Target Cost was zero in production order

Hello,
We are experiencing every 1st day of the month target cost was zero for those production order which basic start date was on the 1st day of the month, this happen last march and this april it also happening but in january and february we did not experienced this issue. we wonder how this happening to us, since as we check those production order which basic start date was on the 2nd date and prior all has values in its target cost, this is for same finished material. How was this happening to our plant? how can we check and resolve this issue? am on a PP guy, as i have check the data of those order nothing peculiar for me, and it those material has cost estimate ok, this was released on the 01.01.2009 in this costing run will last untill of the year this was also been seen in the material master data current cost estimate.
As we have search for the performance assistant in SAP it thus tells us:
Total Target Costs
Total value of the target costs.
Calculated with the following formula:
Total target costs = Target cost debit + Target cost credit.
Use
Target costs are the planned costs adjusted to the actual operating rate.
The target debit on a manufacturing order is the sum of the activity-independent planned debit of the order and the activity-dependent planned debit of the order multiplied by the actual quantity of the order.
The target credit of a manufacturing order results from the goods receipt postings to stock. The delivered actual quantity is valuated with the planned price according to the price control.
The total value of the target costs is the sum of the target debit and the target credit.
The target costs are calculated during variance calculation and updated to the database.
The target costs cannot be shown until you have performed variance calculation for this target cost version. The target credit for the calculation of the total variances and production variances cannot be calculated until an actual quantity for an order exists after a goods receipt posting.
For the calculation of variances, the target costs are compared with the control costs.
Dependencies
The calculation of target costs depends on the selected target cost version.
But still we don't know how to check the issue and fixed it:
Please help us and guide us to resolve this issue
Thanks

Hi,
in some more details i have found out on our issue, one of the prerequisite for our variant calculation is Variance calculation at the manufacturing order level requires that the order is fully delivered (final confirmation is done) and technically completed ( except order pass through the mid night of period end ). Those informations can be displayed in the manufacturing order status.
order should be TECO right? but as said on this order pass through the mid night of period end can be have variance calculation, thus am right? this could be affect why the target cost was zero?
Thanks

Similar Messages

  • Target Cost missing in some production orders

    Hi everyone
    I am observing target cost for few of my production orders. I have observed target cost is misisng in some production orders even they have status techo and dlv while some have staus rel and dlv and i can target cost for them. When i try to run KKS2 for the production order which is not showing target cost it comes up with error KV151 which says 'The quantities on which planned cost were based are zero in the time period concerned. This may be caused by the fact that no goods receipt for a cost object has been entered. This result in target cost to zero.' but we still had valid cost estimate at that for those production orders. Any help would be really apprecited
    Kind Regards

    Any help plz

  • Target cost calculation in an Production order

    Hello
    Can any one guide me , how the target cost was calculated for various activities ?.  
    I believe the actual cost were pulled from the standard cost estimate . We have various activates for Labor / Quality / maintenance  etc..  we want to correct all the cost . Any input will be highly appreciated
    Thanks
    Nic

    Hi,
    You post goods receipt for the order (MB31) and the target cost will be calculated, you may try this if it will help.
    Regards
    Prasad

  • Target Costs not Displaying in Production Order Cost Analysis

    Hi Guys,
    I am not able to see the target costs in a production order. It is showing the actual costs properly. I don't know how to validate the numbers and where am I missing. Please help.
    Thanks and Regards
    Madhu Vutukuri

    Target costs are populated when you do the goods receipt. System will search for the released standard cost estimate and then apply that for each material component. If these 2 conditions are passed, then you will get target cost in order,
    You need to define the following,
    1. Variance Key - Transaction "OKV1"
    2. Assign that to Plant using "OKVW"
    3. Define Variance Variant using "OKVG"
    4. Define Valuation variant for WIP/Scrap calculation using "SPRO"
    5. Define target cost version by assiging sl no 3 & 4 and also how the cost calculation should be used.
    Once this activities are completed, execute production/process order and then after goods movement and some confirmations process Variance using "KKS2" as a period end activities.
    Edited by: sarin toms on Dec 2, 2008 2:26 PM

  • Target cost Not updated in Production order

    Dear All,
    when I save & release the production order system is not showing tgt cost. But once GR thas been done it is showing target Cost.
    How can system should will show target cost without doing GR.

    Dear Sainath,
    It is the standard behaviour of SAP,that only making a GR for a production order you will be able to see the target cost in CO03 -
    -->Goto >Cost-> Analysis.
    IF the order is only created or released you will be able to see the data under cost --->itemization or else cost component
    structure.
    Under Analysis you will not be able to see any data.you can see the data's after making GR.I dont think some option to make the
    data's visible before this.
    Correct me if I'm wrong.
    Regards
    Mangalraj.S

  • Target Cost in the settled process order become zero after cost deletion

    Dear all,
    User has standard cost estimates created in Jan 2010 that valid until the end of 2010 for every material in the system.  user created a process order in April 2010. Target cost of the order was created based on the standard cost estimate and recipes as well as order qty.    The order was also confirmed and settled in April 2010 without problem. 
    However, after I deleted all old costing estimates before I did a costing run for all materials in May 2010, the old order was resettled and all Target cost is removed from the order.  I guess system try to look at April costing estimate but it is not there since it was deleted before I created the new costing estimate in May.  Therefore, all varainces are throwed into remaining variances since the target cost become zero.
    Other than mark the settled order for deletion or keep all old costing estimates,  I am just wondering is anyway in the configuration to prevent the system to recaculate the target cost again for the settlement so I can avoid the problem happens?
    Thanks.

