I am getting an error
The qty stored that was entered is adjusted
Message no. XU 040
at the time of GRN. I am maintaining batch specific Unit of Measure.
Please tell me how to change this error message in to a warning message.
Thanks
Prashant Atri

Hello Prashant,
This is satndard SAP messagge which is maintained in customizing;
SPRO>>Logistics - General>>Batch Management>>Define Attributes of System Messages
Here you can convert this messages to warning message. I urge you to please check with abaper as this may be hardcoded message and it may have implications on valuation and posting.
In the above IMG path you can do the changes
Br,
Tushar
Edited by: Tushar Patankar on Jan 1, 2011 5:36 PM

Similar Messages

  • Change of error message into warning message

    While doing FBZP i have found the following error.
    Clearing acct only allowed for an outgoing bill of exch.pmnt
    Message no. F3029
    I am not able to go further, the above message is coming.
    I want to make the error message into warning message.
    Please suggest, how to overcome

    Hello BSR,
    The Error message F3029 is raised when the clearing account (T042I-VKONT) is filled but the payment method in question is not defined as "Bill/exchange".
    I assume that the field is not changable at the moment. You may make necessary changes (delete the entry or delete the specified account) with the instructions below.
    1. Go to Tcd: FBZP -> Click [Pmt methods in country]
    2. Select the entry for the erroneous country(?)/payment method
    3. Change Payment method classification to 'Bill/ex' and save
    Now you should be able to change "Set Up Bank Determination for Payment
    Transactions" table.
    If you still want to use this payment method, please change back to the original classification after making necessary changes in T042I.
    I believe this information would help you in resolving the reported issue.
    Best Regards,
    Vanessa Barth.

  • Error message into warning message KO450

    Hi,
    There are  unsettle RA  value in project PAD-9114. Because of  this unsettle RA  value in  the project  we are not able to  close the project and receiving error message like below:
    1.There is still WIP for wbs
    2.Balance of  wbs is not zero.
    There is still WIP for WBS PAD-9114
    Message no. KO450
    Diagnosis
    The WIP for WBS PAD-9114 has not been cleared.
    System Response
    WBS PAD-9114 cannot be deleted.
    Procedure
    Calculate the WIP for WBS PAD-9114 so that it can be cleared.  Then settle WBS PAD-9114, including the cleared WIP in the settlement.
    How  to change  above  error message   into warning message so that   it will allow us to  close  the project.
    With regards,
    V.krishnamoorthy

    Hi,
    Thanks  for your answer. But still i am receiving the same error
    There is still WIP for WBS PAD-9114
    Message no. KO450
    Diagnosis
    The WIP for WBS PAD-9114 has not been cleared.
    System Response
    WBS PAD-9114 cannot be deleted.
    Procedure
    Calculate the WIP for WBS PAD-9114 so that it can be cleared.  Then settle WBS PAD-9114, including the cleared WIP in the settlement.
    With regards,
    V.krishnamoorthy

  • Convert Error Message into Warning Message

    I wanted to change alternate account into existing GL account. But it is not permitting to post because it is having balance. So i wanted to change error message into warning message. i tried with the following process but still it is not showing warning message showing as error message only. please suggest us.
    a) OBMSG
        Application area  Msg   Allowed        Standard          Switch Off
               FH                  007    W                   E                       tick mark
    b) OBA5
         Msg                                         Online          BatchI         Standard
         007                                                w            w                 w
    Please suggest me i need it urgently.
    Regards
    D.J. Laxmi

    Hi,
    Certain Error messages are not passed to be changed to warning message eventhough you maintained proper customization for the same. I can only recommend you that neutralize the balance of Gl account and change if reporting is accepted.
    Regards,
    Chintan Joshi

  • Error message to Warning message in MIGO?

    Hi,
    When we are executing MIGO 411 K transaction we are getting error message 'Enter Vendor Number'. I want to supress change error message to warning message.
    Because my requirement is populate vendor dynamically based on combination of Material, Plant, Storage location and Batch. I got user exit for this User-exit (EXIT_SAPMM07M_001) when click on check button.
    We found a User-exit (EXIT_SAPMM07M_001) triggered when User clicks on 'CHECK' button. But since the vendor field (LIFNR) is a mandatory field in MIGO 411 K transaction, its throwing an error message 'Enter Vendor Number'. So unable to proceed further.
    so i want to change error message into warning message and then i will proceed.
    error message i m getting is " Enter vendor number for special stock k".
    Or is there any other to populate the vendor dynamically based on Material, Plant, Storage location and Batch. please help..
    thanks

    This error is dynamic call so you can't make this one as warning message but why don't you try to add the search criteria based on your requirement to the field of vendor in migo.
    e.g. when you do F4 or drop down you will see the list of vendor you can get from diff way.......so add one more earch criteria for your reqs here.

  • How to make error message as warning message

    how to make error message as warning message? ie  i get error message hence cannot save the slaes order   i want to make that error message as warning so that i can save the sales order please help.

