Subcontracting Material MRP.

Hi friends,
Here is my issue,
We have a material 'A' which is a subcontracting material and its subrequired material is 'B'.
when we run MRP (MD04) for the material 'A', here it generating the PR's as required. but when we run
the same for material 'B' it is generating the Planned orders (pldOrd). but this material is not in-house
produced one..
Why it is generating the pldOrd for the material B
Please explain why it is happening and how it should be corrected.
Regards,
Mohan.

Hi,
Check the below settings
1. For Matrl A Ensure the MRP2 , Procurement key is F and spl.proc.key is 30
2.For Matrl B ensure the MRP2 has the Proc key F if you are buying this product externally
Hope you would have maintained BOM as Matrl A header and Matrl B as lower material
3. If you need PR to be generated, Put MRP relevant indicator as '1' in source list by giving proper vendor
4. If you need Sch lines to be created,enter the Sch.agrmnt # in the source list and give MRP relevant
5.Run the MRP for Matrl A in MD03,give the below MRP Control Parameters
           Processing Key NETCH
           Create Pur req    1
           Delivery Sch       3
           Create MRP       1
           Planning mode   3
           Scheduling         2
6.By this MRP run,the lower level material also will get run automatically.
7. If not,run MD02 with the above MRP control parameters 1,3,1,3,2

Similar Messages

  • Moving average price of subcontracted material not picked for Cost estimation

    Hi Experts
    I have the below scenario:
    Finshed Product A has components B, C.
    C is a subcontacted material and it has its own BOM with components D & E.
    We are maintaining moving average price for the subcontracted material C, (because the subcontracter is adding X & Y in addtion to the components D and E, which are sent from us).
    In the mateial maste of C, Procurement type is F and Spl. procurement type 30 are maintained.
    When i do costing for the Finished product A, moving average price of C is not picked up (where as system calculates the std cost for C by adding the values of D & E and purchase info record price).
    Is there any way to Calculate Price of A by using the mvg avg price of C.
    I maintained the below valuation variant settings.
    If i remove the spl. procurement type 30 in the material master of C, it picks up the mvg. avg price. but it affects the MRP planning of  items D & E.
    Please advice.
    Thanks in advance.
    Regards
    Bala

    Hi Big choi
    Thanks for your response.
    I understand.
    1. if we maintain spl. procureent key 30, system calculates standard cost based on raw material and service charges.
    2. If we don't maintain spl. proc key, it considers the material as purchased and picks the mvg avg price from material.
    But, is there any way to pick the moving avg price from material master eventhough i maintained the spl. procurement type 30?
    Thanks
    Bala

  • Subcontracting with MRP areas / Customer consigment

    Dear all,
    I'm currently looking for some information regarding subcontracting processes with MRP areas.
    On the first hand I need a general overview how subcontracting purchase orders would be handled with MRP areas. In addition I'm really interested in the replenishment of the subcontractor stocks. On the other hand some facts about the customizing would be fine.
    My second topic is consigment stocks at the customer. So I need similar information as for the MRP areas but regarding this customer consigment.
    It would be really great if someone has some literature recommendations or official documentations about these issue.
    Many thanks in advance!
    Regards
    Enrico

    Hi Enrico,
    Working with subcontracting and MRP area's gives you the option to plan the requirements for the subcontractor separately and you can then order the components separately. This functionality is used when working with scheduling agreements and direct deliveries to the subcontractor as there this is a requirement.
    A second instance where one would use and MRP area with sucontracting is that when a material is used both by the subcontractor and it's also used directly in the plant production. The requirements for the subcontractor can be separately planned using an MRP area.
    The following links may give you some more information regarding working with subcontracting and MRP area's
    [MRP area|http://help.sap.com/saphelp_470/helpdata/en/c4/106956ae8a11d1a6720000e83235d4/content.htm]
    [Planning for Components to be Provided in Subcontracting|http://help.sap.com/erp2005_ehp_04/helpdata/EN/c4/106956ae8a11d1a6720000e83235d4/frameset.htm]
    Edited by: Peter Pallen on Jun 5, 2011 7:19 PM

