Hi Experts,
May i know how can i make Mandatory, both  Work center (Mn.wk.ctr) Under Person Responsible sub screen and the work center ( WkCtr/Plnt ) under first Operation sub screen  of the Header TAB in PM Order.
Regards,
Kavvya

Hi,
The Work Center (CAUFVD-VAPLZ) field under 'Person Responsible' should always be mandatory as it is hardcoded.
The Work Center (AFVGD-ARBPL) of operation can be set with transaction OIOPD. If the 'work center' field is not available in OIOPD, then see the correction from note [1282463|https://service.sap.com/sap/support/notes/1282463].
-Paul

Similar Messages

  • CO11N work center mandatory and without default

    Dear guru,
    i need to make work center mandatory in CO11N and without any default
    from production routing.
    I donu2019t want to use SHD0.
    Do you suggest any exit to obtain this ?
    Thanks in advance

    Hi,
    I believe the user-exit which you should look at is:
    CONFPP03 PP order conf.: Cust. specific check after op. selection
    or
    CONFPP05 PP order conf.: Customer specific enhancements when saving
    Check with your abaper if the above can meet your need.
    Regards,
    Vivek

  • How to make a field profit center mandatory in sales order?

    Dear GURUS,
    Please help in getting answer for following question.
    How to make a field profit center mandatory in sales order?
    With Regards
    Sandeep D.

    Hi,
    There are 2 ways to make profit center mandatory
    1.Transaction Variant
    2.Incompletion procedure
    1.Transaction Variant
    Step 1:Goto Tcode shd0 and input transaction as va01 and give name of transaction variant as ( example. zva01 ) and click on create or F5
    Step 2.Then it takes you to sales order screen.Just click on enter untill you see profit center field.
    Step 3.check the box required against profit center.
    Step 4.click on save ( under a package name or as local object ) and exit
    Step 5.Assign transaction variant to your sales order type through tcode v0v8.
    2.Incompletion Procedure
    You can add the field  table-vbap,field- prctr,status-04,check-warning to your existing incompletion procedure Tcode- ova2 assigned to your order type in tcode vov8  and check the box - incomplete messeges for your order type through tcode vov8.
    If incompletion procedure is not assigned to your order type than you have to create a new incompletion procedure and assign it to order type.

  • Profit Center Mandatory in Service Order

    Hi ,
    Is there a customising to make profit center mandatory in service orders (IW31)
    Thanks and Regards,
    Vamsee

    Dear,
    You can do this with transaction variant through SHD0. Record the transaction like IW31 and make the field mandatory.
    Please try and come back.
    Regards,
    R.Brahmankar

  • Dyanmic work center selection in production order based on material

    Hi ALL,
    We’ve a business requirement to support the following functionality.
    There are four similar type of milling machines say MILL1 MILL2, MILL3, MILL4, we create a single work center called MILLMC by specifying total capacity of four milling machines in the capacity header screen of work center with 4 individual capacities. And we mention work center MILLMC in the operation of routings for respective materials.
    However, during production order creation, there needs to be provision for detailed planning of work centers as per the following requirements
    In production order, some operations can be performed on any one of the machines MILL1 MILL2, MILL3, MILL4, so provision needs to be there to enter exact machine on which it is performed in the production order operation after the details are copied from respective routing during production order creation.
    In production order, some operations can be performed on only MILL3, so system should select only MILL3 in the respective operation of the production order
    In production order, some operations can be performed on either MILL1 or MILL2 or MILL4 and not on MILL3, so system should not select MILL3 in the respective operation of the production order.
    Please provide your valuable feedback to support the above requirements.
    Regards,
    Satya.

    Hi Satyanarayan,
      Please do refer to the below document. I think the same concept can be used for work centers as it is used for resources in PI industry.
    Resource Classification in Master Recipe for Planning
    Regards
    Kalyan

  • Work center change in Service order not happening

    Hi Experts,
    I am facing a problem when i try to Call a function module in update task where the Function module contains a call to BAPI_ALM_ORDER_MAINTAIN without COMMIT WORK.
    This is done in order to update the Work Center while there are changes to the Warranty Status of the Repair Order.
    So , i have written the Code in the Userexit_SAVE_Document so that the Update gets done.
    But there might be problems when the Repair order does not get saved.
    So keeping that scenario in mind, I tried using the Update task Function  Module in which i wil lbe calling the BAPI for Changing/Updating the Service order.
    BUT , The Change is not getting reflected in the Work centre of the Service order.
    Thanks
    VIJAYB
    Edited by: Rob Burbank on Jun 5, 2009 10:10 AM

    Hai experts,
    i have found the way to do the work center change in update task method .
    I did call the BAPI_ALM_ORDER_MAINTAIN but without using COMMIT since this function module is called in Update task method so whatever is the change being done by that BAPI will be reflected in the Service order once the Update  task has been done for that service order.
    Thanks and regards,
    VIJAYB.

