Work centres operator linkage

Hi,
My client wants in CO11n screen, where we select employee ID by pressing F4, client should get get only those operators ID to be listed  who are assigned to this work centre.
Is it possible? But to get this I should assign in my work centre the names of three operators who will work on 3 different shifts or else who all are possibly be working in this work centre( my work centres are not asigned to any shift, they are available 24 hrs in a day) but where and how to assign?
Regards.

Yasir ,
We have the same kind of requirement  in our case.We developed ZCO11N where operator id /supervisor id ,list of work centre (Asset number ) are added with SAP Tables.U need to discuss with SAP ABAP Developer
More oever , in ECC 6.0 version , for CO11N u have option at Personal Data Tab at the bottom of the screen where u can include the Person Name/Work Centre /Posting Dates/Plant available .
I hope this itselg will solve your problem.Let me know if you want ZCO11n functionality .
regards
Jia
Edited by: Jiaul Haque on Dec 24, 2008 8:41 AM

Similar Messages

  • Difference in Main work centre and Operation workcentre

    Hello PM Gurus,
    In CS order, we have two work centres. One at header level called as Main work centre and another at operation level.
    Why do we have two work centres. The one at operation level itself should have been enough.
    There is a main work centre at functional location too ( Organisation tab). So what is the connection if we use this functional location as the reference while creating a CS order.
    Please reply soon.
    Cheers
    Sunny

    Hi Sunny,
    The work center at haeder i.e., Main Work Center is the reponsible work center(say a department). It means it takes the reponsibility of the whole job mentioned in that work order(or job given by production dept.). Now, assume , it further distributes the whole work to its own sub-dept or different work centers as per nature of job. Say, electrical related work to elec work centers etc., by ,means of assigning to different operations.
    The Main work center's cost center will be copied as responsible cost center in Additional data TAB of the order.Now thus you see commercially the responsibility of doing the job lies with the responsible cost center (or say Main work center).
    Hope it is clear.
    Regards,
    Rajesh

  • WORK CENTRE IN EQUIPMENT MASTER DATA

    Hello All,
    In IE01 tcode > creation of equipment , pls tell me what is the relevance of work centre in location tab ??
    Thanks,
    Sunny

    Hi
    Work Center
    Definition:Operations are carried out at a work center. In the R/3 System work centers are business objects that can represent the following real work centers, for example:
    Machines, machine groups
    Production lines
    Assembly work centers
    Employees, groups of employees
    Use
    Together with bills of material and routings, work centers belong to the most important master data in the R/3 production planning and control system. Work centers are used in task list operations and work orders. Task lists are for example routings, maintenance task lists, inspection plans and standard networks. Work orders are created for production, quality assurance, plant maintenance and for the Project System as networks.
    Data in work centers is used for
    Scheduling
    Operating times and formulas are entered in the work center, so that the duration of an operation can be calculated.
    Costing
    Formulas are entered in the work center, so that the costs of an operation can be calculated. A work center is also assigned to a cost center.
    Capacity planning
    The available capacity and formulas for calculating capacity requirements are entered in the work center.
    Simplifying operation maintenance
    Various default values for operations can be entered in the work center.
    Look at CR01 ,CR02,CR03 Transaction
    table : CRHD Table
    <b>Reward points for useful Answers</b>
    Regards
    Anji

  • Restricting the change of workcentre in CO11N to selected work centres

    Dear PP Gurus,
      I have included the following screen
    0420: Personnel: incl work center and posting date  in the confirmation profile, so that the user can change the work centre at the time of confirmation. However the user wants that there should be a check where in only the workcentres which are used in parallel to be allowed for the perticular operation.
    Please guide how to achieve this? Can we have a check thorugh any of the user exit below:
    CONFPP02  PP order conf.: Customer specific input checks 1
    CONFPP03  PP order conf.: Cust. specific check after op. selection
    CONFPP04  PP order conf.: Customer specific input checks 2
    CONFPP05  PP order conf.: Customer specific enhancements when saving
    Eg.
    For operation 0020 the user may perform the confirmations on Weld1 /Weld2 /Weld 3 machine. Now the system will allow to select any work centre other than these three. That may lead to wrong confirmation. The user wants to restrict the work centres to be selected to these three only. These three machines are mentioend as parallel sequence in the routing.
    Regards
    Ankush

    Hey..
    How did u resolve this? i have the same kind of requirement and getting the same error as direct navigation not allowed.
    Can you please let me know. It's urgent.
    Thanks,
    Mahesh