    Hi,
    Target costs are only calculated after goods movements have occured on the order, the Target Costs are then calculated during the Variance calculation.
    Target costs will only be calculated after the first goods receipt has been posted to the order. Also you have to ensure that the information to calculate target costs exists on the system in particular in OKV6.
    This estimation is based on the customizing for the Target cost version in transaction OKV6 as in turn will the "real" calculation of the Target costs via the variance calculation.
    So in OKV6 the Target cost will be based on preliminary costing on the order, an alternative cost estimate or the current standard cost estimate. Importantly if the choosen option is not fulfilled e.g. no current standard cost estimate, the target costs will not be predicted or calculated.
    regards
    Waman

  • Target cost is zero in Co-Product

    Leading Co-Product (main Finished Product) : A
    Other Co-Products : B & C
    Maintained the Apportionment Structure and  the apportionment rule  of the three materials is 45,30,25.
    I have done  the standard cost estimate before create product order,It was successful.
    Then I issued goods and recipted goods for product order.
    When I check the costing of the order, I don't find target costs,only actual costs.Why?

    You will  see it after doing GR for Production order.
    Regards,
    Ashok
    Edited by: AshokFICO on Feb 1, 2010 10:55
    this is correction to earlier response.I didn't read carefully,that you aleady done confirmation.
    Please clarify,do you use fixed price to valuate CO product? and Have you seen results after calculating variances for order?
    Confirm back.
    Regards,

  • Split valuation for Finished Goods - Target cost was not updated

    Hi,
    We are following split valuation for 'Finished goods'.
    Valuation typte 1 is for 'manufacture' and
    Valuation type 2 is for 'External procurement'
    For production orders with this material, we are not getting target costs. It is showing zero.
    We have done release of standard cost estimate before creation of production orders and goods receipt for these orders. But still it is not updating.
    Pls guide me.
    Regards
    MadhuSekhar Gupta

    Hi,
    Thanks for your reply.
    At the time of variance calculation only the credit part of target cost will update and at the time of goods receipt debit part of the target cost will update.
    Our client has done goods receipt but debit part of the target cost was not updated. and the order status is DLV.
    I simulated the scenario in QAS by creating new finished goods materials (Industry-Construction) one is with split valuation and another is without split valuation, then the debit part of target cost was updated at the time of goods receipt and credit part was updated at the time of variance calculation for both the materials. So this problem was not arised because of split valuation.
    Was this problem arising because of the material master data, because for one material it is updating and for another it is not for the same configuration?
    Regards
    MadhuSekhar Gupta
    Edited by: gms gupta on Oct 22, 2011 3:39 PM
    Edited by: gms gupta on Oct 22, 2011 3:41 PM

  • Target cost is zero in KKF6N

    Hi experts:
        I'm using REM. I've released the standard cost (CK40N), created the cost collector (KKF6N, preliminary cost estimate is automatically created). I checked cost estimator using variant "PREM", it's fine. Then I did backflush and GR. But still in cost collector (KKF6N), the target cost is still zero.
        I also tried to calculate variance. But still target cost is zero. But in this client, in some other plants, target cost has value.
        Not sure what I did wrong in master data, configration or transaction. Looking forward to your advce. Thanks.

    hi!
    thanks for your reply.
    I have exeucted CO8b, then system is posting controlling document and profit center document ( no accounting document).
    then I have executed KKS2, system is calculating target costs, but in process order cost analysis, the target cost is ZERO only, even for co products also.
    while executing KKS2, I am getting error message for other co-products  like "Only remaining var. in version 0 - no target costs for 000001000279 0003 (KV151)", as I am receiving only some co-products. I have changed the settlement rule in header of process order, but even then error message coming. any suggestion to avoid error message for other co-products, as we are not receiving them?
    Is there way to get target costs in process order cost analysis also?
    regs,
    ramesh b

  • Target cost not appearing in process order

    Hi All,
    Please let me know the reasons for target cost not appearing in process order.
    Thanks,
    SAP PQ

    Two more scenarios:
    1. You have co-product.
    2. You reverse the variance calculation.
    It will show the target cost only after you run variance calculation.

