Wrong Selection of Project Profile, how to rectify - Project System

Dear Gurus,
I have problem in Project system, wherein by mistake i have selected customer project profile instead of Capital Investment Project profile.
I have incurred some costs in Network alread in this project & posted.
I am not able change the CJ07 the project profile from Customer Project to Capital Investment, due to which the costs booked already in Network are setting in Network and not able to CJ88 from Network to WBS from WBS to AUC.
I have changed the CJ12 the WBS element from customer to capitable investment, but not able to change the project profile in Project Definition level.
Kindly help if u have any solution.
Thanks in advance
Srihari Ediga

no one responded,hence closed to post new thread.

Similar Messages

  • Creating Project Profile in SAP R/3 Project System

    Hi All
    While creating a project definition in Project System in SAP R/3, it is the mandatory to select a Project Profile from a pick list. How can I create a new project profile for myself?
    Thanks
    Sheenam

    It is mandatory to select a Project Profile while creating a Project Definition. Project Profile can be created using OPSA transaction.
    regards
    Shravan

  • Impact of Project Profile

    Dear All,
    User has selected wrong project profile.
    I need to know what are the implications or impact of wrong project profile on the open project.
    Thanks
    PM

    Hello,
    Project Profile shows the behavior of the project. It contains basic settings related to Organization structure, Planning, Settlement, and various profiles which contains different settings.
    so this is very important and critical field in Project. So you have to check setting in that profile and compare to correct one.
    Thanks
    Sunil

  • Restricting project profile in CJ20N/CJ01 t-code

    Hi Experts,
    Based on the client requirement we have created a new Project Profile named as theShutdown Project. The type of Project is ShutDown. The client wants to restrict the same only for the Plant users usage. 
    I know that the type of the project can be restricted thru standard authorization object -
    C_PRPS_ART. The coding mask is not restricted or defined as of now.
    Since we could not find any standard authorization object which restricts specifically on Project Profile, we tried creating a Z
    auth.object as follows:
    u2022 SU20 -CREATE AUTHORIZATION FIELD
    u2022 SU21 -CREATE AUTHORIZATION OBJECT
    u2022 SU21 -LINK AUTHORIZATION FIELD AND AUTHORIZATION OBJECT
    u2022 SU24 -ADD THE AUTHORIZATION OBJECT IN THE TCODE CJ20N AND CJ01
    u2022 PFCG-CREATE ROLE WITH AUTHORIZATIONS TO TCODES- CJ20N AND CJ01. ALSO
    ADD THE AUTHORIZATION OBJECT MANUALLY. GENERATE THE ROLE AND SAVE THE
    SAME. LINK USER ID TO THE ROLE
    u2022 SE38- LCJWBF7S. CREATE ENHANCEMENT IN FORM PROJ_SET AND ADD
    AUTHORISATION CHECK OF THE ABOVE CREATED OBJECT 
    The issue is that the above procedure is restricting the access for all the other users too despite it being attached to a particular role only. Every project profile other than shutdown  project is getting an error -"You are not authorisedfor this activity"  
    Please advice if our approach is correct or are there any alternative available.
    Regards
    Khushali

    HI,
    You need not have a separate Auth Object for "Project Profile".
    Make use of your standard auth object "Project Type" only.
    Introduce a simple validation to say that The only project type "Shutdown Projects" should be allowed for your Project Profile "Shutdown Project"
    By this, while Project creation, system throws error (Error you defined in the validation) in case both the Profile & Type are incompatible. When the user selects the appropriate "Project Type", then the subsequent standard error would be related to authorization on Project Type for the desired users.
    regards

  • Project Profile from SAP-PS in cProjects

    Hi,
    Need your suggesttion on the below issue. We have cProject & R/3 integration. Project structure will be created in cProjects which will also create a project in SAP-PS. As per standard SAP-PS, CPR0001 is project profile to be used for cProjects & PS interface. Project profile (CPR0001) contains standard settings of SAP such as controllig area / company code / plant etc. I had copied CPR0001 project profile & created new profile to be used for creating project as per our organsaition structure. I observed while creating project from cProjects, it is considering CPR0001 project profile & accordingly the organisation structure is copying where as our required project profile is different.
    I would like to request in cProjects, where it is calling project profile & to make the project profile as per our requirments.
    Thank you for your cooeparation.
    Regards,
    Ranjan

