Checkin enterprise resource isn't possible

PWA --> server settings --> Force Check-in Enterprise Objects --> Enterprise Resources --> choose names ---> nothing happens
there is no queue entry ...
Murol

Hello Kiran,
projects can be checked in by Force Check-in Enterprise Objects .
I opened a project with MS Project Professional and closed the program without checking in. After that I checked in the project with Force Check-in Enterprise Objects. It worked.
The Enterprise Resources are checked out since February 2014.
Now, I had a look at the enterprise resource and they are checked in!! How does this come? I tried to check them in since a few weeks.
It worked after demonstrating the force checkin for you.
Thaks and kind regards
Murol

Similar Messages

  • Is it possible to update standard rate for an enterprise resource using CSOM

    We are facing issues while updating standard rate for any enterprise resource using CSOM. The field standard rate is not available in the enterprise resource. Is it possible to update the standard rate for any resource using CSOM ? 
    Thanks in advance for any help.

    Hi Vikas,
    You can do it via the PSI.
    Please find below a blog post with a PSI code sample for updating the resources standard rate:
    https://epmxperts.wordpress.com/2011/01/30/update-resource-cost-rate-using-psi/
    In addition, here is a blog post by Brian about a PSI bug while updating the resource rate:
    http://blogs.technet.com/b/projectsupport/archive/2013/02/12/project-server-resource-rates-changed-with-psi-not-seen-in-project-professional.aspx
    Hope this helps,
    Guillaume Rouyre, MBA, MVP, P-Seller |

  • Change Default resources Assignment Owner in Project Professional, in the checked-out Enterprise Resource Pool?

    Hi,
    i'm not able to change the default Assignment Owner (massive) in the Checked-out Enterprise resource pool in Project Professional 2013.
    I've also unlocked the "Windows account edit" in the Register Editor.
    Do you know if is this possible or i have to change it for each resource one by one???
    Thanks
    Best regards 
    Daniele
    Daniele

    Hello Daniele,
    I think what you are seeing is by design behavior. Per below article you can set the Default Assignment owner in Project Web Access and it appears in various places in Project client.
    http://office.microsoft.com/en-in/project-help/default-assignment-owner-resource-field-HA010167482.aspx
    If you want to set the same default assignment owner for multiple resources then you can try bulk edit option in resource center.
    Hope this helps.
    Thank you,
    Kiran K.

  • Sync extra AD attributes to Enterprise Resources

    Working with Project Server 2013...
    I am looking for a way to bring in AD attributes like employeeID and physicalDeliveryOfficeName and have them added and updated to user resources when running the "AD Enterprise Resource Pool Synchronization".  I cannot find a way to add any
    extra attributes for the sync job to connect to the resource.  Can this be done?

    Hi Nate,
    You should not write directly to project DB. To create/update Resource Custom fields in Project Server 2013, you can use .NET based Client side object model (CSOM)
    Your starting point to read about CSOM based Project Server API for custom fields will be
    http://msdn.microsoft.com/en-us/library/office/microsoft.projectserver.client.projectcontext.customfields_di_pj14mref(v=office.15).aspx
    Hammad Arif EPM Advice Blog
    Hello Hammad,
    have you updated enterpriseresource customfields with CSOM yet ? 
    Regarding informations from the Project Customization and Programming forum and after checking it on a dev system, i come to the conclusion that it is not possible with CSOM for resource level customfields (...at least not yet).
    Of course you can go with the PSI resource service (web/wcf), but only if you develop for on premise installations not for project online.
    So, question is how do we get customer resource data, from AD or 3rd party system, into ProjectOnline, without entering it manually :-)
    Greets
    Maik

  • Active Directory Enterprise Resource Pool Synchronization

    I'm running in to an issue with Project Server 2013 that has me pulling my hair out.  A co-worker and I switched it over from SharePoint Permissions Mode to Project Permissions Mode and are trying to set up AD Enterprise Resource Pool synchronization. 
    I go in to Server Settings --> Operational Policies --> AD Resource Pool Synch and try to add 1 to 5 groups.  The groups resolve (actually autocomplete) and appear correctly.  If iclick Save or Save & Synchronize Now, nothing happens. 
    No page refresh, no redirect, etc.  If I go in to Security Settings --> Manage Groups, I can edit one of the built-in PWA groups and add the AD group, click save, and get redirected back to Server Settings.  But then going back in to the newly
    edited group, the AD Group field is empty; and on the Manage Groups page the "Active Directory Group" and  "Last Sync" columns are empty.
    I would chalk this up to an AD issue, but I have no problem using the same account to add an individual user as an Enterprise Resource and tie it to an AD account, so I can only assume that this account has all of the permissions required for AD and it can
    query and resolve fine.  Does anyone have any idea what could be going on, or possibly some step I might have missed when setting this up?
    Thanks in advance.