  • Subcontracting with MRP area

    Hi,
    we have a FERT material that  is in the MRP area by storage location.
    This material was produced internally. When we ran MRP the requirements and planed orders for FERT material and its components were showed in MRP area. It was ok
    Nowadays this FERT material was changed to subcontracted.
    We don't have a defined supplier for FERT material.
    When I run MRP the requirements and planed orders for FERT material are still in MRP area.
    When we run MRP for components, the requirements and planned orders go to MRP plant.
    This way if we have in MRP area documents placed to cover the requirements from FERT material, MRP will suggest to cancel them. In MRP plant the MRP will suggest to create another documents to cover. How can We avoid this problem?
    Thanks and best regards,
    Elaine

    Hi Elaine,
    If your FERT material is set to F , 30  then your MRP run in MRp Area will not create any dependent requirement.
    Assuming the setting is X in Material Master,
    Given an option please remove the MRP Area planning and the PIR related to that and shift PIR for you FERT material to Plant level in mD61,MD62. This should avoid Planned order getting created in MRP Ara and Plant.
    in my past experience unlesss you want to do Planning run with Scope as planning as Vendor th euse of MRP Area for planning for PIR leads to confusion for End users.
    Hope this helps.
    Thx
    MJ

  • Goods receipt for subcontracting material

    Hello friends,
    i  am doing operation subcontractiing. My first operation is subcontracted. So, I have assigned PP02 control key to first operation (external processing and no auto goods receipt indicator)  and maintained external processing data for opration in routing. When i saved the order, for that operation PR gets generated.
    Now, I converted PR into PO and assigned raw material that has to be send to vendor. By 541 mvt. type material is issued to vendor. When i do goods receipt in MIGO, system is not showing storage location field. I dont find material in stock anywhere.
    But i can see quantity received in external processing tab of first operation in routing overveiw in order.
    Then how can i issue the material from storage for second operation if it is not in stock?
    How can i get stock of subcontracted material by MIGO?
    Please help me.
    Thanks in advance!

    Kiran,
    Since your scenario is Subcontract of operations, you will not find a material referance in your PR/PO, so there is no GR of Material happening, in this Scenario GR means delivery of the operation.
    If you really want to track, then you need to create an additional material number and assign that material number with Special Procurement key "30", here in this case you can recieve the product after subcontract as this is product sub contract process. In this case Production order is not relevant.
    Regards,
    Prasobh

  • Subcontracting material in Blocked QI stock

    Hi all-
    We have some material that we subcontract out and the material has QI inspect required on it.  The material was received into a subcontractor and we are now having a bit of an issue getting it out of QI/blocked stock. 
    I am not seeing an inspection lot for the material that we can release,  nor can I cancel the receipt of the material, and I am unable to do a transfer posting from block to unrestricted since I do not have a storage location.  Can I get some guidance on what I may be missing?  
    Thxs.
    Larry

    hi,
    You are doing the subcontracting process totally wrong....this is because for VENDOR Subcontractor we have only Unrestricted stock type to which you post via 541....
    The reason for having one stock type is because the reason you have given above....Ie. it has no storage location...
    So, that's the reason we valuated the subcontracting material at plant level only....
    Now you should try to cancel the posting...and try to make the new one...
    I hope you understand the reason....
    Regards
    Priyanka.P

  • AFS material-/mrp-status not active for plant.

    Hello Everyone
    I am facing an issue while executing the sales order
    Issue  :AFS material-/mrp-status not active for plant..
    CAN ANY ONE RESOLVE THIS...
    Regards,Rajneesh

    Hi Rajneesh,
    Tht prb might be the material master.
    Goto Material master, select AFS MRP View and activate/ press the AFS MRP status button and save.
    Reward with points if it is helpful
    Kishore