  • Activity type in work centre

    Hi,all,
    I have a requirement as mentioned below-
    I have certain pm work center like engineer,fitters.But under engineer i have 3 different activity type like Sr.engineer time,Asst.engineer time,Jr.engineer time.I have assigned all these 3 activity type in my work centre in cost tab page along with standard formula SAP008.Now , my requirement is when I assign this work center in my equipment or maintenance order ,in operation tab pages of maintenance order ,only these three activity type should flow from where I want to select my relevant activity type.But instead of this,all the activity type around 10 nos whatever defined by CO consultant , is flowing to my order from where i need to select.I want only those 3 activity type which I had defined in my work center.can anybody please explain how to fulfill my requirement.thanks in advance.
    rgds
    rajib

    hi
    you can make the default cost element by creating the external profile in IMG and assigning to the order type ,also in easy access screen during order creation you can mention as default values in the menu Extras>settings>default values
    As per what cost element has to be specified kindly consult with the CO team,regarding the mandatory field may be you have specified the fields as mandatory in IMG settings,kindly check
    regards
    thyagarajan

  • Work centre change in production order

    Hi,
    During creation of production order, i want  to change the work centre if in the existing operation, that particular work centre is overloaded.
    Could any one let me know what are the steps involved in it.
    Re

    Hi,
    Goto CM25 & select the Overload workcenter &  underload workcenter .
    Inside the planning tabel select the Operation  from "Order (Pool) tabel"  and drag manually to the "under load workcenter " displayed in  upper table (workcenter) for required date. Now the operation workcenter has become changed & rescheduled.
    Regards
    Pradeep

  • Querry regarding work centres

    hi guys
    1. anybody plz explain the concept of standard values that are maintained in workcentres and how they are calculated when work centre is assigned to operations in order.
    2 any doc regarding costing of orders ?
    regards
    pushpa

    hi pushpa
    satandar values are used for calcualtion of time spend for partcular workcenter ,for example if it is machine category you will create standard value which contains setup,machine and labour which contains the formula for calculating the execution times for that particular activity.
    setup-15min
    machine-30
    labour-15min
    then the system will calculat the price based on the planning in KP26
    for PM point it is basically NO STANDARD VALUES,hence you have to specify only the activity type in the costing tab page ,cost center and the formula for calculating the times
    regards
    thyagarajan

  • Work centre

    hi all,
    pls help me with,
    WHAT ALL IS TO BE INTEGRATED WITH WORK CENTRE IN HR..I MEAN IS IT ORGANIZATIONAL UNIT..I MEAN WHAT?n hw to integrate it.
    thanx n regards

    Hi,
    Work Center (CR01 - Create, CR02 - Change, CR03 - Display)
    Using the data maintained for a work center, you can
    determine which machines or people are to be used in the operations
    calculate costs, capacities and dates for the operations
    OP42 - Configure the default value for Work Center during the initial creation.
    After creating many work center in the Routing, the users might want to check what materials and components allocation have been updated with this work center.  You can used this program Work Center in Routing - Search through all the routing for the material and component allocation used.
    The standard program transaction CA80, checks where the work center was used in the routing.  However, it did not list the components allocation for the work center.
    Pooled Capacity field - When a production order 1234567 has the capacity requirement on its work center Wxxxxx. It means it has the requirement on pooled capacity Pxxxxx.  If more than one work center shared this pooled capacity, the requirement (transaction CM01) will be shown on all the work center with the SAME shared pooled capacity.
    In HR system we will the cost per each Work Center level. This work center we can assing org unit leave or postion level also.
    Please revet back further clarifications.
    WarmRegards,
    Devi.,

  • Change work centre in CO11N

    Hi,
    In production order of 10 EA, I have two operations. operation 0010 on work centre T1, operation 0020 on work centre D1.Co11N is done for operation 0010 for 4 EA.
    Now rest 6 Ea of first operation has to be done on work centre T2 ( because T1 is brokedown).
    Pls help how to map this? Else is there any option to enter a new work centre( work centre T2) in CO11N screen during confirmation?
    Regards.

    Hi,
    As we know there is possibility in routing to have alternavtive sequence & parallel sequence along with standard sequence. But there will be one work center always associated to single operation. And as you explained, this change in work center for operation 0010 for 6 quantities was happened due to breakdown for work center T1.
    For work around you can do one thing, for first 4 quantities do the confirmation as per planned work center i.e. T1 (as per routing data). Now go to change production order, change work center T2 from T1 for operation 0010. Now the confirmation for remaining 6 qauntities will happen against T2 work center.
    Now whenever you fetch report for confirmation to that production order, it will always shown two confirmations for operation 0010 with 4 qty -T1 work center & 6 qty - T2 work center. I hope this will slove your problem. Coz change in work center was very uncertain due to breakdown, not a regular one. If it is regular, you can map with sequencing in routing.
    Regards,
    Sandeep.

  • Goods issue against work centre

    is it possible to issue any material type against work centre.
    if possible, please explain how. and which movement type will be use ?

    It is not possible to issue a material with respect to a work center. Input materials are allocated to an operation in an order. The operation has the work center in it.
    You issue materials to a reservation which is linked to an operation in the order.
    Regards
    Ram

  • What is Work centre

    Can u let me know what is Cost Centre / Work Centre ?
    What is the difference between production order / process order
    Thanks in advance.