    I know it looks like a different issue, but that is the only thing logged in ULS regarding Project Server at the time of trying to do the sync.  If it helps, I can provide another log and see if something else comes up, but I did watch the ULS Viewer
    at the time and the same errors kept popping up when trying to do the sync.
    Also, the "other environment" is just a second instance of PWA on the same SharePoint farm, so it's not a separate environment completely.  Using the same AD groups, so there shouldn't be any discrepancies.  It's not the best test I know,
    but I'm still in the middle of setting up an AD test environment and trying it from there, just to see if it's an issue with my SharePoint installation or PWA installation.
    Edit:
    Here's a full verbose log:
    09/11/2013 10:31:49.19    w3wp.exe (0x3BE0)    0x0DDC    Project Server    Security    agsdb    Verbose    PWA:http://portal2013/PWA, ServiceApp:Project
    Server Service Application, User:i:0#.w|*****\sharepointfarmsvc, PSI: Calling license check now; Thread.CurrentPrincipal.Identity.Name = 0#.w|*****\sharepointfarmsvc, Context.Username = i:0#.w|*****\sharepointfarmsvc, LogLevelManager Warning-ulsID:0x001920C1
    has no entities explicitly specified.    c4f9419c-7789-a0b9-3d4a-941ceb42b25f
    09/11/2013 10:31:49.19    w3wp.exe (0x3BE0)    0x0DDC    Project Server    Security    agsdc    Verbose    PWA:http://portal2013/PWA, ServiceApp:Project
    Server Service Application, User:i:0#.w|*****\sharepointfarmsvc, PSI: License check for BusinessObject method Admin.GetActiveDirectorySyncEnterpriseResourcePoolSettings2 passed - user i:0#.w|*****\sharepointfarmsvc (resuid=806f917d-85b6-e211-93ef-00155d0a5600)
    was licensed, LogLevelManager Warning-ulsID:0x001920C2 has no entities explicitly specified.    c4f9419c-7789-a0b9-3d4a-941ceb42b25f
    09/11/2013 10:31:49.19    w3wp.exe (0x3BE0)    0x0DDC    Project Server    Security    agwmc    Verbose    PWA:http://portal2013/PWA, ServiceApp:Project
    Server Service Application, User:i:0#.w|*****\sharepointfarmsvc, PSI: Access Granted for user i:0#.w|*****\sharepointfarmsvc on BusinessObject method Admin.GetActiveDirectorySyncEnterpriseResourcePoolSettings2.  CheckFarmAdmin=False, CheckGlobalPerms=True,
    LogLevelManager Warning-ulsID:0x00196302 has no entities explicitly specified.    c4f9419c-7789-a0b9-3d4a-941ceb42b25f
    09/11/2013 10:31:49.19    w3wp.exe (0x3BE0)    0x0DDC    Project Server    General    ad2n8    Verbose    PWA:http://portal2013/PWA, ServiceApp:Project
    Server Service Application, User:i:0#.w|*****\sharepointfarmsvc, PSI: Running command using non-transactioned Sql session., LogLevelManager Warning-ulsID:0x000DC362 has no entities explicitly specified.    c4f9419c-7789-a0b9-3d4a-941ceb42b25f
    09/11/2013 10:31:49.19    w3wp.exe (0x3BE0)    0x0DDC    Project Server    Administration    agmy5    Verbose    PWA:http://portal2013/PWA, ServiceApp:Project
    Server Service Application, User:i:0#.w|*****\sharepointfarmsvc, PSI: GetActiveDirectorySyncEnterpriseResourcePoolSettings2: Settings retrieved, Status=NeverRun, LastUpdateTime=01/01/0001 00:00:00, ScheduledUpdates=False, ADGroupGuidCount=0, LogLevelManager
    Warning-ulsID:0x0018C61F has no entities explicitly specified.    c4f9419c-7789-a0b9-3d4a-941ceb42b25f
    09/11/2013 10:31:49.19    w3wp.exe (0x3BE0)    0x0DDC    Project Server    Security    agsdb    Verbose    PWA:http://portal2013/PWA, ServiceApp:Project
    Server Service Application, User:i:0#.w|*****\sharepointfarmsvc, PSI: Calling license check now; Thread.CurrentPrincipal.Identity.Name = 0#.w|*****\sharepointfarmsvc, Context.Username = i:0#.w|*****\sharepointfarmsvc, LogLevelManager Warning-ulsID:0x001920C1
    has no entities explicitly specified.    c4f9419c-7789-a0b9-3d4a-941ceb42b25f
    09/11/2013 10:31:49.19    w3wp.exe (0x3BE0)    0x0DDC    Project Server    Security    agsdc    Verbose    PWA:http://portal2013/PWA, ServiceApp:Project
    Server Service Application, User:i:0#.w|*****\sharepointfarmsvc, PSI: License check for BusinessObject method Admin.ResolveActiveDirectoryGroups passed - user i:0#.w|*****\sharepointfarmsvc (resuid=806f917d-85b6-e211-93ef-00155d0a5600) was licensed, LogLevelManager
    Warning-ulsID:0x001920C2 has no entities explicitly specified.    c4f9419c-7789-a0b9-3d4a-941ceb42b25f
    09/11/2013 10:31:49.19    w3wp.exe (0x3BE0)    0x0DDC    Project Server    Security    agwmc    Verbose    PWA:http://portal2013/PWA, ServiceApp:Project
