Error during variance calculation for production order "NO cost estimate "

hi all,
I'm gettin this error message while trying to calculate the variance for a production order. error is "No cost estimate for material xxxx for 01.10.2008.
when i look at material xxx in MM02, under cost estimate for current period there is a value but nothing for previous period. So i'm guessing the the Cost estimate was not run of this material? am i correct here?
Now if i try to run cost estimate for material for the missing periods using CK11N, i get an error "cannot save for past period"
Could some one tell me how can i get a prior year estimate into the material master?
I tried CK40N and CKN1 but just cant get it to work...
Thanks heaps

Hi Tom
unfortunately there is no easy way to get a product cost estimate for a past date. One of the reasons for this would be inconsistant product valuation.
You could in theory create a cost estimate in a current date and use an ABAP or manually adjust the valid from and to dates directly in the tables (e.g. KEKO). To do this in a production environment would be restrictive off course.
The standard cost estimate is the basis for the target costs so as an alternative you could look to change the configuration of the target cost version in OKV6 to either of the following:
- Plan Cost/Preliminary Costing (that is the plan calc done on your production order)
- Alternative Material Cost Estimate (one that is not necessarily a product costing that is set for marking and release).
I hope this is of some help.
Elaine

Similar Messages

  • Variance calculation for production order with settlement receiver as SDI

    Hi...
    I have one query reference to Variance calculation for production order with settlement receiver as SDI(Sales document item).
    I am working on Varaint configuration with strategy 25(Make-to-order for configurable material) with requirement class 046.
    I have created sales order ref. to configurable material,subsequently created planned order & then converted to production order.
    In production order settlement receiver is SDI(Sales document item).
    While doing production confirmation ,variance has been created.
    Now during variance calculation KKS2, I have got error message as no suitable settlement rule found for object Order no.
    Is there any way to come out of this?Or variance calculation KKS2 is not applicable with settlement receiver as SDI(Sales document item).
    Pl. guide
    Redards
    Tushar

    Hi
    In case of non valuated material, concept of variance does not apply...
    Variance is Actual Cost - Cost of Goods receipt posted in stock.. If the later value is zero, your entire actual cost is variance... That is one way of saying it
    But, in SAP, var not calculated in case of non valuated material and that makes sense as well.. Since you are in MTO scenario, it would make sense to analyse costs vs revenues @ sale order level as each SO will be unique in itself
    Regards
    Ajay M

  • Variance calculation for production order

    Hello,
    I am clarifying what's the selection criteria for settled production orders so that we can carry out the following
    close and deletion flag activities.
    I am currently in release ECC605. Need to carify the below questions.
    1. For production order without header material (dismantle production order), no need to do variance calculation before
    settlement,right? Because I found system will respond green light but "no order was processed", this kind of production order
    won't possess "VCAL variance calcaulted" system status.
    2. For all production orders created with header material, vairance calculation is a must, even the variance is 0.
    So the production orders  will possess "VCAL" status after variance calculation transaction is done.
    Thanks for your help in advance.
    B. Regards,
    Nancy

    How does input variance and output varia.nce will be calculated on the settlement of production order after TECO.
    VARIANCE CALCULATION DEPENDS ON CONFIGURATION IN THE FOLLOWING AREAS,
    1) VARIANCE VARIANT -  DETERMINES WHAT VAREIANCE CATEGORIES ARE CALCULATED, E.G MATERIAL PRICE , USAGE, LABOUR RATE , USAGE VARIANCE ETC..
    2) TARGET COST VERSIONS
    3) VALUATION VARIANT FOR WIP  AND SCRAP
    Can we check in KOB3 or COOIS.
    KOB3 -  YES
    COOIS -  CHECK IN COST REPORT

  • Error during Goods Receipt for Production Order

    Hi All,
    When using MIGO to post Goods Receipt for a Production Order, I got a customize message saying that the posting is only available between 2010.08.25 to 2010.08.27.  I have checked in Business Add-in using SE19 but there are no implementation present.  I know that in Logistic Verification MIRO there is a transaction OMRM to set messages.  I would like to ask is there anything similar for MIGO.  
    Or is there any other place in Configuration which allows me to add these Customize message.
    Thanks.
    Edited by: jamison2004 jordan2004 on Jul 9, 2010 9:09 AM

