Hello,
I have a question regarding TO confirmation.
The requirement is to allow the fork lift driver to pick any HU(=SU) in the storage bin during TO confirmation.
The storage BINs have put away strategy Bulk Storage. The system is Full WM u2013 HU managed.
I am simulating the process with the LT03 transaction. When creating the TO in foreground:
a)     Source SU is empty u2013 which is OK u2013 fork lift driver will choose which SU to pick.
b)     Destination SU has only zeroes: 00000000000000000000.
When I create such TO the system gives me an error via sap mail notification: u201CExpress document "Update was terminated"u201D
Error info: SU 00000000000000000000. Already exists.
Solution:
I created a new HU through HU01 and then gave this new (letu2019s say dummy) HU as Destination SU in the process of TO creation.
Now the fork lift driver can choose the real pick HU during TO confirmation. The dummy HU is replaced by the real HU.
My question is:
Is there a solution that the system would automatically generate this dummy HU as destination SU instead of the 00000000000000000000. Or could the destination SU field be empty somehow?
Please help.
Thank you very much in advance

Thank you again for your effort.
As far as i can see in my settings - The SU-managed Bulk Storage is active for the storage type.
But still i have to generate a dummy HU with HU01, which i then use in LT03 as destination SU when creating the TO.
The system doesn't allow the destination SU to be emtpy or all zeroes.
Once again:
The process works, but my question is if i can get rid of the step where i manually have to create a dummy HU which is then replaced with the real HU in the process confirming the TO ( picking in the BIN).
Thank you in advance for any new hints.

Similar Messages

  • How to pick activity type from HR mini master during activity confirmation

    Hi,
    How to pick activity type from HR mini master during activity confirmation via BAPI "BAPI_NETWORK_CONF_ADD".
    I have confirmed activity via bapi BAPI_NETWORK_CONF_ADD, and it is picking activity type from activity. but i wants from HR mini master. In BAPI i am passing Personal no.
    Thanks in advance.

    Hi,
    Did you mention Activity type information in HR Master-315 InfoType (TimeSheet Default value).
    then you can get the value.
    Vemula

  • R/3 request storage unit during TO confirmation

    Dear all,
    I bump into an obstacle while perform TO confirmation.
    During TO confirnmation, there is one screen requesting me to key in the storage unit.
    I tried to put in some of the storage unit from the the search screen (i.e. the little round shape next to the field), but system don't allow.
    May I know how to handle this?
    Do I need to create a new storage unit and put in to this field during TO confirmation?
    thanks
    tuff

    Dear Sinéad, and other,
    Ok this is how I bump into the error (in between, my WM knowledge has not reach the Storage Unit yet).
    I have created a TO for picking from a delivery order via VL02N's menu screen (i.e. movement type 601). Next, I perform a TO confirmation in LT12, and when I click the "Confirm Internally" button, R/3 jumps to this screen requesting the following two data:
    1- Storage unit
    << I tried to assign some randomly existing SU unit to this field but R/3 complaint "Storage unit 00157032650003548391 does not exist Message no. L3209">>
    2- Destination Storage Unit
    << I tried to assign some randomly existing SU unit to this field but R/3 complaint "Target handling unit 157032650000046104 is not assigned to TO 0000353991 Message no. L3822">>
    I just don't know how to proceed now as without the confirmation there is no picking (i.e. as the actual quantity field in the LT12 screen still empty) and there is a problem on PGI later on my delivery.
    Please teach me how to proceed when encounter above obstacles.
    thanks
    tuff

  • Printing during TO confirmation

    Hi Guys,
    We are using RF devices to perform picking. How do I print during transfer order confirmation process. We want to print during TO creation and also during TO confirmation.
    Thanks
    Puneet

    Hi
    As far as I know printing is not Possible through RF devices
    regards

  • Change of bin not possible during TO confirmation

    Hi all.
    I am trying to change the destination storage bin during transfer between bins (WM movement 309).
    The strategy is fix bin (maintained in material master), so the TO is created with fix destination bin and operator must change it before confirmation.
    For example, in GR it is possible to change destination bin during confirmation in transaction LT12 but not for transfer. The receiving storage type is the same in both cases. Is there any customizing missing?
    Apart from this, is there any way to confirm items separately inside a TO? For example, during GR I try to confirm a TO in transaction LT11 for just one item and waiting for the rest to be placed physically in order to confirm all the TO but destination bin can not be modified in LT11. Is there any way to confirm item per item but allowing changing destination bin? it is possible to do it in LT12 but not in LT11.
    Many thanks in advanced and best regards.

