Fetch SNP and PPDS orders

hi,
I am new to APO. How to get PPDS and SNP planned orders from livecache.
Regards
Dhanu

1)     I am able to get all SNP and PPDS order using BAPI called BAPI_PPDSSRVAPS_GET_IO_NODES from Live cache. This BAPI fetching order id as key field.
2)     I need to fetch the data from DMCP table using this order id but there is no link with this order id with DMCP table.
3)     There is a field called GUID in DMCP table. I used one FM to convert order ids to GUIDs to get the data from DMCP table. All order ids got converted into GUID.
4)     Till here everything is good.
5)     But when I am trying to pull the data from DMCP table based on GUID, it is pulling only SNP orders not PP/DS orders.
6)     I have tried so many ways but I am getting SNP orders only.
7) I need SNP and PPDS orders
Can you help me on this?

Similar Messages

  • SNP and PPDs horizons

    Hi,
        If I have SNP horizon of 0 days and PPDs horizon of 0 days. Then does the system plan twice and I see double the quantities because both SNP and PPDS are planning the same time? I mean does it create both SNP and PPDS planned orders doubling the planned qty.?
    Thanks.
    Edited by: Visu Venkat on Jul 30, 2008 3:14 PM

    Typically if both these horizons are zero in the Location Product, the system is supposed to check the PPDS horizon kept in /n/sapapo/mvm transaction. Usually its a best practice to have a non-zero value in the version level. under the situation where even PPDS horizon at version level is 0, I would expect PPDS orders not be created at all by any systemic process. (different PPDS heuristics work differently though) However it should be possible to create PPDS orders manually outside of the PPDS horizon. Usually SNP orders are deleted and PPDS orders created in its place by the PPDS solver as soon as those orders are inside the PPDS horizon. I would be surprised by what you are observing though.

  • Difference between SNP and PPDS.

    Hi all,
    i want to know the functional diff betwn Snp and PPDS. .
    i mean what activities come under Snp, after what activities it is under PPDS. . .
    Any info on the same will be highly appreciated.
    Regards,
    Prasad.

    Hi Prasad,
    SNP basically does rough cut capacity planning on a constrained or unconstraint situation whereas PPDS does time continous finite capacity based on constraint or unconstaint situation.
    SNP & PPDS works on horizons.  There are scenarios were SNP horizon can overlap with PPDS horizon. 
    SNP uses SNP PPM as master data whereas PPDS PPM as master data.  The output are SNP orders and PPDS orders. 
    The minimum day for SNP planning is 1 day whereas PPDS can go upto even 1 sec(ie microscopic planning)
    Starting from a demand plan, Supply Network Planning determines a permissible short- to medium-term plan for fulfilling the estimated sales volumes. This plan covers both the quantities that must be transported between two locations (for example, distribution center to customer or production plant to distribution center), and the quantities to be produced and procured. When making a recommendation, Supply Network Planning compares all logistical activities to the available capacity
    We use the Production Planning and Detailed Scheduling (PP/DS) component
    a) To create procurement proposals for in-house production or external procurement to cover product requirements
    b)  To optimize and plan the resource schedule and the order dates/times in detail
    Regards
    R. Senthil Mareeswaran.

  • SNP and PPDS Horizon

    Hi All,
    Can anyone please let mw know what exactly is the difference between SNP and PPDS Horizon ??
    How is it identified. .
    What are the applications of using these horizons . .
    Thanks in Advance,
    Prasad.

    SNP Horizon: Time segment, during which SAP APO Supply Network Planning (SNP) does not plan production. This means that SNP does not create any planned orders in it but shifts production to the first day after the end of the production horizon.
    PPDS Horizon: Time segment in which Production Planning and Detailed Scheduling (PP/DS) can automatically create, change, or delete receipts. The duration of the horizon begins on the current date and continues for this number of calendar days into the future.

