Work center design and operation confirmation
Hi All,
In my scenario im grouping the similar m/c to a work center
say for ex. 4 lathes m/c into a single work center as LatheALL and also the indiv cap as 4
my customer wants the traceability in which m/c the job is done
So i had designed in such a way that
1 LatheALL -4 cap(this will be additional wc)
2. lathe1 - 1cap
3.lathe2 - 1cap
4.lathe3-1cap
5.lathe4-1cap
in the routing only latheALL will be given., this will help customer in planning
when going for operation confirmation i will give confirmation for that operation and will confirm as lathe1or lathe2 or etc.. this will help prodn dept for traceability in which m/c the work is done
this is method i have informed to client .,
pls advice is this approach is correct ?
also suggest by giving confirmation for another work center will the capacity for the original work center will be reduced
Regards
Anand Srinivasan
Hi Anand,
this is method i have informed to client .,
pls advice is this approach is correct ?
yes, during confirmation time to enter the orginal actual work center, this suitable for your client requirement, do the settings for OPK0 - change the confirmations parameters (0410 or 0420)
Regards,
Sankaran
Similar Messages
-
Change Work Center during production order confirmation
Dear All,
I must to modeling this situation:
I created an production order. In routing I used an work center A.
After I confirmed a half of quantity, the work center A was damaged and I must to change it, with the work center B.
The system allow this change, but when I checked the costing, the situation isn't real. The system counted the costs just for the work center A, and no for work center B.
My question is: it's possible to change the work center, during production order confirmation and the costs updated with new cost?
Thank you for your answer!
Regards,
Marianonce a Order is released, the Process order detaisl for that order is frozen.
however if you want to do it, change the order status to CRTD after reversing the Movements done.
Do READ MAster data , this will copy the new Work center , redo the previously done Moevements.
if the change is long term.
or
Just manually add the new work center and do the processing. if the change is temporary. -
More than one work center for one operation
Hi Experts,
Is it posssible to assign more than one work center to one operation,in a maintenance order?
for example if head fitter and helper has executed maint.activity,how we can do this
Thanks in advance
Regards
PrashilDear,
You cannot assign more then one workcenter to a one operation.
But you can assign to a sub operation,i.e to operation one workcenter and to suboperation anotherworkcenter.
For Sub-operation:
Go to task list change >>> Operation tab.
Let say your first operation number is 0010. Then below it for next operation change operation number to 0010 and next to it there is field for sub-operation give there number 0001 or 0010 as per your requirement. Select suitable control key and work center, give description and press enter. your sub operation 0001 will be created for operation 0010.
I hope it will solve your query,
Thanks,
Mohit -
Dear experts,
I face a problem that system get main work center from equipment master data as a default main work center in maintenance plan when creating maintenance plan. however, if main work center in equipment is changed later, the change will not synchronize to related maintenance plan. if work order is generated from maintenance plan, main work order in order is defaulted from maintenance plan instead of updated work center in equipment.
another problem is that, for those orders generated by maintenance plan, the work centers in operations is defaulted from task list in maintenance plan. in most case, work center in task list is dummy. Actually the work is done by work center in equipment master data.
My expectation is how to auto replace the main work center and work center of operations in work order with the one in equipment master data if order is generated by maintenance plan? is there any standard configuration or enhancement/BADi that can help with this requirement?
thanks!
WesleyWesley,
Sorry - development is the only way.
Another option is to create a batch program that runs before your IP30 run(s) and updates any maintenance items and task lists with the correct work centres.
PeteA -
PP work center capacity and link in Equipment master
Dear All
My client has five equipments which he is clubing them into one work center with five capacities. In equipment master i have given for respective equipments i have given PP work center locations but when i create a maint order for one equip then in planning the capacity avalability is affecting the entire work center for ex if the total work on one equip is 12 hrs then only 8 hrs of capcity should be deducted for to day and 4 hrs for tommorow but in plannig all 12 hrs are getting deducted in todays capacity itself.
Pls give some inputs from your experiances
Thanks and Regards
PankajHi,
Even if we have more than One Equipments in the same work center, PP-PM integration will work.
This is the standard scenario in any Process Industry or in case of an Assembly line of a Automobile manufacturing industry.