    Hello Jiaul,
    Sorry I may have mislead you.  The actual error message is "Goods Receipt for Production Order XXXX can only be made on 2010.08.25 to 2010.08.27".  These two dates are the Start Date and FInish Date for the Production Order in CO03, 
    The Basic Start Date for the current Production Order is  2010.08.25
    The Basic Finish Date for the current Production Order is 2010.08.27
    I think what it means is that you can only Post Goods Receipt for the Production Order only after the Basic Start Date of the Production Order.  Do you know where I can find the configuration for this message?
    Thanks

  • Actual activity price calculation for production order

    Hi
    Can any one guide me in how many ways we can assign actual activity price calculation for production order?
    I knew only one way by assigning PPP2 costing variant?
    I have another doubt is: if we don't mention any material valuation indicator (moving average, standard) in valuation variant, how system will calculate material prices? is there any other way, to recognize the prices by system?
    regards,
    Ramesh B

    Dear,
    Costing variant PPP2 is linked to some valuation variant inn OPL1
    System will check the valuation of material and activity according to this valuation variant
    For material valuation there are many stg acceding to which system will take the price the raw material,
    Valuation strategy for material component
    Strategy sequence that determines the valuation of the materials used in the cost estimate.
    Use
    The materials are valuated using the price in the material master record or the values calculated in a material cost estimate.
    Procedure
    You can enter a single strategy, or you can enter multiple strategies in the form of a strategy sequence. If you enter multiple strategies, the priority of the strategy determines what price or what values are selected.
    Examples
    Assume that the following strategy sequence is entered for material valuation:
    1. Planned price 1
    2. Standard price
    3. Moving average price
    If the system finds a value in the Planned price 1 field (costing view), this value is taken as the value for valuating the material.
    If the system does not find a value, the value in the Standard price field (accounting view) is used.
    If the material does not have a standard price, the system uses the value from the Moving average price field.
    if you have not mentioned, then system will give error that "valuation stg not found"
    Valuation strategy for internal activities and processes-
    Strategy sequence that determines how internal activities and processes are valuated in costing.
    Use
    The activities and business processes used are valuated with the prices from Cost Center Accounting or Activity-Based Costing to determine the production costs or process costs. The prices can either be calculated iteratively through price calculation, or entered manually by the user.
    Procedure
    You can enter either a single strategy or more than one strategy in the form of a strategy sequence. If you enter more than one strategy, the priority of the strategy determines which price is selected.
    Examples
    The following strategy sequence is entered:
    1. Actual price of the previous period
    2. Plan price of the previous period
    3. The most current plan price
    If the system finds a price for the activity type, this price is used for valuating the internal activities. If no price was calculated for the previous period, the plan price from the previous period is used to valuate the activity type.
    If the system cannot find a plan price for the previous period, it looks for a future plan price, using the next price in the posting period to valuate the internal activities. For example, if plan prices have been entered for periods 2 and 3, and a plan price is calculated in period 1 for period 4, the system uses the price from period 3 in accordance with the valuation strategy Most up-to-date plan price.
    Again if you have not mentioned, then system will give error that "valuation stg not found".
    You can use any costing variant for actual (PPP2)and planned(PPP1) according to your requirement.. check in OPL1

  • In DP50 Error during material determination for service order

    Hi,
    While doing Resources-Related Billing request,the following error is displaying..
    Kindly Help
    Error during material determination for service order
    Message no. AD01156
    Diagnosis
    An error occured during material determination for a dynamic item.
    System Response
    The system cannot perform the function.
    Procedure
    Check in the profile being used whether its characteristic allows the assignment of a material to each dynamic item.
    501384
    Message no. AD01156
    Diagnosis
    An error occured during material determination for a dynamic item.
    System Response
    The system cannot perform the function.
    Procedure
    Check in the profile being used whether its characteristic allows the assignment of a material to each dynamic item.
    Thanks,
    Mohit

    Hi mohit,
    You need to check DIP profile setting if profile is attached to your order type or not please check this
    Thanks and regards
    Sachin Kadam

  • Error in cost calculation for production order

    Dear All,
    I got error of cost calculation while release of Production Order due to price of some material is not mantain .
    What will happen if I release , save the Order with error & do Good Issue ???
    Ishwar