    Hi
    If a message is a custom message, then by changing the message type from E(Error) to W (warning)   we can convert the message type into error message. This is done with the help of development guy. A change in the code is needed.
    If it is a standard message, then it depends on whether we have teh access to change the message type. If access is there, then it is possible to change the message from Warning to Error. i.e. If we are capturing std SAP message in our code and displaying then we can change it, else if SAP message is displayed directly, we cant change it.
    So, to change it, capture the error message from SAP in some Zcode and then convert that message into a custom message of message type E.
    The whole change needs ABAP support.
    Try with tcode <b>OVA2</b> settings selecting for sales order or in SAPRO--SD-BF-Log of Incompletion Items
    Message was edited by:
            SHESAGIRI.G

  • Change error message to warning message

    Hi Experts,
    How can we change error message to warning message.
    Eg: T-code : SE91 shows the message. If i want to change message class PG, message no 26 error to warning what will be the process.
    Regards
    Ratan

    Hi Ratan,
    Message class PG is used in the below mentioned Standard SAP Methods and Includes, So it is not suggested to change the SAP standard code.
    Regards,
    Raja Sekhar

  • Change Error Message to Warning Message in GL account

    Hi Experts,
                      I want to Change Error Message to Warning Message In the GL Account - FH142.
    What is the Transcation Code for this.

    Hi,
    Go to transaction code OBMSG and give application area as FH and create new condition for the message 142.
    SAP will support such kind of changes.
    Regards,
    Sankar

  • Change of Message status from Error message to Warning message

    Hello,
    I would like to know the configuration details of changing the status of a message class from Error message to warning message.
    Thanks
    Manish

    Hi,
    You can do it via OBA5 transaction; enter the application code, and put an entry for the message setting the flag to warning. Keep in mind, that not for every message it could be done.
    Regards,
    Eli

  • CONVERTING ERROR MESSAGE TO WARNING MESSAGE

    HI GURUS,
      CAN ANY ONE GIVE ME IDEA HOW TO CONVERT ERROR MESSAGE TO WARNING MESSAGE IN QM MODULE.WHEN I AM POSTING STOCK FROM QUALITY TO UNRESTRICTED. BECAUSE IAM GETTING ERROR WHEN IAM POSTING STOCK GIVING ERROR TRANSFER POSTING THROUGH QUALITY ONLY. MY ERROR MESSAGE NO IS QA495. I TRIED ALL POSIBILITES. BECAUSE I AM NOT GETTING INSPECTION LOT BUT STOCK IN QUALITY. GIVE ME IDEA.
    BHAKTA

    Dear BHAKTA,
    it's not possible to customize every message in SAP System to warning or error.
    It depends on the coding. I have found message QA495 twice in coding, both times it's hard coded in Inlcude MM07MQSS. So it's not possible in standard to change this.
    How to find this information:
    SE91
    -> enter the message
    -> button 'display'
    -> select the line
    -> button 'where-used list' (CRTLSHIFTF3)
    -> now you get a list of all programms where the message is used
    Now you can check if message type is hard coded or read in customizing.
    If you really want this you have to modifiy the coding. But I would not recommed this, as hard coded errors are necessary to make sure that the standard scenarios work correctly.
    Regards,
    Sabine

  • Conversion of error message to warning message

    Hi
    I am facing one error message KI280 while doing PGI.
    It is regarding creation of Cost element in controlling area.
    The G/L which system has asked to create as cost element was never created as cost element till date and everything was working fine.
    This message has only appeared for some 3 deliveries.
    I got a solution that the message can be converted to warning message using OBA5.
    Now what are the consequences if I convert the error message to warning message.
    Points will be rewarded.
    Regards
    Nimit

    Hi Nimit,
        First of all kindly identify why the system is asking to create the GL as cost element.  The possibility to issue the message is only if there is any cost object like order, cost center, profitability analysis anything is assigned in the GL line item. Remove the cost object and then try to post the entry...
    If you change the error message into warning, you may miss out to create some GL account which has to be created as cost element in future..
    Regards
    Kaarthik.D

  • How to change 'z' key into 'A' key with key blinding?

    How to change 'z' key into 'A' key?
    Although txt.setText("A") can set the text field with 'a', but it is not original input from keyboard because it cant trigger the key listener.
    It is possible to perform key pressing more than a key in same time? Example, perform 'q' & 'w' keys pressing at the same time.
    import javax.swing.*;
    import java.awt.*;
    import java.awt.event.*;
    public class Main
    {   public static void main(String[] args)
        {   JFrame f = new JFrame("Test");
            Test GUI = new Test();
            GUI.setOpaque(true);
            f.setContentPane(GUI);
            f.setDefaultCloseOperation(JFrame.EXIT_ON_CLOSE);
            f.pack();
            f.setVisible(true);
    class Test extends JPanel
    {   JTextArea txta = new JTextArea(10,20);
        JTextField txt = new JTextField(10);
        JScrollPane sp_txta = new JScrollPane(txta);
        public Test()
        {   this.setPreferredSize(new Dimension(400,300));
            setLayout(new BorderLayout());
            txta.setEditable(false);
            add(sp_txta, BorderLayout.CENTER);
            add(txt, BorderLayout.PAGE_END);
            Action testAction = new AbstractAction()
            {   public void actionPerformed(ActionEvent ae){ txt.setText("A"); }
            txt.getInputMap().put(KeyStroke.getKeyStroke('z'), "test");    //Change z into A
            txt.getActionMap().put("test", testAction);
            txt.addKeyListener
            (   new KeyListener()
                {   public void keyPressed(KeyEvent e){ txta.append(e.getKeyChar() + " key is pressed \n"); }
                    public void keyReleased(KeyEvent e){ txta.append(e.getKeyChar() + " key is released \n"); }
                    public void keyTyped(KeyEvent e){ txta.append(e.getKeyChar() + " key is typed \n"); }
    }Edited by: 835972 on Feb 11, 2011 8:11 AM

