Help required for Creation of process chain for Open hub destination(table)

Hi Experts,
I am working on creating process chain for the open hub destination which is targeting data transfer into Table. Which is then push to SAP PI.
2.) Steps to create a process chain for OHD????? Not knowing and even after that
3.) What are the steps for Pushing it to PI (I mean we have generated client proxy also) But need to know ABAP related to trigger process chain
please need your expertise and knowledge. Well atleast with the point 2 I need BI experts help...
Regards,
[Gaurav Patwari|http://gauravpatwari.wordpress.com]

Hi Gaurav,
Creating Process chain for OHD.
1. Go to RSPC-> Create a astart variant.
2. Click on process typesin the menu. Fourth from the left. Under this go to LOAD PROCESSES AND POST PROCESSING option.
3. The fifth option is "DATA EXPORT INTO EXTERNAL SYSTEMS". Click on that.
4. Click on F4 and choose your infospoke name.
5. Press the RIGHT button.(if it asks for variant, create a new variant in the same small window besideswritting bar).
6. Join the START process and the 2nd process via dragging.
7. Now add your required other processes.
The general process chain processes are :
1. Start.
2. Delete Indexes (if data loaded to cube).
3. Load process.
4. Delete duplicate request (if it is a full load in cube).
5. Create Indexes.
Hope it helps.
Preet

Similar Messages

  • Multiprovider as Datasource for Open Hub Destination

    Hello,
    Can you pls let me know if we can used the Multiprovider as datasource for the Open Hub destination. Currently we are Bi7.0 and SP9. I am not able to see the option of Mutiprovider in the template.
    Appreciate the input ASAP.
    Thanks
    Gopal

    Multiprovider is not yet supported for Open Hub destination and hence you dont see that option.
    As of SAP NetWeaver 2004s SPS 6, the open hub destination has its own maintenance interface and can be connected to the data transfer process as an independent object. As a result, all data transfer process services for the open hub destination can be used.  You can now select an open hub destination as a target in a data transfer process.  In this way, the data is transformed as are all other BI objects.
    In addition to the InfoCube, InfoObject, and DataStore object, you can also use DataSources and InfoSources as templates for the field definitions of the open hub destination.
    The open hub destination now has its own tree under Modeling in the Data Warehousing Workbench. This tree is structured by InfoAreas.
    <b>Restrictions -</b>
    It is not currently possible to use MultiProviders as the source for the open hub destination.
    http://help.sap.com/saphelp_nw2004s/helpdata/en/43/7c836c907c7103e10000000a1553f7/content.htm
    Hope it Helps
    Chetan
    @CP..

  • Process Chain for Real Time Demon

    Please help I am stuck I followed the step by sdn but this is missing in step. how to create now process chain.
    I created the below
    DSO CONNECTED TO dATASOURCE via Trans,
    Real Time IP
    Real Time DTP
    assigned to Datasource and assigned the DS, IP, DTP to Deamon in RSRDA. NOW I started also manually via start all IP. but How to set the process chains now.
    PLEASE HELP ME STEP BY STEP TO PROCESS CHAIN SINCE i am new to this daemon in process chains
    Thanks
    Soniya
    null

