Write authorization of ACL at WBS level

Dear All,
We activated ACL (No inheri.) at WBS level.
According to my understanding in "write" authorization, we can just change the PS object but we can't delete the object.
We assigned "Write" Authorization to one user, but he is able to delete the object.
Please guide for the same.
Regards.

Hi Praddy,
Please check if the group to which this user belongs to doesn't have superior authorization. Refer to the below thread for more details.
Access Control List - Project System (PS) - SAP Library
Cheers
Sammar

Similar Messages

  • Function modules to get wbs level budgets and activity level cost

    hai gurus can any one tell me the function modules or any other bapis to get the wbs level budgets and activity level costs
    thanx in advance
    afzal

    ok

  • BUDGET LOGIC  TO BE IMPLEMENTED AT WBS LEVEL WITH 10% TOLERANCE

    Budget Logic check at each WBS level allowing 10% tolerance and the project level budget to remain constant
    The project structure or the project hierarchy is not fixed. The requirement is that the  released budget should be allowed 10% above the present released budget.  Also despite this change the budget at the project level should remain constant. The 10% surplus has to be adjusted from the other WBS if they have spare budget and if thereu2019s no surplus budget in any WBS then the system should throw an error. Available budget has to be checked against the PR/ PO creation each time so ensure that Purchase is not made in excess to the budget allocated. Procurement happens thru MM/PS both
    Please advice

    You can activate Budget availibility control aginst Overall Budget / Released Budget.
    Infact,  Budget availability control functionality is designed at WBS level only.
    All you need to do is create required Budget profile  and assign the same to your project profile.
    For detail please refer  this link
    http://help.sap.com/erp2005_ehp_04/helpdata/EN/e0/c4a637f39a6a66e10000009b38f889/frameset.htm
    http://help.sap.com/erp2005_ehp_04/helpdata/EN/d5/74a9371c726343e10000009b38f842/frameset.htm
    Regards
    Nitin

  • Reg: Capturing Cost at WBS Level

    Hi
    I have create two activities(one internal and other External) under one WBS Element.
    I have complete the process of confirmation(for Internal activity) and Purchase process for external activity.
    Now i can see both the planned and actual costs of those activities.
    Now i want the see the costs at WBS Level, which is now happening.
    pl guide me, where i can see and what will be the process.
    Thanks & regards
    pavan

    Hi Pawan !
    You can see all the Reports in project system under-
    Logistic->Project System->Information System->Financial->Varius reports are given there
    you can use Report-
    S_ALR_87013533 - Plan/Actual/Commitment/Rem.Plan/Assigned
    Thanks
    Rewards Point if helpful
    Regards
    Smith

  • Authorization :"OR" control on CELL level.

    Hi,
    I would like to realize "OR" authorization control to the CELL level, not selection level.
    For example If user1 has the following authorization.
    auth1: unit = 1001, 1002
    auth2: material = X001, X002
    report:
    select
    unit     =1000 to 1003
    material =X000 to X003
             unit
    material 1000  1001  1002  1003
    X000     NG    110   120   NG 
    X001     130   140   150   160   
    X002     170   180   190   200
    X003     NG    210   220   NG
    But Under all or nothing rule.
    select
    unit     =1000 to 1003
    material =X000 to X003
    Result:No authorization
    select
    unit     =1001 to 1002
    material =X000 to X003
    Result: OK
    select
    unit     =1000 to 1003
    material =X001 to X002
    Result: OK
    I know by now, it is impossible, so I would like to know how do you do to the same requirement. (I have a experience to realize it, but in this case, the frontend is custom made.
    Kind regards,
    Masaaki

    Hi Daniel,
    I can not imagine such a function.
    What is possible, is that you define the data slices according to what you want to be able to enter. so if you include several char with certain values in your data slices, your mask in the end will have the look, that certail cells are not ready for input.
    Unfortunatly you can not set data slices on key figures, so maybe you need an account model.
    regards
    Cornelia

  • How to get cost at wbs level

    hai gurus can any one tell is there any one tell is there any funciton module to get the cost at wbs level or any other method
    thanx in advacne
    azfal

    Hi
    Use the table <b>BPEJ</b> to Get the Full Year budget costs of all WBS elements
    and actual costs by using the fun module
    <b>K_CO_OBJECT_BALANCE_GET</b>
    <b>Reward points for useful Answers</b>
    Regards
    Anji

  • "No write authorization for personal portfolio of user" from BW

    Hi, we are working on connection from BW 3.5 InfoBroadcaster into EP 6.
    When I try to publish BW webtemplate to EP to my personal portfolio I got follwoing messages:
    "<i>Settings were started from the BEx Broadcaster  
      Processing for user AC3339, language EN  
       Processing setting  
        No write authorization for personal portfolio of user AC3339 
        File 'ZM_P2P_SCORECARD_ORG_HIER_STAT' Was Successfully Created in the Portal</i>"
    Unfortunatelly, after this I cannot find this report in EP. Can anyone help us with this error?
    Thank you
    Vitaliy