    Hi,
    Generally, it is possible to change the destination bin during TO confirmation. However, this is not possible under the following conditions:
    o  With dynamic coordinates                                                                               
    o  If the destination bin location is specified in the movement type
    o  For posting change transfer orders                                                                               
    o  For the physical inventory using a putaway                                                                               
    o  For the addition to existing stock for storage units                                                                               
    o  For the transaction Confirm Single Item (transaction LT11)                                                                               
    o  If a bulk storage type is involved in the stock movement                                                                               
    o  In the event of an individual putaway strategy                                                                               
    o  If the first item of a TO with storage units is already confirmed
       since all the other items of the storage unit relate to the same 
       storage bin. When you save the first TO item, the system changes 
       the destination storage bin for all dependent items.                                                                               
    o  If this is a replenishment transfer requirement for a fixed      
       storage bin.                                                     
    Please see SAP Note number 443916 for an explanation.
    Thank you.
    Patrick

  • Restrict Authorization at Material level during production confirmation

    Hi SAP Gurus,
    I would like to ask if its possible to restrict authorization at Material Level during production confirmation.
    Our scenario is we have SFG and FG which are handled by different group of people but it has the same Order Type. Now we want to restrict authorization such as one department can only confirm SFG and the other department can confirm FG only.
    Is it possible to set authorization at material type or production scheduler level. IF not possible, is there other way except creation of new Order Type?
    Thanks,
    Raymond

    Hi Raymond,
    DO you mean I should create a customized table for this?
    Yes
    Are there no standard way?
    As per my knowledge, you can control through production order type, so you need to create seprate order type for this
    Thanks,
    Sankaran

  • Problem with goods movement during operation confirmation

    Hello,
    While doing the operation confirmation,the goods movement are not posted for the components attached to that operation i.e i am not getting the quantity of the components in the "goods movement" tab while confirming.
    check points done: 1) Final confirmation tick is activated during ope. confirmation.
                                 2) Backflushing is activated for material(componenets that areattached to that operation).
    please let me know what is the reason for not getting the qty displayed in the "Goods Movement" tab
    Thank you.
    Regards
    Santosh

    hi
    Normally if you activated the backflush for the material in the order,the material wont be displayed in the goods movement tab unless you activated the All materials in the parameters for confirmation in the intial screen of IW41
    kindly check
    regards
    thyagarajan

  • Goods movement during operation confirmation

    Hi Gurus
    Currently My system is backflushing all the components when i partially confirm the operation through Co11n T-code, which i dont want. I want the backflushing should happen only after the final confirmation of the operation.
    Is there any configuration change required to stop the backflushing only during partial confirmation.
    Thanks in advance,
    Quantum.

    Hi
    In SAP U can do backflush in 3 ways
    Indicator: Backflush
    Determines whether the backflush indicator is set in the production order. Here, a 3-level hierarchical logic is applied:
    1. In the routing, the backflush indicator is set in the component assignment.
    2. In the material master record, the backflush indicator has the characteristic "Always backflush".
    3. In the material master record, the backflush indicator has the characteristic "Work center decides",
    the indicator being set in the work center.
    If at all u dont want to Backflush at the time of Confirmation in CO11N, partial confirmation , dont set any backflush indicator in any level, u can go for Manual Goobs issue Using MB1A, So that u can confirm Goods issue , and final component u can confim By setting Auto goods recipt with the help of Control Key for the last operation in routing.
    i Hope this will help.
    madhu

  • User Exit  during TO confirmation

    hello,
    I need to find a user exit that we can use during TO confirmation..need to capture some information from the TO , such as source , destination bins , quantity and user ....plz advise
    Kind Regards
    Edited by: BrightSide on May 18, 2009 9:29 AM

    Hi,
    In transaction CMOD you have to create a new proyect and assign the enhancement MWMTO002. There are only one user exit (EXIT_SAPLL03T_002).
    You have to create the include ZXLTOU02. In this include you can put a break pint to check the user exit (the user run in update task, so you need to activate the update debuggin).
    In the user, you have the structure I_LTAK_VB with the header data of the TO that you are confirming and the table T_LTAP_VB. This table is filed with all positions that you are confirmed (if you confirm the TO, all positions is filled in the table, if you confirm only one position, only this appear in the table).
    Regars,
    Pepe

  • Manual Zero Stock Check during TO confirmation in SAP 5.0

    Dear All,
    1.We have a requirement to do zero stock check for SU managed Bulk Storage type during TO confirmation. Is there any exit/enhancement which can help us achieve this? We hve used FM L_TA_QUITTIEREN for TO confirmation for bulk storage type.
    2. We also want to do manual zero stock check during TO confirmation as we have same source SU in multiple TO line item in a TO. SAP note 22067 only says to do manual zero stock for this type of scenario. We are able to request empty bin in manual zero stock check. But unable to post any difference. Is there any exit or enhancement which will enable us to post difference during manual zero stock check?
    Best Regards
    Dinesh

    Solved Probelm on my own

  • IDOC problem during goods confirmation in SRM

    Hi guys,
    I am facing some problem during goods confirmation in SRM.I am getting an error relate to IDOCs.i have setup the desired message and partner ID for goods confirmation in SRm but the IDOC gets stuck with the code 30 and the idicator is yellow.But when i manually reproces trhe IDOC after that it works fine.I dont want to process it manually.Can anyone help me out with the possible source of problem.
    Regards,
    Pawan.

