WIP process doubt

Hi Experts,
I have a problem in wip process, the scenario as follows
Sales order quantity is 10(say example), we raised po for 10 qty. to vendor, but vendor is not ready to send all the quantity, vendor will send based on the agreement like 1st month 2, 2nd month 5 remaining in 3rd month. Now our client is following the process is when we receive the 1 st month quantity client issuing to customer and customer is sending the amount for that 2 qty.  now client is booking directly sales invoice, now they are transfering the sales amount in wip account through manually. becasue in client view actual order quantity is 10, but we are isseud to customer is 2 so they are treating as a wip.  Once the final i.e third month billing they are reversing the total amount (which is transfred to wip account) from wip to sales and cost of sales a/c.
1. My doubt is once we book the invoice can we transfer to wip a/c in sap.
2. Please give some suggestions for the above process.
regards,
Gopi.P

Hi,
It seems that your client is manually posting to WIP A/c. Normally WIP are those which captures unfinished goods
in the Production Order during the periodic processing.  You process through KKAX every month how many
production orders are still pending to be converted into Finished Goods, calculate the variance and settle
the production orders which reverses the previous period pending value in WIP which is done automatically
in SAP.  If you have not received raw material goods from the vendor for delivering finished goods to customer
and without passing the difference qty. in production order, it is not correct to treat it as Work in Progress.
Regards,
Sadashivan

Similar Messages

  • WIP Process

    Hi All,
    I am trying to process scrap scale which my client sells the manufacturing waste to some of the customers. I have created an item which is scrap and trying to place a work order and run a report which determines how many kilograms of scrap is there.
    I am stuck with the WIP process - I placing a work order, doing the picking and then transact the same by assining serial/lot numbers.  Can some body help me in WIP process right from placing the work order- transacting them and completing them. since my report is going to display
    Forging No/ ForgingRev/Serial No Bond/Lot Num/ForgingWeight(in Kg)/Finish PartNo/FGRevFOQ /Metal type FG/Weight(InKg)/Batch cardNo./ScrapWeight(Inkg)
    The WIP process will populate majority of the columns which is Scrap weight/Serial no/lot num/Forging weight which is important.
    Can some body help me with the WIP Process with screen shots - work order- que moving -transacting them and completing the work order
    Regards

    Hi,
    It seems that your client is manually posting to WIP A/c. Normally WIP are those which captures unfinished goods
    in the Production Order during the periodic processing.  You process through KKAX every month how many
    production orders are still pending to be converted into Finished Goods, calculate the variance and settle
    the production orders which reverses the previous period pending value in WIP which is done automatically
    in SAP.  If you have not received raw material goods from the vendor for delivering finished goods to customer
    and without passing the difference qty. in production order, it is not correct to treat it as Work in Progress.
    Regards,
    Sadashivan

  • Third Party Subcontracting Process doubt

    Hello all Gurus,
    I have one doubt regarding the third party subcontracting process. I have created a PO with delivery address as that of SC vendor.
    Now how to do the GR for components if the SC vendor lets me know that he has received the materials from the 3rd party vendor??
    Can someone tell me the process after a PO is created for this scenario???
    Thanks and Regards,
    Umakanth.

    Hi,
    As I perceive you are speaking about the provision of subcontracting components from one of your vendor directly to another one,
    In this case you did well if you wrote the vendorID in the suitable field on 'Delivery address' tab of your PO. 'SC Vendor' thickbox should be also checked. This is not the subcontracting PO itself, it is only a PO to procure the components for subcontracting - your SC vendor receive the components directly. That's why there's no point in speaking about 'L' item category.
    After getting information from your SC vendor about the arrival of the goods (components) the only thing you have to do is to do a GR against your PO. The goods will get to your SC vendor's special stock via mvt 101 + 'O'.
    That's all.
    BR
    Csaba

  • Integration Process Doubts

    Hello everyone,
    I have the next scenario requirement:
    Informix -> XI -> R/3
    but the answer from the R/3 BAPI has to be evaluated to send an email in case of error and to update some rows in Informix database, the query in the sender jdbc is a JOIN from several tables, so my doubt is as follows, I could obtain 'n' rows from Informix in the same structure, but they need to be processed in R/3 in pairs, one field is the difference in this pair some 210 and 212 values, so I need to send to the ABAP Server Proxy two rows one with 210 and one with 212, how can I divide this rows in XI in my Integration Process????, or is there a way to configure the sender communication channel to restrict the query for two rows so every message taken via JDBC are going to be the exactly quantity of rows I need in this case two, thanks in advance for your answers.
    Regards,
    Julio Cesar