  • CIF PDS for SNP and PPDS

    Dear Experts,
    I am using SNP and PPDS
    do i need to have sales bom for SNP PDS  is it mandatory ,
    or just normal production bom is enough for having both snp and ppds Product data structure
    Thanks & Regards
    Raj

    Dear Satya,
    Thanks for your reply
    I know PV is needed for SNP PDS , is the PV which is used for SNP PDS is same for PDS PP/DS, or we need to use and special key during CIF ing to APO from ECC 6
    Regards
    Raj

  • DP, SNP and PPDS

    Hi Gurus,
    I am new in APO. Can anybody tell what are the different steps in DP, SNP and PPDS. What are the commonly used transaction in those module?
    Regards
    Rajib Pathak

    Dear Rajib,
    Please search the forum before you asking this type of general qn.
    However please follow the below link..it wud be helpful for you..
    http://help.sap.com/saphelp_scm50/helpdata/en/7e/63fc37004d0a1ee10000009b38f8cf/frameset.htm
    https://websmp110.sap-ag.de/bi
    Thanks,
    Satyajit

  • SNP to PPDS order conversion

    Hi,
    I am trying to do small testing over PP run in SAP APO.
    I have created everything manually in SAP APO(Product,location,No source of supply at Plant)
    When running SNP at plant getting planned order without source of supply.Now i am trying to convert the same order into PPDS order using program(indicator is set).
    Getting the below error:
    "In-house production 188401198 is not valid for the conversion"
    Any suggestion if this conversion is posible?
    Thanks,
    Krishna

    Hi Krishna,
    Yes you can create the order without source of supply by doing setting in Model/Planning Version Management  /SAPAPO/MVM but you cant use that for conversion.
    Go to SPRO---Supply Chain Planning----Production Planning and Detailed Scheduling (PP/DS)---Production Planning and Detailed Scheduling (PP/DS) here you will get the Heuristic Conversion SNP->PP/DS in that it is define Use SNP source of supply.
    Regards,
    R.Brahmankar

  • SNP and PPDS planning horizons

    Hai,
            I am reading through SNP and PP/DS planning horizons. I understand that SNP doesnot plan anything within SNP production horizon whereas PP/DS plans only within the PP/DS horizon.
    Now, I get confused when trying to understand the following sentences:
    1. If production horizon of SNP is smaller than the PP/DS horizon, the planning horizons of SNP and PP/DS overlap with each other. In this horizon, SNP determines the receipts with most cost-effective sources of supply and lot sizes and PP/DS plans the receipts in more detail.
    2. If requirements within the SNP production horizon cannot be covered by PP/DS, then SNP plans the receipt outside the SNP production horizon(this corresponds to the logic in the PP/DS planning time fence in short term planning).
    3. If the PP/DS horizon in the product master is set to be greater than SNP production horizon, this gives rise to an overlapping area in both SNP and PP/DS receipts are created.
    Can anyone please help me undestand the above? An example or somedocumentation reference is appreciated.
    Thank you.

    Hi Visu,
    Good question. You missed Planning Time Fence in the equation.
    |--||--
    >
    1.       PTF             SNP            PPDS
    You execute PPDS Heuristic (Product Heuristic) then requirements upto PPDS horizon will be covered by receipt elements (beyond Planning Time Fence). If you run SNP Heuristic then receipt elements will be created from SNP Horizon out in future deleting the receipt elements created by the previous PPDS run. But note that while PPDS planning is down to the second level SNP planning is minimum at a day level. If you have weekly buckets then all requirements for one week will be clubbed and single receipt element will get created. However you can consider SNP orders as fixed during PPDS Net Requirement Calculation through appropriate development.
    |--||--
    >
           PTF              PPDS           SNP
    2. This is also not clear to me as I cannot build the scenario as described. The above diagram is the closest I could come up with. But in this case if you run SNP Heuristic and there are unmet requirements (sitting between PPDS and SNP horizon) then the receipt for that will be created only at the start of the SNP Horizon.
    3. This is correct but already explained in 1.
    Hope this clarifies or at least does not add to the confusion. BTW if you are interested then please read OSS Note 481906 - SNP - PP/DS integration (documentation).
    Thanks,
    Somnath

  • Key Differnence between CTM in SNP and PPDS

    Dear Experts,
    Can any one tell me what are the key difference between SNP CTM and PPDS CTM
    Thanks & Regards
    Raj

    Hi Raj,
    You can use CTM both for master data of type PP/DS, and
    for master data of type SNP.
    Because CTM planning works on an order basis, you can
    determine and trace the relevant receipts and supplies for each
    demand in the entire supply chain, after the CTM planning run.
    PPDS in general will be used for short term planning wherein
    CTM can be on mid to long term planning.
    Both belongs to SDM  category of SCM which uses order series.
    In terms of master data, the plan explosion will decide on usage of
    plan for PPDS.  For resources, you can use time continuouse for
    PPDS relevant and bucket for SNP oriented
    Regards
    R. Senthil Mareeswaran.