So it should work. Please check the following points again,
1. Assignment of Work Center to Equipment Master
2. System Condition - '0' Not in Operation in Both header as well as against Individual Operations (in Work Order for that Equipment)
3. Work Order has been released.
4. Same Work Center is used in Routing and the same is Planned for a period.
If we have all the above points right, then while dispatching the Production Order system should show the Period of block and should shift/plan the PO accordingly.
Regards
Sam -
Work Center Hierarchy and Routing
Hi,
I would like to know what exactly Work Center hierarchy mean?. Where is it used. In Routing, we maintain Sequence of operation along with workcenter where this operations are performed . Would like to know does work center hierarchy is linked to sequence maintained in Routing?. ThanksHi,
Any one can explain me the use of Workcenter Hierarchy?. In Routing, we maintain the sequence of operations. Does Routing and Workcenter Hierarchy has relation?. If Yes, what is the relation between these 2.
Thanks in advance -
Can you have multiple Rates within one Work Center with multiple operations
We have a work center called Pipeshop. Within the Pipeshop we have multiple operations such as Welding, Threading, Cutting, Grooving etc. Each of these operations have a different cost assoicated with them. How can you have different cost for these operations?
Thank you,
LorettaHi,
For this case you need to do following activities.
1 Create individual activity accoding to requirement, that will be used for costing.
2 Activity planning w r t work center. In this cost per unit is declaring.
3. Create Routing and modify the default activity type, w r t required activity type, suitable to operations.
Now Order is referring the activity type, refered in Routing rather than, work center.
Regards
Gururaja Hebbar -
Work Center Hierarchy and Capacity
Hello SAP friends,
Can someone please help me with the following scenario?
I have 3 Work Centers
MAQ00 - (Capacity 10:00 x 2)
MAQ01 - 8:00 -- 18:00 (Capacity 10:00)
MAQ02 - 8:00 -- 18:00 (Capacity 10:00)
I have a hierarchy
HICY01
MAQ00 - Root of hierarchy
|_ MAQ01
|_ MAQ02
Then, I have a routing
10 - PP01 - MAQ00 - 1H
20 - PP01 - MAQ00 - 2H
If I go to CM01 for Work Center MAQ00 I can see the capacity and requirement, where:
Capacity: 10:00 x 2
Requirement: 3:00
But if I go to transaction CM21 for Work Center MAQ00 the capacity and requirement is not correct. Can someone please help me with this?
Thanks in advance,
Adelmo SilvaHi,
CM01 will give the cumulative requirement as 3 hrs but CM21(Gradhical View) shows the individual spread of oprn. 10 and 20 as 1H and 2 H resp.
Does the above help you?
-Thaila Shree -
CO11N work center mandatory and without default
Dear guru,
i need to make work center mandatory in CO11N and without any default
from production routing.
I donu2019t want to use SHD0.
Do you suggest any exit to obtain this ?
Thanks in advanceHi,
I believe the user-exit which you should look at is:
CONFPP03 PP order conf.: Cust. specific check after op. selection
or
CONFPP05 PP order conf.: Customer specific enhancements when saving
Check with your abaper if the above can meet your need.
Regards,
Vivek -
Buyer Work Center performance and persoanlizations
Hi All,
we are currently on R12.1.3 and we've few issues with the way the Buyer Work Center is working
1) The performance of BWC is very slow. Navigating from one field to another field takes at least 5seconds. For fields like project, task, org etc the form takes 10seconds also. Combining all this, creating a PO with 10 lines takes about 10-15mins for our users. Is this normal? Are there ways to improve the performance?
2) There are multiple screens to navgiate. First the users start off with header then to line summary and then to line details/schedules/distributions etc. Is there a simple way to make all information available in one single page so that the users do not have to spend time navigating from one screen to another screen? This will be really helpful for users creating POs with more than 10lines. I'm thinking of persoanlizing the PO line summary screen and make POET available there. Has anyone done any customizations to the PO line summary screen?
I'm sure you must have faced similar issues with your clients. Please let me know if you handled these issues.
