Wrong lead times calculated between activities

Hi expert,
Client has following activity flow: 1 - 1A - 1B - 2. Relationship lead times: 1- 1a: 5day, 1a- 1b: 5day, 1b- 2a: 0day, 1- 2a: 1day.
We have maintained relantionships as necessary. But lead times from activity 1 to activity 2 is still not calculated as 1 day. Lead time for actitivity 2 calculated after activity 1B.
Please advise on solution.

Hi expert,
Client has following activity flow: 1 - 1A - 1B - 2. Relationship lead times: 1- 1a: 5day, 1a- 1b: 5day, 1b- 2a: 0day, 1- 2a: 1day.
We have maintained relantionships as necessary. But lead times from activity 1 to activity 2 is still not calculated as 1 day. Lead time for actitivity 2 calculated after activity 1B.
Please advise on solution.

Similar Messages

  • Lead time calculation

    Dear Gurus,
                             I want to calculate lead time between purchase order and goods receipt.how to do that???
    Am having some doubts.
    Does the lead time links with
    Planned Delivery Time
    Goods Receipt Processing Time
    Purchasing Processing Time in material master. plz explain???

    Hi,
    If you create PR for a material, using MRP, then the planned delivery time would be picked up from the material master, please note that there is no source maintained yet in the PIR, so obviously that rules out planned delivery time of PIR and Vendor Master( even when u convert this P.R to P.O the planned delivery time will not change and will not be taken from the PIR)
    Now if you directly create a P.O then the planned delivery time of the PIR is picked up , please note this difference.
    I would recommend that you change the planned delivery time in the material, mnake it different from the planned delivery time of the PIR, and then run MRP, You will see that the planned delivery time in the PR would be based on the material planned delivery time.
    Even if you assign source and convert this P.O using ME59 the PDT will not change.
    Then you can try and create a P.O directly with the vendor, here you will notice that the PDT flows from the info record.
    Please let me know if this addresses your concern.
    Regarding your soure list issue, either you can remove the source list mandatory tick in MM or add the vendor whose PIR you are using into ME01, and it will definitely work.
    Regards
    Shailesh
    Edited by: Shailesh Rajan on Jun 30, 2011 7:51 PM

  • Lead Time Calculation in SNP Heuristics

    Dear All,
          Please let me know how the lead times are determined in SNP heuristics?
    Ex: Distribution Center to Production Plant and
           Production Plant to Supplier.
    Thx,
    Ram.

    Hi,
    Please check the below link for help: [Scheduling|http://help.sap.com/saphelp_scm70/helpdata/EN/05/f8923945b12c4de10000000a114084/frameset.htm]
    Best Regards,
    Ada

  • How is lead time calculated for QM notifications

    Can somebody please tell me what fields are used to calculate lead time?  It is field SUMDLZT in MCQMEL?  Is there documentation on how this is calcuated?

    MICK,
    Could you give more details on the same / explain a scenario for which you need this information.
    Since there has been no activity on this post for about a month , I will close this as answered , however if you still want this to be answered - mark it an unanswered and add more details to the same so that you can get more relevant answers.
    Arun

  • Lead Time calculation in process order

    Hi,
          I have a process order to be created of 112.6 L. i have only one phase  & one resource allocated. i have maintained my OH time as 1 H in my master recipe. now for resource i have maintained scheduling formula as ZRUNA = OH.
    After creating Process order the system calculates phase timing as 1:17:44. Can anyone pls let me know how did system calculate 17 min & 44 sec extra.
    Thanks & Regards,
    Rohan Somji

    Dear Rohan,
    1.Check the length of break timings defined in the resource that is assigned in the phase.
    2.Check in OPUZ whether for the process order type and plant combination whether scheduling is to include the break time also
    (whether the check box for scheduling with breaks) is included.
    Check and revert back.
    Regards
    Mangalraj.S

  • Lead Time in Item Master

    Hi
    Does Lead Time in Item Master respect weekends and only count working days?
    Meaning, for two weeks do I enter 10 or 14?
    Thanks
    Franz