    Dear Ishwar,
    Check the log's created for costing and rectify the same.
    I feel its better to rectify the cost related errors and then release the production order and proceed to Good's Issue.
    Check whether there is a MAP for all the Raw-materials and an origin group in costing 1 view.
    The Finished product must be having a standard cost estimate that's valid for the current period.
    Revert back in case of any more help needed.
    Regards
    Mangalraj.S

  • Error in scheduling parameters for production orders

    Hi Guys,
    Greeting for the day u2026u2026u2026.
    I am trying to create production orders creation for own order  type ex MM01, but I am getting error message as u201C scheduling parameters are not defined for the order type u201C even though I have maintained following parameters as below,
    Production scheduler      -
    xxxxx,
    Detailed scheduling -
    check box of scheduling ticked,
    Rough cut scheduling    --- scheduling id u201301, scheduling and generate capa requi,, boxes     ticked,
    Adjust scheduling  -- requi to operation  date,
    Scheduling control for detailed scheduling ---backwards and check box of auto scheduling ticked
    Operation segment ---setup,
    All operation in order will be reduce
    Do not reduce,
    Could any one light on this issue,
    Thanks in advance,
    Mohan

    Hi,
      This error will come if you have not maintained Define scheduling parameters for production orders.
    Check this order type whether linked with respective plant in OPU3.*And give production scheduler * mark ie, all.*
    And in Define production scheduling profile - OPKP, link your order type in the page below.
    In material master work scheduling view, input production sch profile or prod scheduler.
    Regards,
    Dharma

  • Error when doing GR for production order with serial number

    I'm not familiar with serial number and equipment management but I'm trying to help my user resolve this issue.
    This product is returned from customer site.
    I saw that this material is being reset in IQ02 from status in warehouse to become Available when the material is consumed in the production order via 261 movement type. So now the status is available. Then the user went to change a new serial number. Later, GR for production order is done in MB31. Errors are encountered when prompted to enter the new serial number.
    Configurations XX01 and XX02 are different
    Message no. CX126
    Configuration of serial number SN02 incompatible with document item
    Message no. IO226

    Hi..
    Can you please explain in detail, I facing same problem, while assigning unrestricted stock to sales order.
    Regards,
    Sumit Pukale

  • Standard table for production order settlement cost

    Hello,
    Is there any standard table available which carries the production order settlement cost?

    Dear,
    Once you do Production order settlement using T.Code KO88.
    You will find all relevant tables once RKACSHOW is executed for the corresponding object .
    Try the table is COEP
    Thanks,
    MS

  • Variance Calculation for Prod order

    Deal All
    I have problem when run prod order variance calculation (KKS2) for period 8 why the order for period 9 is also calculated ?
    why this happen ?
    Thanks and regards

    Hi Aditya
    The program is designed in a way that all open prod orders are considered in it.. however, variance will not be calculated on it
    For eg: You calculate Var in 009 for period 008.. Prod order created in fag end of 008 and processing started in 009... During var cal, system will give an error for this prod order saying "Only rem variances can be calculated for it" or some error of that sort
    you can ignore this error... I got a note released from SAP for this error.... however, that note is under reconstruction now and hence not available
    You can raise an OSS msg mentioning note no 1320759 and ask them when it will be available again
    Regards
    Ajay M

  • Run time error while running BDC for production order creation and confirmation:

    Dear Gurus,
    We have a situation, where the users are trying to do the entries creation of order or confirmation (through manual and BDC). But, if there is any kind of a deficit quantities in consumption or GR quantity, then it is going to run time error and Dumps are coming in program SAPLCORB
    and the transaction code is coming for CO11N.
    How to avoid this error to run the production system in smoothing way...Any flash lights on this will be great full
    Regards,
    Madhu.G