    Hi Ranjan,
    1. Project element is creating as WBSE & project definition in PS. But there is no one -to-one mapping. I would like to transfer various phases as WBSE in R/3 but it is n't happening
    >> There tow scenario of the replication, one is role-based, other is task-based. In case of role-based, the phases are not used, as role is not under the phase. In case of task-based, the phase should be used, as it is in most cases the parent of the task. I am not 100 percent sure at this point.
    2. Dates are n't getting transferred to project in project structure of SAP-PS.
    >> At the replication, only some data are mapped to the WBS, mostly the costs relevant information, as the purpose of this functionality is costs. Even the left-right relationships can not guaranteed in some cases.  
    3. The WBSE which created in PS from cProjects, master data are locked
    >> Worked as designed.  The idea is to forbid the use change the master data of the replicated WBS. It is somehow inflexible, but it is customer requirement, which trigger this feature. You can unlock it manually in the ERP system.
    4. Tasks are n't getting transferred as network activity into PS
    >> Not possible in cPro. 4.0, in release 4.0 the project system integration (other name multiple level controlling)  will be mapped to WBS. In Release 3.1, it is possible to get. But from my point of view, map to WBS is the better way.

  • Defalut Project profile

    Hi,
    I want to make default project profile for project coding mask.
    I have 2 different types of projects. 1 is starting with HHD/2008/001, HHG/2008/001
                                                       2nd starting with HPC/2008/001, HPW/2008/001
    I have 2 Project Profile. Profile - 1000 n 2000
    I want to have default project profile like, if the Project is starting with HH, it should pick only 1000 and if the project is starting with HP, it should allow only 2000 Profile.
    As both the Projects have different Co Codes.
    Advise me the best solution. Rewards Points guarnteed.
    Regards
    N.Raju

    Try this-
    T Code : OPSI
    Validation for Project Definition:
    Prereq:
    PROJ-PSPID :1-2: = 'HH'
    Check
    PROJ-PROFL = '1000' OR PROJ-PROFL = '2000'
    If check NOT fulfilled.
    Error
    Refer this in the project profile.
    Regards
    Sreenivas

  • How can I add system font to Acrobat Pro X?

    I tried to use "Edit Document Text" Function. There is an error pop-up as " All or part of the selection has no available system font. You cannot add or delete text using the currently selected font.". How can I add system font to Acrobat Pro X?

    It is referring to the fonts installed on your computer - to edit text within a PDF you must have the same font installed (i.e. one with the same PostScript name). Acrobat doesn't have a separate way to load fonts, you install them in the normal way through your operating system control panel after downloading/purchasing the font files from a vendor.

  • How to select the printer and select the ICC profile for printing with VBScript?

    I try to automate my printing procedure in photoshop. The problem is that I don't know how to select the printer and select the icc profile for printing with vbscript like I manually do in the print-menu in photoshop?
    Anyone has done this before?
    Thanx!
    jus

    Client/Server version:
    - D2KWUTIL.PLL library provides a 'Select Printer' dialog box to be used in Forms: WIN_API_DIALOG.SELECT_PRINTER
    http://guenter-huerkamp.dyndns.org/oracle-doc/docs/html/d2kwutil.html
    I suggest you to create a form to invoke the report, allowing user to select the printer and then pass it as parameter DESNAME

  • How to Rectify Goods Return posted in wrong date

    Dear Expert
    Please guide me how to rectify the Goods return posted in Wrong Date.
    Regards
    Rajani patel

    DEAR GORDAN
    I am talking about Purchase Goods Return based on GRPO then how can i rectify it
    Scenario is like this
    GRPO date:10th April 2010 and client has made Goods Return in 21th Sept 2010 instead of same date of GRPO
    Regards
    Rajani P Patel

  • How do you move changes from your project developments into the maintenance development system?