  • MESSAGE ERROR: WIP a target cost only possible with Product Cost by Period

    I work with orders assign to WBS Element (Non-valuated stock).
    If I enter confirmation to an order created, and then execute KKAX transaction to calculate WIP, the system shows this error message u201Cu2018WIP a target cost only possible with Product Cost by Periodu2019u201D, but actually the result has been calculated ok.
    If WIP is executed collectively KKAO the error message is the same but the result is not calculated
    Everything suggests that what we want is possible, but the error doesnu2019t disappear
    Does anyone know what could be reason for the error?
    Thanks

    Hi
    Check your RA key and WIP customizing... WIP at target cost is possible only in Product cost by period
    Check your settlement rule in Prod Order.. I guess it would be FUL and not PER.. FUL settlement means you are in product cost by order.. There seems to be a mismatch between your settlement type (FUL/PER) and WIP config
    Moreover, if your stock is non valuated, do you at all need to calculate WIP for prod orders? I dont think so
    Ajay M

  • Preli cost compo struc of production orders to sales orders -Non valuated

    Hi experts
    We use Non valuated sales order cost/settlement and assembly order processing. So production order is created from sales order and prel cost estimate is created in the production order. Now we notice that the cost component struc in production order is not copied into sales order. Only the EK02 is copied with total cost.
    How to bring cost compo struc from production order to sales order ?
    This may be a special cost estimate with costing and Is it possible to bring cost compo struc to copa record type A or F.
    I know standard cost compo mapping in copa but I could not see the costing variant used in production order in copa master data configuration.
    regards
    KT

    If the sales order is not a cost object, you cannot cost in it, and you can therefor also not see the cost component split.
    When you sell the material, you can pull through the cost component to PA, via the material master using the COPA valuation strategy. However, only the info for the material in the sales doc line item.
    You don't link to a costing variant, you link using the above valuation strategy and the costing key. The costing variant sits inside the costing key.

  • Cost Center field in Production Order CO01 and PO tables

    Hi SAP Consultants,
    Is there any Cost Center field in Production Order transaction CO01 ?
    What are the tables where Production order data is stored/saved ?
    Any help would be appreciated.
    Thanks in advance.

    Need to understand your purpose first. Let's not make it any more technical than it should be, talking in terms of fields and layouts.
    All the replies given before mine are referring to the operational costs - which are what are passed on "for performing each operation" of the production order. These are the costs coming to the production order from the work center where the operation is performed. At the end of several operations, the production order would have collected all these costs of different operations, and also those of the materials used in the process. There may be other (overhead, etc) costs coming on to the production order too.
    If you're looking for one "cost center" for the entire production order, what cost center is this? Is it the department to which you want to settle the production costs? This is possible, that all the costs accumulated in the production order over the course of its life are finally "settled" to a different cost object, which can be an inventory account, or a sales order, an internal order, or a cost center etc. (There are exceptions, where a production order need not be settled but lets leave this to save us some complexity).
    What exactly are you looking for? What is the business purpose you are trying to achieve? Or is it just a purely technical reason to write a report or something? Even then we need to know the purpose and objective of the report/enhancement before being able to answer your question.
    -Ram

  • Rework cost not capturing in production order

    Hi Experts,
    I'm not getting rework order cost in the main production order while settlement of the production order. I maintained settlement rule in the rework order as ORD (Main production order number).
    Please help me.
    Naren

    Hi
    If settlement is done properly i.e. w/o test run indicator and the rework order has values posted to it - Then KO88 or CO88 must be successful. If not, system would tell you the error #
    br, Ajay M

  • Material costs not captured in production order

    Hi all,
                After clicking 'Cost order' (Ctrl+F7) in production order header screen, if i am checking the cost component structure(Goto->Costs->Cost comp. structure) of production order, only the operation costs are captured. The materials costs are not captured here. Please suggest me in this issue.
    Regards,
    Krishna Chandra.

    Hi everybody..thanx for the replies..i want to clear the following things to u,
    1. Costing variance key is PPC1 for planned and PPC2 for actual.
    2. I have maintained the prices in the material master - MAP for child items & Std for the header item.
    3. This is happening for all the production orders
    4. I have kept the costing relevancy for all the materials in the BOM.
    Apart from these please give me the possible inputs to solve the problem.
    Regards,
    Krishna Chandra

Maybe you are looking for

  • New External Drive connected to Time Capsule moving files problem

    I have a late 2009 13" unibody MacBook Pro, that I primarily use for video editing/converting. I use my Time Capsule as a network through which I can connect to my external hard drives via USB for videos and such. I've used at least two other externa

  • ID CS3 : the 101 buttons bug - PDF file turning into a form

    Hi there, I'm just mentionning this issue with a clear title (I had mentioned it in another thread but with a wrong topic name, since I hadn't found out the bug). When working in inDesign CS3, there's a slight but annoying issue with interactive PDF

  • EBay keeps signing out from MBP

    Hi all I don't know whether this is everybody's problem or just mine but my eBay account keeps signing out by itself. It does this constantly, i signed in to my ebay account and after browsing some stuffs just it signed out automatically. I didn't pr

  • How to Setup Query properties in WEB

    Hi Gurus, How to setup query properties in WAD(Web Application Designer). Thanks Liza

  • Convert automator object to applescript

    Hi, 6 months ago I was working with automator and in my web searching I found a technique to convert the automator object (in the editor) to applescript. I have forgotten the trick and cannot find it... How is that done???? I thought it was a drag an