Hi all,
In my system, I have a scheduled program which runs in every Half an hour. Yesterday the user got expired and concurrent program stopped working.
Today I have removed the expiry date before 1.5 Hr. But still the program is not triggered. Do i need to schedule the same again?
Can you please tell me what need to be done ?
Thanks,
AM

But it is not.. ( I am not sure wht happened )
In our prod environment i could see that one request ended (canceled) saying ' XYZ user is expired' but i am not very sure whether the user got expired or password got expired. But now the user is active . And was updated last night. (not able to reach the person who updated :( )
I know it is difficult to think :( but so many things are stuck on prod :(
I have checked the latest prod clone . There there is no end date for user and password expiry in 60 days .

Similar Messages

  • How can i schedule concurrent program for every one hour from back end

    Hi ,
    I want to schedule concurrent program for every one hour from back end .
    Example
    1) xyz is the concurrent program that should run for every one hour with a parameter 111 and the SAME concurrent program that
    should run every 2 hours with a different parameter like 222.
    I mean Conc prog should run for different parametrs with a different scheduling..
    Please guide me to solve the issue.
    Thanks in advance...
    Regards
    Narender B

    Hi ,
    I have used following code for scheduling the concurrent program from backend.
    declare
    l_request_id NUMBER;
    l_return_code boolean := FALSE;
    BEGIN
    fnd_global.apps_initialize(62991,54477,20003);
    l_return_code := FND_REQUEST.SET_OPTIONS ('YES');
    l_return_code :=fnd_request.set_repeat_options('16:36:00','','DAYS','START','','Y');
    l_request_id:=fnd_request.submit_request(application => 'xbol',
    program => 'NAPP_START_GENERATE_CHART_DATA',
    description => 'Processing chart ',
    start_time => SYSDATE,
    sub_request => FALSE,
    argument1 =>4000130957231588,
    argument2 => null
    COMMIT;
    dbms_output.put_line('Program has been submited and request id is '||l_request_id);
    END;
    Here the issue was concurrent program is completing with a warning like
    Resubmission of request 75588551 has been cancelled.
    FND_RESUB_PRIVATE.PROCESS_INCREMENT EXCEPTION: ORA-01403: no data found
    Resubmission of request 75588551 has been cancelled.
    FND_RESUB_PRIVATE.PROCESS_INCREMENT EXCEPTION: ORA-01403: no data found
    so i could not find the solution for this issue,please anybody guide me to solve this issue.
    Regards
    Narender B

  • How to check the all scheduled concurrent programs.

    Hi All,
    APPS : 11.5.10.2
    DB:9.2.0.8
    how to check the all scheduled concurrent programs at a time, is their any script for this?
    Thanks a million in advance.

    Hi,
    Please refer to the following threads.
    How to know The request is scheduled or not??
    How to know The request is scheduled or not??
    Need Report or Query to see all scheduled jobs
    Need Report or Query to see all scheduled jobs
    Regards,
    Hussein

  • Schedulling Concurrent Program in Fixed Assets

    Hi Team,
    Currently we are working on the Oracle Assets implementation. We want to know that what all concurrent programs like Post Mass addition program that are normaly scheduled by the business? Client wants to plan the concurrent programs that should be scheduled in Fixed Assets. So based on the experience with the business users, kindly guide us that what all programs should be scheduled in Fixed Assets?
    Thanks
    Garima Arora
    Ph no 9642355228

    Hi Garima,
    While uploading assets into the system you may have to run
    1) Post mass additions for adding assets to corp books from interface table.
    2) Periodic mass copy to copy assets into tax books from corp books.
    Other than this you may have to schedule 'Depreciation run' request set to close the books at the end of every period.
    Thanks,
    Vinod