  • Returnable transport packaging for Subcontracting material

    Dear All,
    I have a doubt regarding a new process to be followed in our company. We need to issue raw material to our subcontractor for processing. We also intend to send packaging material to the subcontractor along with the raw material. Ie We are sending the raw material to the subcontractor along with the packaging material ( say, in boxes).
    I would like to know how to address this issue.
    What We tried
    Standard SAP is allowing the vendor's Packaging material to be "received" from the vendor when we Purchase material from the vendor using movement type 501 'M'. After this, we are able to see this as a "special stock" as RTP ( Returnable Transport Packaging ) in T code MMBE. After this we can issue the packaging material  back to the vendor using movement type 502 'M' . There is also a provision to send " our" packaging material to a customer through a Sale order, and receive it back from them.
    But is there any standard process for sending "our" packaging to a subcontractor and receiving it back from them ?
    We also tried including the packaging material in BOM, and sending it through 541 movement  but in this case, when we perform Goods receipt ( 101 movement of the parent material ), the packaging material gets consumed, which should not happen. We want them back in stock.
    We also tried using the option "Non - Ordered item" for the packaging material while performing Goods Receipt of the parent material. But this would increase the stock of the packaging material without us even issuing the same to the vendor initially. ie  More stock will be there than is actually present.
    So how else do we address this issue ?
    Regards,
    Velu

    Hi Velu,
    This scenario can be automated as well in BOM.
    While maintaining the BOM for the subcontracting material, include the packaging component as twice, but one with negative quantity. PFB screen shot.
    Also turn of the costing relevancy indicator and maintain material provision indicator as "K"(customer material) for both the line item.
    So while doing GR for the sub contracting, system post automatically 543 and 545. Hope this is useful, if it is so, your rewards are awaited .
    Regards,
    Chinna

  • Scheduling agreement with Subcontracted material

    Hello Gurus,
    There is scheduling agreement with subcontracted material.
    While maintaining the schdule with ME38  , I want to make the warning message of "Please create components"   ME114 as error message.  I went into configuration and set this message as " E" . But still while maintaining the schdule with ME38 , I am getting this message as Warning only and not error message.
    I would like to know is there any other setting other what i did?
    Please help me
    Thanks in advance

    Thank you for your reply.
    By going into the T code OBMSG , and doing the needful config., still result is not achieved.
    Please guide

  • Subcontract material

    Hi Experts,
    Please tell me following.
    1. In costing variant --- Valuation variant -
    Overhead , there is check box for  Overhead on subcontracted  material
    I want to know what & where do I get its effect if I mark or unmark this check box.
    2. I have fully processed on process order till GR,in which I did not issue extra raw material quantity. Status of order now is REL  CNF  DLV  PRC  BASC BCRQ GMPS MACM . where I found Total target cost for component is 1040.70 & Total actual cost 1041.00
    & Target/Actual varience is 0.30. Why system showing this variances as I issued only planned quantity.
    Regards,

    Hi,
    Pasting SAP help, guess it is quite descriptive & should answer your query, else revert.
    Regards,
    Vivek
    Overhead on Subcontracted Materials
    Indicator specifying whether, in respect of materials subject to subcontracting, overhead is applied in accordance with the costing sheet in the valuation variant.
    Use
    Set this indicator if you want to apply overhead to subcontracted materials (for example, to include material and administrative overhead).
    Note
    The application of overhead to subcontracted materials is included in material costing as well in unit costing on a manual basis for any subcontracting items entered.
    Dependencies
    When a material cost estimate is transferred to a unit cost estimate, items are flagged as Do not apply overhead if the indicator is not set in the valuation variant of the receiving object.

  • Subcontracting material valuation

    Hello,
    Is it possible to mark labour costs on a subcontracting Material as cost not relevant during costing valuation on a per material basis?  We would like to implement subcontracting, but keep the ability to mark the labour as cost not relevant for some materials.
    Any suggestions appreciated.
    M

    Hi
    Welcome to SDN!
    Lab cost relevant or not is decided at Cost Comp Structure Level in OKTZ... This applies to the Plant / Comp Code as a whole
    This cant be controlled at Material level
    Sorry that I could not offer you a +ve reply on your 1st post.. But thats the correct answer
    br, Ajay M

  • MRP Not Running on Subcontracting Material

    Hi All,
    I have done the following :-
    Created a SUBCON Component with all the correct views, procurement type 30 etc.
    Created a RAW Material again with all the correct views.
    Created a BOM for the Above.
    Created Subcont PIR for SUBCON Material
    Created Standard PIR for RAW Materal.
    Sourcelist for both.
    When I create a PO ME21N i can see the BOM explosion etc so Subcon works fine.
    The problem is if i want to maintian safety stocks for the SUBCON Component and run MRP it doesn't generate any Planned Orders/Purchase Reqs?
    Why is that?
    If i maintain safety stock for the RAW Material and run MRP it generates me reqs which is correct but why doesnt it do the same for SUBCON Material?
    Thanks

