How Program RCPMAU03 or FM CX_IN_HOUSE_PRODUCTION_TIME calculates Prod time

Hi All,
FM CX_IN_HOUSE_PRODUCTION_TIME is used in Program RCPMAU03 which is used for Material Master Update from transaction CA47 or CA47N. I want to know how this FM calculates Processing(BEARZ) and InterOperation(MARC-TRANZ) time.
Thanks in advance. Helpful answers will be rewarded.
Kartavya Kaushik.

hi,
from routing screen,extras>scheduling>schedule(give a variant name)>scheduling results>update material master.this writes the info in the temp file.use tcode CA96 to update material master.this updates lot size dependent in house production time in work scheduling view of material master and  deletes the lot size independent inhouse prod, time in MRP2 view.this tool gives more accurate results  for your  inhouse prod. time.
> Hello experts,
> I would like to calculate the Scheduled in-house
> production time based on route.
> Actually this is done in the prod. route in tcode
> CA02. (via menu Extras => scheduling => schedule).
> After getting the schedule table press the
> 'scheduling results' button I received the Processing
> time, Setup and teardown time,... Scheduled in-house
> production time.
> So I'm looking for a function or any tool to use it
> in report.
>
> thanks,
> Eli

Similar Messages

  • How performance meter in vision assistant calculates estimation time

    Hello...
    I want to know that how performance meter in vision assistant calculates the estimation time of each step?????
    I mean what is the concept behind this???
    please i need to know...
    Thanks in advance..

    Hello,
    I have performed the same operations in Ni Vision Assistant and in LV (without OCR):
    The VI is attached.
    The values are very similar. Maybe I do not understand your problem correctly. Please explain, if I missed the point.
    Best regards,
    https://decibel.ni.com/content/blogs/kl3m3n
    "Kudos: Users may give one another Kudos on the forums for posts that they found particularly helpful or insightful."
    Attachments:
    time Estimation_2010.vi ‏22 KB
    NIVISION.png ‏150 KB

  • How CA47N or CA47 calculates Interoperation time (MARC-TRANZ)

    Hi All,
    FM CX_IN_HOUSE_PRODUCTION_TIME is used in Program RCPMAU03 which is used for Material Master Update from transaction CA47 or CA47N. I want to know how this FM calculates Processing(BEARZ) and InterOperation(MARC-TRANZ) time.
    Thanks in advance. Helpful answers will be rewarded.
    Kartavya Kaushik.

    Hi,
    why you want raw mat via co01.
    Since it is raw material and the procurement type is external the system might have included GR Processing time , Purchse processing time and Planned delivery time in addition to queue time.
    Queue time:
      is an additional means of neutralising any disturbances for each operation.
      queue time is defined in both work center and in routings.The system carries out
      scheduling using queue time from work center only if we have not maintained a queue time in the operation.
    Regards,
    nandha

  • How to execute a transaction code in prod.Server from development server

    Hi Friends,
    How to execute a transaction code in prod.Server from development server,Pls give me your valuable suggestions...
    Regards,
    V.Balaji

    i have  a program in production system if i type the request and execute its sends a mail to my admin saying to transport the request to production system.....thats y??????
    just tell me ur idea.............

  • How to created a Report to calculate On-Hand inventory for pending sales

    hi,
        how to  created a Report to calculate On-Hand inventory for pending sales orders.for this report what are the tables and fields we have to use give me sample report.
    thank you
    radhakrishna.

    Hi!
    Tables:
    VBAK - sales order header data
    VBAP - sales order position data
    VBUK - sales order status header data
    VBUP - sales order status position data
    VBELN field is the key between the tables.
    Statuses in tables VBUK, VBUP: A-uncompleted, B-partially completed, C-fully completed
    Regards
    Tamá

  • How to make an ABAP program run for a specified number of times ?

    assalamoalikum all!!!
    Can some 1 plz tell me that How can I make my ABAP program run ONLY for 2 times (after it went in production etc)
    AND when the program runs for 2 times It then gets hanged/Locked foreever.
    Suppose my program is:
    REPORT twice002.
    write ' I will run only twice bye bye'.