  • Rolling schedules for steel options between SNP and PPDS

    We are trying to set up something within the APO SNP/PPDS tool to
    plan rolling schedules for steel.
    eg multiple resources, most of which are 100 percent rolling schedules,
    with many different "blocks", and common rolls may occur say every 4 weeks, or
    every 14 weeks.
    And so each roll we need to plan "Quantity required before the next roll" - eg
    a 14 week quantity.
    We have set up PPDS Blocks using CDP settings with characteristics in our
    test system.
    Seperate to that we have an SNP model where we plan across multiple plants,
    for a 12-24 month period, and we have multiple level BOMS where there may
    be 2 semi-finished products between the Finished and Raw material. Eg heat
    treated and non-heat treated.
    Sometimes one of the interim semi-finished products is the bottleneck, so we
    need to use capacity leveling to reduce quantities at all levels of the BOM.
    Our main issue is that the SNP quantities that we plan, we are not able to feed into
    the PPDS blocks, as SNP does not deal with characteristics.
    So in our test, all we can do is use the SNP quantities for higher level plans.
    Then delete the SNP orders, and re-run a new PPDS plan to get quantities in our blocks,
    but we then have lost all the capacity levelling information from SNP.
    Does anyone have any method to deal with this scenario? ie how to model rolling schedules
    by utilising the strengths of the SNP mult-plant and capacity leveling data, and then
    somehow also taking into account "blocks", or "rolling schedules"?

    In our testing. With CDP setting, we create a fcst element with a characteristic on the material. eg RED/BLUE/GREEN, and in PPDS, I can then create a PPDS order with the characterstic linked and visible in the PPDS order, and linked to the BLOCK on the resource (Blocks of RED GREEN for example)
    But SNP orders do not work with these characteristics.
    This is backed up by various documentation from SAP.
    eg
    http://help.sap.com/saphelp_scm50/helpdata/en/b0/3c2463c7cbb54bacfb75c789100ad4/content.htm
    SNP cannot plan with characteristics. However, the characteristic assignments remain and can be evaluated in PP/DS.
    CDP in SNP
    CDP cannot be used in SNP as the SNP does __not support__ characteristics.
    http://books.google.com.au/books?id=KjvOY_4P8JEC&pg=PA13&lpg=PA13&dq=CDPSNPcharacteristics&source=bl&ots=tG9-FGeIo9&sig=CzW-hktRFP2DrlOaied2QMY7gNE&hl=en#v=onepage&q=CDP%20SNP%20characteristics&f=false
    (In this book - a list of which APO areas do and do not work with Characteristics. SNP does not)

  • Min max lot size time based for use with SNP and PPDS

    Hi all, Is there anyway to set up time based min and max lot sizes? ie we want to have a Max lot size which is small for use with the first 3 months of our plan which starts life in SNP and then converts to PPDS and into blocks for block planning, but months 4 to 36 we want to leave as large max lot sizes as there is no need to have the small max lot sizes for the different horizon.
    As far as I can see there is only a material/plant lot size  and Max lot size and no way to have a different setting in a different time period.
    Thanks
    j

    Hi John,
    As you know, in the product master, the lot size maintenance is time-independent, so that obviously can not be used for your scenario. As per my understanding, to meet this using standard functionality, you can maintain multiple product specific t-lanes (for STRs) and PDSs (planned orders) with required lot size ranges and validity dates (for short or long term horizon). But, again since the validity of t-lanes and PDSs will not be automatically rolling forward so the updating the validities will be a challenge.
    The other option could be to enhance the heuristic functionality at lot size selection step while creating order.
    Regards,
    Umesh

  • Master data related fields for DP, SNP and PPDS needed in Material Master

    Hi Gurus,
                  Can any one please suggest or guide me what are the fields need to be done in Material master in ECC for SAP APO DP, SNP (heuristic with capacity leveling)& PPDS(Heuritic with optimizer).
    Please it will be really great help.
    Thanks in advance
    Regards,
    Kumar

    Hi Kumar,
    For DP, many of the fields under MRP3, forecasting tab
    views will be utilised more in material master of R/3.
    For SNP, MRP 1, 2,4 and basic data views will be mostly
    useful
    For PPDS, Fields under Bom, routing, receipe, production
    versions will be used along with few fields in material
    master
    Regards
    R. Senthil Mareeswaran.