    >> how can I divide this rows in XI in my Integration Process????,
    I m not really sure about your actual scenario but if you are looking to club together values based upon some key,you can easily do that in message mapping by using formatByExample standard function.
    Please have a look at the below blog to see its functionality.
    New functions in the Graphical Mapping Tool XI 3.0 SP13

  • WIP process order on transaction KKAO

    Hi Gurus
    I have a process order in WIP on transaction KKAO.
    When i run KKAO i have a positive value on columns  WIP(Cumul) and WIP(Period ) ,two values are equals.
    I don't know what is the problem, other similar process orders have value zero on column WIP(Cumul) and WIP(Period )
    Can you help me ?
    Thanks in advance
    Regards

    Hi
    OK, now I got your intention... Here is the answer
    WIP *** means Total WIP over all the periods...
    WIP Per means current period WIP
    WIP (***) - WIP (Per)
    100 - 100 (This happens in 1st month i.e. when WIP is generatedfor the 1st time on a Prod order)
    200 - 100 (this means 100 is added in 2nd month to WIP and Total WIP is 200)
    0 - (-200) - This means Order is now complete and WIP is reversed in current period.. Hence total WIP is zero)
    0 - 0 (This means Order has no values posted on to it and/or there is no WIP on that order)
    Hope this helps
    br, Ajay M

  • IMPORT process doubts

    HI
    i have some doubts
    1) is it possible to have our imports cvd and customs value to take directly in miro for customs ????
    usually as we do customs invoice earlier, we get blank values , then is it possible to take values directly in MIRO
    also the values we taken in PO and the values on BOE may not match some time
    2)can we do GR based IV for IMPORTS
    never did with gr based IV
    please guide
    regards
    kunal

    1) is it possible to have our imports cvd and customs value to take directly in miro for customs ????
    usually as we do customs invoice earlier, we get blank values , then is it possible to take values directly in MIRO
    also the values we taken in PO and the values on BOE may not match some time
    It is really painful doing customs miro if number of line items we receive everytime is more.
    Personally i have experience with one of client imported 17 spares(17*7=119 items in customs miro)
    I'm also looking for solution for this question long time,customization(try this) is only option.
    My suggestion is,
    Here cut,copy,paste quantity & values from miro(scroll to right side of miro),when values are pasted
    you can also add a button like calculate in miro for converting customs value * exchange rate in p.o.
    2)can we do GR based IV for IMPORTS
      never did with gr based IV
      please guide
    It will deviation from functional process,you can clear materials from customs after paying duties
    then only we can receive material in plant.
    I have never tried it,if we directly do GR without doing customs miro after entring boe values in p.o,
    customs duties will be captured in foreign currency

  • Customs declaration process doubts

    Hi experts...........
    I have small doubts on GTS customs declaration process...
    Suppose if my client is an US based company and my client is having business process in EU Zone,
    My doubt is if i process customs declaration, that time i need to maintain converter system like NCTS to US customs and also I need to maintain converter system for EU? if the answer is need to maintain at both levels, then again is it possible to maintain NCTS for both customs departments?
    Please share your knowledge it will help to me to get more discussion on

    Hi Gopala,
    Assuming that you make use of the licence for the Seeburger convertor that comes free with GTS, the message mappings are all provided with the package.
    Use of NCTS in the EU depends on where and how the Import Declarations are processed.
    Has your client already decided to go ahead with the GTS implementation?  If not, maybe he can find a more confident consultant to persuade him?
    Regards,
    Dave

  • BPC 7.5 upgrade process - Doubts

    Hi,
    Once we had the confirmation and approval to upgrade the system from SP00 to SP03 (on .NET server components), we noticed that some functional configurations had been made in the meantime. This new scenario where new things had been done from a functional perspective makes me wonder if any of that configuration could be lost while or after upgrading the server component?
    Also, after reading Note 1453797 - Planning and Consolidation 7.5 SP03 NW Central Note, section "Before you install" to be more specific it says to uninstall any previous version of the .NET server and client components. Also Scott recommended me that as a best practice. This applies when the upgrade is being done from BPC 7.0 to BPC 7.5 for example or it also applies to my case (uprading BPC 7.5 system from SP00 to SP03)?
    Thanks again for your help.
    Regards

