Hello Gurus,
I configured variant and executed. system generates Planned order and when i tried to convert Plnd order to prd order its give me message (You cannot make an assignment to make-to-order stock)
please let me know where i'm making mistake.
Thanks

Hi,
Check ur planned order and the master data of it if there assignment of the sales order is there then the system will allow you to convert this into production order.
check ur settlement profile assigned to ur order type.
Go to -
>md12-->put planned order num.----> go to master data -
> there you will find the sales order assigned to that order .
Then check settlement profile assigned for ur order type with standard settlement profile PP01 at OK07
Please use notes 432109.
Regards,
R.Brahmankar

Similar Messages

  • You cannot make an assignment to make-to-order stock - Message no. CO684

    Hi,
    During conversion of planned order to production order in variant configuration scenario I am getting following error message....
    You cannot make an assignment to make-to-order stock
    Message no. CO684
    Diagnosis
    The component cannot be allocated to an individual stock because make-to-order production and engineer-to-order production cannot be executed with this order.
    A possible cause is that you are trying to create an order with reference to a sales-order/project, where an account assignment to a sales order/project is not allowed in the settlement profile that is assigned to the chosen order type. This is inconsistent.
    System response
    The following responses are possible:
    Order processing is canceled.
    The system resets the special stock indicator back to the original value.
    Procedure
    Choose another order type.
    Any ideas or suggestions to correct this issue..
    Pavan

    Hi Pavan,
    This is one of the most common problem comes during MTO execution.And the real problem is massage no itself because you will get the same massage no. for many reason and that's it becomes more difficult to find out root cause.
    Check below threads and settings,
    - Order type for MTO is not maintain in Production scheduling Profile.Go OPKP or CORY and maintain Order type for MTO to it.
    - [Thread 1|Error Message while cretaing a Process Order;
    - [Thread 2|Error in Variant Configuration CO684;
    - [Thread 3|error information when covert plan order to production order;
    - [Thread 4|You cannot make an assignment to make-to-order stock;
    Regards,
    Dhaval

  • You cannot make an assignment to make-to-order stock

    HI ALL,
    Here my scinario is make to order scenario. When in material master i given MRP PD, lot size lot for lot. Strategy 20. after creating sales order i did MRP run system created planned order but while converting plan order to process order the system not allow the conversion and gives following message ?You cannot make an assignment to make-to-order stock?. Please let me know why this erroer comes ?
    Thanks & Regards
    Rahul

    hi,
    can u please tell me the message class and number for your error.
    regards
    ramesh

  • MTO: You Can not make assignment to make to order stock.

    Dear All,
    I am facing an issue during production order creation. The following error message persisting while creation of production order for setuping Make to order scenario.
    Details:
    I have created a sales order with configurable material (Not BOM).
    Item category: TAC, Stratergy Group: 20, Requirement Type: KE, Requirement Class: 040. (Contains, Acc *** Cat: 'E' and Special Stock Indicator 'E'.)
    Sale Order successfully saved and Requirements passed to MD04. I have run the MRP, System created Planned Order successfully.
    From MD04, When I am transferring Planned Order to Production Order The below error is persisting.
    Error Message: You Cannot make an assignment to Make to Order Stock. Message No: CO 684.
    I am using a custom production order type (Say ZP01) with settlement profile SD1 assigned to it.
    I have also activated the sales orders in TC: OKKP.
    I am using ECC 6.0. and Implemented OSS note: 723180 Still the above error Message is persisting.
    Since the development is in middle of the stage and deadline is very near I need your valuable suggestions to get the clues.
    Thanks & Regards

    Hi Ugameshk,
    First go to OMS2 ang do quantity value upadting tick.....for KMAT material type.
    I am sure you will get your problem solved.
    regards
    tara
    Edited by: tara  bhapkar on Oct 1, 2009 11:37 AM
    Edited by: tara  bhapkar on Oct 1, 2009 11:38 AM

  • You cannot make direct posting to the g/l account

    Hi
    While creating the std po I am getting the message you cannot make direct posting to the g/l account 165000
    I am working on chart of accounts INT
    I have not checked the check box for automatic posting
    error mesage that I am getting
    No direct postings can be made to G/L acct. 165000 in CoCode BP01
    Message no. ME038
    Diagnosis
    The G/L account you entered is a control account. Transactions cannot be posted direct to a control account.
    Procedure
    Check your input.
    Inform the individual or section responsible for G/L accounts in the relevant company code.
    Thanks
    Prabind Kumar Singh

    Hi
    Goto Transaction code FS00, enter the G/L account 160000.
    enter the company code BP01.
    Click on display, if the system says account does not exist, click on create with refernce or template
    In the popu enter the G/L account 160000 & compnay code 0001.
    Please ensure this account is flagged as Balance sheet account, Recon. account for acct type - K Vendors.
    now do the postings.
    Thanks & Regards
    Kishore

  • This database was connected to a Microsoft Access Services site that is not compatible with this version of Microsof Access. You cannot make design changes or modify data in database.