    Well, I guess the only full proof way is to create a custom "Z" table which will hold the counter, in your program you would update this table every time the program runs. In this same program before updating the counter, you would retrieve the counter and check if it is = 2, if so, then write a message and RETURN.
    Regards,
    Rich Heilman

  • How can i calculate execution time for methods?

    I'm making a project that i want to calculate execution time for a
    method in "miliseconds" or "microseconds".You see,I have a sort algorithm and i want to calculate execution time of this algorithm.How can i do?
    Thanks...

    Just remembered.
    The answer you get isn't trustworthy below a hundred millis, so you may need to sort a hundred or a thousand times to get a reasonable elapsed time. You also need to run the test five or ten times and take an average. In Windows you should fire up the Task Manager and be sure that your other CPU usage is as near to zero as you can get.

  • How to calculate the time between start trigger,first scan and first A/D in DAQ

    Environment: Labview 6.1, N6052E DAQ board(max scan rate=333KHz, max channel rate=333KHz, settling time=3.5usec+1LSB)
    I am using external scan clock 10K scan/s collecting data on 16 AI channels, and external channel clock 200KHz.
    Could show me how to calculate the time betweent he start trigger, the first scan and the first A/D conversion?
    Thanks

    I read the one you give to me. still cannot work out. I am using Labview 6.1 DAQ vi, including AI config.vi. clock config.vi, AI control.vi, AI read.vi, working on colect data on 16 AI channels. So I belong to SCAN function and external scan and sampling timing, right?
    But it says the T1 and T2 are determined by external signals. How can I calculate that?
    T1=1/10KHz or T1=1/160Khz?
    T2=1/200KHz?
    Is the above correct?

  • How to calculate Response time in HH:MM:SS format ?

    Hi,
    How can we calculate reponse time in HH:MM:SS format?
    I have tried this formula but doesnt really seems to be providing desired output
    CAST (FLOOR (TIMESTAMPDIFF (SQL_TSI_HOUR, "Service Request"."Opened Date and Time" , "Service Request"."Closed Date and Time" ) /24) as CHAR) || ' Days, ' || CAST (FLOOR((TIMESTAMPDIFF (SQL_TSI_MINUTE, "Service Request"."Opened Date and Time" , "Service Request"."Closed Date and Time" ) - FLOOR (TIMESTAMPDIFF (SQL_TSI_HOUR, "Service Request"."Opened Date and Time" , "Service Request"."Closed Date and Time" ) /24) *1440)/60) as CHAR) || ' Hours, ' || CAST (TIMESTAMPDIFF(SQL_TSI_MINUTE, "Service Request"."Opened Date and Time" , "Service Request"."Closed Date and Time" ) - (FLOOR (TIMESTAMPDIFF (SQL_TSI_HOUR, "Service Request"."Opened Date and Time" , "Service Request"."Closed Date and Time" ) /24) *1440) - (FLOOR((TIMESTAMPDIFF (SQL_TSI_MINUTE, "Service Request"."Opened Date and Time" , "Service Request"."Closed Date and Time" ) - FLOOR (TIMESTAMPDIFF (SQL_TSI_HOUR, "Service Request"."Opened Date and Time" , "Service Request"."Closed Date and Time" ) /24) *1440)/60)*60) as CHAR) || ' Minutes'
    Output for this formula :
    Opened Time Closed Time Response Time
    16/10/2008 08:50:00 21/10/2008 11:33:21 5 Days, 2 Hours, 43 Minutes
    16/10/2008 08:57:00 24/10/2008 15:17:38 8 Days, 6 Hours, 21 Minutes
    16/10/2008 09:55:00 27/11/2008 10:44:36 42 Days, 0 Hours, 50 Minutes
    16/10/2008 10:13:00 21/10/2008 13:53:38 5 Days, 3 Hours, 41 Minutes
    16/10/2008 11:18:00 20/10/2008 09:11:29 3 Days, 21 Hours, 53 Minutes
    I just need time difference between Closed Time and Open time in HH:MM:SS format.
    Regards
    Ahmed