    Hi Ethan,
    Thanks for the quick response.
    Actually I'm new installing BO BPC and maybe I've not used the correct words to describe that configuration I've detected while trying to install SP03. What I've noticed is that an Initial Application Set has been created. Actually, this is the only thing I have found but I'm not sure if that imply any other configurations either in .NET server or ABAP server that could be lost after upgrading the server component from SP00 to SP03. The same question arises if I decide to uninstall the current installation to perform a fresh one using SP03 directly as its described in note 1453797.
    In summary, is there any chance to lost the configuration made on a BPC system (.NET and ABAP servers or client) if any of the above upgrade process is performed?
    Hope being clear enough this time thanks so much for your help.
    Kind regards

  • Shared server/dedicated server process doubt?

    when oracle database is not configured for shared server is it compulsay to include SERVER=DEDICATED clause in the connect descriptor.?
    Thankx.

    Hi,
    is it compulsay to include SERVER=DEDICATED clause in the connect descriptor.?No, the MTS is defined at startup time, via the MTS parms.
    Here is a sample of shared server definition in the init.ora file:
    # Multi-threaded Server parameters
    local_listener="(address_list=
    (address=(protocol=tcp)(host=sting.janet.com)(port=1521))
    MTS_MAX_DISPATCHERS=5
    MTS_MAX_SERVERS=20
    MTS_DISPATCHERS="(ADDRESS=
    (PROTOCOL=tcp)(HOST=sting.janet.com))(DISPATCHERS=3)
    service_names=testb1
    http://www.dba-oracle.com/unix_linux/epc_disabled.htm
    However, be aware that the MTS is not a panacea, especially at times when you want to invoke a dedicated process for your program. For Pro*C programs and I/O-intensive SQL*Forms applications, or any batch processes that have little idle time, you may derive better performance using a dedicated listener process. For shops that segregate task into online and batch modes, the DBA sometimes create separate listeners—one with the MTS and another for dedicated connections.
    Hope this helps. . . .
    Donald K. Burleson
    Oracle Press author

  • Screen Processing Doubt!

    Hi Friends!
         I ve 5 Screens in seqential order 100 200 300 400 500
       When the user is in screen 200 i want him to branch to screen 400 without going toscreen  300.
      For that i ve to write this module
    DATA: REQSCRN LIKE SY-DYNNR VALUE ‘400’.
    MODULE SET_NEXT_SCREEN.
    SET SCREEN REQSCRN.
    ENDMODULE.
    [<u>b]Can any one tell me where i ve to write this module in screen 200.</b></u>
    Looking for your reply
    Thanks in advance.
    Rahul.

    In the USER_COMMAND module of screen 200,  you would have your case statement for handling all of the funciton codes of this screen, depending on the user pressing a certain function code, then you would branch to screen 400.
    case ok_code.
        when 'BACK'.
            clear ok_code.
            leave to screen 100.
        when 'GO'                         "<--- LIke this
            clear ok_code.
            leave to screen 400.        "<--- LIke this
    endcase.
    Regards,
    RIch Heilman

  • How exactly does "remote wipe" via Mobile Me work?

    In a moment of curiosity I decided to enjoy the new features of Mobile Me for the iPhone's 3.0 software. I tried the locate phone function, worked great. I then decided to try the remote wipe functionality of the website. I had the phone right in front of me, so I figured I'd see how it worked.
    I initiated the process (with my phone sitting on my desk in front of me) and the phone within an instance turned off and went to the Apple logo. It stayed on the Apple logo for a few seconds and then turned off. At which point I received an email stating that the remote wipe process had been initiated at 4:23pm (PST) yesterday.
    Unsure how long the process took I let the phone sit for 4 hours. I went to turn it on, same thing: Apple logo for 10 seconds and the phone turned off. I figured it was low on battery (despite having a full charge prior to the remote wipe) so I docked it while plugged into my machine. (Apple logo for 10 seconds and the phone turned off)
    Fast forward to 10:23am PST this morning (18 hours later) and I'm still dealing with the same thing.
    Anyone else try the remote wipe feature? Have any success? I'm inclined to believe that the phone isn't going to wake up at this point. But I was curious if anyone else shared in my curiosity.