    Server Service Application, User:i:0#.w|*****\sharepointfarmsvc, PSI: Access Granted for user i:0#.w|*****\sharepointfarmsvc on BusinessObject method Admin.ResolveActiveDirectoryGroups.  CheckFarmAdmin=False, CheckGlobalPerms=True, LogLevelManager Warning-ulsID:0x00196302
    has no entities explicitly specified.    c4f9419c-7789-a0b9-3d4a-941ceb42b25f
    09/11/2013 10:31:49.19    w3wp.exe (0x3BE0)    0x0DDC    Project Server    Active Directory Sync    af8v6    Verbose    PWA:http://portal2013/PWA, ServiceApp:Project
    Server Service Application, User:i:0#.w|*****\sharepointfarmsvc, PSI: ResolveActiveDirectoryGroups; resolving encodedClaims=c:0+.w|s-1-5-21-2100168755-2748282862-3037512304-1280, LogLevelManager Warning-ulsID:0x00162560 has no entities explicitly specified.  
     c4f9419c-7789-a0b9-3d4a-941ceb42b25f
    09/11/2013 10:31:49.19    w3wp.exe (0x3BE0)    0x0DDC    Project Server    General    ad2n8    Verbose    PWA:http://portal2013/PWA, ServiceApp:Project
    Server Service Application, User:i:0#.w|*****\sharepointfarmsvc, PSI: Running command using non-transactioned Sql session., LogLevelManager Warning-ulsID:0x000DC362 has no entities explicitly specified.    c4f9419c-7789-a0b9-3d4a-941ceb42b25f
    09/11/2013 10:31:49.19    w3wp.exe (0x3BE0)    0x0DDC    Project Server    Administration    agmy5    Verbose    PWA:http://portal2013/PWA, ServiceApp:Project
    Server Service Application, User:i:0#.w|*****\sharepointfarmsvc, PSI: GetActiveDirectorySyncEnterpriseResourcePoolSettings2: Settings retrieved, Status=NeverRun, LastUpdateTime=01/01/0001 00:00:00, ScheduledUpdates=False, ADGroupGuidCount=0, LogLevelManager
    Warning-ulsID:0x0018C61F has no entities explicitly specified.    c4f9419c-7789-a0b9-3d4a-941ceb42b25f
    09/11/2013 10:31:49.19    w3wp.exe (0x3BE0)    0x0DDC    Project Server    Active Directory Sync    af8vj    Verbose    PWA:http://portal2013/PWA, ServiceApp:Project
    Server Service Application, User:i:0#.w|*****\sharepointfarmsvc, PSI: Entered ActiveDirectoryUtility::TryGetGroupInfoByClaim, LogLevelManager Warning-ulsID:0x00162549 has no entities explicitly specified.    c4f9419c-7789-a0b9-3d4a-941ceb42b25f
    09/11/2013 10:31:49.19    w3wp.exe (0x3BE0)    0x0DDC    Project Server    Active Directory Sync    alv2g    Verbose    PWA:http://portal2013/PWA, ServiceApp:Project
    Server Service Application, User:i:0#.w|*****\sharepointfarmsvc, PSI: Querying for fqdn/netbios mapping of server *****, LogLevelManager Warning-ulsID:0x002D5706 has no entities explicitly specified.    c4f9419c-7789-a0b9-3d4a-941ceb42b25f
    09/11/2013 10:31:49.20    w3wp.exe (0x3BE0)    0x0DDC    Project Server    Active Directory Sync    af8vl    Verbose    PWA:http://portal2013/PWA, ServiceApp:Project
    Server Service Application, User:i:0#.w|*****\sharepointfarmsvc, PSI: Entered ActiveDirectoryUtility::TryGetGroupInfo, LogLevelManager Warning-ulsID:0x0016254B has no entities explicitly specified.    c4f9419c-7789-a0b9-3d4a-941ceb42b25f
    09/11/2013 10:31:49.20    w3wp.exe (0x3BE0)    0x0DDC    Project Server    General    aeby8    Medium    Error is: GeneralUnhandledException. Details: General
    Unhandled Exception in _Admin.ResolveActiveDirectoryGroups_ Attributes:  System.Collections.Generic.KeyNotFoundException: The given key was not present in the dictionary.     at Microsoft.Office.Project.Server.ClaimsHelper.GetFormsAuthenticationProviderName(Uri
    context, SPUrlZone zone)     at Microsoft.Office.Project.Server.BusinessLayer.ActiveDirectoryUtility.TryGetGroupInfo(String domain, String searchPath, String searchFilter)     at Microsoft.Office.Project.Server.BusinessLayer.ActiveDirectoryUtility.TryGetGroupInfoByClaim(String
    encodedClaim)     at System.Linq.Enumerable.WhereSelectArrayIterator`2.MoveNext()     at System.Linq.Buffer`1..ctor(IEnumerable`1 source)     at System.Linq.Enumerable.ToArray[TSource](IEnumerable`1
    source)     at Microsoft.Office.Project.Server.Wcf.Implementation.PWAImpl.<>c__DisplayClass10a.<AdminResolveActiveDirectoryGroups>b__109()     at Microsoft.Office.Project.Server.Wcf.Implementation.WcfMethodInvocation.InvokeBusinessObjectMethod(String
    businessObjectName, String methodName, IEnumerable`1 actions)  . Standard Information: PSI Entry Point:  Project User: i:0#.w|*****\sharepointfarmsvc Correlation Id: da702be3-ee1a-e311-93f8-00155d0a5600 PWA Site URL: http://portal2013/PWA SA Name:
    Project Server Service Application PSError: GeneralUnhandledException (42), LogLevelManager Warning-ulsID:0x00101622 has no entities explicitly specified.    c4f9419c-7789-a0b9-3d4a-941ceb42b25f