    Hi Franz
    As far as I know, NO. You only have the option to include holidays in the MRP wizard itself which will then calculate against lead times. Best would be to test on a test database with both scenarios (with 10 or 14, and tick/untick holidays in MRP) and see what the results are.
    According to the Online Help the above is correct:
    Consider Holiday Table for Production Planning Factors in holidays and weekends in lead time calculation, as defined in the Holiday Details window. Holidays and weekends increase the lead time interval for MRP calculations.
    Consider Holiday Table for Purchase Planning Factors in holidays and weekends in lead time calculations, as defined in the Holiday Details window. Holidays and weekends increase the lead time interval for MRP calculations.
    Kind regards
    Peter Juby

  • Lead time in LSP determination

    Dear all,
    in subcontracting, there is obviously some time constraint: I have to submit a freight order to the carrier at least x days/hours before planned loading date. As far as I can see, there is no such field in the carrier profile (where it could be associated with transportation lane or at least starting location). Another logical point would be the freight agreement (I agreed with the LSP that he can handle all freight I submit to him x days/hours before planned loading date), but nothing there as well. The only way I see to model this is via incompatibilities (do not assign a freight order to a specific carrier if the loading date is less than x days/hours ahead of actual date), but this seems not very convenient to me.
    Any other ideas?

    Hi Franz
    As far as I know, NO. You only have the option to include holidays in the MRP wizard itself which will then calculate against lead times. Best would be to test on a test database with both scenarios (with 10 or 14, and tick/untick holidays in MRP) and see what the results are.
    According to the Online Help the above is correct:
    Consider Holiday Table for Production Planning Factors in holidays and weekends in lead time calculation, as defined in the Holiday Details window. Holidays and weekends increase the lead time interval for MRP calculations.
    Consider Holiday Table for Purchase Planning Factors in holidays and weekends in lead time calculations, as defined in the Holiday Details window. Holidays and weekends increase the lead time interval for MRP calculations.
    Kind regards
    Peter Juby

  • ASCP Yield and Resource Lead Times

    Hi,
    I am working on Advanced supply Chain Planning on R12. Both ERP Source and Planning are on different instances. We are also using Oracle Shop Floor Management. In the Network Routings we have included a lead time resources at step 10, 20, 30. The resources are as follows:
    These resources are defined as 'Machine'
    Resource for operation 10: ASSY-LT, 112 hours, Schedule 'yes'
    Resource for operation 20: TEST-LT, 64 hours, Schedule 'yes'
    Resource for operation 30: PACK-LT, 48 hours, Schedule 'yes'
    We also have only one shift with 8 hours. The resources are not available for 24 hours.
    We also have yield at each of the above operations.
    Lead time rollup calculates 28 days for the item correctly.
    We are encountering a problem with ASCP Plan. The start dates and yield calculations using constrained plan with Enforce Demand Due Dates constraint seems problematic. If we check 'Calculate Resource Requiremnents' option, the plan calculates yield but the lead time gets reduecd by one third and start and completion dates for a planned order (and ATP etc.) are not accurate.
    If we uncheck 'Calculate Resource Requiremnents'option in the plan, lead times are accurate but plan does not calculate yield.
    We are not sure what is causing the problem.
    Does anybody know what options or profiles control this behaviour?
    Your help is highly appreciated.
    Thanks.
    Vijay

    Hi Vijay,
    important for your lead time calculation is the setup of the calendar and shifts and what shifts are assigned to the resource.
    You say you do not have enabled the 'Available 24h' option. We are also using leadtime resources in certain cases, for example LT for Assembly. But in these cases we enable the 24H option. Next to this we set the Resource capacity to 'unlimited' by setting units to a very high number (1000 etc.) on resource level, to prevent that the system gets into capacity conflicts here.
    And the yield calculation indeed should be quite independent of the leadtime resource.
    best regards,
    David.

  • Difference between Req with insufficient lead time and lead time const

    Hi ,
    1) Can anyone explain the difference between Requirement with insufficient lead time and Requirement lead time constraint exception messages. Both seems to be similar for me with the compressed time.Also at what situations these exceptions are generated.
    2) what is minimum lead time required ,actual lead time and its calculation.
    Thanks...