    It is possible to perform key pressing more than a key in same time? Example, perform 'q' & 'w' keys pressing at the same time.With r.keyPress method, it only can perform single key pressed at a time. Do you have any idea how to perform multiple key pressed at a time?The javadoc for Robot.keyPress suggests ( "+The key should be released using the keyRelease method+" ) that the key remains "pressed" until you keyRelease(...) it. So, press the keys sequentially:
    theRobot.keyPress(KeyEvent.VK_Q);
    theRobot.keyPress(KeyEvent.VK_W);
    // At this stage both Q and W are pressed "in same time"
    ... // do stuff
    theRobot.keyRelease(KeyEvent.VK_W);
    // At this stage, only Q is pressedI suspect that in real life, unless you're a very gifted musician, you don't really press keys "at the same time" (under the time resolution of a keyboard, which I imagine is around a few milliseconds).

  • I have just installed Illustrator CS6 yesterday, but I found it was in French. Could help me figure out how to change the language into English?

    I have just installed Illustrator CS6 yesterday, but I found it was in French. Could help me figure out how to change the language into English?
    I got my series number from my Institut (which is in Paris, FR). I do not use Creative Cloud.
    When I was installing the software, I cannot select a language.
    Could you help me with my problem? Do I have to get a different series number?

    lunc,
    You will have to get a new application in English, to replace the French one.
    You, or your Institute will have to get help from Adobe, I am afraid.
    You may try a chat here,
    Get help with orders, refunds, and exchanges (non-CC, chat open between 5AM and 7PM PST/PDT on workdays)
    http://helpx.adobe.com/x-productkb/global/service-b.html
    or (have your Institute) talk to Adobe in France
    http://helpx.adobe.com/adobe-connect/adobe-connect-phone-numbers.html
    If you fail to get any help, please report back here, and I will ask a special forum staff friend to try to find the right one at Adobe to have things sorted out.

  • ESS Business Package - How to change error message

    Hi,
    In ESSBusiness Package Leave Application screen, if we enter some character XXX for From and To date field and try to proceed further (preview button) It is showing a error message 'Enter the value in format 11/25/1987" that we want to change to 'Enter the value in format MM/DD/YYYY".
    Please let us know from where this standard message is coming whenever we put some character values for any date control and how to change the same to customer specific message.
    Regards
    Sudhir

    Thank you Poojith,
    This is a standard message not only coming for Calender control in ESS application but also behaviour is same for custom webdynpro applications. So this message is not part of Leave Component message pool
    Regards
    Sudhir

  • Need to convert Error message to Warning message in MIGO

    Hi Guys,
                   I need a warning message instead of error message in MIGO.
    For example if a material is having shell life expiry when i am doing GR,if I dont enter the Manufacturing date.Its gives a error meesage.
    The error message is in program MM07MMHD, MESSAGE e018(12).
    In configuration when i press F4 its has only one value 'E'.
    So how to change this to warning (W) instead of 'E'.
    Thanks,
    Prasad.

    Hello,
    Check the message in these T.Code and change category from E to W.
    OPJB for production messages
    OBA5 for CO messages
    OMT4 for material master messages
    OMCQ Batch and quantity related.
    Also you can check SE91 for this.
    Regards,
    Pallavi

Maybe you are looking for

  • Logical and physical clear in ASO

    Hi There, I found one statement for Logical and physical clear in essbase dbag The process for logically clearing data completes in a length of time that is proportional to the size of the data being cleared. The process for physically clearing data

  • Billing due date change

    I would like to know why my billing due date is being changed. I have been a long standing customer of AT&T back even when it was Cingular. I do not want my billing date changed at all. I have electric and car payment due at the middle of the month.

  • Generate Report for each value of a certain column in a different pdf file

    Hi, I am generating a Group Above report in Oracle Reports Builder 10g. The scenario is that this report needs to be generated for several branches of a bank. The report needs to get generated in a different pdf file for each branch. The report, I ha

  • How can I de-authorize computers that no longer work that I can't access

    I have a total of 3 machines authorized to play iTunes songs a Mac and 2 PC's but I want to de-authorize both PC's but they don't work anymore how can de-authorize them?

  • URL from Character Style

    I am trying to figure out how to create a script of some kind (apple or java) that will search a document for any instance of a character style and turn that into a URL. If this has been posted before does anyone know where? I searched but can't find