Dear Expert,
Can you please help me on this scenario.
I am currently using 2 Valuation types for a Product (NEW and Repair). If I have a rework material, I will just use the Repair Val type for the cost. Now I want to use another Standard Cost for other rework for this material, could you please tell me the possible way?
Thanks a lot..

Hi,
Shall i understans your scenario like this?You are going to sale the material with differrant prices based upon its rework which is done internally.
like mat 1 rework type a---50usd
mat1 reworkwork b  --60usd like that.
and you are already saling the rework type a with a sale order with valuation type 100 say.
If so then for rework type b  can this be with other valuation type b say.
Does there are  number rework types?
A better answer can be provided with more details.
Regards,

Similar Messages

  • Is the standard delivery cost for calendar in UK really £7.19?

    Is the standard delivery cost for calendar in UK really £7.19? I want two different calendars, already designed, and think £14.38 is a ridiculous amount to pay for postage......help please!

    The shipping prices for the UK are listed here:  The prices are really that high:
    http://store.apple.com/uk/help/print_products

  • Track changes for Standard Heirarchy Cost Center details( Tcode: OKEON)

    Hi all,
    I have a requirement to track the changes for <b>Standard Heirarchy Cost Center</b> data and whenever it change i need to initimate with email to certain group of people in organization.
    Transaction code : OKEON .
    Whenever standard heirarchy get changes then i need to send email to certain group people .
    My findings and questions are as follows :
    1. I understand that the changes can be track by using CDHDR table .
    2. What is Object Class for Standard Heirarchy Cost Center  ?
    3. Is there any standard report available for that please let me know .
    4. How to track the changes when Cost center Group got changes ?
    5. Is there any exits or BADI for this requirement ?
    Please respond this question as soon as possible . For every useful answer points will be awarded.
    Appreciate your help.
    Thanks.
    Mark

    You can try using the option GoTo - Change Documents, which is available, when you display cost center hierarchy.
    Regards
    Rakesh Pawaskar

  • Difference between sale order Costing & Standard Product Costing

    Hi experts
    I wanted to know Importance of Sales Order Costing & standard Product Costing.what are the benefits of these.
    Regards
    Sandeep patil

    Dear Sir,
    we are implementing SAP in packing industry. In packing industry in PP Bill of material is frequently change, for this we are implementing sales order costing.
    We are doing the following things,
    1. we are doing the inquiry at that time we are doing unit costing.
    2. On the basis of inquiry we are preparing the quotation. the unit costing done in inquiry flow to the Quotation because we r preparing the quotation with reference to inquiry.
    3. Similarly we are preparing the sales order based on quoation and unit costing data flows.
    4. Now when we run the MRP it doesnot explode the unit costing material requirement.
    Please tell us how the unit costing material data will flow to MRP run.
    Please reply.
    Regards,
    Bhadresh

  • Standard & actual cost table

    Sir,
    I ve to create standard & actual cost report for client in PP
    But i cant gate table & field name for:-POWER & UTILITY,
                                                                PACKING COST,
                                                                SALARY & WAGES,
                                                               FACTORY OVERHEAD,
                                                               DEPRECIATION          
    Hi gurus please suggest table names
    Moderator: If it's PP, why do you ask it on Conrolling forum? Anyway, a question likes this could not be properly answered

    Hi
    Check the fun modules
    K_VARIANCES_PARALLEL_CALC    
    K_VARIANCES_HIERARCHY_CALC  
    K_VARIANCES_OBJECT_CALC     
    <b><REMOVED BY MODERATOR></b>
    regards
    Anji
    Message was edited by:
            Alvaro Tejada Galindo

  • Rework cost in notification

    hi
    how to capture the rework cost in notification which are created throw defect recording and saparertliy
    i want to generate the report which part has done rework , and waht is the cost .
    regards
    Baswaraj

    To capture rework costs you need to use either Internal orders or QM order
    Check this out
    http://help.sap.com/printdocu/core/print46c/en/data/pdf/QMCOST/QMCOST.pdf
    Marwadi.

  • Standard SAP Cost Report which captures costs incurred for replacementgoods

    Hi Friends,
    We want to track the costs related to the Replacement of goods sold free of charge and under warranty shipped to our customers. We are currently using the field "Usage" on the item level of the sales order.The item category  created within the Sales Order is either ZST0 or ZMO0.
    Unfortunately, I can't find any report in which the field "Usage" would be presented along the costs related to the item. The report I'm looking for would be used to evaluate, on a given period of time (ex. Fiscal Year or a month), the total costs associated to the replacement units by sales order item.
    1) An existing report (which I have not found) exists, please let me know which one
    2) There is another way to track such costs within SAP.
    Please let me know if there is a standard report which tracks costs related to replacement goods.