  • To make Cost Center Mandatory on Internal Order

    We want to make the Responsible Cost center Mandatory on the Internal Order. Can you pls let me know the config. piece of it.
    Thanks in Advance.
    Vineet

    In SPRO-Controlling-Internal Orders-Order Master Data-Screen Layout-Select Fields. Select your order type. In the area Master data display select Field selection. There you make the fields you want as mandatory, display or hide.
    pls assign points if helpful as a way to say thanks.

  • Read Routing and work center details from transfer order

    Hello
    I am using transaction LT31 to print a form for the transfer order.
    The customer wants me to print a field that is in the work center details of the routing for this material and plant.
    I can see this data with transaction CA02 where i enter material and plant,and then the work centers are beeing displayed.From here i can double click on the work center and see the field Supply area that i have to print.
    My answer now is,how to read details on the work center starting from my transfer order number.Which is the table connection between transfer order table LTAK and the tables where i can find the work center details.
    Thank you

    I have found the solution:
    ltak-tanum = mseg-tbnum
    read aufnr from mseg and go to afko
    mseg-aufnr = afko-aufnr
    read plnnr from afko and go to plpo
    afko-plnnr = plpo-plnnr
    from plpo read arbid and go to crhd
    plpo-arbid = crhd-objid
    from here,we can find the arbpl and the field that i was looking for PRVBE

  • Require help on coast center and work center tables through sales order

    dear experts
    my requirement is to report the cm05(capacity planning ) transaction.
    The original capacity planning consists of workcenter details.
    but my client needs the report as follows
    on which sales order and on which work center we require the capacity of materials.
    any tables and fields for this report please.
    help needed.
    kindly update me.

    hi,
    Please explore table CAUFV View "Order Headers PP/CO" ,here you will find the relationships between the three.
    Regards,
    Neha

  • Operations Executed at a Particular Work Center for a Sales Order

    Hi All,
    We are using a MTO scenario. I have to get a report in which I have to list work center wise operations (and the corresponding material) which are carried out for a particular sales order.
    User will create a sales order, and then do Sales Order based MRP in MD50. System will do a BOM explosion for the header material and will generate planned orders for the production relevant materials. User will then convert all these sales order specific planned orders to production orders. For a particular sales order these would be many operations (at different BOM levels may be ) that would be carried out at a particular work center. I need to get a logic for generating this report. Is there any FM etc or table table-field fetchig logic....
    Regards

    hi,
    maintain initial screen entry as sale order.
    Pass values to AFPO table. Identify all AFPO-AUFNR values which satisfies AFPO-DAUTY = 10
    Transfer AUFNR values to AFKO and check AUFPL (Routing number of operations in the order)
    Transfer AUFPL  to AFVC and check the value of AFVC-ARBID (Object ID of the resource)
    Transfer ARBID to CRHD and check value of ARBPL (Work Center)
    Regards,
    Pavan

  • Work center wise production order infomation report

    Hi all,
    i have a requirement that workcenter wise (with date) production order information with quantity details (plan and actual).
    Eg: My production order quantity - 40 nos. (it takes 4 days to finish).
          i have three operation in production order.
          my order scheduled start date - todays date.
    In standard, when enter my first operation work center, system showing production order and its quantity (40 nos) . but i need to split that order quantity in report.. means on todays date for particular production order - order quantity = 10 nos.
    Clent want like that (with quantity break) report..
    Any standard report ???
    If customization.... How it can be mapped in SAP.??
    Thanks in advance

    Hi,
    You can use the FM COIS_SELECT_ORDER_DATA_READ.
    CALL FUNCTION 'COIS_SELECT_ORDER_DATA_READ'
          EXPORTING
            iv_prod_order_sel       = lv_prod_order_sel
            iv_proc_order_sel       = lv_proc_order_sel
            iv_planned_order_sel    = lv_planned_order_sel
            iv_rem_objects_only_sel = lv_rem_objects_only_sel
            is_objects_to_read      = ls_objects_to_read
            it_parameter            = lt_parameter  "General Structure for PARAMETERS and SELECT-OPTIONS
            it_status_hdr           = lt_status_hdr
            it_status_opr           = lt_status_opr
            it_status_cmp           = lt_status_cmp
          TABLES
            ct_ioheader             = lt_ioheader
            ct_ioitem               = lt_ioitem
            ct_iodocl               = lt_iodocl
            ct_ioopdocl             = lt_ioopdocl
            ct_iomamo               = lt_iomamo
            ct_ioconf               = lt_ioconf
            ct_ioopconf             = lt_ioopconf
            ct_iosoconf             = lt_iosoconf
            ct_iogomo               = lt_iogomo
            ct_ioopgomo             = lt_ioopgomo
            ct_iosogomo             = lt_iosogomo
            ct_iogmer               = lt_iogmer
            ct_ioopgmer             = lt_ioopgmer
            ct_iosogmer             = lt_iosogmer
            ct_iosequen             = lt_iosequen
            ct_iooper               = lt_iooper
            ct_iosoper              = lt_iosoper
            ct_ioopcomp             = lt_ioopcomp
            ct_iooppreq             = lt_iooppreq
            ct_iosopreq             = lt_iosopreq
            ct_iooppord             = lt_iooppord
            ct_iosopord             = lt_iosopord
            ct_ioopmst              = lt_ioopmst
            ct_ioopprt              = lt_ioopprt
            ct_ioopcap              = lt_ioopcap
            ct_ioopscap             = lt_ioopscap
            ct_iosocap              = lt_iosocap
            ct_iososcap             = lt_iososcap
            ct_ioopsccf             = lt_ioopsccf
            ct_iososccf             = lt_iososccf
            ct_ioprodlist           = lt_ioprodlist
            ct_iomatver             = lt_iomatver.
    This FM get data from the report used by transaction COOIS. If you needed the header data then you can use lt_ioheader table and seperate the data with the date. If you need at operation basis the you can use lt_iosoper table. You can use this FM to create custom report even with the checks like material availability, PRT availability, capacity requirement etc.
    Thanks and regards,
    Pradip
    Edited by: Pradip Ray on Aug 26, 2009 8:26 AM
    Edited by: Pradip Ray on Aug 26, 2009 8:26 AM
    Edited by: Pradip Ray on Aug 26, 2009 8:26 AM
    Edited by: Pradip Ray on Aug 26, 2009 8:27 AM