    Hi
    refer to this
    CREATION OF PROCESS CHAINS
    Process chains are used to automated the loading process.
    Will be used in all applications as you cannot schedule hundreds of infopackages manually and daily.
    Metachain
    Steps for Metachain :
    1. Start ( In this variant set ur schedule times for this metachain )
    2.Local Process Chain 1 ( Say its a master data process chain - Get into the start variant of this chain ( Sub chain - like any other chain ) and check the second radio button " Start using metachain or API " )
    3.Local Process Chain 2 ( Say its a transaction data process chain do the same as in step 2 )
    Steps for Process Chains in BI 7.0 for a Cube.
    1. Start
    2. Execute Infopackage
    3. Delete Indexes for Cube
    4.Execute DTP
    5. Create Indexes for Cube
    For DSO
    1. Start
    2. Execute Infopackage
    3. Execute DTP
    5. Activate DSO
    For an IO
    1. Start
    2.Execute infopackage
    3.Execute DTP
    4.Attribute Change Run
    Data to Cube thru a DSO
    1. Start
    2. Execute Infopackage ( loads till psa )
    3.Execute DTP ( to load DSO frm PSA )
    4.Activate DSO
    5.Further Processing
    6.Delete Indexes for Cube
    7.Execute DTP ( to load Cube frm DSO )
    8.Create Indexes for Cube
    3.X
    Master loading ( Attr, Text, Hierarchies )
    Steps :
    1.Start
    2. Execute Infopackage ( say if you are loading 2 IO's just have them all parallel )
    3.You might want to load in seq - Attributes - Texts - Hierarchies
    4.And ( Connecting all Infopackages )
    5.Attribute Change Run ( add all relevant IO's ).
    Start
    Infopackge1A(Attr)|Infopackge2A(Attr)
    Infopackge1B(Txts)|Infopackge2B(Txts)
    /_____________________|
    Infopackge1C(Txts)______|
    \_____________________|
    \___________________|
    __\___________________|
    ___\__________________|
    ______ And Processer_ ( Connect Infopackge1C & Infopackge2B )
    __________|__________
    Attribute Change Run ( Add Infobject 1 & Infoobject 2 to this variant )
    1. Start
    2. Delete Indexes for Cube
    3. Execute Infopackage
    4.Create Indexes for Cube
    For DSO
    1. Start
    2. Execute Infopackage
    3. Activate DSO
    For an IO
    1.Start
    2.Execute infopackage
    3.Attribute Change Run
    Data to Cube thru a DSO
    1. Start
    2. Execute Infopackage
    3.Activate DSO
    5.Further Processing
    6.Delete Indexes for Cube
    7.Execute Infopackage
    8.Create Indexes for Cube

  • Authorizations setting for running the process chain

    Hai
    Iam planning to run the process chain for loading the data into ODS. But i dont have authorization for it.
    so what are the authorizations i need to run the process chain in my system. And how can i set all those authorizations to my user-id.  I have all authorization rights .
    Pls let me knw
    kumar

    Hi,
    Authorizations for Process Chains
    Use
    You use authorization checks in process chain maintenance to lock the process chain, and the processes of the chain, against actions by unauthorized users.
    ·        You control whether a user is allowed to perform specific activities.
    ·        You control whether a user is allowed to schedule the processes in a chain.
    The authorization check for the processes in a chain runs when the system performs the check. This takes place upon scheduling or during synchronous execution. The check is performed in display mode. The check is performed for each user that schedules the chain; it is not performed for the user who executes the chain. The user who executes the chain is usually the BI background user. The BI background user automatically has the required authorizations for executing all BI process types. In attribute maintenance for the process chain, you can determine the user who is to execute the process chain.
    See also: Display/Maintenance of Process Chain Attributes ®  Execution User.
    Features
    For the administration processes that are bundled in a process chain, you require authorization for authorization object S_RS_ADMWB.
    To work with process chains, you require authorization for authorization object S_RS_PC. You use this authorization object to determine whether process chains can be displayed, changed or executed, and whether logs can be deleted. You can use the name of the process chain as the basis for the restriction, or restrict authorizations to chains using the application components to which they are assigned.
    Display/Maintain Process Chain Attributes
    Use
    You can display technical attributes, display or create documentation for a process chain, and determine the response of process chains during execution.
    Features
    You can display or maintain the following attributes for a process chain:
    Process Chain ® Attribute ® ...
    Information
    Description
    ( Rename)
    You can change the name of the process chain.
    Display Components
    Display components are the evaluation criterion in the process chain maintenance. Assigning the process chains to display components makes it easier to access the chain you want.
    To create a new display component, choose Assign Display Components in the input help window and assign a technical name and description for the display component in the Display Grouping dialog box that appears.
    Documents
    You can create and display documents for a process chain.
    For more information, see Documents.
    Last Changed By
    Displays the technical attributes of the process chain:
    ·        When it was last changed and who by
    ·        When it was last activated and who by
    ·        Object directory entry
    Evaluation of Process Status
    If you set this indicator, all the incorrect processes in this chain and in the overall status of the run are evaluated as successful; if you have scheduled a successor process upon error or always.
    The indicator is relevant when using metachains: Errors in the processes of the subchains can be evaluated as “unimportant” for the metachain run. The subchain is evaluated as successful, despite errors in such processes of the subchain. If, in the metachain, the successor of the subchain is scheduled upon success, the metachain run continues despite errors in “unimportant” processes of the subchain.
    Mailing and alerting are not affected by this indicator and are still triggered for incorrect processes if they have an upon error successor.
    Polling Indicator
    With this indicator you can control the response of the main process for distributed processes. Distributed processes, such as the load process, are characterized as having different work processes involved in specific tasks.
    With the polling indicator you determine whether the main process needs to be kept until the actual process has ended.
    By selecting the indicator:
    -         A high level of process security is guaranteed, and
    -         External scheduling tools can be provided with the status of the distributed processes.
    However, the system uses more resources; and a background process is required.
    Monitoring
    With the indicator in the dialog box Remove Chain from Automatic Monitoring?, you can specify that a process chain be removed from the automatic monitoring using CCMS.
    By default CCMS switches on the automatic process chain monitoring.
    For more information about the CCMS context Process Chains, see the section BW Monitor in CCMS.
    Alerting
    You can send alerts using alert management when errors occur in a process chain.
    For more information, see Send Alerts for Process Chains.
    Background Server
    You can specify here on which server or server group all of the jobs of a chain are scheduled. If you do not make an entry, the background management distributes the jobs between the available servers.
    Processing Client
    If you use process chains in a client-dependent application, you can determine here in which client the chain is to be used. You can only display, edit, schedule or execute the chain in this client.
    If you do not maintain this attribute, you can display, edit, schedule or execute the process chain in all clients.
    Process variants of type General Services that are contained in a process chain with this attribute set will only be displayed in the specified client.
    This attribute is transported. You can change it by specifying an import client during import. You must create a destination to the client set here in the target system for the import post processing (transaction RSTPRFC)  The chain is activated after import and scheduled, if necessary, in this client.
    Execution User
    In the standard setting a BI background user executes the process chain (BWREMOTE).
    You can change the default setting so that you can see the user that executes the process chain and therefore the processes, in the Job Overview. You can select the current dialog user who schedules the process chain job, or specify a different user.
    The setting is transported.
    The BI background user has all the necessary authorizations to execute all BI process types. Other users must assign themselves these authorizations so that authorization errors do not occur during processing.
    Job Priority
    You use this attribute to set the job priority for all of the jobs in a process chain.
    Hareesh

