WIP  to  cost of sales order  to settlement

Dear Experts,
Can you look at this issue
What are the steps we need to do WIP  to  cost of sales order  to settlement
Thanks
Bhaskar

Hi
You should follow following steps for Order Settlement after confirmation :
1. After Final Confirmation of Order ( Status : CNF) T.Code:CO15  make GR for for order using Tcode : MB1A / MB31 so Production Order Status will be DLV.
2. Then complete the order technically by using Tcode : CO02--> Functions ( Menu)---> Restrict Processing -
> Technically Complete. You can carry out TECO for multiple Orders in Tcode : COHV (Mass Processing).
3.Now Calculate Overheads using Tcode : KGI2 - Individual Processing
CO43 - Collective Processing
4.Calculate WIP using Tcode : KKAX - Individual Processing
KKAO - Collective Processing
5.Calculate Variance by using Tcode : KKS2 - Individual Processing
KKS1 - Collective Processing
6.Finally do the settlement of Order in Tcode : KO88 - Individual Processing
CO88 - Collective Processing
Note:(calculate WIP and Variance get posted during this step)
/message/6351141#6351141 [original link is broken]
Hope this helps.
Edited by: Dublin on Oct 17, 2009 10:54 AM

Similar Messages

  • Product Costs by Sales Order - Settlement Options?

    Hello All -
    I am trying to understand if I need to settle to a sales order (SDI) or directly to material (MAT) or to COPA (PSG).
    If i look at my sales order, it has item category ZPSF, which product costs by sales order configuration shows a requirement class ZKE.  ZkE has a valuation of M, which means separate valuation of reference to sales document/project.
    Does this mean I need to settle to sales order first?
    Then i run vA88 to settle sales order to copa?
    if ZKE valuation is blank, does that mean its not valuated?  I have read on other sap help pages that means it is valuated.  Please clarify.
    also, when does one directly settle to MAT? what scenarios?  this confuses me.
    Thanks!
    Emmas

    I'll give this a try. When working in a make-to-order environment there are 2 settings in the requirments class that you must consider in determining how to settle the costs (and maybe the revenue as well).  The first setting is the account assignment category.  In the standard system "E" is used to designate the sales order as a cost collector.  "M" is used to if you don't want the sales order to be a cost collector.  Whether the sales order is a cost collector or not will determine your settlement options. 
    The second critical field is the valuation setting.  If you set it to "M" then the stock assigned to the sales order will be valuated (by valuated I mean that once the goods are produced they will be held in inventory as sales order stock with a value).  If you leave the valuation field blank then the stock assigned to the sales order will be held in inventory without a valuation. 
    If the sales order is not a cost collector then the cost to manufacture the order will be collected in your production order and the settlement rule for the production order will be to the material you are producing.  Since the material has a valuation, the costs collected in the production will be reduced by the material's valuation once it is received into finished goods inventory.  Any remaining costs are settled to wip or variance based on the production order's status and the RA key and variance key settings.
    If you have set the sales order as a cost collector then the production order costs can either settle to the finished material or to the sales order.  If you are using valuated sales order stock you would normal have the costs settle to the material and the production order would behave very much like the previous example.  If you are not using valuated stock then you would need to settle the costs to the sales order and all the production costs would accumalte in the sales order.
    If you are using the sales order as a cost collector than you will probably want to settle the sales order as well.  During the sales order settlement you have the option of settling the cost and revenue assigned to the sales order to COPA.  The settlement profile along with the RA key assigned to the sales order controls how these are settled.

  • WBS settled cost in sales order

    Hi,
    We settlele the WBS to Sales order and where we can see the settled cost in sales order.
    Kindly suggest.
    Thanks,

    Dear Sudha,
    You can check if the costs are transferred from WBS element in CJI3 (you will see a credit posting for the WBS element)
    You can check if the costs are debited to the Sales Order using KVBI (you wlll see a debit posting for the Sales Order item)
    Note: Cost elements that you see could be a settlement cost element /original cost element based on the allocation structure used.
    Kind Regards
    Umapathi G

  • Producrt Cost by Sales Order with Valuated Stock

    Hi Gurus,
    My client is having  Producrt Cost by Sales Order with Valuated Sales Order Stock. Can anybody reply me for my following issues.
    1. while calculating Sales order cost estimate thru VA02 , the same Cost estimate is appearing against with EK02 condition type in Sales order Condotions. what is the use of Sales order Cost estimate? is there any impact on production?
    2. What is Difference between Sales Order Cost Estimate and Order BOM Cost estimate?
    3.when can we calculate Sales Order Cost estimate ? whether before Production or before billing ? can anybody tell me please..
    4.while settling the production order also system picking the cost in VPRS not in EK02, i am not sure about this step.can any body correct if i am wrong
    5.I know we can caluculate WIP in Sales order also. when can we calculate ? before settling the Production order or after production ?
    thanks
    Prasad