Thanks,hadimulam wrote:
2) There are multiple screens to navgiate. First the users start off with header then to line summary and then to line details/schedules/distributions etc. Is there a simple way to make all information available in one single page so that the users do not have to spend time navigating from one screen to another screen? This will be really helpful for users creating POs with more than 10lines. I'm thinking of persoanlizing the PO line summary screen and make POET available there. Has anyone done any customizations to the PO line summary screen? Same question was asked by my client, I recommended them to go directly to the "Distributions" tab and search for the PO. Actually most of the key fields from the header, lines, shipments and distributions are available at the distribution tab and you can add many more fields by clicking on the "Add Another" field. Moreover, you can save the final view for future reference so that you don't need to add the same fields again.
Yes, it is a workaround, as you will see repeated lines for multi shipment and distribution scenarios but single shipment - distribution scenario will be OK.
Thanks,
PS. -
When I try to open an video in youtube or facebook the player just goes black and white.
With google chrome and opera I don't got any problems..Hello,
Starting in Firefox 23, if a secure page includes certain types of insecure content, Firefox blocks the insecure content and a shield icon will appear in the address bar. See this article for more information about the new mixed content blocker: [[How does content that isn't secure affect my safety?]]
To temporarily allow the mixed content to be displayed:
*Click the '''shield icon''' [[Image:Mixed Content Shield]] in the address bar and choose '''Disable Protection on This Page''' from the dropdown menu.
[[Image:Fx23MixedContentBlocker]]
To allow insecure content to be displayed in all secure pages, enter '''about:config''' in the address bar and double-click on this preference, to toggle it from true to false:
'''security.mixed_content.block_active_content'''
You can also use this add-on instead, to toggle the preference:
*[https://addons.mozilla.org/firefox/addon/toggle-mixed-active-content/ Toggle Mixed active content] add-on
You may want to do this only for the current session, then reset the preference back to "true" and check back with the site to see whether it's been fixed, since this is a global setting that exposes you on all sites, not just the one you care about.
Let us know if this helps! -
Flash app works in FF and Opera but not in IE
Good day all,
I am not a flash fundie, but i am part of a project which has
run into a snag and i have been left to do research what is causing
the snag.
The testing browsers we used:
FireFox 3.0.5 (used in linux and windows) with Shockwave
Player 10.0 r15
Internet Explorer v6.x as well as v7.0.5730.13 (windows only)
Opera v9.63 (linux version)
We are building an online fixed odds poker game for a client.
Front end is flash and actionscript (v3) with the backend being a
combination of php and c++.
The issue:
When playing the game in Firefox (both in linux and windows)
one can play a game from preflop to flop to turn and to river. And
when you shuffle the deck each player gets new cards and each of
the mentioned stages has new cards, thus a new game. Note that the
game does work correctly in opera as well.
But when playing it in IE in windows we find that the first
game you play repeats; over and over again. As long as you place
your bets in the same order each time the same game will repeat
never ending. Change the order of your bets and the game throws a
developed communications error. Then you restart the game, you now
get whole new set of cards but when you reshuffle the deck at the
end of the game you get exactly the same cards again, and then if
you keep the order of the betting the same you will find that the
game repeats non-stop.
We have cleared the cache of IE, we have "cleared the cache"
of EVERYTHING! :P But still the issue persists in IE in windows.
The issue occurs on both the versions described earlier and occurs
on three separate PC's of which two are in our offices and one is a
home pc.
My experience in flash and action script is zero (i am a
php/JS/mysql programmer) but we have little resources and i am
standing in for the flash person who cannot get an opportunity to
to research this matter.
Any questions you have, feel free to ask. Any remarks or
feedback or opinion you may have feel free to give it with as much
technical details as you prefer. I will pass all details i receive
on to the Flash developer.
Any and all assistance would be greatly appreciated.
Thank you.How are you getting the data for the dealt cards?
If it is thru some external data source, using a url to call
it in, you can try adding ?nocache= XX
where XX is a randomly generated number (so it isn't the same
all the time) The significance of using nocache as a variable name
is probably none... meaning it could probably be called
anything. -
I am unable to save a service work order designated and configured as MRS work order
Every time I try to create a SM work order, and save it, I get the following message"
Error in the ABAP Application Program
The current ABAP program "/MRSS/SAPLRSG_PM_ORDER" had to be terminat
it has
come across a statement that unfortunately cannot be executed.