    Hi
    check info given BY sap to clear ur doubt
    Definition
    Operations are carried out at a work center. In the R/3 System work centers are business objects that can represent the following real work centers, for example:
    Machines, machine groups
    Production lines
    Assembly work centers
    Employees, groups of employees
    Use
    Together with bills of material and routings, work centers belong to the most important master data in the R/3 production planning and control system. Work centers are used in task list operations and work orders. Task lists are for example routings, maintenance task lists, inspection plans and standard networks. Work orders are created for production, quality assurance, plant maintenance and for the Project System as networks.
    Data in work centers is used for
    Scheduling
    Operating times and formulas are entered in the work center, so that the duration of an operation can be calculated.
    Costing
    Formulas are entered in the work center, so that the costs of an operation can be calculated. A work center is also assigned to a cost center.
    Capacity planning
    The available capacity and formulas for calculating capacity requirements are entered in the work center.
    Simplifying operation maintenance
    Various default values for operations can be entered in the work center.
    The following graphic illustrates the use of work center data.
    Use of work center data
    Structure
    A work center is created for a plant and is identified by a key. The work center category, which you define in Customizing the work center, determines which data can be maintained in the work center.
    The data is grouped thematically together in screens and screen groups. Examples of such screen or screen groups are:
    Basic Data
    Assignments (to cost centers, Human Resource Management System (HR))
    Capacities
    Scheduling
    Default values
    Hierarchy
    Technical data
    Integration
    Task Lists
    Work centers are assigned to operations in task lists. If you change default values in a work center, the changes are effective in the task list if a reference indicator has been set for the default value.
    Work Center Hierarchies
    Work centers can be arranged in hierarchies. These are important in capacity planning. You use hierarchies to cumulate available capacities and capacity requirements in a hierarchy work center.
    Assignments to Objects in the Human Resource Management System
    A Logistics work center can be assigned to either an organizational unit or a work center in the Human Resource Management System (HRMS). Assignments to other HR-objects, for example employees or qualifications, can be maintained via the HR work center.
    Vishal...

  • Results Recording Work List By Work Centre

    Experts,
    My Inspection Plans have two work centres.
    Can I run a report which lists how many results (not UD) each work centre has recorded on a particular day?
    Thanks
    Welshy

    Hi,
    Quite unique and interesting!
    As per my knowledge there is no specific standard report for this. You may have to go with work around- Z report for this. I do have a suggestion. Just check whether feasible.
    1.     The date on which result recording is carried out gets stored in QAMR table. The field is QAMR-ERSTELLDAT.
    2.     Work centers 2 in number, means you are dealing with 2 operations.
    3.     The main task here I think, is to correlate inspection lot number with its work centers which is quite cumbersome, even if you try to link QALS, PLPO, CRHD tables with each other.
    4.     Node number in table QAMR (field VORGLFNR) is nothing but operation number. Instead of work center if you go with operation number as input, may serve the purpose.
    5.     Give input as inspection lot number, date of result recording QAMR-ERSTELLDAT and operation (optional)
    6.     For the given input date if you find any data in QAMR, you may conclude RR is carried out on this date.
    7.     Rest of the details (material code, material description, vendor etc) you can very well fetch once you know inspection lot number.
    Regards,
    Anand Rao

  • Planner group vs maintenance work centre?

    hi
    in IDES server generally planner group and maintenance work centre are same.can they be different if so then please
    explain with example.
    regards
    sanjay

    Hi,
    Work Center - represents a unit that is capable of performing work. It can be a group of person, equipment and special resources used to MANAGE the work order and/or PERFORM work order operations during maintenance execution. It can be used to model a resource availability within the organisation. There are 2 types, Main Work Center (responsible for overall managemetn of the work) and Operational Work Center (executes the operation activities).
    Planner Group - represents a person or group of persons responsible for the PLANNING and PROCESSING of several maintenance Work Orders.
    Cheers,
    Joey

  • Settlment Cost element determined from work centre

    Hi
    I want to settle costs on plant maintenance orders to different type 21 cost elements depending on the main work centre on the order.
    I understand that the ORDER TYPE can have different SETTLEMENT PROFILES and that these can determine the cost element to post to. HOWEVER the problem I have is I can not create new order types for this purpose (to much re-work).
    any help would be appreciated
    phil

    Hi,
    I dont think so that in Standard setting you can assign Settlement profile by work center. Automatic assignment of settlement profile is possible by Order type . Manual assignment of settlement profile will also not work as in one PM order you may have mutiple operation which belongs to different work center.
    So this looks very unique requirement and you will have to go for some development or user exit which can make you able to post the settlement based on Work center.
    regards
    Ranjan

  • Work centre capacity utilization

    Dear guru ,
    i have a work centre that always work in the same moment for 3 different production order.
    If my total daily available capacity is 11 hours for my 1 individual capacity is right that I assign to the work centre a capacity utilization of 300 percent in order to have a daily available capacity of 33 hours and I can use capacity levelling in the best way ?
    Or there is other better solution for solving this problem ?
    Thanks for your help.

    you can also put no. of individual capacity as 3.