  • Project Server 2010 - Active Directory Enterprise Resource Pool Synchronization limitations

    Greetings again.
    I have a quick question about the limitations of Active Directory Enterprise Resource Pool Synchronization.  Specifically, what has your experience
    been with extremely large numbers of users (10k plus).  Is anyone aware of a
    practical limit of users in your AD group you would recommend when using the
    Schedule Synchronization feature on a nightly or weekly basis?
    There is a caveat to this question however.  The client has decided (perhaps for some misinformed reasons) to allow access for every user, to every
    project site, within their PWA environment.  They’ve selected the View Project Site option within the
    Categories for the Team Members PWA Group for which 90% of their intended users reside.  So when we ran a couple test syncs in DEV with a smaller AD group of about 8,000 users, the sync understandably
    lasted upwards of 18 hours.  Obviously unacceptable for a PROD environment on a nightly basis and not necessarily ideal for a weekly sync either.
    Experience in addition to documents like these, “Best
    practices for managing a large number of resources in Project Server 2010” tell me that we are way over the practical limit of a scheduled resource pool synchronization...IF
    the client really desires that all users access all their sites.  But before I submit my recommendations, I wanted to check with the community just in case others may have found a way to synchronize large numbers of users (10k plus) on a nightly or weekly
    basis, within a reasonable time frame AND allowed all users to access all sites within PWA.
    What do you think?
    As always, thanks for your help.
    Chris Addis - MCTS

    Hello Hrishi.
    My delayed response has been due to a large amount of testing we have been performing on this particular topic.  Here is an update, please feel free to provide feedback.
    We went back to testing and spent more time reviewing the documents: 
    Best practices for managing a large number of resources in Project Server 2010 and
    SharePoint Server 2010 capacity management: Software boundaries and limits.  Our team interpreted those documents as saying, 1,000 security
    scopes per site is a recommended limit.  It does not say it’s a hard limit, just a recommended limit.  “When the recommended unique security scope boundaries are exceeded, performance issue can occur.”
    So we decided to perform some tests (31 in total) to try and get a gage of what we are seeing.
    We needed to establish a baseline first.  So we performed a series of 23 Active Directory Resource Pool Synchronizations with various settings in a clean, Out of the Box, environment in order to see some consistent numbers.  Here is it’s summary:
    Our AD group of 8,000 users took about 32 minutes, on average, every time to sync.  The difference between the first sync and last sync differed only by 1-3 minutes.
    Adding 40 project sites increased the average sync time from 32 to 120 minutes.
    Adding 100 users to each of those 40 project sites, did not increase the sync times.
    One setting (identified at this time) reduced the synchronization time.  It was the
    Project Site Permissions check box found within the Project Web App > Server Settings > Project Site Provisioning Settings area.  By deselecting this check box we reduced or synchronization time back to the 32 minute
    average.
    The View Project Site check box within the Project Web App > Server Settings > Manage Groups > Team Members group had no apparent effect on the sync times besides what we had gleaned from the Microsoft documentation.
    Naturally, this left us with a problem.  As I’m sure you know, by deselecting the check box (Project Site Permissions), our project sites are now (figuratively speaking) orphans with no connection to the parent site.  This generates
    a new set of issues.  For example:
    Newly created project sites cannot be accessed by the owner and team members.  They will require someone like the farm admin to come in behind them and add the intended users to the project site along with their required permissions.
    All current and futures sites will no longer have users added via the standard method of building a team and publishing the project, but will have to be added manually.
    You can use the Synchronize option found within Project Web App > Server Settings > Project Sites page, but that kinda defeats the purpose.  It would require constant updating on a per site basis to keep up with
    PM changes.  Not very sensible, but it does work.
    With this baseline information, we moved our tests into our DEV environment which somewhat mimics our PROD environment.  This environment has 352 project sites and we performed 8 tests.  This is where we had some large sync time numbers. 
    Here is the DEV test summary:
    With the Project Site Permissions check box cleared, our AD group of 8,000 users took on average 30 minutes to sync.  This was in line with our baseline times.  With the exception of one test sync that took 99 minutes to complete. 
    That anomaly is acquiescent with what I’ve seen over the years.  Sometimes syncs do some unusual things.
    With the Project Site Permissions check box selected, our AD group of 8,000 users took on average 690 minutes (11.5 hours) to sync.  Unacceptable of course.
    So here’s what we’ve learned when dealing with extremely large numbers of active directory users in your Resource Pool sync:
    We did not see a decrease in subsequent sync times after the initial Active Directory Resource Pool Synchronization as some might expect.
    Our attempt to decrease sync time via the option of removing the View Project Sites was not successful.  (Unless we interpreted Microsoft's document incorrectly.)
    However, our interpretation of the recommended software boundaries and limits of SharePoint Server 2010 as it pertains to security scopes per site at 1,000, appears to be correct.
    Using the option of clearing the Project Site Permissions does produce a reduction in AD sync time, but at a cost segregating your project sites and thus the creation of new processes of maintaining them.
    I’ll remind others that these results are particular to our environments, there may still be exceptions yet to discover.  Others may see numbers contrary to ours.
    The biggest surprise to some members on our team (myself excluded) was that we did not see a reduced sync time after any of our initial syncs.  Some are under the impression that after your initial sync, you should see reduced sync times.  I haven’t
    found that to be the absolute case in all situations, just in some situations.  The reason for this still eludes me.  Any thoughts would be appreciated.
    I’ll let this sit a bit longer, but if no one disagrees with the results, I think we have our answer:
    The number of project sites directly affects your Active Directory Resource Pool Synchronizations if you are using the
    Project Site Permissions option.  If you plan on synchronizing over 1,000 users
    and you have a large number of project sites, proceed with the knowledge that you may have performance issues and long sync times.
    As always, I’d love to hear from you or others just in case I’m missing something.
    Chris Addis - MCTS