    Hello All,
    I am getting this error while I am connecting my access database website for the change
    "This database was connected to a Microsoft Access Services site that is not compatible with this version of Microsof Access. You cannot make design changes or modify data in database."
    I am using SharePoint 2010 and Microsoft Office 2010.
    I have created one Contact Database Site and now I am trying to modify the layout of the form in Access. and I am getting the error that I have mentioned.
    Please provide help on it.
    Thanks in Advance....

    Hello All,
    I got the answer, we have to enable the port 80 or where the access service is deployed and we have to change Trust setting and also, enable the macro from Access.
    Hope this will help to other....

  • I can't make a call but i can received calls and send text messages its say you cannot make a call check the phone settings!

    i can't make a call but i can received calls and send text messages its say you cannot make a call check the phone settings!

    It is not a cell phone.

  • Assignement to make to order stock.

    HI ,
    While converting the plan order to production order i am getting error that ,
    you cant make assignment to make to order stock.
    I am using strategy 20.
    Regards

    HI
    Are you running MRP for sales order or its for customer requirement ......?
    have you recently changed any settings related to requirement type or class and the sales order is being generated before this changes....?
    have you tried to create directlt the production order for the present sales order......?
    revert back , for further discussion.
    Regards
    Ritesh

  • Make to order stock delivery issue

    hi sap guys
    i m creating delivery for make to order stock, when after creating order i try to do vl01n it gives error that * No deliveryrelated items ,no shedule lines due for given date
    and  in sales order when i check shedule line  it shows confirm quanty 0 .
    so plse help- wht could be the reason for this
    is there any settings or different item category
    points will be rewarded

    First create an order and save. As it is an Make-to-order item, a Assembly order is generated from the Sales order, which you can find in the Schedule line of item > "Procurement" .
    Click on the" procurement" button below the screen, there you will find a Assembly order no.
    Presently ,you do not have stock of the MTO material. Once it is assembled, you will receive into your stock against this assembly order.
    So, receive the stock in your plant.
    Now if you will check the availability, you will find stock is available under "Sales order stock".
    You can go for Picking & then PGI.
    After PGI, the MTO stock (Sales order stock) is finished, beacuse we do not produce extra as it can not be supplied to other customer.

  • Subcontracting availibility check on make to order stock

    Dear All,
    I have a material let's say  'X' which with a BOM/routing which includes a subcontracting step of material "Y" which is a also a make to stock item. When I create a sales order for material X and run a Plannings run I first produce material Y. Because it's a make to order item the stock it will be customer specific stock. The next step is to send material Y away to the subcontrator, in order to complete material X. However when a create a subcontracting PO and wants to delivery it via transaction ME2O I get the error message that there is no stock available. The reason for this is that teh availibilty check doesn't check the Make to order stock quantities.
    I have treid several option but i am Not able to let sap to check the make to order stock when creating a subcontracting delivery. What I am missing or is this not supported by standard SAP?
    Thanks in advance.

    Dear All,
    Thanks for your replies but it doesn't solve my problem because when creating a delivery SAP still uses the normal availability check (B) and not the client specific availability check (BE).
    Just for the clarification the underlying material is a client specific item (with special stock indicator E) that needs to be send to the subcontractor. However the administrative stock of this material is stored as client specific and won't be picked up when we make a subcontracting delivery because the standard process use availability check B instead of BE.
    Like I mentioned maybe it is not foreseen in the standard functionality.

  • Material Training of AC520 (Controlling for Make to Order/Stock Production

    Hi,
    Is there anybody have the documentation (beside from SAP Doc) or training material of AC520 (Controlling for Make to Order/Stock Production ) ?
    I really need it urgently.
    Thanks

    Hi,
    I got the training material for other than AC520. Send me message to [email protected]
    regards,

  • Message " You cannot make an assignment to make-to-order stock"

    Hi,
    i'm trying to create a production order for a specific material, but I get this error message:
    "The component cannot be allocated to an individual stock because make-to-order production and engineer-to-order production cannot be executed with this order.
    A possible cause is that you are trying to create an order with reference to a sales-order/project, where an account assignment to a sales order/project is not allowed in the settlement profile that is assigned to the chosen order type. This is inconsistant."
    I have checked the settlement profile and valid receivers: "G/L account" and "sales order" are set to 1 "Settlement Optional".
    Which can be the problem?
    Thanks in advance,
    Luis.