    Hi,
    there are 3 types of scenarios in MTO.
    In Two scenarios Sale Order would be cost object - (Non-Valuated Sale orders stock and Valuated Sale Order stock with Sale order being Cost Object)
    In third scenario (Valuated Sale Order Stock without Sale Order controlling), Only Production Order is the Cost Object.
    In all the cases wherever the Sale Order is the cost object, Sale Order is the final Receiver.  Only the difference is that in valuated sale order stock, stock entries would be passed to FI and in non-valuated sale order, no goods movement for FG will be there.
    Please let me know if you need further details in this regard
    Surya

  • Product costing valuated sales order stock

    Hi all,
    We are in complex mfg & currently re-vamping all the ERP SAP instances ( totalling 13 company codes into one single)
    All 13 units( who use NON Valuated scenarios for cost object controlling) wil use valuated sales orders & projects. The old 13 companies will be trated as profit centers with transfer pricing functionality ( Multiple valuations)
    My issue is to get a product cost for sales order in <b>profit center view</b> ( plan cost) exactly same as to the marked standard cost itemisation of the FERT material.
    We mark & release the std cost in Jan & the client wants to have the same itemisation of the cost ( with same values) even if they create a sales order in 2nd or 3rd or last quarter. ( As you might be knowing that the sales order wil always cal;culate the values as per the current qty structure date. In Std SAP date control, there is nothing which allows us to cost exactly the same cost estimate as marked & released in JAn)
    Could somebody pls give pointers as how to get this sales order plan cost itemisation exactly equal to prevously marked & released itemisation ?
    We use the Std costing variant ( Costing Type = Profit center valuation) with Std date control.
    Thanks in advance to all of you,
    Warm Regards
    Dhiraj

    Hi,
    If the sales order stock is valuated, you have immediate access to its value in Financial Accounting. The assigned accounts are debited and credited as a result of the valuated goods movements. From the viewpoint of MRP, the sales order stock is available for the sales order only.
    If the sales order stock is not valuated, it is managed via a cost collector. The system does not carry out invoice verification postings for goods movements, and you cannot obtain an overview of how the stock is valuated until the end of the settlement period in Controlling.
    Valuated sales order stocks have the following advantages:
    The full costs are available at each manufacturing level.
    All goods movements are immediately reflected in Financial Accounting
    Assign points if helpful
    Regards,
    Saurabh

  • Product cost by sales order with Valuated Sales order stock

    Hi Gurus,
    I am working on Poduct cost by Sales Order with Valuated stock. but i have doubt ragarding to Cost estimation.
    1.In sales order scenario also Standard Cost estiamtion (CK11n and CK24) and Marking, Releasing is Mandatory? if not how can we estimate the cost?
    2. If we are estimating the cost by using Standard Cost estimate, when can we estimate the cost?
                can anybody please give me the steps which we are following in Poduct cost by Sales Order with Valuated stock from starting to end Settlement
    Thanks&Regards
    Prasad

    Hi,
    there are 3 types of scenarios in MTO.
    In Two scenarios Sale Order would be cost object - (Non-Valuated Sale orders stock and Valuated Sale Order stock with Sale order being Cost Object)
    In third scenario (Valuated Sale Order Stock without Sale Order controlling), Only Production Order is the Cost Object.
    In all the cases wherever the Sale Order is the cost object, Sale Order is the final Receiver.  Only the difference is that in valuated sale order stock, stock entries would be passed to FI and in non-valuated sale order, no goods movement for FG will be there.
    Please let me know if you need further details in this regard
    Surya

  • Report to see WIP calculation details for sales order

    Hi,
    I want to know which is the best report to see the details of WIP calculation for a sales order. There is a WIP posting of 1 million to a sales order and i want to understand how this amount was computed.