  • Resource Center - Need to change a Local Resource to an Enterprise Resource

    The Resource Record for a resource was accidently deleted.  This resource was still assigned to active project tasks at the time of the delete.  A new Resource Record was created but it has the resource as a Local Resource.  How can I move
    this resource back to the Enterprise Resource Pool?
    As a Local Resource the Assignment Owner field on his assigned tasks are not populating, so he cannot see any tasks on his timesheets.  Also, the resource cannot be assigned to any new project tasks because he cannot be added to the Project Enterprise
    Pool.
    Attempted to remove the Resource Record that was created using Delete Enterprise Objects -> Resources and Users but since the resource is Local and not Enterprise his record is not showing to select it for delete.
    Would the Admin Restore->Enterprise Resource Pool and Calendars functionality put his original record back in place?  I understand only one version of this backup is kept but that should be the version we currently have.  What data might be
    lost using this functionality?  Any chance other users would be adversely impacted?
    We are using Project Pro 2010

    Hi Dennykat,
    As mentionned in your previous post, restoring the resource pool should work, since it is restoring resources with their metadata and with the exact same UID. Thus the deleted and restored enterprise resource should have everything back (assignments, timesheets...).
    Since I never tested such as process, I strongly advice to test it in the dev environment on a simple test case.
    I remember that if also adviced you to recreate the enterprise resource and type in the resource sheet on one of the resource's project the exact enterprise resource name (exact same syntax), so Project should ask you when saving if you want to replace the
    local resource by the enterprise one. Can you confirm that it didn't work?
    Hope this helps.
    Guillaume Rouyre - MBA, MCP, MCTS

  • How Many Enterprise Resources Can Be Checked-Out at Any One Time?

    Hi Folks,
    Using Project Server Online, I am trying to select and edit a resource pool containing approximately 1200 enterprise resources in MS Project Professional 2013.  I can open a few at a time, but when I "select all" it does not do anything. 
    Is there a limit on how many enterprise resources we can check out at a time?
    Thanks in advance,
    \Spiro Theopoulos PMP, MCITP. Montreal, QC (Canada)

    OK..I was able to edit 495 resources at a given time. The moment I click 496th resource, nothing happens when I click the Open in Project button.
    So, to Dale's point, there seems to be some kind of limit on the number of resources that can be edited at any given time, but what's puzzling is that the limit seems to be different for every tenant.
    I will try and find more information, but at this point, the solution is something you already know. Edit few resources at a time.
    Cheers,
    Prasanna Adavi, Project MVP
    Blog:
      Podcast:
       Twitter:   
    LinkedIn:
      

  • The replay of the song isn't possible because the song isn't available or through DRM is restricted. All the songs are buyed in the iTunes Store. Give it a solution to activate the songs on my ipod touch ?

    Hello together, I've a problem with some songs in my playlists on my new ipod touch. The error message says that the replay of the song isn't possible because the song isn't available or through DRM is restricted. All the songs are buyed in the iTunes Store. Give it a solution to activate the songs on my ipod touch ?

    Do the non-syncing songs play in iTunes?
    Were the syncing and non-syncing songs purchased with the same account?
    Can you directly download the the songs to the iPod? See:
    Downloading past purchases from the App Store, iBookstore, and iTunes Store

  • I just bought the new ipod touch, but when I try to sync it I get told to use the cloud and download from there.  How do I sync it to my itunes so that I get all my songs without going through cloud? Otherwise if this isn't possible I am taking this back!