  • Process chains for deltas

    hello I have one scenario...Can anyone explain how we can implement it?
    I want to load data from R3 into Master Data Attribute in BW/BI..and it should include future delta loading also.....
    and I want to use Process Chains for this....how can we do it.?(I have knowledge of loading data from R3 To MD Attribute using Process Chain but without deltas)
    Thank you
    Regards
    NR

    Hi......
    Sorry for late reply.......
    If we take the second implementation of PC in your abbove post.....as we included fullload in PC....before delta init.....can it be possible that fullload happens all the time as its in process chain?
    yes..........since it is a part of the process chain every time when you will execute the chain.........full upload will also done..............you can do one thing you can copy the chain.......and remove that process......I mean open the chain in Planning view.....in the top where we write tcode......there write Copy...
    then the chain will be copied.........remove the start process and the full upload and init upload.........then create a new start process.........look you have to create a new start process.......because you cannot use the same start variant twice..........
    whats the use of attrib change run in PCs in general?
    Attribute change run is used to activate the master data.......ie to convert the master data from M version to A version..........because upon activation of master data SID will generate...........which is needed to link the master data to transaction data ie dimension table.........in extended star shcema............Also Once active, the data is available in your reports........
    Attribute change run also adjust aggregates........
    Another thing......This process is just required for Attributes and Hierarchies, not for Text data.
    Hope this helps..
    Regards,
    Debjani........
    Edited by: Debjani  Mukherjee on Nov 4, 2008 2:11 PM

  • ABAP Routine for Deleting and creating index for ODS in Process chains

    Any pointers for the ABAP Routine code for deleting and creating index for ODS in Process chains.

