Work schedule display in capacity leveling cm25

Hello,
In our company we have created a work schedule (tcode OP4A) and have associated to a work center (tcode IR02).
However, capacity leveling (tcode CM25) doesn't display the work schedule associated to our workers in the graphical planning table.
Do you have any idea how to solve this problem?
Thank you very much,
Óscar

It could be issue with your over all profile..
Use - Over all profile SAPPM_G001  
Overall prof: SAPPM_G001           PM: Ind.cap/tab/day/avail.lab./norm.schd
       Select.profile:                     SAPPM_S001      PM: Tab/work center/lab/
       Control profile:                    SAPPM_C004      PM: Capacity planning table individual
       Time prof:                          SAPPM_Z0T1      PM: Tab. short-term (1 month)
       Evaluation prof.:                   SAPPM_A001      PM: Plant maintenance
       Strategy prof.:                     SAPPM_T002      Lead time sched. backwards
       Capacity planning table (tab.form): SAPPM_R001      PM: Plant maintenance/Individual caps.
Note: Don't modify the Standard profile .

Similar Messages

  • Capacity Leveling(CM25 Transaction)

    Xperts,
    could you please give us some documentation/online material on Capacity Leveling(CM25 Transaction)?
    Rewards for your inputs.

    hi
    To Know about Capacity levelling, u can use this thread
    http://help.sap.com/printdocu/core/Print46c/en/data/pdf/PPCRPLVL/PPCRP_LVL.pdf
    http://help.sap.com/erp2005_ehp_02/helpdata/en/8a/a58eb24adc11d189740000e8322d00/frameset.htm
    regards
    Palaniappan

  • Issue with Capacity Levelling-CM25

    Hi Everyone,
    We use CM25 for capacity levelling.
    Issue:
    Total Capacity req. = 186.8 Hr
    Available Capacity on 01.01.2012 on the resource = 380.2 Hr
    Now when I try to dispatch the capacity req. for a planned order manually on 01.01.2012, system distributes the capacity-
    Distributed   Period
            5.0    31.12.2011
          23.8    01.01.2012
          23.8    02.01.2012
          23.8    03.01.2012
          23.8    04.01.2012
          23.8    05.01.2012
          23.8    06.01.2012
          23.8    07.01.2012
          15.6    08.01.2012
        186.8
    But we want to dispatch capacity say on one particular day or split it onto two different days i.e. 90 Hrs on 01.01.2012 & 90 Hrs on 02.01.2012. Is it possible? If yes, how?
    Additional Information-
    Capacity Defination in resource-
    No. of indiv. cap.   16
    Operating time       23.76
    Capacity             380.16
    Relevant to finite scheduling
    Thanks,
    Parashar.

    Hi Amol,
    Thanks for your input.
    As I have said I already have Capacity more than what is required.
    Capacity Available per day: 380.2 Hr
    Total Capacity Requirement: 186.8 Hr
    I am trying to know that whether what issue has been raised is possible to solve in Capacity Levelling & How.
    We are not maintaining shifts in SAP at present.
    Thanks,
    Parashar.

  • Is employees personal work schedule is same as daily work schedule?

    Hi,
    Is employee's "personal work schedule" is same as "daily work schedule"?
    Where they are maintained?
    Thanks,

    Hi Thaman,
    The personal work schedule represents the lowest level of work schedules. It contains the work schedule of one individual employee.
    You can refer to the personal work schedule for the working times of a specific employee, as well as any working time provisions that apply on a particular day. The personal work schedule also contains any changes made for individual employees from when maintaining infotypes, in addition to any changes made for entire employee subgroup or personnel area groupings.
    The daily work schedule determines the structure of working times in your enterprise at the daily level. You can also define actual normal working conditions and those that differ from externally or internally determined daily working times. In this way, you set up working times defined for specific employees.
    The daily work schedule, along with Break Schedules, comprise the working times for a particular day.
    Use the below for maintaining Work schedule....
    Choose Human resources -> Time management -> Administration -> Work schedule -> Change.
    If you are looking for IMG configuration of WS, pls let me know...
    Regards
    Ghouse

  • Capacity Leveling of Work Center

    Hi all,
    I have a problem with Capacity of Work center (WC).
    I have a Internal Activity, and i assigned a WC for this Internal Activity. WC's capacity is 100H/day for 1 number of element.
    Work of this WC is 250H, duration 5 days, number of element 1. Default capacity of this WC is distributed by Distribution Key define in Activity. . And they are divided equally between factory days in 5 day. That is capacity requirement is 50H/Day
    So, i want to edit this WC's capacity following value:
    Day 1: 100H/day
    Day 2: 50H/day
    day 3: 0H/day
    day 4: 0H/day
    day 5: 100H/day
    How can i do it?? I try to use Dispatch Manually but i cant solve this problem.
    Please help me for this case.
    Thank all.
    NLQ