    WITH m AS
      SELECT [Minutes] = CAST(21.52 * 60 AS int)
    SELECT CAST([Minutes] / 60 AS varchar) + ':' + RIGHT(100 + [Minutes] % 60, 2)
    FROM m
    Best Regards,Uri Dimant SQL Server MVP,
    http://sqlblog.com/blogs/uri_dimant/
    MS SQL optimization: MS SQL Development and Optimization
    MS SQL Consulting:
    Large scale of database and data cleansing
    Remote DBA Services:
    Improves MS SQL Database Performance
    SQL Server Integration Services:
    Business Intelligence

  • How do I calculate a time such as work hours

    How do I calculate a time such as, a cell may have any time valve pertaining to daily work hours. 8:00 or 7:00 or 10:30. My question is I want another cell to represent any amount over 8:00. Like in a nine hour day you would have 8:00 with 1:00 overtime

    This may help:
    The first row is a header.
    select the three columns and format as  "Duration":
    now enter the formulas as:
    B2=IFERROR(IF(A2>DURATION(0, 0, 8), DURATION(0, 0, 8), DURATION(0, 0, 0)), "")
    C2=IFERROR(A2-B2, "")
    select B2 and C2, then fill down as needed

  • Calculate the time spent to execute your program

    Hi
    I have a pgm which calculates the response time in milllisecond using method System.currentTimeMillis(). And I get answer 0.
    My question is If we measure the time in terms of nanosecond, do you think we still get zero answer?and What is your explanation for that?
    Waiting for reply. Thanks in Advance
    Regards,
    Jyoti

    Hi,
    Here is the code for calculating the response time.
    public class RunLinkedEvenOddList {
         public static void main(String[] args) {
              long time1;
              long time2;
              time1 = System.currentTimeMillis();
              System.out.println("Program 2 output:");
    LinkedEvenOddList eolist = new
    ew LinkedEvenOddList();
              eolist.insert(9);
              eolist.insert(4);
              eolist.insert(3);
              eolist.insert(2);
              eolist.insert(5);
              eolist.print();
              System.out.println("print Even:");
              eolist.printEven();
              System.out.println("print Odd:");
              eolist.printOdd();
              eolist.delete(9);
              eolist.delete(1);
              System.out.println("list after delete 9, 1:");     
              eolist.print();
              System.out.print("execute isMemeber(3): ");
              System.out.println(eolist.isMember(3));
              time2 = System.currentTimeMillis();
    System.out.println("The starting time: " + time1 +
    +
                        " milli seconds.");
              System.out.println("The ending time: " + time2 +
                        " milli seconds.");
    Answer the following questions based on the output of
    your code:
    1. Calculate the time spent to execute your program
    based on the value of time1 and time2; you need write
    your formula first and then give the answer in
    millisecond.
    Answer:
    time2-time1
    time spent to execute your program = 0 millisec
    2. If we measure the time in terms of nanosecond, do
    you think we still get zero answer?
    Answer:
    3.What is your explanation for that?
    Answer:
    Pls help me in answering question 2 and 3. Thanks in
    advance.Hai Ram!
    Yeh homework mai hai.
    Akhela mai karo. (Do your own work).

  • How to program for multiple tasks at the same time.

    I want to start a data acq, then detect a level change in a switch which also corresponds to a visible timer starting. The timer will stop when one of three switches is closed. In the middle of this I would like for there to be a selectable (controllable/ adjustable) time delay andthen a signal is sent to one of three random lights. Can anyone please assist?