    Hi
    Which SRM version are you using ?
    <b>Please see related links -></b>
    Note 549846 - FAQ: Goods receipt confirmation EBP
    Note 847250 - IDoc error remains in alert monitor although IDoc is ok
    <u>Othere related OSS Notes -></u>
    Note 1049536 Incorrect reference doc year when deleting goods receipt
    Note 683848 Problems with delivery note number with upper/lower case
    Note 747422 Replace internal units with ISO codes - modification
    Note 545657 Error in ERS procedure in back end: Delivery note missing
    Note 338985 BBPCF & IV: incorrect IDocs in backend system
    Note 561881 Posting of returns for partial confirmation not possible
    Note 550884 Check of return delivery and reversal against back end
    Note 514669 Goods receipt cannot be posted
    Note 502869 Return delivery possible despite posted return delivery
    Note 430153 Classic scenario: Goods receipt/issue slip, bill of lading
    Note 360833 "Purchase order & is being processed", IDoc error
    Note 388601 Follow-up processing for GR/SE confirmation is not possible
    <u>Do let me know.</u>
    Regards
    - Atul

  • Auto pick release and auto ship confirm in 11.0.3

    Hi All,
    Anybody having sample code to do auto pick release and auto ship confirm process in 11.0.3?
    Any suggestions please.
    Thanks & Regards,
    Gowri

    Set hold until date to the order lines and run the auto release concurrent program.
    Thanks / Bhaskar Akkala

  • WM - Message L3 025 during TO confirmation

    Hi all,  during TO confirmation (with tcode LT22 using foreground mode) I receive the error L3 025 "Act.quantities and diff.quantities are not target quantities. Check entry" .
    I am not changing the date quantity.
    thanks
    Ignazio
    Message was edited by:
            Ignazio Marchese

    Hello Ignazio Marchese 
    Are you trying to change the qty during the confirmation? if yes, then the sum of Actual confirmation qty and difference qty must be the same as target TO qty.
    Hope this helps.
    Regards
    Arif Mansuri

  • Pick and pack allowed during TO confirmation

    Dear fellow warehousers,
    In the WM-Shipping interface I have been able to have my HU generated automatically during LT12
    But, during LM05 it is not doing it.
    I think it should not make a difference between the method of confirmation.
    What do you think?
    Thank you for your time.
    Sandeep

    Hello,
    there are two standard SAP RF transaction:
    LM45                 Pick and Pack
    LM46                 Pick and Pack by Delivery
    On first screen you can scan pick HU (also automatically generated).
    Andrzej

  • Cost Element Error during Activity Confirmation

    Hi,
    We are using assembly processing to create projects. After project is created, a requirement arises and we manually assign few internal activities in CJ20N. When we do like that, a cost element gets picked automatically in the cost element field of External TAB along with Purchase Org & purchase group though it is an internal activity. This doesnt happen in already created activities during automatic creation.
    We don't need the system to bring these values for cost element, purchase org. & group. We are not using this cost element anywhere. In network profile cost element field is blank.
    So whenever we confirm the activity it throws an error message. CK197, G/L account for company code / costelement does not exist.
    Kindly advice.
    Regards,
    Rahul

    Hi, Rahul,
    Have your system is gone for any recent upgrade for EHP4 ?
    This error is due to EHP4 please implement following said notes
    1285728, 1277967.
    And after that remove the cost element from activities present in external tab which are created before not implementation which are giving error.
    revert after resolving the issue.
    regards,

Maybe you are looking for

  • EXCEPTION_ACCESS_VIOLATION trying to import existing project into eclipse

    Eclipse Europa version 3.3, Java 1.6 No problems using Eclipse on other projects But trying to import an existing project into Eclipse. File->Import->General->Existing Projects into Workspace Import Projects box-> Select root directory-> browse to pa

  • I can not print black and white only documents and I have a full black ink cartridge

    I have been an loyal HP customer since the orginal laserjet in the early 90s and then many inkjets from HP after that.   I bought an HP 6600 All in one for the house and have only ever printed in black and white.  For some reason one of the color ink

  • HVX200 Ingest workflow?

    Anyone have a good workflow with ingesting hvx200 footage? Once I import all my media from a certain card or drive I then wrap them all then delete them from the final cut bins. I then find them via "bridge" from adobe's cs2 and rename all my clips f

  • IPhone won't sync music unless it's in a playlist

    Hi All, When I first got my iPhone 3G I could drag music onto the iPhone icon in iTunes to put music on the phone. Now it won't do that for any of the music in my library. The only thing I can do is make a playlist for the iPhone and sync it. Any ins

  • Is Sun's JMF RTP RFC3550 compliant?

    I have been tasked with making sure Sun's JMF RTP library is compliant with the RFC 3550 spec. Does anyone know if this is true? I have been searching through this site and haven't been able to find a definitive answer. Here is a link to the IETF spe