    Dear
    Capacity leveling depends on some of the basic set up of Capacity Requirement Planning .You need to have proper CRP set up frist .
    Couple of check points : -
    Did you work centre is relevent for finitie scheduling in CR02-Capacity Header and wht is the over laod percentage for work centre ?
    Did you have Capacity Requirement Related Set up like Over all profile , time profile , Startegy Profile -OPD0?
    Did your Capacity Check -OPJK -Order Control at order level are active for availibilty Check 1 and 2 and assinged Over all Profile ?
    Set up :
    1.Please assing a operation control key like PP01 where Details Capacity Check and scheduling is active .
    2.In CR02-Work centre -Capacity Header -You should have Follow check box marked
    1.Releven for Finitie Scheduleing
    2.Can be used for multiple Operation
    3.
    3.OPU3/OPU5 -Define Scheduling paramter -Mark Scheduling and Capcity Check for planned order or production Order
    4.In SPRO -Shop Floor Control-Define Production Scheduling Profile -You need to matian the relevent Parameters like
    1.Schedueling Automatically 2.Scheduling Log 3.Adjust Scheduling -Basic date , Depedent Requirement date 4.Scheduling Type -Backward etc .
    These are all basic level set up beside CRP overall profile and other profile like strategy /time etc which may in place as you are analysing in CM01.
    Please find below some of the useful CRP details : Refer this threads which are self explaintory :
    http://help.sap.com/saphelp_47x200/helpdata/en/8a/a5a3154adc11d189740000e8322d00/frameset.htm
    http://www.scribd.com/doc/17026521/SAP-ECC-60-PP-Capacity-Planning-httpsapdocsinfo
    capacity planning
    http://help.sap.com/printdocu/core/print46c/en/data/pdf/PPCRPSFC/PPCRP_SFC.pdf
    Capacity Planning
    capacity requirements planning
    How to dispatch operation to do Capacity Leveling at Work Centre Level :
    1.Frist Check the  over load at work centre . Goto -CM07/CM05-give plant only -then hit the Stnadard view -You will find weekly or daily baiss load ( Requirement , Avaliable Capcity , Overlaod etc )
    2.Check the week in which days you are tring to dipatch -if you selet the week check box and double clik it will show u all the dataiul load .Basde on the available capacity in other week-days u need to dipatch in CM22/CM31  or CM25/CM21
    While dipatching in CM22/CM31-Select the Stragegy button on the top header -Mark Date entry when dispatching  so that when you select the operation of any production order or planned order for certain work centre , it will pop with window having information of Date , Work Centre , Time .Onec you did this you will receive Scheduling log with certain information .
    Hope this helps
    regards
    JH

  • Display the PO in the capacity leveling

    Hi,
    in the capacity leveling CM21 there is a table section.
    In the table section I get Production order and planned order.
    I just want to display the production order in this sections or in the oders pools.
    How can I customize the system.
    Thanks
    Dede

    Hi
    Use CM25 and the selection profile you can select order.
    Thanks
    S.Murali

  • Capacity leveling. Aim is to have oders scheduled within 1 day if possible

    Hi All,
    I have a list of 10 prod. orders with same basic/scheduled start/finished date= today
    In capacity leveling, if i select a whole list of these orders and dispatch them, i get all orders with start day= today, finish date= today+ x days.
    I would like to have orders scheduled with start/finish date within 1 day.
    I have available capacity of 4 hours per day. Each order takes around 1,5 hours, thus i can have 2 orders scheduled for today, and so on. This is exactly what i need.
    My kind question to you is how to setup SAP in a such way.
    NB: If i do leveling for each order one by one, then i get what i want: e.g. order is scheduled within 1 day.
    Best Regards,
    Andrey

    Dear Andrey
    Your requirement is, Automatic capacity levelling based on the available capacity.
    In SAP R/3 PP module, only manual capacity levelling is available. Automatic is possible in APO.
    If the requirement dates are same for multiple orders, system will through all the orders in the same date and it will display overloaded. So manually we need to dispatch the overload to the required date.
    Please check the below thread also.
    Re: Triggering Finite Scheduling
    Hope it helps
    Regards
    Bala

  • Capacity leveling, after Deallocate scheduling dates getting changed.

