Working time approval with MSS

Hello,
I am trying to configure the MSS in order to approve the recorded times. Using cProjects for resource handling I would like to see the times to approve in the hierarchy of the project (with project, phase and taks). I would like this hierarchy in combination with the personal no, ... by choosing different views.
At the moment I only found the time approval application for the line manager. This isn't sufficient for us in terms of userfriendlyness.
Now I am searching the application sap.com/msscatapproval/CatProjectApprove in my portal. Unfortunately without success at the moment.
Could someone describe me how you are using the record time approval? How does the hierarchy of the items look like. Did you write your own application? Is it possible to drill down and drill up the data?
Thank you,
  Vanessa

Hi Mariana
You would have the use the workflow and create a Portal role containing only UWL
Best wishes
Stuart

Similar Messages

  • MSS working time approval by project leader

    Hello all Gurus,
    We are implementing ESS / MSS with ECC6. We are in the need to approve time recorded in ESS. We have completed the time entry part. The problem comes in the authorization with MSS. We need the person responsible (project lead) in Project System (PS) to approve time for resources. We have created the approval profile in SPRO, we have asigned the parameter CATS_APPR_PROF in su01 as it was mention in past forums. We assigned the MSS roles and activated them. We assigned in the OPS6 transaction the person responsible of the project (project lead).  When we go to the time approval in MSS it shows that there is no records to approve.
    Is there any more configuration to this or does anyone have any solution or experience in project leaders approving time with MSS.
    Thanks
    Regards,
    Enrique Lona

    Raj,
    Thanks for the the quick answer. Please could you send me a little more information into where to configure OADP settings for time approval. And how to set the evaluation path.
    Thanks,
    Regards,
    Enrique

  • Time Approval in MSS

    Hello Gurus,
    We  want to implement the Time Approval in MSS using the Webdynpro Application sap.com/msscatapproval/CatManagerApprove and don't want to implement workflow for this since users want to do a collective approval .....how can we implement this ?....we are also not using chiefs.....Please help.

    Hi R Kumar ,
    Can you let me know the exact requirements. You can obviusly do the collective approvals using the "sap.com/msscatapproval/CatManagerApprove " een when using the WF. Infact the out-of-the box solutions works this way.. So why do you need to not have the workflow? I do not see any down sides of having a work flow here.
    regards
    Raj

  • Working Time Approval

    Hi Gurus,
    We are using the SAP Std. Working Time application. Employee is submitting his/her working time and the manager received a Work Item in his UWL.
    While clicking on it, Manager is redirected to the collective approval screen.
    Is there a way that he can approve individual employees request rather than doing it collectiviely?
    Please advice...
    Regards,
    Rekha Malavathu

    See if the following customizing node helps:
    Integration with Other mySAP.com Components -> Business Packages / Functional Packages -> Manager Self-Service (mySAP ERP) -> Working Time -> Approve Working Time
    Also check out the node(s) documentation.

  • How to find Working Time approval Enterprise services in ECC 6.0 EHP #3

    Hi All,
        We are on ECC 6.0 EHP #3. We have activated the EA-HR  & EA-TRV  ENTERPRISE_EXTENSIONS & related business functions in transaction sfw5.  How and where do I look for Working Time entry and approval enterprise services in ECC. I tried to find through SOAMANAGER and SE80-Enterprise services browser but could not find them.
    Do we need to activate anything else or am I not looking at the right place?
    Thanks,
    Rajive

    Hi,
    Enterprise Services are delivered by SAP with Enhancement Packs (Ehp). So number of services you can see depend on your Ehp and activation of business function while installing Ehp.
    You can see ES in transaction SICF (to activate) and you can search services in transaction SE80->Repository Information System ->Enterprise service (search).
    Regards,
    Gourav

  • Record Working Time - Approve Status

    Hi,
    How can an Employee checks whether his Time has been approved or not? I am in "Record Working Time" iView in Portal, i wasn't able to see any status on previous timesheets/weeks whether the time has been approved by the manager or not.
    Please advice.
    Thanks
    Vijay

    We can see on Daily View by clicking on DETAILS link on each line.

  • Sorting feature for columns in time approval screen - MSS

    Hi ,
    In the portal for MSS , while on the 'Approve Time Sheet Data' , how can we provide sorting for the different columns ? As of now , the sort is only available on the Employee column .We want to provide the same on the Att/Abs type column too.Is this achievable through personalization in the portal or handled through some code ? Kindly suggest. Thanks in advance.