    Check out
    http://help.sap.com/saphelp_scm50/helpdata/en/99/ed3a981d0f11d5b3fc0050dadf0791/content.htm
    particularly the section "Which functions of the operations relevant to scheduling are supported?"
    It will give you a flavour of what can lead to difference in planning.

  • DIFFERENCES between BASIC SCHEDULING and LEAD-TIME SCHEDULING.

    Hello SAP Gurus,
    Kindly let me know the differences between BASIC SCHEDULING and LEAD-TIME SCHEDULING.
    Looking for your early feedback.
    Warm regards,
    Kaushik.

    Hi,
    Basic scheduling :
    1.Basic dates are calculated.
    2.Exact to day.
    3.No cap reqmts are generated.
    4.uses the inhouse production time from material master.
    5.carried out automatically during planning run.
    In basic date calculation ( order start date/ order finish date ) the system always
    calculates backward scheduling.
    1. From the reqmts date the system subtracts the GR processing time to
    calculate the order fininsh date.
    2. From the order finish date the system subtracts the inhouse production time to calculate the order start date.
    3. From the order start date the system subtracts the opening period given in scheduling margin key to calculate the order opening date.
    Lead time scheduling :
    1.Exact to second
    2.ie production start date /time and finish date and time are calculated.
    3. cap reqmts are generated.
    4. uses times from routing.
    5. carried out only if the scheduling mode in MD02 screen is kept with indicator 2.
    From the order finish date the system subtracts the float after production to calculate the production finish date.
    From the production finish date the individual operations in the routing are scheduled backwards to calculate production start date.
    From the production start date the system subtracts the float before production
    to calculate order start date.
    Regards,
    nandha

  • Difference Between Basic Date Scheduling and Lead Time Scheduling.

    Dear FRndz,
    Kindly help me out the difference between the Basic Date Scheduling and Lead Time Scheduling.
    Regards,
    SRini

    Dear,
    Basic scheduling :
    1.Basic dates are calculated.
    2.Exact to day.
    3.No cap reqmts are generated.
    4.Uses the inhouse production time from material master.
    5.Carried out automatically during planning run.
    In basic date calculation ( order start date/ order finish date ) the system always
    calculates backward scheduling.
    1. From the reqmts date the system subtracts the GR processing time to
    calculate the order fininsh date.
    2. From the order finish date the system subtracts the inhouse production time to calculate the order start date.
    3. From the order start date the system subtracts the opening period given in scheduling margin key to calculate the order opening date.
    Lead time scheduling :
    1.Exact to second
    2.ie production start date /time and finish date and time are calculated.
    3. cap reqmts are generated.
    4. uses times from routing.
    5. carried out only if the scheduling mode in MD02 screen is kept with indicator 2.
    From the order finish date the system subtracts the float after production to calculate the production finish date.
    From the production finish date the individual operations in the routing are scheduled backwards to calculate production start date.
    From the production start date the system subtracts the float before production
    to calculate order start date.
    Same thread.
    https://forums.sdn.sap.com/click.jspa?searchID=19281092&messageID=3548465
    Please refer this link,
    [Difference|scheduling]
    Hope clear to you.
    Regards,
    R.Brahmankar

  • Calculating Lead time.... Help......

    We have two field in qals
    QALS: Lot created     (ENSTEHDAT)
                Time                (ENTSTEZEIT)
    Similarly we have two field in QAVE
    QAVE: UD Code Date
                Time            (VEZEITERF)
    I need to calculate the lead time
    i.e.
    Lead time = (Lot Created date & time - Date of UD & Time - Holidays as per factory calendar) / 24:00:00 hrs.
    How to proceed????