    Dear Experts,
    I have a issue in Capacity leveling using transaction CM25 - Online. I have created some production orders (using forwards/backwards scheduling) for overloading of WorkCentre's. When I dispatch orders it’s getting scheduled perfectly, but when I Deallocate same orders scheduled dates are getting  changed.
    Even after deallocation production orders schedule dates should be the same. Can you please help me in this regard?
    Thanks in advance.
    Prashanth

    Hello Prashanth,
    From SAP help Date Determination in Dispatching and Rescheduling - Capacity Leveling (PP-CRP-LVL) - SAP Library
    The current dispatching data is cancelled. The status "dispatched" of the operation is reversed. The order is rescheduled.
    If further operations exist for an order which has already been dispatched, the system automatically carries out midpoint scheduling. If no other dispatched operations exist, the system carries out lead time scheduling.
    If order date is in past then it schedules to current date during de allocation if you do not have enter number of past days allowed to start date in scheduling parameters.
    Br
    KK

  • Work Center(Capacity Level) Change Documents

    We have a requirement to capture work center change documents at the capacity level which I understand is not supported by standard SAP; note 352485(point 15). Is there, though, a customized solution that can be developed? Any thoughts would be greatly appreciated.
    Thank you in advance.

    Hi Usman,
    I have already tested the method you are mentioning. You cannot save a order without work center. So, you need to use a dummy work center and change all the open orders.. if you want to change capacity category from A to B. New capacity category should be mentioned in dummy or original work center.
    When you replace the work center, order will be gng for scheduling.. which leads to change of Basis start date and earliest start date... this is an inconsistency...
    To avoid it... i followed below steps
    1. Uncheck the capacity requirement indicator in all open orders
    2. when u try to delete, it will say "Capacity is still being used"
    3. Table KBED, use capacity ID and run, it will list out the pending orders
    4. When the table has no entries, delete the capacity category
    5. check all capacity indicator
    - Pithan

  • Sequential scheduling of orders in capacity leveling

    Dear All Hi,
    I working on capacity leveling where in the clients want the following requirements, please give your valuable inputs & your help will greatly appreciated & rewarded.
    The following is the scenario:
    If have 3 orders scheduled on 3 consecutive days (considering each order completes in a single day) then if drags the first order to forward date, then the system forward schedules only the selected order but the client wants order number 2 & 3 to move automatically. That is if I push the first order, then sequentially 2nd & 3rd order should move automatically & gets rescheduled sequentailly.
    Similarly it should happen when I drag the 1st order to left then the proceeding orders should simultaneously move along left in leveling screen
    Thanks in Advance.

    Hi Mario,
                   Thanks for your reply.
    All the 3 orders are independent & are of finished goods. All the orders are scheduled on the same work center. Due to machine break down during the processing of first order, there's a loss of time, so i will select the first order & dispatches to forward date & at the same time i want the 2nd & 3rd order to get resheduled correspondingly.
    Suggest the solution for this, Thanks in advance.

  • Infinite scheduling with capacity leveling.......

    Hi there ,
                   If we go for infinite scheduling & then after MRP run go for capacity leveling ..........
    then will we get the same effect as finite scheduling .....
    Please suggest me
    Regards
    Kaushik

    Hi Kaushik,
    If my understanding is correct, you are asking for the difference between manual and automatick despatching of orders in capacity levelling?
    when we set finite scheduling in capacity header view of work center, and run MRP with scheduling parameter 2 set.
    In capacity planning the availabile capacity will be compared with the required capacity and the load will be depicted as a graph or in table format. This only gives the load situation against the period.
    For this the despatching of order will be done manually based upon the load per day by a scheduler in capacity levelling.
    And to add more,
    In R/3 finite scheduling is not there and this is drawback and APO was put in front for this purpose.
    Can you confirm me whether the system automatically levels the order or despatchs the order in finite scheduling.
    Best Regards,
    Sendil

  • Substitutions display in Personal work schedule

    Hi,
    I have a client that captures several substitutions for an employee for a specific day or period. Of the four substitution types, 3 substitutions are marked with the reduced working hours flag. This in turn, allows the client to capture several substitutions and to run the personal work schedule report successfully.
    They now want to run the report displaying all substitutions, which would require de-activating the RWH flag. If this is done, then the personal work schedule report displays an error message for the days that more than one substitution has been captured.
    My question is, how can I display more than one shift substitution on one specific day within the personal work schedule without doing development.
    Regards
    TS

    Hi,
    1. Check for the following customisation:
           Group  Personnel Subareas for the Work Schedule
           Group  Personnel Subareas for the Daily Work Schedule
           Define Employee Subgroup Groupings
           Define Groupings for the Public Holiday Calendar
           Set Work Schedule Rules and Work Schedules
           Define Counting Classes for the Period Work Schedule
           Set Personnel Subarea Groupings for Time Recording
    2. In case if the error is coming for one employee just check the latest IT 0000 record and see if the WSR assigned is valid for the respective PSA and ESG's else neglect this point.
    I hope this helps.
    Thanks,
    TS