    Did you setup authorizations as described:
    On BW side: You need special authorizations to be able to use information broadcasting. System administrators need authorization object S_RS_ADMWB with the field RSADMWBOBJ = BR_SETTING. Users that precalculate business intelligence content and would like to schedule things require the authorization object S_RS_BCS. To be able to schedule broadcaster jobs in background the authorization to run batch jobs should be granted on BW side. The authorization object is S_BTCH_JOB "Background Processing: Operations on Background Jobs"
    From my own experience:
    On portal side: The users, to which personal folders it is necessary to publish, should exist both in EP and BW (have the same name), be active and have “Business Explorer” role assigned in EP (i.e. "Personal BEx documents" folder in KM should exist for them)

  • Copy project description (defined in WBS Level 2) automatically to activity

    Hi Gurus,
    How to copy project description (defined in WBS Level 2) automatically to activity name/description?
    For example:
    WBS element (Level 2): "Telephone System Replacement"
    When create a new Activity, the description will be: "Telephone System - xxxxxxxx"
    The first 16 characters "Telephone System" from the WBS Level 2 are automatically populated to Activity Short Text field.
    How to realize that?
    Thanks.
    JM

    >
    Virendra Pal wrote:
    > you can use substitution rule
    > transaction OPSN
    > check out the standard substitution fields available
    > if not you can always use an exit in substitution
    >
    > In the project profile enter this substitution and check the auto box
    >
    > This then on save will carry out substitution - use Intermediate save button and then add or replace the xxxxxxx
    >
    > Edited by: Virendra Pal on Nov 27, 2009 12:26 PM
    Thanks Virendra!
    I am new to PS, could you please explain in more detail?
    In OPSN, I am not sure which one to choose: Network Header or Network Activity, for my case. Looks like there are no standard substitution fields available. Could you please check it out for me? If no, how to use an exit? Is this exit the same as a user exit used for enhancement?
    Sorry, so many question marks. You help will be greatly appreciated!
    JM

  • Settlement profile WBS level 3 to level 2

    Good Day All,
    Please advice, is there any configuration to automatically create settlement receiver to WBS to WBS .
    We have requirement which is to make automatically generate settlement receiver from WBS level 3 to WBS level 2.
    Our structure for example :
    Proj Definition
    WBS level 1
    WBS level 2
    WBS level 3 (automatically generate WBS level 2)
    Is there any configuration in settlement profile or default rule?
    Cheers,
    Nies

    I found the answer in another thread.
    https://supportforums.cisco.com/thread/2144096

  • Control the authorization base on material type level

    Dear Experts,
    We want to control some users only can create or modify the material base on material type level .
    For instance , user A only can modify the 'ROH' type material , he can not maintain any 'FERT' type material .
    I set the authorization object 'M_MATE_MAR' in the user A's profile , but it doesn't work .....
    System : SAP4.7 x 200
    DB : oracle9i
    Has someone can tell me it is possibile to control the maintain authorization base on material type level ?
    Or give me some suggestions.....
    Many thanks
    Best Regards,
    Carlos Zhang

    Hi
    Yes this works & the authorisation object found by you is also correct.
    For the object - M_MATE_MAR
    Maintain the activity 01,02,03
    Maintain the authorisation group  - each material type can be assigned to an authorisation group. In OMS2 , you can assign the authorisation groups to the material type.
    For E.g if the material type is ROH- enter the authorisation group as ROH.
    Ensure that the user does not have this object, As If this object is present in any other role with authorisation group as * then the * will overirde any value.
    Thanks & Regards
    Kishore
    Edited by: Kishore Kumar Chiluka on Jun 13, 2008 11:18 AM

  • Cost element group authorization check on controlling area level

    Hi!
    When maintaining cost element groups (KAH1, KAH2, KAH3) is it possible to run an authorization check on controlling area level?
    We have one global chart of account but several controlling areas. When we create a cost element group it is created at chart of account level for all the controlling areas. When someone changes a cost element group it changes in all controlling areas. I cannot restrict user's authorization to be able to change cost element groups only in their own controlling area.
    Is it possible somehow?
    Thanks for your help.