    Hi,
    Yes when i went there and call up the line items report i got the following error :-
    Display of debits for object type SDI is not included
    Message no. KD232
    Diagnosis
    You want to display a report for the current sender. This function is currently only possible for the following object types:
    Cost Object
    Orders
    WBS Elements

  • Product cost by sales order

    Dear FICO Gurus,
    I come to know that for the above method, production order in company A can be settled to Sales Order item in Company B (with assumption that Company A & Company B are intercompany and assigned to 1 Controlling area.
    My question, under what scenarios that organisations adopt this method of settlement. To me, Company A still needs to report its profitability. Without Purchase Order from Company B to Company A, Company A would not have the revenue to sustain its operation.
    Can anyone share with me, what is the logic for organisation to practice the above mentioned business process.
    Regards,
    -Alice-

    HI,
    It could be a complex MTO scenario and hence the need to track costs on sales order along with revenue.
    Company B - Trade invoice (PR00/PI02)
    Company A - I/C invoice at a predetermined transfer price (PI02/EK02).
    As far profitability, both 'Trade invoice' & 'I/C invoice' are posted to CO-PA for margin reporting.
    Hope this helps.

  • System status REL is active , Message no. BS013,CO88 COST-BY-SALES-ORDER

    Hi Experts,
    I meet error when i do the production order settlement"CO88" ,
    Which the production mode is cost-by-sales-order undifferentiated mode.
    the error information as bellow:
    System status REL is active (ORD XXXXX)
    Message no. BS013
    Diagnosis
    Object ORD XXXXXX has system status REL (Released).  According to this status, transaction 'settelemtn' is not allowed.
    Procedure
    You can only carry out the requested function if this is allowed according to the status of the object.
    Pls. Help in resolving.
    Best Regards,

    Dear Szymon and Mukthar,
          Fisrtly,Thank you for your help!
          I have changed the status "TECO"(the status is "TECO PCNF DLV  PRC  GMPS MANC SETC"),then I settlement the production order.
         The system still error:
    "Debit from actual settlement" not allowed (Sys. status REL, object VB0000000015000010)
    Message no. BS051
    Diagnosis
    The status check for the status object VB0000000015000010 indicated that the procedure "Debit from actual settlement" cannot be performed because Sys. status REL forbids it.
    System Response
    Procedure "Debit from actual settlement" is not performed.
    Procedure
    If procedure "Debit from actual settlement" is to be performed, the Sys. status REL of object VB0000000015000010 must be reset.
    Other statuses than Sys. status REL can also prevent the procedure. This message does not tell you all statuses which currently prevent procedure "Debit from actual settlement".
    Regards!
    Gang.Tian
    remark:
    I use the MTO mode, the receiver of settlement is SALES ORDER.(the settlement rule is SDI)

  • Product cost by sales order - conceptual clarity required

    Hi,
    We are a manufacturing company with both Make to Stock and Make to Order Scenarios. In cost object controlling, we have made the settings for product cost by order. Now, the question is whether product cost by sales order is a mandatory setting in MTO scenario. I understand this is a conceptual question but i never got the clarity after reading help files, threads and blogs.
    I'll put down my understanding - pls correct me.
    If i do the product cost by sales order, there will be a statistical cost object ie sales order. Now every cost incurred (with a component split) will be recorded stastically in the sales order in case of production orders created from S.O.s
    If I don't do the setting i cannot get a component wise split for the cost of sales order to do any analyses. but still I'll have the COGS which i'll capture to COPA and take the profitability.
    Can you please give me some more clarity on this scenario? Are there any other factors/ advantages/mandates in product cost by sales order?
    Best Regards
    Vimal

    Hi  Vimal
    Prod Cost by SO is done in the case of MTO.. Here, you have 3 possible scenarios
    A. Only Qty i.e. GR from Prod order is tagged to Sales Order.. Sales order is not a CO Object....
    This scenario is as good as MTS... Only that GR is tagged to SO....
    Your costs are collected on Prod order....
    PGI uses GBB-VAX i.e. does not post to sales order... Billing updates revenue and COGS to costing based COPA
    B. SO is cost obj with non valuated stock (SAP recommends this)
    C. SO is cost obj with valuated stock...
    B -
    Prod Order is settled upon sales order.. GR from prod order does not update any acc doc
    Sales order is settled to COPA.. Here you can use a PA Trf Str where in you have replicated your Cost Comp Str... i.e. You can create as many assignment lines in KEI1 as your CCS in OKTZ and assign each one of them to a separtae value field
    No question of variances in this case
    C
    Prod order is not settled upon sales order.... GR from Prod order updates acc doc.... However, variance from prod order can be settled to the sales order if you create variance account as a cost element... Else, it is settled to COPA
    Upon PGI, the COGS is posted to Sales Order as a single line item
    Here, in your PA Trf Str, you would create an Assignment line and tick "Qty Billed/Delivered".... This would update the Billing Qty to COPA upon settlement of Sales order
    This Qty update will trigger KE4R.... i.e. You need to assign CCS to VF in KE4R for PV=01 and Rec Type = C.... This would update the CCS in COPA as per the Sales Order cost estimate
    The Costing Key in KE40 should refer to "Sales order cost estimate" and not "Std Cost estimate"
    br, Ajay M