  • "Display Work Schedule" in Portal( Generic iviews)

    Hi All,
    Is there any way to display the "Display Work Schedule " in Portal.
    We are trying use the Generic iViews to display the reports in Portal and we created a SAP Query with the IT 7 ( Planned working time ) .
    Here we would like to see the view thats similar to the view we see when we go display of IT 7 and then click on "Display Work Schedule "
    Can some one tell me how we can acheive this " Display Work Schedule" thru generic iview in Portal.
    Appreciate your valuable inputs on this.
    thnks,
    NR

    hai..
    The iViews and Web Dynpro applications of the Business Package for Employee Self-Service (ESS) are based on the Floor Plan Manager. Business Package for Self-Service Administrator.
    SAP Service Marketplace at service.sap.com/ep-content , BP Product Availability Matrix.

  • WORK FLOW & PROCEDURE FOR FOR SNP CAPACITY LEVELLING HEURISTICS RUN

    Dear Sir / Madam,
    Currently, we are  taking  only SNP Heuristics Run  and the output viz. planned stock transfer requisitions are being passed to PPDS as such. But now we feel, SNP capacity leveling can play a vital role in getting more fine tuned results from PPDS. So, We wants to start using the SNP Capacity leveling run. We shall like to know the work flow / procedure for taking the SNP capacity level run i.e. what inputs should be properly reviewed before taking the SNP capacity level run and what shall  be its output..? Kindly let us know the procedure / work flow for taking the SNP Capacity Levelling Run.
    Your early reply in this regard shall be really appreciable.
    Thanks & Best Regards,
    Sanjeev Chugh
    25-Mar-10

    Hi Sanjeev,
    as in any other module, correct master will play a key role in getting effective results in capacity levelling. you will need to check the following master data while setting the system for capacity levelling :
    Consistency in BOM in R/3 and PPM/PDS
    Consistency in Routing in R/3 and PPM/PDS - the actual through put on the shop floor should be the same as that in the routing and in the PPM/PDS. unless this is in sync, no amount of levelling can return good results.
    Maintenance of shift - again as present in the shop floor.
    you can provide the dump of the above master data and ask the shop floor engineers to validate the data as it exists in the ssytem. you can do the consistency check between R/3 and APO yourself using queries. Once they have validated this master data and the the actual master data reflects in your system, i think, the job is more than 50 % complete.
    also you need to check the lot sizes, rounding profiles, and period factor, becasue all three combined play a major role in giving good or better results after levelling.
    you may also check at what level you want to run the levelling. whther the bottleneck is at the finished component level, or 2nd level, etc. you may check whther you have discrete manufacuring or REM and if you really want to levelling on REM order.
    then you need to analyse, what is the lengh of horizon you want to run the capacity leveling on. sometimes it makes no sense to run on the entire horizon because if capcities are already overlaoded, you will not achieve the desired results.
    hence depending upon the level of your understanding and comfort of the planner (who will be using this result), the horizon can be increased grdually.
    if you are starting to implemement capcity levelling, you can sumulate runs and show the results to the planner and check if the standard capacity heursitics satisfies their requirement. else you can go for custom requirement.
    you will also have to decide on the stratagies, priorities,etc based on the business requirement.
    i think the above should give some starting direction to implement capcaity levelling in your system.
    award points if you find this useful.
    Rgds, Sandeep
    Edited by: Sandeep Budhiraja on Mar 25, 2010 11:49 AM

  • Display Work Schedule in ESS

    Hello,
    I am trying to provide the same functionality that PZ17 transaction (Display Work Schedule) provides in the backend, to the portal. The transaction PZ17 does what I want essentially. Now the problem I have is how do I make it come up in the portal as a service within Portal -> ESS, like leave request. I did not see any configuration in the IMG that would enable this service.
    I am new to this, so am not aware if SAP provides this functionality in ESS or not. Any help will be appreciated.
    Thanks,
    Ajay

    Please note some of the services based on ITS which are using cannot be lauched using Webdypro, So you need to make a new service as described using SICF, ALso read the note  870126.
    SO you need to create it ie
    This is an SICF service which invokes
    transaction (which you are using )using the SICF parameter of ~transaction. try creating it
    Or note for displaying Work schedule use pt63, you can add this transaction code as well.
    Also check this
    https://www.sdn.sap.com/irj/sdn/wiki?path=/display/home/article-Employ
    SAPGUIforHTMLinsteadofanInternet+service
    read the note 1010519