    I just bought the new ipod touch, but when I try to sync it I get told to use the cloud and download from there.  How do I sync it to my itunes so that I get all my songs without going through cloud? Otherwise if this isn't possible I am taking this back!

    Thanks for no help... but for anyone else, turn off itunes match on the ipod

  • I am getting the below mentioned error in the weblogic console.  Jun 26, 2014 12:14:45 PM IST Error javax.enterprise.resource.webcontainer.jsf.application BEA-000000

    Hi,
    After migrating to Spring webflow 2.4.0 , I am getting the below mentioned error in the weblogic console.
    <Jun 26, 2014 12:14:45 PM IST> <Error> <javax.enterprise.resource.webcontainer.jsf.application> <BEA-000000> <Unable to determine expected return type for java.util.List()>.
    It doesn't affect  the application but not able to find the cause for it.
    Regards,
    Sneha

    After many hard working days.i finally found the error cause,i needed to make weblogic datasource also ADF doesnt work on internet explorer browser,it works on safary.hope it helps somebody

  • Project Templates with Enterprise Resources

    I'm using Project Server 2013 ( latets updates installed for both Client and Server)
    I've created a project template and attached this to a project type. My template has enterprise resources speciified. So far so good.
    Now I'm trying to create a project using this template and I'm getting some errors.  (See below)
    As soon as I remove the resources from my template the project creates fine.
    It looks like 'rsResourceCannotAddLocalWithSameNameAsEnterprise'  in the error below means that Project Server looks at the resource in the template and considers the resources in the template always to be a local resources. And of
    course the resource already exists in my enterprise resources and therefore the project creation fails.
    Datasets:
    ProjectDataSet
    Table ProjectResource
    Row:  RES_UID='0bb2c5b5-1716-e311-a1c1-005056992257' PROJ_UID='3121855b-f13b-e311-9f7f-005056991b52'
    Error rsResourceCannotAddLocalWithSameNameAsEnterprise (2058) - column
    RES_UID
    General
    Queue:
    GeneralQueueJobFailed (26000) - ProjectCreate.ProjectAddToMessage. Details: id='26000' name='GeneralQueueJobFailed' uid='353d845c-f13b-e311-9f7f-005056991b52' JobUID='3a21855b-f13b-e311-9f7f-005056991b52' ComputerName='13fdabbe-0ac0-4cca-b382-49d1853aec73'
    GroupType='ProjectCreate' MessageType='ProjectAddToMessage' MessageId='1' Stage='' CorrelationUID='147f4f9c-ae30-b04b-aec7-382a52fa5fdf'. For more details, check the ULS logs on machine
    13fdabbe-0ac0-4cca-b382-49d1853aec73 for entries with JobUID
    3a21855b-f13b-e311-9f7f-005056991b52.
    My questions are:
    Are Enterprise Resources in templates supported?
    Is there a way around this? We're trying to make it easy to select a subset of the enterprise resources available.

    I have experienced this exact same thing and my situation is highly irregular. 
    This is with Project Server 2013.
    I had an EPT with a Project Schedule that had Generic Enterprise Resources assigned and was able to create new projects without problems using the EPT from the New button in the Project Centre in PWA.
    I was creating new projects to test and demonstrate Portfolio Analysis and was able to model Organisational Capacity represented by my Generic Resources and also the Surplus/Deficit element of Resource Constraints on a Portfolio. The Hired Resource Report
    was failing.
    A Service Pack and Cumulative update were applied to the Server and now I cannot create new projects using EPTs that have a project schedule with Generic Enterprise Resources assigned to tasks in the schedule.
    I checked the error message for the Failed and Blocking job in the queue and the GUIDs were for my Generic Enterprise Resources. I deleted the offending Generic Enterprise Resources and then re-created them anew, edited the Project Template to have
    these Generic Enterprise Resources on the Project Team and randomly assigned them to tasks in the schedule to generate a notional demand for work in the Project Template. I then Saved the Template in Project as a new Project Template and edited my EPT
    to reference this new Project Schedule. 
    Same error encountered again.
    Perversely I can open the Template schedule in Project Professional and do Save As and save it as a new project to the Server and that works just fine - the schedule is visible in the Project Centre and I can edit the schedule in both Project Pro and in
    PWA.
    My hunch is that the Cumulative Update and Service Pack which were applied to try and resolve the failing "Hired Resources Report" in Portfolio Analysis, which sadly it didn't resolve - has probably provoked this interesting challenge as it is
    the only material thing to change on the Server during the time that this issue has manifested itself.
    Am I the only one to encounter this?
    Dominic Moss | MAPM Microsoft Certified Technology Specialist | Our Newsletter:
    PM News Project Server Specialists
    Project Server PRIME | Twitter:
    @Twitter | Facebook:
    @Facebook | Linkedin:
    Wellingtone