    Hi Sachin,
    find the following ABAP code to delete ODS ondex.
    data : v_ods type RSDODSOBJECT.
    move 'ODSname' to v_ods .
    CALL FUNCTION 'RSSM_PROCESS_ODS_DROP_INDEXES'
      EXPORTING
        I_ODS = v_ods.
    To create index:
    data : v_ods type RSDODSOBJECT.
    move 'ODSname' to v_ods .
    CALL FUNCTION 'RSSM_PROCESS_ODS_CREA_INDEXES'
      EXPORTING
        I_ODS = v_ods.
    hope it helps....
    regards,
    Raju

  • Error in Process chain for CO-PC

    Dear ALL
                I am facing one problem.I have a process chain for CO-PC cost object controlling.In that after start process i have another process chain Manufacturing order.After this other processes are there.Upto 4th march i have the delta running fine.After that the manufacturing order PC is failing when i open the process chain i find its failing in DTP section.
    Now what i did is i run the DTP for manufacturing order actually it consist of ATTRIBUTES AND TEXTS.After finishing i find in manage that the records are transferred but 0 records added and when i find the log its saying
    @5C@     0PRODORDER : Data record 1 ('000001000000 ') : Duplicate data record     RSDMD     191     
    Thanks in Advance

    Hi,
    Check below these links for more business knowledge about CO-PC.
    http://help.sap.com/printdocu/core/Print46c/en/data/pdf/COPCIS/COPCIS.pdf
    https://www.sdn.sap.com/irj/sdn/go/portal/prtroot/docs/library/uuid/fb07ab90-0201-0010-c489-d527d39cc0c6.
    Regards,
    Praveena.

  • Process Chain for Consolidation Functions

    Hi Team,
                  We have created a process chain for consolidation function as required by client, but we want the process chain to check the preceding  task status and only on successfully completion it should  proceed to next task. Is there a standard program or function module which does this, please update.
    Also we would like to pass dynamic permanent parameter values for the variants of task.
    Thanks in advance.
    Kind Regards
    Sridhar

    Hi Collet,
                 We have created a process chain  as  below:
    Period Initialization - Data Collection -LDS - Calculation of RE - Validation of RFD - Interunit Elimination -COI.
    I have created the Separate variants for  each of the above functions with program UCBATCH01.and the process chain is working fine.
    But we want the process chain to check the task status before it proceed to next task execution and stop if any error occurs in the task. Also we want the  dynamic selection of parameters from Permanent Parameters of Consolidation Monitor.
    Kind Regards
    sridhar

  • How to create process chain for 0EMPLOYEE

    I want to create process chain for 0EMPLOYEE attribution and text, how to create it and make a schedule for daily loading? Could anyone write steps in my case? Thanks!

    Hi,
    Follow the following steps:
    1. Go to RSPC->create->give name and disc of your chain.
    Start Variant Creation
    2.  Now you will be prompted to give a start variant,create a  new variant(click on page icon )
    3.Change Selections->date/ time.
    4.give date and time for start of the chain.
    5.click the check box for periodic job->period values->daily->save->save
    Addition of process types
    6.Select the process type "Execute Infopackage"
    7.select the name of the infopackage which loads attr data to 0EMPLOYEE.
    8.Attribute Change run will come automatically( if not then drag it as well and create variant )
    9.select the name of the infopackage which loads text data to 0EMPLOYEE.
    10.Attribute change run wil again follow.
    (connect the process types which are not connected,by right clicking the process types )
                                 start
                           IP A     IP  T
                          attr          attr
    A = attribute
    T = Text
    Please Reward points if useful
    Manish

  • How to create process chains for Master Data?

    I need information on " how we can create process Chains for Master Data"

    Hi Sachin,
      http://help.sap.com/saphelp_bw33/helpdata/en/ad/6b023b6069d22ee10000000a11402f/frameset.htm
    and also Modelling aspects in process chains (ppt)
    https://websmp109.sap-ag.de/~sapidb/011000358700002337702003
    Hope this helps.
    Srini

  • How to Create Process Chain for Remote Cube.