  • How to Transfer the Scheduled concurrent Programs

    Hi,
    I have Migrated the EBIZ instance from RHEL 32 bit to RHEL 64 bit with 10.2.0.4 DB & R12.0.6 Apps.
    But now i dont have the scheduled concurrent requests in the New instance since the system is migrated. Now is there any ways to bring the Scheduled concurrent req from Old server to New server.
    Or Do we have FNDLOAD scripts or Linux scripts to transfer the scheduled programs.
    Kindly suggest.
    Regards
    Karthik

    You should migrate the instance by implementing the steps in the following docs which should keep your scheduled concurrent requests (as is) in your target instance.
    Migrating Oracle E-Business Suite R12 from Linux 32-bit to Linux 64-bit (Doc ID 471566.1)
    Oracle E-Business Suite Upgrades and Platform Migration (Doc ID 1377213.1)
    If you haven't done so, then please follow the steps in the docs.
    Thanks,
    Hussein

  • Scheduled Concurrent program breaks without any reason or log hint

    We have one concurrent program which calls a Custom PLSQL package scheduled to run every 5 minutes. Schedule runs fine for 15-20 days fine, after that, suddenly one instance of submission completes, and will not re-submit. We have always had problems with 2-3 concurrent programs like this.
    The last instance of submission will show NO hint of error or reason why not submitting the next one, rather, it completes succesfully. It just doesn't put an extra line of "Successfully submitted with request ID #####" that we normally see in scheduled requests log file.
    Applications Version is 11.5.9, Database at 10g.
    Any help pls.
    Thanks,
    Rajkiran.
    Message was edited by:
    Rajkiran Bingi

    you can use this Doc :134035.1(ANALYZEREQ.SQL - Detailed Analysis of One Concurrent Request ) for the request that completed last time.
    In addition could u let us know [1]what the custom req will be doing and [2]which CM is assigned to pickup the request.[3]does the request had picked up by CM after any time..[4]Does the CM which will pick up the request is busy with scheduling any other request at that time..
    Hope any of above questions will give some Info..
    BestRegards
    RS/
    RS
    Message was edited by:
    R.S

  • Scheduled concurrent requests/ request sets

    Can anyone please help me with a query for picking up list of scheduled concurrent programs and also list of scheduled request sets using backend database tables?
    Thanks,
    SK

    Thanks for your responses.
    The query is picking up the concurrent programs that are pending for normal execution. But my focus in on the below mentioned details:
    1) Concurrent programs that have been scheduled for future execution.
    2) Request Sets that have been scheduled for future execution
    It will be great if you provide me two different queries, one for concurrent programs and another for request sets
    Thanks,
    SK

  • Not able to do 'cd $DIRECTORY_NAME' from host concurrent program

    Hi Friends
    I am trying to run the below from a host concurrent program:
    cd /interface/j_dcgr07/DDCGRI/incoming
    and I am getting
    /ddcgri/applmgr/CUSTOM/xxdc/11.5.0/bin/XXDCIMAGECOPY.prog: line 43: cd: /interface/j_dcgr07/DDCGRI/temp: Not a directory
    but now when I log into the mid-tier as the concurrent program user I am able to do a "cd" for the same directory.
    Has anyone else encountered the same error? What could be the issue here? We are on Oracle 11.5.10.2 on AIX 5.3 (64 bits).
    Thanks in advance !
    Regards,
    Shashank

    user8094949 wrote:
    The directories exists. Below is the output:
    $ ls -l /interface/j_dcgr07/DDCGRI/temp
    total 0
    $ ls -l /interface/j_dcgr07/DDCGRI/
    total 10
    drwxrwx--- 2 tmoss j_dcgr07 2 Sep 28 2010 archive
    drwxrwx--- 3 j_dcgr07 j_dcgr07 4 Jun 7 10:40 incoming
    drwxrwx--- 2 j_dcgr07 j_dcgr07 2 Sep 28 2010 invalidfiles
    drwxrwx--- 3 j_dcgr07 j_dcgr07 3 Sep 28 2010 outgoing
    drwxrwx--- 2 j_dcgr07 j_dcgr07 2 Sep 28 2010 src
    drwxrwx--- 2 j_dcgr07 j_dcgr07 2 May 27 03:02 tempIs "j_dcgr07" the owner of the application tier node files?
    Thanks,
    Hussein

  • Can I retain my concurrent program schedule During R12 Upgrade ?