  • Product costing by sale order

    Dear all,
    Please tell me the process in product costing by sales order.
    In my client place, i have done the configuration but i dont know the process.
    Please guide me.
    Thanks & Regards,
    AR

    Hi,
    Product cost by sales order is useful when  a finished product is manufactured  for a specific customer rather than for the normal make-to-stock inventory. You can use the Product Cost by Sales Order component in the following situations:
    When you are manufacturing in-house with reference to a sales order in complex make-to-order production
    When you are purchasing customer-specific trading goods with reference to a sales order and reselling them to your customers
    When you are providing services whose costs are assigned to a sales order
    When you want to collect the sum of the actual costs incurred for the sales order item on the sales order item (standard cost of goods manufactured of sales plus variances) For detailed information, refer to the sections Valuated Sales Order Stock and Settlement in Product Cost by Order or Period.

  • Product costing by sale order(urgent)

    Dear all,
    1. Please tell me all the configuration steps to do product costing by sale order.
    2. Also please tell me how to test it after configuring.
    3. Please explain me the end user part also.
    I will award full points.
    Thanks & Regards,
    A.Anandarajan.

    Hi,
    Product cost by sales order is useful when  a finished product is manufactured  for a specific customer rather than for the normal make-to-stock inventory. You can use the Product Cost by Sales Order component in the following situations:
    When you are manufacturing in-house with reference to a sales order in complex make-to-order production
    When you are purchasing customer-specific trading goods with reference to a sales order and reselling them to your customers
    When you are providing services whose costs are assigned to a sales order
    When you want to collect the sum of the actual costs incurred for the sales order item on the sales order item (standard cost of goods manufactured of sales plus variances) For detailed information, refer to the sections Valuated Sales Order Stock and Settlement in Product Cost by Order or Period.

  • How to keep the same cost in Sales order and return order?

    Hi experts,
    When I create a sales order with item cost 100 USD.
    Then the cost of item changed and down to 90 USD.
    When I do goods return refer to the sales order. How can I keep the same cost (VPRS) 100 USD but not 90 USD?
    I made a test the cost in sales order is 100 USD but 90 USD in return sales order.
    I want the cost in return sales order is 100 USD.
    How can I do?
    Thanks,
    Lance

    Hi,
    Let me tell u my understanding of your requirement, after the sales the cost of the item is changed to some thing low than it was in sales order or invoice, in this scenario you need to transfer the cost of the material as it is in the sale order or invoice (which you are taking as reference to create a Return Order), am i right?
    If so, you can proceed like this.
    In the copy controls of Billing to Sales orders ( F2 to RE) we have the pricing type N assigned to it ( Transfer pricing components unchanged, New Cost) here the system is reading the change of the cost again from the material master. if you don' t want it to read the material master data again we can have a change try with pricing type 'D'  (Copy Pricing elements unchanged), and try now.
    let me know the result.
    hope this will solve your problem.

  • Update the cost in sale order

    dear sir
    i check with abaper ,he says the value is updated from sale order
    they get the consumption of sales using customized transaction
    actual cost is zero
    user create the material master withot pricing
    we ask to update the material master and they do the costing run
    in material master standard costing estimate found
    after they  run the consumption report ,once again actual cost is zero
    i chech\ked in  costing status using CK11N ,std cost estimate found
    is it  possible to update the cost in sales order
    (redetermine or recalculate the pricng in sale order)
    so that my consumpotion report will update
    thanks

    Hi,
    Check the following link
    http://help.sap.com/saphelp_46c/helpdata/en/90/ba6da4446711d189420000e829fbbd/content.htm
    Regards,
    Saju.S

  • Plan cost on sales orders

    Good morning,
    does anyboby know if and how is possible planning costs on sales orders?
    Currently, sales orders are set as account assignment; actual costs are accounted without problems on sales orders and report KKBC_KUN properly shows costs. But no plan data.
    Furthermore, we execute cost estimate on sales orders through CK51N.
    Please tell me something more if you know.
    Thanks,
    Regards
    Enrico

    Dear Enrico,
    check the documentation at
    http://help.sap.com/saphelp_erp60_sp/helpdata/en/90/ba81d2446711d189420000e829fbbd/frameset.htm
    br, Guido