    Good day colleagues.
    We are in the process of introducing retrofit, and the picture is clear for us, generally speaking, to retrofit the project landscape with the changes done in the maintenance landscape.
    What about the other way around? We mean, when the project is set to Go Live, we understand the transports will be all added, e.g. to the Production System buffer to be moved there via Maintenance Cycle, based on the way we defined the project and the logical component being used.
    However, how do you feed those project transports to your Maintenance Development System using ChaRM?  or do you do that Manually?  We doubt. Copying Production back into Development?  no way !!!
    How do you establish that?  We have a sort of idea but the documents about retrofit only seem to talk about moving transports one way, as far as we have found.
    Many thanks for any feedback.
    Juan Carlos

    Hi Piyush.
    I apologize for a late close on this questioning about moving projects back into the maintenance stream.
    Basically there are 2 solutions as far as we know:
    1. What Vivek mentions, which is performing a cutover and repacking the project transports into 2 transports in the maintenance stream:  A workbench and a customizing.   In that sense, at the end of the day you end up moving just 2 transports to the maintenance stream up to Production.   They contain all your project objects.  Thanks to Vivek, again.
    This is a very practical and interesting approach.  The only reason we did not adopt it, is based on the fact that if by any chance we encounter an issue with a project transport object in the maintenance stream (Dev or QA), now that all is bundled together, we may be stuck right at the time weare getting ready to GoLive.  How tough is going to be that issue? how easy and quick to fix?how much would that affect the whole project time frame?   Those questions made us decide to option 2.
    2.  What we are doing is that at cutover we move at the same time all project transports to the transport buffer of each of the maintenance stream systems (Dev, QA, and Prod).   We first open the gate to move the transports to Dev and we test, then to QA and we test, as well.  If there may be an issue, and the issue can not be quickly resolved by the project team, we can go up to the extreme of using a new feature introduced in ChaRM in SP10, if we are not wrong, but definitely available in SP12.  That feature provides a way to selectively decide which transports of the release are to Go Live and which ones do not, although we have no had to use that feature, yet, but it is there.
    We do not see any risk on adding the transports to the maintenance buffers at the same time.  There are ways to control the systems that are open for receiving transports, and the project phases, which guarantees no room for error.  There have to be deliberate actions taken (more than one in our case), to wrongly move a project to GoLive before its time comes.
    That is more or less the scenario Piyush.    
    Hope that explains the scenario.  So far no decision on really publishing as a blog.  It seems not to be written on stone, as consulting with different companies, each adds its own flavor to the recipe and shuffle ideas to get to what they are looking for and makes them happy.
    Juan

  • Validation for Project defination and project profile

    Hello,
    I have to create validation for Project Definition and Project Profile.User requirement is when the project (Exp: Z/0120) is creating with project profile Exp: Z0001_Z system should allow , If user is trying to select other than this profile system has to give the error.
    I tried below validation but it is not working:
    Prerequisite - PROJ-PSPID = 'Z'
    Check   -  PROJ-PROFL = Z0001_Z
    Kindly any suggest how can i give the validation for the same.
    Regards,
    Lakshmi.
    Message was edited by: Mohamed Rafi - Many threads available on this topic search for those.

    Hi,
    Have you tried to save the project? Because validation rule will call at time of saving the Project.
    I have created the same but for start with 'U'
    When I create project and at time of saving, validation rule will call and system throw error if I don't create project start with 'U'.
    Now If I am creating here, start with 'J'. System  is throwing error as per validation rule.
    Also Pl check if you have assigned same correct rule on project profile.
    Regards
    Shishir

  • HT3678 everytime I open qt pro i have to enter the registration code. This is really annoying. Does anyone know how to rectify this problem?

    everytime I open qt pro i have to enter the registration code. This is really annoying. Does anyone know how to rectify this problem?

    This procedure will check for files in your home folder that are locked or have a wrong owner. It makes no changes and will not, in itself, solve your problem.
    Launch the Terminal application in any of the following ways:
    ☞ Enter the first few letters of its name into a Spotlight search. Select it in the results (it should be at the top.)
    ☞ In the Finder, select Go ▹ Utilities from the menu bar, or press the key combination shift-command-U. The application is in the folder that opens.
    ☞ If you’re running Mac OS X 10.7 or later, open LaunchPad. Click Utilities, then Terminal in the page that opens.
    Drag or copy — do not type — the following line into the Terminal window, then press return:
    find . -flags +uchg,uappnd -o ! -user $UID
    The command may take a noticeable amount of time to run. Wait for a new line ending in a dollar sign (“$”) to appear.
    Post any lines of output that appear below what you entered — the text, please, not a screenshot.
    If any personal information appears in the output, edit before posting, but don’t remove the context.