    Hi,
    We are approaching Oracle R12 Upgrade go live. We have large number of concurrent programs scheduled by various users. We are planning to put these programs on hold before upgrade. When we upgrade, do upgrade driver removes all schedules from concurrent program schedules? Is it wise to cancel all scheduled programs and reschedule them after upgrade?
    Please help!
    Best Regards,
    Dhaval Khamar

    When we upgrade, do upgrade driver removes all schedules from concurrent program schedules? No.
    Is it wise to cancel all scheduled programs and reschedule them after upgrade?No, just put them on hold before the upgrade then resume those jobs after the upgrade.
    Thanks,
    Hussein

  • Concurrent program to be submitted y only one user at a time

    Hi
    I have an issue with one of my reports. The report is using temporary tables, those will under go insertion and deletion while the report is running. So, to make sure that two or more concurrent requests submitted for same report, will not conflict, I want to make my concurrent request to be submitted by only one user at a time.
    How can I do that?
    Any help is appreciated.
    Thanks
    BalaKrishna

    The "run alone" box should not be checked. This indicates that this program can only run when no others are running. Pl see MOS Doc 1078462.6 (Custom SQL Concurrent Program Returns NO MANAGER Error). This option should typically not be used.
    To be able to achieve what you need, set the incompatibility (as you have done) and then bounce the concurrent managers for the setting to take effect. Pl see these MOS Docs
    436186.1 - Cannot Make Concurrent Programs Incompatible With Itself
    142944.1 - How to Make a Concurrent Program Incompatible with Itself
    HTH
    Srini

  • Manuals users should not be able to submit a concurrent program at a specific time frame:

    Hi
    Please let me know is it possible to restrict some users to submit a Concurrent program during a selected time frame .
    Eg we have an issue in which Process Lockboxes concurrent Program is submitted by the batch user and is also by the Users manually from Front end .What I want is that during a particular time frame everyday say from 12:00 AM to 6 PM I want to restrict manual users to submit this program ,whereas the Program can be submitted by the Batch user any time  .
    Please let me if its possible to achieve this and how .
    Thanks
    Rishabh

    Please don't post duplicates -- restrict user to submit concurrent Program
    Continue the discussion in your original post.
    Thanks,
    Hussein

  • How to get the User entered value in the Submit request form for a parameter of a concurrent program in Oracle applications.

    Hi All,
    I have a requirement where i need to get the user entered value in the Parameter of a concurrent program while submitting it. i tried to query the FND_CONCURRENT_REQUESTS table but in that it stores the ID values from the value set of the Parameter.
    After submitting the Concurrent request when we click on the view Details button it opens a form where it displays the arguments in the parameter field .  i want to get that string.
    Thanks a lot in advance for your time and help.
    - Vijay

    Hi All,
    I have a requirement where i need to get the user entered value in the Parameter of a concurrent program while submitting it. i tried to query the FND_CONCURRENT_REQUESTS table but in that it stores the ID values from the value set of the Parameter.
    After submitting the Concurrent request when we click on the view Details button it opens a form where it displays the arguments in the parameter field .  i want to get that string.
    Thanks a lot in advance for your time and help.
    - Vijay

  • How to capture the user name who is running concurrent program

    Hi Everyone
    In oracle apps when i want to store the user name who is running a concurrent program in specific responsibility.
    For that I created a table as USER_INFO which has a column called USERNAME.
    T o capture the user name i created a before report trigger and wrote the following code which will store the username into USER_INFO
    function insert_trg return boolean is
    begin
      insert into USER_INFO(USERNAME) values
    (select fnd_profile.value('USERNAME') from dual);
    COMMIT;
      return (TRUE);
    end;In the above code i used fnd_profile.value('USERNAME') to store the username but after running the concurrent program when i am query the table it returns no rows .
    It means the fnd_profile.value('USERNAME') is not storing the value.
    Please tell me what to do?
    Regards
    Sabyasachi