    Hi,
    I got the required from MBEWH table.
    Thanks
    Aravind

  • Name of the table for Standard Output/Cost maintained in in the IO

    Dear All,
    We go to KO03, enter the order no, display the order. Go to extras, Cost analysis. There are two columns. Total target cost and total actual cost. I need to find out the name of the table where the target cost/standard output is stored.
    Thanks in advance,
    Thanks,
    Satya

    Hi,
    The tables are :
    COSP
    COSS
    COSL
    COSB
    Regards,
    Eli

  • Rework cost not capturing in production order

    Hi Experts,
    I'm not getting rework order cost in the main production order while settlement of the production order. I maintained settlement rule in the rework order as ORD (Main production order number).
    Please help me.
    Naren

    Hi
    If settlement is done properly i.e. w/o test run indicator and the rework order has values posted to it - Then KO88 or CO88 must be successful. If not, system would tell you the error #
    br, Ajay M

  • Standard Network Cost

    Hi,
    I have created Standard network with activities and assigned work center and activity type. I want to see the cost of the standard network. can one please tell where to check for the same in the standard network.
    Rgds,
    Prasad

    Hi Prasad,
    It is true that it is not possible to see the cost of any std network, only when it becomes an operative network it has an actual cost.
    Please jot down ur requirements properly.
    regards
    sunil kar

  • Best Practice on Moving Standard Hierarchy (Cost /Profit)  into production

    Hi,
    What is the best practice to move standard hierarchy into production? Is it better to move it as a transport? Or is it better to upload into production with LSMW?
    Thanks,
    Santoshi

    Hi,
    Best practices applied to all developments whether it is R/3, BI modelling or Reporting and as per the best practice we do development in Development system, testing in testing box and finally deploy successful development to production. yes for user analysis purpose, user can do adhoc analysis or in some scenario they create user specific custom queries (sometimes reffere as X-query created by super user).
    So it is always to do all yr developement in Development Box and then transport to Production after successful QA testing.
    Dev

  • Standard Product Costing help needed

    Hello SAP Gurus,
    To cost a manufactured product, my company does the following:
    Raw material cost+ labor hours* labor rate+ overhead+subcontracting charges (if done)
    overhead = labor hours* overhead rate
    Please guide me as to how I should configure the overhead cost elements, costing sheet and other configurations.
    I have read up the material on product costing but am finding it difficult to do the settings in my scenario.
    Please help me. Its very urgent.
    I will award the points immediately.
    Thanks,
    Eilzaa

    Elizaa,
    For this you need to define Costing Sheet.
    You need Base --- On which Overhead need to applied
                   Overhead Key -- how much percentage/value of overhead need to be applied
                   Credit key ---  Offsetting crediting Cost Element and Cost Center
    Suppose you want to Apply $20 overhead on every 1Hr Labor then .
    Assume you have 2 Activity types with respective allocation Cost Element 91000 and 91001
    Overhead Cost Element is 94000 and overhead Cost Center is 1000
    Your calculation Base is B00 --- with values 91000 to 91001
    Your Overhead Key is Quantity Base overhead key O00 -- with Actual overhead and planned overhead of $10 per 1 HR
    Your Credit Key is C01 --  94000 with 1000
    Thus, if there is 1.5 Hrs of labor hrs (Activity1 and Activity2)  are performed then system will calculate 20+10 = $30 Overhead and will credit 94000 with 1000 Cost Center and Debit the Production order.
    So total cost in this example will be
    Raw material Cost + Labor Cost based on Activity Prices + $30 Overhead Costs
    Thanks
    Sivaram

  • Booking of rework order cost on original order

    Hi,
       I want to know the complete process for booking the cost of rework order on the original order. It means how to do variance calculation & then settle order to original order.
    It is urgent. I want step by step process.
    thanks

    Hi
    Create a Reference operation set with a operation that needs to be reworked on and with the control key of a Rework type. Assign this to the trigger point in the parameters. Assign this Trigger point to the last operation in the standard routing you created for that product.
    If you create the trigger point as to be triggered at the partial confirmation of the order, then at the confirmation of the order, enter the rework quantity in that field with partial confirmation selected and save the confirmation. while saving, this will create a rework order.
    While assigning the parameters to the trigger point, make sure that the order type also is a rework order type.
    you can do fcost for rework costing
    do KKS2 after teco for the order
    use KGI2 for overhead caiculation.
    do KO88 for order settlements
    award points if useful.
    regards
    N.Ramesh

  • Update of Price in Material Master  when standard costing is released.

    Hello SAP gurus,
    When we created standard cost estimate, various cost estimate is created in various views Cost of good sold, cost of good manufactured and Inventory ( commercial ). Different view have different cost estimate.
    But we I release costing , the material master is updated by cost estimate of Inventory ( commercial). The cost estimate from Cost of good manufactured should be update?
    I am not able to solve the above issue , please help with customizing link
    Regards,
    Anand Agrawal

    Hi Anand,
    While you configure the Cost Componenet structure you define the attributes of cost Components in OKTZ.
    When defining the cost components, you must specify whether the cost component plays a role in the creation of the different prices that are transferred into the material master record. You have the following options:
    Standard price
    Costs that are flagged as relevant for stock valuation form part of the standard price if the results of the standard cost estimate are marked and released. These costs also serve as a basis for the following:
    The calculation of target costs in variance calculation
    The valuation of scrap in variance calculation
    The valuation of work in process for the confirmed yield for the operation (order-related production, process manufacturing) or at the reporting point (repetitive manufacturing)
    Commercial price
    Costs that are flagged as relevant for inventory valulation for the purposes of commercial law form part of the commercial price. This price is calculated in an inventory cost estimate and can be written to the material master record.
    Tax price
    Costs that are flagged as relevant for inventory valuation for the purposes of tax law form part of the tax price. This price is calculated in an inventory cost estimate and written to the material master record.
    The above information will prove helpful.
    Regards,
    amol

  • Transport cost center standard hierarchy & profit center herarchy

    Dear All,
    Pls guide how to transport cost center standard hierarchy, cost center groups, profit center hierarchy and profit center groups from config client to production?
    Regards
    Komal

    Hi,
    For CO data go to OKE6 transaction and create a change request.
    For PCA, go to 0KEQ and do the same.
    Regards,
    Eli