    Hi,
              I created Remote info cube, data from ECC, loaded Successfully, I want to create Process Chain for Reomte Cube, Please Help me.
    Thanks,
    Nandish Gowda

    Hi Nandish,
    After initialization, th next delta will come as per your delta nature, if it is 0calday: Then your next delta will come tomorrow only.
    If you are able to 7 records in RSA3, why not in PSA( Why it's only 5 records). Analyze this closely.
    Sometimes, RSA3 exactly doesn't match with PSA because, RSA3 works on update mode F.
    Regards,
    Suman

  • HOW TO CREATE PROCESS CHAIN FOR PSA ARCHIVING

    SDN EXPERTS,
    i like to create process chain for archiving. but i dont see any event for archiving when i go to create a process chain for PSA archiving. please let me know.
    thanks

    Hi,
    In the below document on the 14th page it says it is not possible to archive the master data & PSA.
    https://www.sdn.sap.com/irj/servlet/prt/portal/prtroot/docs/library/uuid/f47fec9f-0501-0010-ce84-8a7231715ae6
    As per my understanding..
    But one thing you can do is use another ODS and load the same data that you're loading to something else and try to archive that data(Only if you have transformations in the current CUBE/ODS).
    Correct me if i was wrong and eloborate your requirement.
    Regards, Siva

  • How to create Process chain for Aggregate for Master data

    Hello friends,
    I created Aggregates on Navigational Attributes.
    Now they are working fine, but i need to know that how shall i create the Roll up for Aggregates on Navigational Attributes.
    The point is the master data changes frequently a lot of time for e.g. for 0customer etc.....
    So if any one can send me the step by step documents so as to know how to roll up the Aggregates for Navigation attributes or for aggregates created on Master data....
    How to create process chains for the same ?????????
    Because if master data changes, then rolling up the aggregates straight forward will not help.
    So we need to write a process chain so that it deactivates the aggregate and reactivate again and fill up again..........
    If i mis interpreted something please rectify it.......
    Please advise

    Hello,
    the changerun that you have to schedule in order to activate the master data will adjust the aggregates automatically.  There is no need to deactivate them after master data loads.
    Best regards,
    Ralf

  • CORUPROC (Process chain for confirmation, collective background processing)

    Hello Guru,
    Can you please explain me the program CORUPROC (Process chain for confirmation, collective background processing) that can be use in SE38. and how it its important for CO16N (Reprocessing Incorrect Production Order)?
    CORUPROC is also the same as CO1P transaction code.
    Please explain the use of this program.
    Thanks
    Edited by: Ryan on Feb 3, 2009 7:55 AM

    Hi Carina,
    It might take some time for the attribute change run.
    what you can do is right click on th running process , go to display messages and check if every thing is fine.
    also goto batch monitor from there and see if the job is still running.
    alternatively, if you are not sure if the job got strucked up, kill the job from batch monitor and run the attribute change run manually.
    you got two options two do now.
    1)Wait for some time for the process to complete and check the messages.
    2)kill the job and run att change run manually.
    i suggest you to go for option 1 and if it is taking too long ar there is any error message, analyze and then go for option 2
    hope this helps.
    cheers,
    Srinath.
    Edited by: Srinath Singamsetti on Aug 4, 2009 5:44 AM

  • Process chains for loading data to target is not functioning

    Hi SAPians,
    Recently, we have upgraded the firmware on IBM P590 with the help of IBM on Saturday i.e. 06/12/2008 (The firmware of P5-590 was SF235_209. It was upgraded to SF240_XXX) and since then the process chains for loading data to targets are not functioning properly.  We have stopped all the SAP services, database services & OS services from our end and services have been rebooted after firmware upgrade.
    However, the problem with the process chains that load transaction data and hierarchies is solved but the chains that load master data are still not working as scheduled.
    We tried to load the master data manually, by running DTP to load data to an object analysis code (attributes) the request remained YELLOW. After refreshing it several times, the request turned into RED. The error message was - PROCESSING TERMINATED (screenshot 1 attached).
    To mitigate this we tried deleting the bad request and it prompted with the below message:
    "Cannot lock request DTPR_4C37TCZGDUDX1PXL38LVD9CLJ of table ZANLYSIS for deletion (Message no. RSMPC178)" (screenshot 2 attached)
    Please advise us how the bad request should be deleted?
    Regards,
    Soujanya

    Hi Sowjanya,
    Follow the below procedure to make yellow request to RED:
    Use SE37, to execute the function module RSBM_GUI_CHANGE_USTATE
    From the next screen, for I_REQUID enter that request ID and execute.
    From the next screen, select 'Status Erroneous' radiobutton and continue.
    This Function Module, change the status of request from Green / Yellow to RED.
    Once it is RED, you can manually delete that request...
    Releasing LocK
    Gott Transaction Code SM12 and release the lock.
    Hope It helps you.
    Regardss,
    Nagaraju.V