In include "/MRSS/LRSG_PMCS_APPSCHEDF02 ", in line 93 of
"/MRSS/SAPLRSG_PMCS_APPSCHED ", the following syntax er
have occurred:
The row type of the table "G_APPOINTMENT_LIST" is not compatible wit
field symbol type "<APPOINTMENT_LIST>".
Author and last person to change the include are:
Author SAP
Last changed by "SAP "
Any help or advise that would allow me to successfully create the work order and then open the planning board to view both the demand and the resources? I would appreciate any help. ThanksHi Hussein,
I found a SAP note 2030049 that is relevant to the problem: http://service.sap.com/sap/support/notes/2030049
But when attempting to implement the note, it showed a syntax error.
Will likely log this with SAP for resolution.
Regards, Warren -
Select query not working with like & and operator
Hi,
The below is the select query which is used to select only the failed rollup jobs from DB table ( background jobs ) the status 'A' which means only the failed roll up jobs.
select jobname status from v_op into table zjob_rollup where jobname like '%ROLLUP%'
or jobname like 'BI_AGGR%'
and status like 'A'.
Right now my internal tables is picking the job name other than status A also.
Can you please help.
Note: Ps consider the performance of select query also.
Thanks,
SivaHi,
select jobname status
from v_op
into table zjob_rollup
where ( jobname like '%ROLLUP%' or jobname like 'BI_AGGR%' )
and status = 'A'. -
I have checked my setting and options and I cant seem to get igoogle to load the modules to load.
Ok, to copy the Drive from one to another, get carbon copy cloner to make an exact copy of your old HD to the New one...
http://www.bombich.com/software/ccc.html
Or SuperDuper...
http://www.shirt-pocket.com/SuperDuper/
Believe it or not, anything on the Desktop uses 3 times the Resources of the Mac than if stored elsewhere, I can note a slowdown from just 30 items on the Desktop on a really fast Mac, so the less the better on the Desktop.
DW will not tell you about Bad Sectors, it's just the very best at Repair Directory damage & such.
At this point I think you should get Applejack...
http://www.macupdate.com/info.php/id/15667/applejack
After installing, reboot holding down CMD+s, (+s), then when the DOS like prompt shows, type in...
applejack AUTO
Then let it do all 6 of it's things.
At least it'll eliminate some questions if it doesn't fix it.
The 6 things it does are...
Correct any Disk problems.
Repair Permissions.
Clear out Cache Files.
Repair/check several plist files.
Dump the VM files for a fresh start.
Trash old Log files.
First reboot will be slower, sometimes 2 or 3 restarts will be required for full benefit... my guess is files relying upon other files relying upon other files! :-)
Disconnect the USB cable from any Uninterruptible Power Supply so the system doesn't shut down in the middle of the process.
Maybe you are looking for
-
AT&T family plan - 4 iPhones in use by family members (4s, 4g, and two 3g's). Weird things happen when we text message: 1. Sometimes, received messages look like they are sent messages - and no alert is sounded. The conversation looks like you a
-
Can we display the selected fields in two screen?
HI friends i have got a problem where i am have two screen 1000 and 102. In 1000 screen i have got 2 push buttons display and cancel if i click display by giving emp_id then module and email has to be display for which i have given code as... MODULE
-
I am getting a hang when running my java program. Part of the stacktrace is below. I see an 'overflowEi' in the trace. Is that the problem? What does that mean. Thanks in advance!! 3HPNATIVESTACK Native Stack of "Thread-19" PID 5753 NULL ------------
-
N95 8GB Newbie question re Text Messaging
Hello Folks, I live in the USA an have AT&T as a provider. I am just learning my around the N95 8GB. When I try to send a text message I get a screen with two window. One is label "Text message Center" and the other has "message center number" in it.
-
.js includes and caching in MII 12
We are keeping all our javascript in a .js file outside the .irpt. At times when we change the .js file it is not carrying over to the .irpt. Pretty sure this is some kind of caching issue. Have tried clearing javascript cache and IE (delete files