    Ok, I took a shot at what I think you are trying to do. The attached VI monitors an analog signal. When the analog signal goes above 5V (could be easily modified for any level), the program pauses for a selectable amount of time, then writes to one of three randomly selected digital lines (the LEDs on my digital lines were reverse logic, so you might have to adjust the polarity). This will at least give you something to work with. Hope this helps!
    -Alan A.
    Attachments:
    analog_in_one_dig_out.vi ‏111 KB

  • How to calculate Average time from a date field

    Hi All,
    I have a date type field in my table .
    I want to calculate average time for a given country in a select query. Date has to be exculded. Only time has to be taken into consideration.
    Kindly help me.
    Sample data
    india 25-JUN-09 08:12:45
    india 25-JUN-09 09:01:12

    Take which one you want.WITH dates AS
      (SELECT sysdate x FROM dual
        UNION
       SELECT sysdate + 1 +1/24 FROM dual
    SELECT TO_CHAR(to_date(AVG(to_number(TO_CHAR(to_date(TO_CHAR(x,'HH24:MI:SS'),'HH24:MI:SS'),'sssss'))),'sssss'),'hh24:mi:ss')
       FROM dates;
    WITH dates AS
      (SELECT sysdate x FROM dual
        UNION
       SELECT sysdate + 1 +1/24 FROM dual
    SELECT floor(24 * AVG(x- TRUNC(x)))
      || ':'
      || floor(mod(24 * AVG(x- TRUNC(x)),1) * 60)
      || ':'
      || floor(mod(mod(24 * AVG(x- TRUNC(x)),1) * 60,1) * 60)
       FROM dates;By
    Vamsi

  • How to calculate total time of mouse movement

    Hi Everyone.
    I am doing project on gesture recognition with touchpad. I need to find out the total time of completion of gesture on touchpad. For that I need to calculate total time of cursor movement on laptop touchpad. When cursor starts moving, that time I need to capture time and when it stops also. I need to find out difference between the start time and stop time. Please help me to do this task. Presently I am trying with event structure and timed structure but I am getting only present time only. I tried with counter but unable to get the difference.

    I missed the mouse move event when I saw this earlier, and for some reason I thought the first attempt would give you what you wanted. 
    Here is a different VI. It uses mouse move event with some logic that remembers the first mouse move event. Otherwise, you won't get the correct time.
    Attachments:
    Mouse Move Time.vi ‏11 KB

  • How to Calculate the Time Between two days in ABAP

    Hi,
                  I have one scenario like i need to calculate the time between two days please can you suggest me.
    Thanks,
    Harinath

    Hi Peeleti,
                Check this code,
    DATA : DATE1 LIKE SY-DATUM VALUE '19830125',
           DATE2 LIKE SY-DATUM VALUE '20070219',
           DAYS1 TYPE I,
           WEEK1 TYPE I,
           MONTH1 TYPE I,
           YEAR1 TYPE I,
           C_YEARS1 TYPE I.
    CALL FUNCTION 'HR_99S_INTERVAL_BETWEEN_DATES'
    EXPORTING
      BEGDA           = DATE1
       endda           = DATE2
      TAB_MODE        = ' '
    IMPORTING
      DAYS            = DAYS1
      C_WEEKS         =
      C_MONTHS        = C_YEARS1
      C_YEARS         = C_YEARS1
      WEEKS           = WEEK1
      MONTHS          = MONTH1
      YEARS           = YEAR1.
      D_MONTHS        =
      MONTH_TAB       =
    *WRITE : / 'DAYS   = ', DAYS1,
            / 'WEEKS = ',WEEK1,
          /  'MONTHS = ', MONTH1,
          / 'YEARS   = ', YEAR1.
    Using this code you can calculate the No Of Days Between two dates. Based On days you will easily calculate the Hour. [  No of days * 24 ].
    Thanks.
    Reward If helpful.