    Use these instructions and you're phone will be back in service asap:
    1. Wake your iphone up so you see the apple logo
    2. Hold down the power button (the one on top) and the home button until the screen goes black.
    3. This turns the phone off, don't keep holding the button or the phone will restart
    4. Now that the phone is off, press and hold the home button
    5. While holding the home button connect your phone back to your computer, continue to hold the home button until itunes says it has found a phone that needs to be restored.
    6. restore phone
    Basically your just turning the phone off and putting it in force recovery mode

  • 4 hours and Security Wipe still continuing in Q5

    I set my phone on security wipe and its been 4 hours and its still not finished. I removed the media card... 
    Need urgent help. Hard reboot is alos not working
    Solved!
    Go to Solution.

    Hello noorenayat
    Relax, let the wipe process finish and connect it to the wall charger. There's wipe with more than 12 hours. It depends on data size.
    Also your phone number listed in your profile. It's not recommended as this is open forums and spammer may send junk messages to your phone. Edit it from My Setting at top left of this page and change to your carrier name.
    Good luck.
    • Click Likes to appreciate those who helps you
    • If your issue solved, mark the best post in your thread as Solution

  • My iCloud Backup restore process seems to be stuck

    I am trying to restore an iCloud backup to a iPhone5s. I started the process about 20 hours ago. Most of my data was restored within a couple hours, but since then, it seems to be stuck restoring. It looks like my Podcasts and Pictures are the two areas left that say they are still downloading with no progress for the past 12-15 hours at least.
    Is there any way to get the restore moving again or do I need to wipe and start over?
    Thanks,
    Tim

    I have done that several times to no avail. That's what I was afraid of that, I need to start over. I was just trying to avoid it since I had trouble once already.
    This is actually a replacement for another bad phone I got yesterday at the Apple store. While I was in the store, I started the restore process and it also stuck, but they seemed to get it going again and after I was home, it continued to restore until the point mentioned above.
    I went ahead and wiped and now starting the wipe process over. I hope the backup I am restoring isn't the problem.
    Thanks for your help.
    -Tim

  • Waiver process during Production order

    Hi,
    My client has a requirement whic is called as waiver process, whereby a part could be replaced by another alternative part during production order process, however the whole process need to be integrated with ECM and workflow for seemless communication and approval.
    Has anyone come across manufacturing waiver process and can this process be designed within ECC60 or is it better to look for MES or MII tool to address the business requirement?
    Appreciate any response concerning this topic.
    Thanks and regards,
    Bhaskar

    I resolved this issue by using the process in SAP ME and ECC, using WIP processing in MES.

  • HELP!!! How do i cancel a wipe from BlackBerry protect?

    I lost my phone and signed into BB Protect.  BB Protect was unable to connet to my phone but I did set a phone wipe for when my phone was connected to a network.  I have now found my phone and I want to cancel the phone wipe that I set.  I see on my phone that my BB protect has recently been upgraded and I hadn't logged into BB protect and acceted Terms and Conditions so effectively BB protect wasn't active on my phone.  Now if I log in to BB protect on my phone and accept the terms and conditions will the wipe still happen? Advice appreciated!

    Hi sassythom
    You can delete or archive this device,but data related to that device will be lost.And I am unsure if it will stop the wipe process as soon as you login with the same BlackBerry I'd, but you can try it and see what happen.
    Let us know of your progress .
    Click " Like " if you want to Thank someone.
    If Problem Resolves mark the post(s) as " Solution ", so that other can make use of it.

Maybe you are looking for

  • Adobe Reader 8.1 verses 6.0

    I have been using 6.0 for years. Each time I received an email with attachment as a PDF a flash would come up to intall updates. After the 500th time of getting the notice, I finally aggreed to get the updates. I have installed 8.1 twice, I have gone

  • Selecting data from table

    Hi just have a Labview programming question that I'm not too sure how to implement. Right now I have a VI that takes in an Excel file and dumps the values onto a 2D table. I'm extracting individual columns of values from the table by using "delete fr

  • Cannot setup Web Services on my HP Photosmart 7525

    After setting up a manual IP address for my printer, I can now print on the network BUT Web Services are unavailable. I have followed the printer instructions, your website instructions, confirmed the proxy, IP address, DNS settings, etc. From the Wi

  • Resize Volume in SAPDB

    Dear Experts, Previously i'm sorry if this question is rather out of topic because i can not find group for sapdb question. Direct to my question, now i already installed sapdb in unix server for sap content server purpose, and my question here is ho

  • Logic Pro 7 Academic Productions

    With LP7 academic, am I able to sell what is created with the software? If not, how can you tell if it was created with LP7 academic or not? Papic