  • Fetch Netvalue and Sales order No.

    Hi Friends
    Kindly help me to Fetch 'Sales Order Number' and 'Net Value of the Sales Order in Document Currency' before Saving the Sales Order since i need to store in custom table.
    Thanks in Advance

    Hi Senthil Ram Kumar Palanisamy Ganapathi,
      In Include -> MV45AFZZ -> FORM USEREXIT_SAVE_DOCUMENT.
       We will get SO Number and NETWR 'Net Value of the Sales Order in Document Currency'. So, In this Exit let say You Custom Table is ZTAB. Then do as follows in this Exit.
    IF SY-TCODE = 'VA01'.
       ZTAB-VBELN = VBAK-VBELN.
       ZTAB-NETWR = VBAK-NETWR.
       UPDATE / Insert ZTAB.
    ENDIF.
    Regards,
    Suneel G

  • Should PPDS orders consume capacity in the SNP Capacity view in 9ASNP94?

    Dear Gurus
    Should PPDS orders consume capacity in the Capacity View in 9ASNP94?
    We currently only use PPDS, but are looking to implement SNP for mid-range planning and S&OP.  I would like to demonstrate the simplicity of the capacity view in SNP, but the planned orders in PPDS do not consume the capacity of the Resource in the standard planning book/view SNP94(2).  We are using Single mixed production resources which I thought were suitable for both PPDS and SNP planning.  This is a particular concern because I would expect that the SNP and PPDS horizons will have to cross over and so PPDS and SNP will have to take into account the capacity consumed by orders in the other module.
    Any help will be appreciated!
    Elamobel

    If you are using PDS you probably need this BADI:
    Note 657185 - RTO: Sample code for calculating bucket consumptions 4.0
    As standard only the continuous consumption is maintained in the PDS by the CIF, the bucket consumption (which is the SNP view of capacity) is missing.
    Check the related notes too (especially 1462965)
    If you are using PPMs you can just maintain the missing data directly

  • APO SNP optimzer & PPDS optimizer

    Dear Experts,
    When i am doing my capacity leving using optimzer method in SNP
    system propose optmizer server is not installed in SNP
    its seems no optimzer server for SNP and PPDS was not installed , i try to run test connection to optimzer server
    it fails
    Just wonder as functional consultant what need to tell to the basis team
    can any one guide me on this technical stuff
    Thanks & Regards
    Raj

    Hi Raj Kumar,
    1) Once you show them the error, they fully understand
    what is the action to be done for that error
    2) You can also tell them to check the RFC connections
    3) Tell them to check the Optimiser installation is proper or not like
    4) Ask them to use transactions /sapapo/opt12, opt03 if required
    This will suffice.
    Regards
    R. Senthil Mareeswaran.

Maybe you are looking for

  • Remote App missing some keys

    I am using the remote app and I have to enter my iTunes password to purchase a movie, the problem is that some of the keys are missing on my remote app, this is on my iphone and my iPad. I am missing the Parenthasis keys. Both open and close. They ar

  • While creating po, the vendor material no should updated in PIR.

    hi all, i am facing one issue the issue is, while creating po, we can search the material no according to vendor material no, but when we change the vendor material no in po item details in material tab and save the PO, that is updated in the PIR, if

  • Low FPS when accesing iPhone video output image buffer

    2 down vote favorite Hi, I'm trying to do some image processing on iPhone. I'm using http://developer.apple.com/library/ios/#qa/qa2010/qa1702.html to capture the camera frames. My problem is that when I'm trying to access the captured buffer, the cam

  • Multi-Master Replication Problem

    Hello all, I am working an environment where I am trying to keep two masters in sync with no extra consumers. I have followed the proceedures in the documentation but for some reason I am only seeing replication in one direction. IE: Server B -> Serv

  • UCCX 7 performance

    Hi all, I have a question about the performance of the UCCX 7.0(1) SR05_Buil504. (Package: Cisco Unified CCX Premium) How many calls can this version handle? (calls per hour or day) How many agents can work with the agent desktop? (at the same time)