    Hi,
    Like how the global chart of accounts is at the client level, the cost element groups are also independent of the controlling areas.  Infact, the cost element groups are created at the global COA level. 
    In such a case, I don't think it is possible to restrict the authorizations to amend the cost element groups at controlling area level.
    Thanks and Regards,
    Bhuvaneswari.S

  • How to load Cj01 create project for WBS level 1,2 and 3

    Dear All
    I want to load the project for WBS element.I had used IDOC project01 for the same but I am getting error as 'SaveReplica'method was not called up via ALE.I am presently trying with LSMW recording for tcode CJ01 in order to populate the
    wbs levels 1 ,2 and 3 since the hierachy is not fixed i:e there is no limit as to how many 2 or 3 wbs levels are there so how shall i proceed with recording.If any body has migrated Projects for WBS elements please do share me.In my recording i am getting error 'Do not enter a level greater than 2'.is it that i have to carry t recording for each level seperately.
                        Tried with Bapi Bapi_project_maintain and all Bapis related to it most of the cases i am getting
    error as to no initialization created though having executed Bapi_Ps_Initialization.
    Regards
    Somnath

    Hi Somnath,
    The BAPI, BAPI_PROJECT_MAINTAIN should work for any levels of requirement..and you dont need to initialize it. First, go through the documentation given in the SE37 transaction code. It will explain all. Just concentrate on the reference number. If you see in the example given there, two wbs elements are being created.
    Then you have to use methods like create,save...unlike other BAPI's.
    Just go through the documentation once.
    Regards,
    Vishwa.

  • How to trace the missing authorizations using NWBC at object level

    Hi all,
    In SAP R/3 any authorization issue can be tracked down till authorization object level using SU53 tcode and ST01 tcode.
    1 - I have a super user who has all the roles in Solution manager system and test user which I created with just 1 role Incident management role. But when I login with Super user ID I can see in tcode (WDY_APPLICATION - Incident Management ) I have 4 tabs (Overview,Messages,Reports and Queries) but when I execute the same tcode using test ID I can only see Overview and Messages tab. Report and Query tab were missing . Please advice on how to trace the missing authorizations using NWBC at object level? or how to solve this issue......
    2 - How to add a Web dynpro Transaction code (example WDY_APPLICATION - Incident Management )while building a role in PFCG?
    Thanks
    LAK

    Hi Gurus,
    Can anyone please help me with my questions.
    In addition here are few more info that I need
    How to bring in the new authorizations without logiing off and logging in back in NWBC ( Equivalent to Menu-->Refresh in SAP GUI)
    Thanks
    LAK

  • Raw Materail Quantity blockage on wbs level

    HI Guru's
    I am currently on the ETO based project where in on a particular WBS i may have no of production orders. Now client want the quantilty blockage for the raw material consumption in the order.
    I know through availabilty control i can block the cost consumption.
    Over here client want for a particuler production order the raw material quantity as well as the cost shud be blocked at wbs level.
    ex raw material-- 2000kg and budget for production order -
    5000000
    so do we have any concept for the same?
    Regards,
    Kamal Rana

    Wrong forum - this is the Basis forum here.
    Please close here and create a new forum entry in the MM area
    Markus

  • Functional area change at WBS level

    Hi Experts,
    I just want know the possibility of functional area change at WBS level.
    If we assign Functional area at project level, can we change functional area of WBS?
    if it is possible then is it possible to assign/change functional area of WBS after releasing the same?
    Please update me.
    Thanks & Regards
    Suresh. J

    Hi Surej,
    FA in project is in Basic tab and FA in WBS is in Assignement tab. Both functional area for Project or WBSes could be different. All this functional area could be changed. However, please note if you changed the FA once the data is posted into the WBS, the system will give a warning message not to change the FA. This FA in master data is to ease data entry. The FA will be copied over to FA area field during data entry. In fact, you can change the FA during data entry.
    Hope this explains your query.
    Thanks.
    Regards
    Fauzi

Maybe you are looking for

  • Using Old PC DVD Drive as external on Macbook Pro?

    Does anyone know if you can use an old internal DVD-Drive from an HP Notebook as an external DVD-Drive on a new MacBook Pro Retina? I recently switched from PC to Mac.  I sometimes, though rarely, use CDs/DVDs; and I certainly don't use them enough t

  • Dynamic file name in receive FTP file adapter

    Hi, All, I have a ABAP proxy -> FTP scenorio. The sender side MT is like this: <Sender_MT>   <FileName>abc.txt</FileName>   <Record>       <TEXT>.......</TEXT>       <TEXT>.......</TEXT>      <TEXT>  ......</TEXT> </Record> </Sender_MT> I would like

  • Trace Changes in Material Document

    Dear All, Is there any way to trace which material document has been changed manually by the user? Our situation is as follows:      User use MB02 to update header text field in the old material documents. We need to extract all the changes informati

  • C4 Page Properties Problem

    I use a table for my navigation links, one cell per link. I set page properties-link to Never Underline, and change the color for Rollover. Then published the page. I copied the cells from one page to the next. The first page http://www.essentialthea

  • Approver again receiving workitem in inbox

    Hi All, I have implemented legal contract workflow, based change ststus(RA ) workflow should be triggered. for that i have given a condition.my workflow is 2 level approval workflow. 1st level approved then status to be changed to a1,if he rejected s