    CATS_APPR_PERSP
    Here you define the approval views
    In the first case it can determined by period, in case
    you dont use period then  collective approval criteria.
    can be used for grouping
    Example period
    Period Type
    Specifies the period for which the recorded data
    is to be grouped in one line of the collective approval.
    Please check the IMG for cross application components and Approve working time

  • Lion: don't work  time machine with NAS Buffalo or Thecus (AFP error)

    backup with Time machine, does not recognize the disk, used with the previous version. The AFP system error that is not compliant, with both NAS.
    bye
    Alex

    If your NAS/TimeMachine manufacturer doesn't provide an update, you could probably revert to the old ways:
    http://www.alexanderwilde.com/2011/04/os-x-lion-connection-error-with-afp-and-wo rkaround/
    This has solved AFP issues for some but I haven't been able to verify it for TM.

  • Approve Working Time

    Dear All
    I have a requirement.
    When an employee books time in the section "Record Working Time", it goe for approval in "Approve Time sheet data" in MSS under Work Overview>Team>Employee Working Times>Approve Time sheet data.
    Now my client needs that it should come in the UWL under the section "Tasks" as it comes in case of a leave request approval.
    I just wanted to inform that in the table TCATS in the section "Workflow" we have neither checked "With SAPBusiness Workflow" and nor "With auto determination of recipient".The Task field is empty.
    So please help me to know what exactly to do.
    Thnks a lot

    Hi
    No in SBWP I am not able to see. But all the leave requests that are generated can be seen.
    This is the case for both the approver and the person who requests the leave.
    But no such aaproval of work time is visible in sbwp
    Please give me a solution

  • Approve Working Time Error

    Hi
    We are on EP7 with ECC6.0 as backend.
    We are trying to use the Approve Working Time iview in MSS but it gives the following error:
    Critical Error
    A critical error has occured. Processing of the service had to be terminated. Unsaved data has been lost.
    Please contact your system administrator.
      The ASSERT condition was violated., error key: RFC_ERROR_SYSTEM_FAILURE
    We have maintained the following customizing in backend(
    1.Define Approval view: SAP_LINE ( SAP Approval by Line Manager)
    2.Define Field Selection for Individual Approval view:  SLIN1 and  with it Field customizing Field label
    Personnel Number , Attendance or Absence Type,Text for Attendance or Absence Type, WorkBreakdown Structure Element, Receiver Order etc.
    3. Define Field Selection for Detail View: Attendance, Counter etc
    4.Define Profiles and Assign to Views: SAP_Line: Initial View=SAP_Line.
    5. Create Rule Groups: SAP Standard( 01)
    6 Adjust Webmo feature: Time Sheet Application..assigned rule group: SAP Standard(01)
    The Approver is a Manager with A012 relationship with a particular org unit.
    Kindly suggest where may lie the problem.....we have a requirement of Collective Approval of Working Times of his subordinates by the Manager.
    I would like to add here that we are able to approve Working time requests individually through UWL...but we need to use the Approve Working Time Iview.

    Hi
    We are using the standard taskTS20000460.   But we want to use the Approve Working Time service iview. 
    When we were using the evaluation path for approving the working time data through A012( Chief) in MSS, we were able to see all the working times recorded by the subordinates of the said Chief( Manager) in the service Approve Working Time itself, we did not necessarily have go to UWL and approve from there....Now after we have made the required changes in the evaluation path and made A002 as the approver, the same iview Approve Working Time has a message that "No date exists that needs to be approved'.
    At the same time we are able to view and approve the working time data from UWL of A002.
    Is there a change that needs to be done in the service to get it working  ? or it this because of some other reason.
    Please advise.

  • MSS Time Approval - multiple (different) selection options for manager?