    hi Uttamagarwal,
    Please check the below sample Code. You need to do declare the Appropriate Variable and ITAB.
    "as NSTomar  said , First use the FM to get the Date and Time difference
    call function 'SD_DATETIME_DIFFERENCE'
      exporting
        date1                  =  enstehdat  "Lots Created Date
        time1                  =  entstezeit " Lots Created Time
        date2                  =  vaedatum  " UD Change Date
        time2                  =  vezeitaen  " UD Change TIme
    importing
       datediff               =  date_diff
       timediff               =  time_diff
    *   EARLIEST               =
    * EXCEPTIONS
    *   INVALID_DATETIME       = 1
    *   OTHERS                 = 2
    if sy-subrc <> 0.
    * MESSAGE ID SY-MSGID TYPE SY-MSGTY NUMBER SY-MSGNO
    *         WITH SY-MSGV1 SY-MSGV2 SY-MSGV3 SY-MSGV4.
    endif.
    * then Please use the below  FM To get the Number of Holidays
    * between the Lots Created date and UD Changed date
    call function 'HOLIDAY_GET'
    EXPORTING
    *   HOLIDAY_CALENDAR                 = ' '
       FACTORY_CALENDAR                 = fac_cal   " Pass the Factory calendar here 
       DATE_FROM                        =  enstehdat      " Lots Created Date
       DATE_TO                          =   vaedatum       " Ud Changed date
    * IMPORTING
    *   YEAR_OF_VALID_FROM               =
    *   YEAR_OF_VALID_TO                 =
    *   RETURNCODE                       =
      tables
        holidays                         = it_holidays
    * EXCEPTIONS
    *   FACTORY_CALENDAR_NOT_FOUND       = 1
    *   HOLIDAY_CALENDAR_NOT_FOUND       = 2
    *   DATE_HAS_INVALID_FORMAT          = 3
    *   DATE_INCONSISTENCY               = 4
    *   OTHERS                           = 5
    if sy-subrc <> 0.
    * MESSAGE ID SY-MSGID TYPE SY-MSGTY NUMBER SY-MSGNO
    *         WITH SY-MSGV1 SY-MSGV2 SY-MSGV3 SY-MSGV4.
    endif.
    "Check the Number of Entries in it_holidays which is equal to Number of Holidays
    describe_table it_holidays lv_count.
    if you want to find the date difference i.e., Lead Date
    Lead date = date_diff + lv_count
    if you want to find the time difference i.e., Lead Time
    Lead Time = ( ( date_diff + lv_count ) * 24 ) +  time_diff
    Edited by: Rob Burbank on Aug 5, 2010 9:26 AM

  • Stock transfer between storage locations and lead time

    Hello,
    We use stock transfer orders between different storage locations. Is it possible to maintain the transport lead time between storage locations somewhere or do in need to use routes and scheduling?
    rgsd
    GAR

    Hi,
    Try using movement type 313 and 315
    313 -- Transfer posting SL to SL --- Remove from issuing SL
    315 -- Transfer posting SL to SL  -- Placing in Receiving SL
    Regards

  • How is lead time in working days calculated in 2LIS_05_QVUDN

    I was wondering if someone knows how lead time is being caclulated for 2LIS_05_QVUDN.  I've found the tables associated and the function module but I can't find the actual calculation
    Thanks

    Hello
    The lead time in working days works like this
    If you have 1 inspection lot for a material   -the time from  Lot creation to Usage decision given  is the lead time.
                                                              Lot created               Usage Decision made       Lead Time
    for eg Material X , inspection lot no   14/05/2008 10: 00          14/05/2008 14: 00            4 Hours
    it converts the hours in to days . =4/24= 0.16 days
    For total lead time individual lot's lead time sum is calculated
    Hope this clarifies your doubt
    Regards
    gajesh

  • Difference between Compute lead time and Rool up lead time

    Hi All,
    Could you please clarify what is difference between Compute Lead time and Roll up lead time.
    I see in Routing > Tools.
    Thanks in Advance
    Regards
    Ravi

    Refer The Oracle document
    Manufacturing Lead Time Computations
    Manufacturing Lead Time Computations (Oracle Bills of Material Help)
    Rolling Up Cumulative Lead Times
    Rolling Up Cumulative Lead Times (Oracle Bills of Material Help)

Maybe you are looking for