    Hi,
    in the allocation structure assigned in the settlement rule, is there an assignment for receiver category "SDI" (Sales Order Item) maintained? If not  thats the reason.
    best regards, Christian

  • Make to Order Stock

    Dear  PP  GURUs,
    I have a problem with Sales Order stock in MTO (Make to Order)
    Prob : I have one FG (FG-001) with MTO, and One more FG (FG-002) with MTS
              One Raw Material (RM-001) common for the both FG's.
             Due to some reasons, Some quantity (Ex : 100KG) of RM-001 is spared in MTO
             Now I don't want to do MTO (FG-001).But I want to use the spare quantity  in MTS (FG-002) manufacturing.
    While running MRP for FG-002 (MTS), system not considering existing stock (MTO stock -100 Kg of RM-001). System againn generating Purchase requizations. If system consider the stock, need not required any purchse requizations.
    How to configure these in System.
    Please any body suggest me in this.
    I am on line.
    adv. thanks,
    with regards,
    Anand.M

    Hi Anand,
    The reason i said that was not because of any smart thinking, but simply because it would be helpful if there were some basic rules defined.
    Tommorow a scenario could arise where you could be asked why are you considering sales stock for normal MTS scenario, then what would your reply be?
    SAP is a system at the end of the day & we can configure / enhance it to meet any of our needs, but does that justify a good practise is what needs to be seen.
    Anyways in MRP-4 view for Indv/coll indicator set it as blank & run MRP & check if it meets your need.
    Good luck.
    Regards,
    Vivek
    If your query is resolved, award points & close the thread, else revert.
    Edited by: Vivek on Feb 19, 2009 3:59 PM

  • Buy/make to order /stock

    hi,
    may i know buy to order, buy to stock, make to order and make to stock all these processes,
    1 where is the setting to capture value in copa?
    2 what kind of information will go to copa from these 4 processes?
    thanks

    Check
    COPA Document not generating from MM postings

  • I don't have SSN or any other U.S. IDs. So I cannot make pre-order for iPhone5. Do I still have chance to purchase an iPhone5 at Apple Store on 9/21/2012?

    Hi, I'm an international student and I don't have SSN and other IDs which are needed when making pre-orders.
    I think Apple Store will save iPhone5 for those who have made pre-orders and choose to pick up at Apple Stores.
    So, I'm wondering whether Apple Stores have enough devices for those who haven't made pre-orders.
    It takes more than two hours for me to get to the nearest Apple Store.
    I really want to go home with my new iPhone. I'm a big fan.....

    All you can do is phone the store and explain your position.   They could probably take a credit card payment over the phone as a last resort.

Maybe you are looking for

  • Problems with Apple mail

    This problem has been occurring over the last month with no change in settings. I receive an e-mail into my inbox and when I forward it onto someone else the original goes into my 'sent' box and doesn't appear back into my inbox unless that person an

  • Japanese characters retrieved from UTF8 d/b from excel

    Hi All, I am generating a csv file(comma seperated) through a query from Oracle 9i database. There is one field which is Japanese. Our database is UTF8 enabled and when the csv file is opened from notepad/textpad then it is showing the Japanese chara

  • 2.2 Generation one Ipod touch having trouble connecting to wifi

    Ok, I am having a BIG issue with connecting my ipod touch to a linksys WRT54GX4 wireless router running WPA/WPA2 wireless security (there is an option that allows BOTH to be selected, but I disabled WPA2 as an option after I first started having issu

  • Please help computer extremely slow and need to update?

    my comp is so slow it can take up to 25 minutes to sign on, then to make matters worse after, I go through this process frequently, I get the error message that it is in offline mode, and have to shut down and start the process over again. Also I am

  • [ANNOUNCE] JavaServer Faces Resources Page

    Hi Everyone, I've compiled a list of everything related to JavaServer Faces and put a page on my website for it. Here it is: http://www.jamesholmes.com/JavaServerFaces/ If you see anything that I've missed, feel free to drop me a line. -James [email