    Hi all
    I am setting up MSS Time Approval delegation in ERP2005 without workflow, leave request, nor portal development environment set up.
    In this case, the customer needs to have multiple selection options for who to approve:
    1. The manager's direct reports (standard functionality)
    2. All subordinates, all levels down
    3. Delegate's (manager or non-manager) view of a particular (other) manager's direct reports
    3b. This might extend to a set of different delegation selections
    4. Add or remove certain individuals
    Now, getting 3. and 4. to work was simple using the BAdI (I think the enhancement spot is named APPR_CUST), method ...-edit_selection, but I am having difficulties with 2. and 3b. Now I am thinking along these lines, and I would greatly appreciate your input:
    A. It seems that the MSS "Approve working time" app only loads the data selection at the entry into this screen (INIT command from portal), using the start perspective determined for example by the IMG for defining the approval profile <-> view. My debugging suggests that the view change from the drop down menu (CHANGE_PERSPECTIVE command) only picks a different way to present the same data set.
    Could anybody please confirm or contradict this conclusion?
    B. Is it possible to present the entire "Approve working time" section in MSS in multiple different copies so that they would all generate an INIT command? Or is it possible to copy and modify the entire MSS tab, resulting in an ESS tab, one MSS, one "D"SS, one "A"SS (well, not suggesting that the top manager is one, but you get the drift...) and so on?
    If either of this were possible, it would be simple to make two modifications, one at the beginning of the FM called by the portal and one at the FM that returns the start perspective.
    So far I have been trying to catch and alter the CHANGE_PERSPECTIVE command into an INIT in the back end, but the Time Approval functionality is a bit too complex for me to feel entirely comfortable with this approach.
    Your input is much appreciated!
    Kind regards
    Niclas Arndt

    We too are using MSS for time approval of time entered via ESS.  We are on ECC 6.0 for the backend (no enhancement packs, at least not yet), currently sp stack 10 with hrsp 24, and EP 7.0 with stack 10 for the ESS/MSS business packages.  We are using the standard MSS UWL functionality for the approval, so it is workflow-based in my understanding.
    In other parts of MSS, the managers can see a few levels deep in the organization structure, based upon the definition we gave for their structural profiles.  For instance, in the team calendar/overview, or other team information, they have a choice for multiple levels or only direct reports.  However, in the time approval application, only direct reports are shown, so if a manager goes on vacation, at present the only way to cover time approvals for that manager's employees appears to be to temporarily assign a new 'chief' to that org unit, so HR involvement becomes necessary.  The manager doesn't have any method for delegating the approval or other MSS authorities.  We were hoping that by allowing multiple levels in the structural profile, such approvals would "roll up" to the next level, i.e. the manager's supervisor, so the next level manager could act as a backup to his/her managers on vacation.  That doesn't work, however.
    We have heard that a delegation feature for MSS will be available in an upcoming release, but I haven't found any information regarding whether that requires an upgrade, an enhancement pack, a later service pack level, or what or when that functionality will be available.  Does anyone know anything about that?
    Regards,
    Matt

  • MSS Time Approval Layout

    We are implementing ESS/MSS in Portal 7.0, ECC 6.0. For working time approval, I would like to provide managers with the ability to view employee time entries in a grid layout - similiar to what the employee uses to enter work time, also similiar to what's available via CATS_APPR_LITE. I've heard that this layout/view was available in previous portal versions, but I've not been able to verify this. Does anyone know if this layout/view was ever available or how to develop this? 
    My other option is to create an iview linking to the CATS_APPR_LITE transaction, but I've had problems limiting the employee selection to just direct reports, not indirect reports.
    I appreciate any guidance/assistance.

    Please check the configuration ie available
    You can select the columns to appear
    In the IMG (transaction SPRO), go to
    - SAP Customizing Implementation Guide
      - Cross-Application Components
        - Time Sheet
          - Specific Setting for CATS regular
            - CATS regular
              - Approve Working Time
                - Define Field Selection for Individual Approval View
                - Define Field Selection for Detail View

  • Approval of Working Times tasks show in UWL and shouldn't

    Our employees use ESS to record their working time and the managers use MSS to approve that time.  Occasionally the task Approval of Working Times, along with the sender date, name and a Cats attachment, appears in the managers UWL which makes it look like someone has time to be approved however, we do not go to the UWL to approve time.  If this task is clicked on in the UWL a u201CService cannot be reached HTTP 404 u2013 Not foundu201D error is thrown.  The send date of this task does correspond with a date when the employee entered time in ESS which the manager approved a few days later in MSS.  So it appears that occasionally but not regularly or in any sort of pattern, time workflows to both MSS where the managers approve it and to the UWL where we donu2019t want it and sits there and drives the managers crazy.  (Managers do go to the UWL to approve PCRs.)  We have checked the workflow log and cannot see a split.  How do we prevent the time approval from routing to the UWL?