  • Block production work center during maintenance order

    Dear Experts,
    iam trying to do the integration between PM and PP, I want to block the production work center from any production order  when there is any maintenance order opened for a certain equipment which is inside this  work center ,
    till now i did the following:
    1) the production work center is now inside the equipment location tab
    2) when i open any maintenance order i put system condition as zero
    now what i only achieved ,
    - in transaction CM25 the capacity is black for the period of the maintenance order
    BUT the work center is not blocked and any production order can be created without any error
    please help and much thanks in advance
    Best Regards

    Hi,
    Till time you have performed right things to integrate PP-PM & system is also responding according to setting.
    Showing block capicity in CM25 against the Maintenance Order.
    If you want to block production order as well, you need to do one more setting.
    go to t- code OIOI, selection Production order types (those you want to block) & in capacity Availabilty choose Collect conversion as 3 : No creation if there is insufficiant caacity.
    i hope this will definately solve your problem.
    - Yatharth

  • Tag production order to Work center

    hey everyone,
    I need to tag the correct work center to the prod order. One Production order has say 5 materials and they have different movements on it. We need to fetch the correct work center for each material movement. I am able to find work center for materials that have entry in the RESB table but for material that is final produced has no entry in RESB thus we cant tag it to any work center.
    Does any one know how to tag the produced material to the correct work center according to the operation on that production order.
    any suggestions would be appreciated.
    thanks !!

    Hi,
    Yes, one production order has only one material produced. this material can be found in CO03. But i cant find the appopriate work center for this material. Do you know how ? Because this material has no entry in the reservation table.
    thanks
    Laura.

  • Tag Work center to Materials in Production Order

    hey everyone,
    I need to tag the correct work center to the prod order. One Production order has say 5 materials and they have different movements on it. We need to fetch the correct work center for each material movement. I am able to find work center for materials that have entry in the RESB table but for material that is final produced has no entry in RESB thus we cant tag it to any work center.
    Does any one know how to tag the produced material to the correct work center according to the operation on that production order.
    any suggestions would be appreciated.
    thanks !!

    Laura: Please don't post the same question in different forums. Thanks!

  • Change Work Center on a Prod. Order

    Hi,
    I have been searching through the archives and found a lot of maybe, but no final ideas.
    How do you change a Work Center on a Prod Order?
    Anybody has a suggesfull way of doing it?
    Thanks
    Andy

    Andy,
    Try using BAPI_ALM_ORDER_MAINTAIN. The documentation states this BAPI is for maintenance orders, but we have used it to change the bill of materials and other parts of the production order.
    Glenn

Maybe you are looking for

  • Published pdf form is unable to connect with database

    Hi Guys! I have created a PDF form using Adobe Live Cycle Designer which have some text fields namely RECORD and NAME. I have connected this form with a Database. When I enter a record in the RECORD number field the NAME field of this form has been p

  • UILoader won't display images from PHP/MYSQL query

    I'm working on an online photo catalog, it works in straight PHP/HTML http://www.buckleyphotos.com/search/index.php but the photos are too easy to grab (Facebook and myspace are loaded with my photos). I know anything on screen can be grabbed, I just

  • Center channel is

    So the problem is, I have X-Fi ExtremeGamer Fatalty and my center channel is very quite - barely hearable. I've done pretty anything - reinstalled drivers, reinstalled console launcher (now installed those beta drivers and console), gone through vari

  • How to edit a webdynpro JAVA application of ESS portal

    Hi, I have to work on a webdynpor JAVA app configurged in ESS portal,the app shows the salary slip of the employees,but don't have logo in it,so i am suppose to put logo there,but not able to understand how to start work on it. i have fair idea of We

  • PSE 8 Layers and Effects

    Hi All my first post here, I came across this forum whikst googling for a solution..... I run Windows 7 and have PSE 8 - last night I was playing with layers and effects in PSE 8 and I clicked on the small blue box with FX written in the corner of th