  • Project Server 2013 AD Enterprise Resource Pool Synchronization Exception

    Hello,
    I am looking for assistance from the project server community.
    When I click “Save and Synchronize” on the Active Directory Enterprise Resource Pool Synchronization page nothing happens and the status does not change.
    This is a new instance of PWA and I am preforming this task using the farm admin account. The farm admin account can read AD.
    Error 1:
    w3wp.exe (0x1B98) 
    0x0B8C       Project Server              
    General      aeby7         
    Exception [bucketHash:F08803DE] Exception occured in method 'Admin.ResolveActiveDirectoryGroups' System.Collections.Generic.KeyNotFoundException: The given key was not present in the dictionary.    
    at Microsoft.Office.Project.Server.ClaimsHelper.GetFormsAuthenticationProviderName(Uri context, SPUrlZone zone)    
    at Microsoft.Office.Project.Server.BusinessLayer.ActiveDirectoryUtility.TryGetGroupInfo(String searchRoot)    
    at System.Linq.Enumerable.WhereSelectArrayIterator`2.MoveNext()    
    at System.Linq.Buffer`1..ctor(IEnumerable`1 source)    
    at System.Linq.Enumerable.ToArray[TSource](IEnumerable`1 source)    
    at Microsoft.Office.Project.Server.Wcf.Implementation.PWAImpl.<>c__DisplayClassf2.<AdminResolveActiveDirectoryGroups>b__f1()    
    at Microsoft.Office.Project.Server.Wcf.Implementation.WcfMethodInvocation.InvokeBusinessObjectMethod(String businessObjectName, String methodName, IEnumerable`1 actions) StackTrace: 
    at Microsoft.Office.Project.Server.Native.dll: (sig=[sig]|2|microsoft.office.project.server.native.pdb, offset=3C1E) at Microsoft.Office.Project.Server.Native.dll: (offset=1254D)                       
    d360539c-6d89-70e7-c077-92da686b0689
    Error 2:
    Error is: GeneralUnhandledException. Details: General Unhandled Exception in _Admin.ResolveActiveDirectoryGroups_ Attributes: 
    System.Collections.Generic.KeyNotFoundException: The given key was not present in the dictionary.   
     at Microsoft.Office.Project.Server.ClaimsHelper.GetFormsAuthenticationProviderName(Uri context, SPUrlZone zone)   
     at Microsoft.Office.Project.Server.BusinessLayer.ActiveDirectoryUtility.TryGetGroupInfo(String searchRoot)   
     at System.Linq.Enumerable.WhereSelectArrayIterator`2.MoveNext()   
     at System.Linq.Buffer`1..ctor(IEnumerable`1 source)   
     at System.Linq.Enumerable.ToArray[TSource](IEnumerable`1 source)   
     at Microsoft.Office.Project.Server.Wcf.Implementation.PWAImpl.<>c__DisplayClassf2.<AdminResolveActiveDirectoryGroups>b__f1()   
     at Microsoft.Office.Project.Server.Wcf.Implementation.WcfMethodInvocation.InvokeBusinessObjectMethod(String businessObjectName, String methodName,
    IEnumerable`1 actions)  . Standard Information: PSI Entry Point: 
    Project User: i:0#.w|[DOMAIN\UserID] Correlation Id: f1f1a77f-6b45-e311-9407-00155d2abe21 PWA Site URL: [PWA URL] SA Name: Project Server Service Application PSError: GeneralUnhandledException (42), LogLevelManager Warning-ulsID:0x00101622 has no entities
    explicitly specified.