    Hi,
    For me it seems that the the workflow should be turned off. There are ways to disable tasks from UWL, etc. (to not show them), but I would definately take a look to the CATS configurations in SPRO (unfortunately I don't remember the exact path, but it should not be too difficult to find). Basically there is place where you define that which workflow task is send to the manager when the employee releases the timesheet. You can perhaps remove this task from the configuration or perhaps there is some checkbox or something where you can turn of the workflow or whatever. Take look to this first. If you have CATS/HR people on your site, they will probably know what I am talking about.
    Another perhaps good option could be that you do certain configurations for UWL and then the CATS approval application is opened when the managers click the item in UWL -. but I would first try to prevent the work item to be sent to the workflow at all, if it should not be sent there at the first place.
    Regards,
    Karri

  • To Approve work time

    Dear All,
    After releasing the time sheet(releasing work time data) by the employee through Portal-ESS, It needs to go his line manger. In this case I am able to release from ESS but I did not find any link for approval.

    For working time approval there is an application available. You can access this one with the standard MSS Portal role.
    regards,
    Markus

  • HCM MSS Change in Working Time - Workflow

    Hi All,
    Im New to HCM & WOrkflows too...
    I need your help, it would be very helpful for me to prove my skills.
    I have a requirement like, The requirement is to initiate  the Change in Working Time process from MSS( Manager Self-Service ) for a particular employee .
    Desc:
    Manager can  initiate the Change in Working Time  process for his /her employees/reportees via MSS . The manager will use a web-based  interactive form (Adobe interactive form within HCM P&F framework) to fill in the details of the new changed work schedule of the Employee in question. Once this form is submitted by the Manager  ,  the corresponding workflow will be triggered which sends a work item to the HR Administrator ; the HR Administrator will update the backend SAP  accordingly. Once successfully updated an email notofication will be sent to the  Manager of the Employee (in normal cases the Manager at this stage is the Initiator of the process)
    And how to do this workflow development(only workflow part), if u can please tell me the skeleton structure to achieve this.
    i have seen WS61000074 - this is ESS Change in working time. Same thing i need to do in  MSS. Only thing is, in MSS Employee is not included.
    Thanks in Advance,
    Rani.

    Hi Bentow,
    Thanks for your reply.
    And in my FS, there is no word like CATS.
    Mine is compeltely a workflow part.
    I just copying my FS workflow process part: Please Tell me some idea, if possible.
    A custom workflow template needs to be developed for Change in Working Time (MSS) process.
    Once the Manager submits the Change in Working Time form via MSS for any of the reporting Employees  the corresponding Workflow will be triggered.
    The workflow will route the submitted form to the relevant HR Administrator (which can be fetched based on an Agent determination rule , if needed  or can be maintained in the workflow template).
    The HR Administrator will  open the form and update the backend SAP system accordingly.
    Once the HR Administrator successfully updates the system , he shall  process the form  and complete it.
    Once the form is successfully completed by the HR Administrator , the workflow will send an Email notification to the Manager of the  concerned Employee. [In a normal scenario, the Manager will be the Initiator of the current Change in Working Time process]
    The above workflow configuration needs to done as part of the usage of  HCM P&F framework.
    The Workflow will be triggered when the Requestor(Manager) Submits the Change in Working Time
    form in MSS.
    Thanks in Advance,
    Rani,

Maybe you are looking for

  • Calendar Display - resolved

    I've recently switched to the "BB Dimension Today" theme on my BB and fell in love with it.  I especially love the portion of the main screen that shows my upcoming events as entered in the calendar.  I enter a majority of my events using my email ad

  • HT1349 i have an iPad 2 that  disconnects from Safari and App Store regularly.  Is there an easy fix

    I have an ipad 2 that disconnects frequently from Safari and App Sotore.  Any known fixes?

  • RTMT ALARM CallProcessingNodeCpuPegging

    We are receiving an RTMT alert for one of the node in the cluster. Error is [RTMT-ALERT] CallProcessingNodeCpuPegging. Processor load over 90 Percent. hostagt (45 percent) uses most of the CPU lease suggest what to do for the resolution of this and a

  • Afraid to make the switch.....Convince me otherwise!

    I have been a PC guy since 1988 (had the original macintosh before then) and overall quite happy. Now, with owning an iPod for the past year and purchasing it for others, I have been bombarded with apple products while visiting the local store. Actua

  • Premiere Pro CS6 is crashing, how do I contact support?

    Premier Pro CS6=Producion Premium Creative Suite 6=kept crashing=Apple techs say contact Adobe=comp is OK=tried re installing just Pro=still crashed=uninstalled ALL=tried to reinstall FULL Suit6=will not  re install=claims  =possible pirate=accepts