    Hi,
    Issue Resolved,
    I removed forward consumption and backwards consumption and MRP is working now.
    Forward and backward consumption has nothing to do with safety stock level. MRP will plan with your safety stock even if you write values in those fields.
    Forward and backward consumption comes into picture when you want to set the system how SOs should consume PIRs.
    So, I do not think you fully described your original situation since merely setting forwar/backward consumption periods to zero cannot solve this issue as per my best knowledge. I've tested the same and those fields have no effect on how MRP considers safety stock.
    BR
    Csaba

  • Individual purchase order with subcontracting material

    Hi all,
    I've implemented a individual purchase order in a sale order by means of 'TAB' category item. The material has been set as 'subcontracting'.
    When I create the sale order, a purchase requisition is automatically created with M imputation and special stock 'E'.
    Once I create, the purchase order with reference to purchase requisition, I set 'L' category item. Then I save the purchase order.
    In order to simplify the flowchart, the vendor has enough stock to manufacture the required material.
    Then, Tx. MIGO, stock input with reference to purchase order.
    For the FERT material --> movement 101 E + is set.
    For the component --> movement 121 E - is set.
    How can I obtain 121 'O' - movement for components in order to decrease SC vendor stock?
    Thank you very much in advance for your support.
    Best regards,
    Alberto Ramos.

    Dear Charlie,
    Thank you very much for your response. As you comment, I made a mistake with the number of movement. Certainly the movement for raw material consumption is 543.
    I have executed the flowchart you describe. In your case, an independent subcontracting purchase order is done. This flowchart works correctly (with the results you comment. Actually the raw consumption are related to mov. 543 O -).
    The problem is when purchse order is related to a sales order. That is:
    1. Sale order TA with only one position material A. Category item 'TAB'.
    2. Material master for material A --> MRP 2 view --> Special procurement field: 30 - Subcontracting
    3. An automatic purchase requisition is created (thanks to 'TAB' category item, schedule line, ...)
    4. Tx. ME21N --> I create a purchase order with reference purchase requisition:
        4.1. Account assignment category field is set to 'M' from sales order / purchse requisition
        4.2. I manually set Item category field to 'L' for indicating subcontracting (I don't force this to be 'L' from sales order / purchase requisition because I need to use the same flowchart for subcontracting and not subcontracting materials)
    5. Tx. MIGO
        5.1. For Fert material the system executes mov. 101 E +  (as in your description)
        5.2. For raw materials the system exectures mov. 543 E - ( instead of 543 O -). I would like to obtain the reduction of subcontracting stock, because this material is in my center but povided to SC manufacturer.
    Should I do a 'Subsequent adjustment' by means of Tx. MIGO the movement are:
      - FERT material 121 E - (depending on adjustment)
      - Raw materials 543 E - (again 'E' instead of 'O' which is the result I would like to obtain).
    I will very much appreciate your comments.
    Thank you again,

  • How to restrict the Material (MRP relevant )from manual creation of Pur Req

    Hi,
    If we have a material "ABC"  which has MRP type as "PD" (MRP relevant) in Material Master.
    If we don't want to give user the option of creating manual Purchase requisition for Materail "ABC", Whether this is possible in Std SAP ? If yes, then How?
    Thanks in advance,
    Pravin

    Hi,
    In standard there is no option to restrict at material level.
    But using BADI ME_PROCESS_REQ_CUST method PROCESS_ITEM you
    meet your requirement easily.
    Regards,
    Sunitha.

  • Report for subcontracting material

    Dear all,
    I need your help.
    we have two plants suppose plant 1 and 2
    plant 1 have sent some material to plant 2 by subcontracting challan
    so i need a detail like
    1) material sent via 57f4
    2) input material (raw material)
    3) output material (finish material after subcontracting)
    4) vendor
    5) price, qty
    is there is any report like this....

    Hi
    Go to J1ILN > Indirect taxes > procurement > subcontracting > reports > chalan Listing.
    This may be of your help. beyond this you will have to develop client specific report.
    Best Regards
    Nishant Shende