    Hi,
    I also get the same error when I'm trying to do the synchronization between Enterprise Resource Pool and Active Directory.
    I am in a single domain topology between Project Server 2013 and AD, and I'm doning the synchronization with the farm admin account, who has read/write access to AD.
    Here are the last relevant messages I see:
    w3wp.exe (0x2BE8) 0x1568 Project Server General aeby7 Exception
    [bucketHash:F0FACBDF] Exception occured in method 'Admin.ResolveActiveDirectoryGroups' System.Collections.Generic.KeyNotFoundException: The given key was not present in the dictionary.
    at Microsoft.Office.Project.Server.ClaimsHelper.GetFormsAuthenticationProviderName(Uri context, SPUrlZone zone)
    at Microsoft.Office.Project.Server.BusinessLayer.ActiveDirectoryUtility.TryGetGroupInfo(String domain, String searchPath, String searchFilter)
    at Microsoft.Office.Project.Server.BusinessLayer.ActiveDirectoryUtility.TryGetGroupInfoByClaim(String encodedClaim)
    at System.Linq.Enumerable.WhereSelectArrayIterator`2.MoveNext()
    at System.Linq.Buffer`1..ctor(IEnumerable`1 source)
    at System.Linq.Enumerable.ToArray[TSource](IEnumerable`1 source)
    at Microsoft.Office.Project.Server.Wcf.Implementation.PWAImpl.<>c__DisplayClass10a.<AdminResolveActiveDirectoryGroups>b__109()
    at Microsoft.Office.Project.Server.Wcf.Implementation.WcfMethodInvocation.InvokeBusinessObjectMethod(String businessObjectName, String methodName, IEnumerable`1 actions) StackTrace:
    2b3d83ee10e5|2|, microsoft.office.project.server.native.pdb, offset=3C1E)
    at Microsoft.Office.Project.Server.Native.dll: (offset=1255D)
    w3wp.exe (0x2BE8) 0x1568 Project Server Unified Logging Service c91s Monitorable
    Watson bucket parameters: Microsoft Project Server 2013, ULSException14, 070f6ea0 "project server",  0f001181 "15.0.4481.0", 6962a0f6 "microsoft.office.project.server.administration", 0f0011ad "15.0.4525.0", 51ade0c4 "tue jun 04 14:42:44 2013",  0000020f
    "0000020f",  0000003b "0000003b",  0560164b "keynotfoundexception", 00101621 "aeby7"
     w3wp.exe (0x2BE8) 0x1568 Project Server General aeby8 Medium
    Error is: GeneralUnhandledException. Details: General Unhandled Exception in _Admin.ResolveActiveDirectoryGroups_ Attributes:  System.Collections.Generic.KeyNotFoundException: The given key was not present in the dictionary.
    at Microsoft.Office.Project.Server.ClaimsHelper.GetFormsAuthenticationProviderName(Uri context, SPUrlZone zone)
    at Microsoft.Office.Project.Server.BusinessLayer.ActiveDirectoryUtility.TryGetGroupInfo(String domain,  String searchPath, String searchFilter)
    at Microsoft.Office.Project.Server.BusinessLayer.ActiveDirectoryUtility.TryGetGroupInfoByClaim(String encodedClaim)
    at System.Linq.Enumerable.WhereSelectArrayIterator`2.MoveNext()     at System.Linq.Buffer`1..ctor(IEnumerable`1 source)
    at System.Linq.Enumerable.ToArray[TSource](IEnumerable`1 source)
    at Microsoft.Office.Project.Server.Wcf.Implementation.PWAImpl.<>c__DisplayClass10a.<AdminResolveActiveDirectoryGroups>b__109()
    at Microsoft.Office.Project.Server.Wcf.Implementation.WcfMethodInvocation.InvokeBusinessObjectMethod(String businessObjectName, String methodName, IEnumerable`1 actions)  . Standard Information: PSI Entry Point:  Project User: LUXAIRLG\SQLADMIN2012
    Correlation Id: 6cef3814-b3a2-e311-93f9-005056921080 PWA Site URL: xxx SA Name: PS2013 - Project Server Service Application PSError: GeneralUnhandledException (42). LogLevelManager Warning-ulsID:0x00101622 has no entities explicitly specified.
    w3wp.exe (0x2BE8) 0x1568 Project Server Project Web App af04k Medium
    Void SaveButtonClick(System.Object.System.Web.UI.WebControls.CommandEventArgs) : GeneralUnhandledException
    Any ideas?
    Thanks in advance

  • Filter Enterprise Resources Dialog Box

    Hello,
    Today, after create new Enterprise Resource (Actually we have 2004 Enterprise Resource) when I try to add Resource in Project Professional 2010 using Build Team from Enterprise... show me a Dialog Box named "Filter Enterprise Resource" for to filter
    the resource. My question is if exist a way for this dialog box not show me and show me directly the window Build Team for "Project" 
    Thanks for your answers

    Christian --
    Microsoft Project Professional 2010 displays the Filter Enterprise Resource dialog automatically when you have 1,000 or more resources in your Enterprise Resource Pool.  There is no way to force the system NOT to show it.  I would recommend that
    you explain to your PMs why they are seeing the dialog, and then recommend that they simply click the OK button to proceed unless they actually want to filter.  After a while, they will get used to seeing this dialog.  Hope this helps.
    Dale A. Howard [MVP]

  • Using Enterprise Resources

    Hi,
      Normally when we add Users as enterprise resources in the project server. Project manager would be able to add the users in project plan after which the user would be able to access PWA to enter time.
      My question is does microsoft project server 2007 has an option where I want to add the user as Enterprise resource but not let the resource log into pwa and enter efforts.Idea is to have resources as enterprise resources in Project plan. Do we have
    any option in Project server to do this. Please advise
    Thanks
    MP

    Hi,
    A resource which is only a resource and not a user (meaning with no valid AD account) cannot log in any way to Project Server (including PWA) thus cannot use any feature like timesheet or project site. 
    Project Server 2010 introduced a feature called "delegation" which allows a user submitting
    a timesheet (or doing any other operation) on behalf of another user. The restriction is that it applies only to users and not resources with no valid account.
    Finally, to do waht you want to do, I'd suggest to use the assignment owner column in MS Project Pro. If a task is assigned to a resource (and not a user), it will not be able to create and submit a timesheet, neither his manager to act of his behalf. But
    if the manager enters his name for the assignment in the assignment owner column in MS Project Pro and publishes the project plan, then he'll receive the assignment in his own timesheet. This feature allows giving a status update and/or asubmitting timesheet
    on behalf of someone who cannot do it for any reason, like for a customer who does not have a CAL (licence).
    Hope this helps,
    Guillaume Rouyre, MBA, MVP, MCP |