOURCE_ID
    FROM apps.MTL_TXN_REQUEST_LINES
    WHERE TXN_SOURCE_ID = MMTT.TRANSACTION_SOURCE_ID
    AND ORGANIZATION_ID = MMTT.ORGANIZATION_ID
    AND LINE_STATUS = 9)
    AND TRANSACTION_SOURCE_ID = :P ---your WIP_entity_id
    If you have records in this check then and try to manually drop the LPN into the destination subinventory.
    HTH

  • Discrete Job Component Pick Release (SRS)

    Hi All ,
    For Push - Supply type , we can issue items to the job manually . Could any one brief purpose of Discrete Job Component Pick Release (SRS) in WIP
    Thanks
    Kiran

    Hi,
    Pls check if below MOS(metalink) note helps you:-
    Move Order FAQ #2: Quantity Delivered vs Detailed in Move Order Lines (MTL_TXN_REQUEST_LINES) [ID 431479.1]
    11i Move Order Transaction - FAQ [ID 114156.1]
    Oracle Work in Process Product Documentation [ID 67009.1]
    Also below discussion:-
    http://kr.forums.oracle.com/forums/thread.jspa?threadID=951381&tstart=0
    http://www.oracleug.com/user-guide/work-process/component-pick-release
    Thanks,
    JD

  • Unrelease Discrete Job become demand in MRP.

    Hi,
    I facing a problem that need to know.
    In PCBA environment which the discrete job only issue once because all the process is link together. However, in the Plastics environment which will break into two proseses which MOLDING as one and ASSEMBLY as another. There will be two different discrete job issue to this in order to complete a FG goods.
    PFDX1081UA is the Assemblt FG for the plastics environment. The purchase part is L6HAYYYK0010. When I check the discrete job for the PFDX1081UA which entered MRP NET QTY as 30,000 and the status of the discrete job is unrelease.
    The demand in the Purchase part L6HAYYYK0010 which treat this unrelease discrete job qty as demand.
    Is this correct?
    How come the discrete job quantity for the PCBA will not show as demand in MRP?

    Please expand your question ; I could not able to understand the issue well. From the subject of the questions"Unreleased Discrete Job become demand in MRP.", I can say that unreleased jobs will be considered for MRP Plan provided if it is MRP Planned item.
    In this case, unreleased job will be considered as Supply and Components associated with the Job will be considered as Demand (If it is MRP Planned item).
    This is correct logic by design.
    thanks,
    dr

  • How to update automatically a job status type to Complete - No Charges ?

    Hello,
    I'd like to update automatically (= no user intervention) jobs status type from "Complete" to "Complete - No Charges".
    I've tried the Wip Mass Load program (using WIP_JOB_SCHEDULE_INTERFACE), but it didn't work because this program can only update jobs to Unreleased, Released, Complete, On Hold, or Cancelled.
    Can anyone help me please ?

    hello,
    changing the status from "Complete" to "Complete - No Charges" without user intervation is not posssible,user has to assign it meaning that all resources have been charged,if there are any pending material transactions you can correct it & then assign this status.
    regards,
    ganpa

  • Material shortage for Planned Order (Discrete Job) in PWB

    Client has planned orders on planner workbench (PWB) ready to release as Discrete Jobs but, because they have frequent revisions, they waits till all components (required to build job) are onhand before releasing from PWB.
    They would like an easy way to either check or be notified when the last component required for job is received into inventory so they can release from PWB. They cannot use the standard "Discrete Job Shortage Report" as the job is not created yet. And they don't want to release from PWB till ALL material is onhand
    Could we create a custom report perhaps (using same logic as "WIP Mass Load" to determine all component required versus onhand), but does anyone have a better solution how we can solve this?
    Regards,
    Hugh
    Edited by: user13050057 on 13-May-2010 02:09
    Edited by: Hugh Parker on 13-May-2010 08:13

    1) Why would you check for components of subassemblies? e.g. Say your BOM looks like this.
    FG1 is made up of SA1 and SA2 and COMP1.
    SA1 is made up of COMP2 and COMP3.
    Say you are releasing planned order for FG1. As long as the planned order is pegged to onhand for SA1, SA2 and COMP1, you are good. Right?
    2) If you have to add custom logic, I would do it using a when-validate-record personalization on the PWB. The personalization will call a function that accepts order number ; does all pegging checks and returns true or false. If it returns false, then the personalization returns error and does not allow release of the planned order. The function will have to be an interative program that traverses the pegging loop to ensure that all lowest level demands are pegged to onhand.
    Hope this helps
    Sandeep Gandhi

Maybe you are looking for

  • Keep getting "Fatal error during installation" messages on install of 7.0 SP1

    Hi, I keep getting the following error on installation (dialogue box) on Win2K of WLS 7.0.1.0: "Fatal error encountered during file installation. The installer will now cleanup and exit! [file size error for E:\ ...]" While this looks like an obvious

  • MDX parser program name

    Hi I am getting connection error in RFC Destination MDX PARSER. Error is that the program does not exit in the system. Can you please tell what does this program contain or how to find this program. Regards Lalit K Tyagi

  • Installing oracle developer suite under a different oracle home than the DB

    I have Oracle 10g r2 installed on a RHAS4 server. I installed Oracle developer suite 10.1 on this server. In the installation procedures, there are specific instructions to not install it under the ORACLE_HOME for an existing database installation. O

  • Function Reference and Table Sort

    I have a table that I use to track numerical data to a fixed size table. After adding new data I sort the columns, for example in descending order. My question is this, is it possible to specify the references in say the Average Function to refer to

  • Prodn order costing error

    Dear All, I am getting an error at the time of release of prodn order CSER i.e. system is giving planned cost calculation error.Pls. help in this regard. r sehgal