  • Validation Rule for the coding mask and project profile

    Hi,
    I have two project profile and two coding masks. I want one project profile to be only used by defined coding mask for that profile.
    So i have maintained a validation rule as follow -
    Prerequisite - Project Def. :1-3: = 'A5M'
    Check - Project Profile = 'ABC'
    And if the above check is failed then give me an error message.
    Now i am trying to add the project profile other than 'ABC' for the coding mask starting with 'A5M', but still the system is not giving me an error message configured and allowing me to save the project.
    Is there any other thing which is tobe activated other than assigning the validation rule in project profile and clicking the Autom. validation check box in OPSA.
    Request to confirm share the views.
    Thanks

    Hi,
    Try the following, this must work.
    Prerequisite
    PROJ-PROFL = "ABC"
    Check
    PROJ-PSPID: 1-3: = "A5M"
    Message
    Project profile & Coding mask wronly assigned
    Repeat the same for other project profiles also.
    Enter this validation in your project profile. Check in "Auto Validation"
    In transactinal data,
    Enter project def and select the wrong profile. when you save the project system will show you the error message.
    Hope this will help you.
    Regards
    Prabu

  • How to download project template into the SAP NetWeaver Developer Studio

    Hi,
          I want to download project template into the SAP NetWeaver Developer Studio related to invoice detail get detail,get list etc.
    How to do so?Actualy my requirement is to create an iView whcih contain the detail about the invoice.
    Thank,
    Kundan

    Hi
    If you have zip file of the project then unzip it into your project  location where all projects are there .then in NWDS go to file->import->multiple existing project into workspace->browse the file where you have saved it and select the comp folder inside the project folder->click finish.Now you are able to see the webdynpro project in the webdynpro explorer.If its not appearing then go to Navigatore and right click on project and click on open project, it will open the project in webDynpro explorer.
    Thanks
    Susmita

  • Creation of Project Profile & Network Profile

    Hi Experts,
    I am new to PS. We have a customer project which has two company codes.
    Company 1 has three plants and company 2 has one plant. Our client will use PS for new product development projects. That new product will be developed in a single plant itself. Each plant is dedicated to one kind of product development only.
    Please let me know how many project profiles & network profiles have to be created for this scenario.
    Thanks & Regards,
    Kabir
    Edited by: Kabir on Nov 16, 2008 8:23 AM

    Hi Virendra,
    Thank you for the reply.
    In our case, by New product development project, my client means that they will develop a new product for their customers based on the new specifications & designs. For example, an auto component.
    The client also wants to do the billing. So we will take it as a customer project here. We will have WBS for Design, Production, Delivery etc...with activities in it. In such case, is one project profile & one network profile sufficient ? Please suggest.
    Thanks
    Kabir

Maybe you are looking for

  • Sound - No microphone gain ?

    MSI P35 Neo 2 FS Intel E8400 processor 2 x 1 Gig Corsair Ram 8800 GT Graphics card 550 watt Trust PSU Window Xp Home Edition. Realtek ALC 888/888T audio. When I try and connect to SKYPE the recipient informs me that my microphone volume is too low, a

  • How do i get rid of an add on i dont like i dont like smoothwheel

    '''bold text'''''* * italic text''

  • Sheduling OWB process flow.

    Hi, I am new to OWB. I created a process flow. And I am able to execute it using OWB. But now I want to shedule my process flow. I am using oracle warehouse builder 10g R 1. I am using work flow server 2.6.3 I am having oracle enterprize manager. But

  • Golden Gate v/s Streams

    Hi, I'm looking for some info on these. Please let me know where I can find more info on these. • Product Roadmap (Streams being discontinued vs. golden gate now and in future) • Product Comparison (architecture, reporting, monitoring etc) Regards, N

  • How to identify different environments (Self Service)

    Hi with Forms, we can set site level profile option for sitename, and this will display PROD, TEST, DEV etc. Is there anyway we can do this with the self service side of Apps ? Or, does anybody have any other ways to tell user which environment they