    Hi Madhu,
    Expert Caetano has rightly point out. Refer Note 1840705 - RAISE_EXCEPTION short dump if running CO11N in background
    Cause
    The short dump is triggered because SAP transaction CO11N contains new GUI elements that cannot always be dealt with in a background process,
    such as the confirmation texts.
    Resolution
    SAP recommends that the standard production order BAPIs, such as BAPI_PRODORDCONF_CREATE_TT, should be used to post a confirmation in background.
    If this is not feasible, the following workaround may be uses:
    Define a confirmation profile in transaction OPK0; 
    In the detail areas, remove the area "Confirmation text"; 
    Set this profile as standard, so that it is chosen automatically by the system when a batch-job
    is started; 
    Assign this confirmation profile to the batch user with transaction SU3 using parameter CORUPROF.
    Also see Note 429432 - CO11N: Batch input in background dumps if long text is maintained
    Refer to note 1154692 - Endless loop during confirmation in background if you doing Auto GR during confirmations
    Thanks & Regards,
    Ramagiri

  • Avoid variance calculation on product order

    Hi experts,
    i have a question. We have a material with cost estimate with quantity structure, cost estimate is release. All cost components in cost component structure are in inventory valuation. On the product order are then target costs. When material is producing, one component of BOM (cost element XXX) is not consumption on product order. When i start variance calculation, SAP calculate variance to this one component (cost element XXX) and by settlemnet of order, posting variance to FI. But this thing i don´t want. It is possible prohibit calculation of variance for this component of BOM - cost element XXX on product order? It is possible prohibit settlement this variance to FI? What i can do for it?
    Thanks a lot,
    Gustavo

    Hi,
    i must settlement product order, so i need variance calculation. So can i settlement variances to FI only for some components of BOM and one variances of one component leave on procuct order? Or can i settlement variances of one component of BOM to other cost centrum than others components (alternatively under other cost elements)? Maybe substition.... If yes, how?
    Thanks a lot,
    Gustavo

  • Error During Confirmation Reversal of production Order

    Dear experts
    In production client during confirmation reversal for ,we are getting below error message
    Enter only true account assignment.
    Regards
    sandeep Patil

    Hi Sandeep,
    If it's just a warning, press the enter key and it should post.
    or then you will have to debug the reversal process to locate from where the error message gets triggered..
    Regards,
    R.Brahmankar

  • Restrict Automatic serial number calculation for Production order release

    Hi,
    I need the solution for following requirement.
    Release production order(CO02) . Then go to Menu header-> Serial Numbers.
    Here I am getting serial numbers automatically as the material used in production order is set for automatic serial number calculation.
    But I want to restrict automatic serial number assignment based on production order type.
    If order type is 'XYZ', I dont want to calculate serial numbers automatically.
    Can anyone tell me how to do it?
    Regards,
    Manan Desai.

    When you press Release Order button the BADI 'WORKORDER_UPDATE->AT_RELEASE' will be called.
    At this point the internal tables for Serial numbers are filled by the program automatically.
    So call function module 'SERIAL_INTTAB_REFRESH' which will refresh the internal tables for serial numbers generated before teh serial number window pops up.
    Also at the BADI 'WORKORDER_UPDATE->AT_SAVE' call the same function module because before this BADI call when you press 'SAVE' the program again checks if automatic serial number is set for that material and if yes then check if no serial numbers are generated then it generates the serial numbers again and fills the internal tables. So clear the internal tables again based on the conditions.
    In these BADI's we have access of header information which can be used to check condition.
    I hope this will give you better idea.
    Thanks for your efforts.
    Manan Desai.

Maybe you are looking for

  • Session Timeout Alert + login page has changed

    Hello, We recently updated our SAP CRM 7.0 from EHP1 to EHP3. Since than we get this "Session Timeout Alert" error and it is very annoying. I've changed the rdisp/plugin_auto_logout parameter to 7200 s but the session is still ending after about 10mi

  • How can I put a single song in ipod without having to reset it ?

    How can I put a single song in ipod without having to reset it ?

  • Automatic change of component in bom

    After certain perion of time if i need to change a component in bom automatically ..is this possible..? if yes pls help  guru.....

  • Using chart to track changes over time

    Hi, I'm monitoring the progress of recovery from injury and need to analyse changes in grip strength over time. I would like to use a chart with grip strength on the Y axis and time along the X axis. Unfortunately, the records were not taken at regul

  • How to Remove Previous Values in Field Symbols

    Hi, My code goes like this. Loop at i_vbap. read table itab assigning <fs>. if sy-subrc = 0. endif. Endloop. This is good if my subrc for read is always 0. however, if my subrc = 4, my <fs> still contains the previous values. How do i clear my <fs> w