    In order to fetch any FND_PROFILE or FND_GLOBAL values you need to initialize apps
    fnd_global.apps_initialize(user, resp_id,resp_application_id)
    begin
    fnd_global.apps_initialize(0,20420,1);
    dbms_output.PUT_LINE (FND_PROFILE.VALUE('ORG_ID'));
    dbms_output.PUT_LINE (FND_PROFILE.VALUE('USER_ID'));
    dbms_output.PUT_LINE (FND_PROFILE.VALUE('USERNAME'));
    end; Check the following MOS note
    How To Set the Applications Context (FND_GLOBAL.APPS_INITIALIZE) [ID 209185.1]
    Cheers,
    ND
    Use the "helpful" or "correct" buttons to award points to replies / Mark the thread as answered, if your question is answered.

  • Oracle Apps -Concurrent program schedule details

    From which table that I can find concurrent program schedule details .
    NB:-
    I know select RESUBMIT_TIME, RESUBMIT_INTERVAL from FND_CONCURRENT_REQUESTS ,
    RESUBMIT_TIME, RESUBMIT_INTERVAL will be the schedule details .
    But the table FND_CONCURRENT_REQUESTS is get purged periodically , how can i find the master details of scheduling the concurrent.
    Thanks in advance,
    Arya Sreedhar.

    Give this a whirl ...
    Regards,
    Jon
    SELECT req.request_id
    , decode (prg.user_concurrent_program_name, 'Report Set', 'Report Set:' || req.description, prg.user_concurrent_program_name) AS name
    , argument_text as parameters
    , req.resubmit_interval
    , nvl2 (req.resubmit_interval, 'Periodically', nvl2 (req.release_class_id, 'On specific days', 'Once')) AS schedule_type
    , decode (nvl2 (req.resubmit_interval, 'Periodically', nvl2 (req.release_class_id, 'On specific days', 'Once')),
    'Periodically', 'Every ' || req.resubmit_interval || ' ' || lower(req.resubmit_interval_unit_code) || ' from ' || lower(req.resubmit_interval_type_code) || ' of previous run',
    'Once', 'At :' || to_char (req.requested_start_date, 'DD-MON-RR HH24:MI'), 'Every: ' || crc.class_info) as schedule
    , fus.user_name as owner
    , to_char(requested_start_date,'DD-MON-YYYY HH24:MI:SS') as next_submission
    FROM
    apps.fnd_concurrent_programs_tl prg
    , apps.fnd_concurrent_requests req
    , apps.fnd_user fus
    , apps.fnd_conc_release_classes crc
    WHERE 1=1
    AND prg.application_id = req.program_application_id
    AND prg.concurrent_program_id = req.concurrent_program_id
    AND req.requested_by = fus.user_id
    AND req.phase_code = 'P'
    AND req.requested_start_date > sysdate
    AND prg.language = 'US'
    AND crc.release_class_id(+) = req.release_class_id
    AND crc.application_id(+) = req.release_class_app_id
    ORDER BY name

  • How to increment GL Period using Oracle Application concurrent program scheduler

    Hi All,
    In R12, I came to know that we can increment GL Period also using Oracle Application Concurrent Program scheduler.
    We have a requirement to schedule 'Account Analysis Report' for different legal entities. We would need to increment GL Periof for each department.
    In 11i, we can not increment GL Period.
    Is there a way, to increment GL Period to schedule 'Account Analysis Report'
    Please advise.
    Appreciate your time and help.
    Oracle Application Version: R12.1.2
    thanks in advance,
    Ganesh

    Hi,
    could you please help me?
    thanks.