Using the date 9/29/2007, I expect the return from the following to be 4:
SELECT TO_CHAR('09/29/2007','W') FROM DUAL
However, it returns 5!!! Testing further I tried the next day, since it is a Sunday, it should be the start of the next week, 5..
SELECT TO_CHAR('09/30/2007','W') FROM DUAL.. I do get a 5..
I understand that the implementation of TO_CHAR with the 'W' parameter defaults a week start on what ever the first day of the month is, but I need a method that is more calendar like (Sunday is the start of a week, Saturday end of the week).
Anyone have a nifty solution?
Thank you,
Tony Miller
UTMB/EHN
This works pretty well. Please note that it is zero based, so add 1 if you want it to start with the first week as 1.
WITH TAB AS
(SELECT TO_DATE('12/01/2007', 'mm/dd/yyyy') DATE_COL FROM DUAL UNION ALL
SELECT TO_DATE('12/02/2007', 'mm/dd/yyyy') DATE_COL FROM DUAL UNION ALL
SELECT TO_DATE('12/03/2007', 'mm/dd/yyyy') DATE_COL FROM DUAL UNION ALL
SELECT TO_DATE('12/04/2007', 'mm/dd/yyyy') DATE_COL FROM DUAL UNION ALL
SELECT TO_DATE('12/05/2007', 'mm/dd/yyyy') DATE_COL FROM DUAL UNION ALL
SELECT TO_DATE('12/06/2007', 'mm/dd/yyyy') DATE_COL FROM DUAL UNION ALL
SELECT TO_DATE('12/07/2007', 'mm/dd/yyyy') DATE_COL FROM DUAL UNION ALL
SELECT TO_DATE('12/08/2007', 'mm/dd/yyyy') DATE_COL FROM DUAL UNION ALL
SELECT TO_DATE('12/09/2007', 'mm/dd/yyyy') DATE_COL FROM DUAL UNION ALL
SELECT TO_DATE('12/29/2007', 'mm/dd/yyyy') DATE_COL FROM DUAL UNION ALL
SELECT TO_DATE('12/30/2007', 'mm/dd/yyyy') DATE_COL FROM DUAL UNION ALL
SELECT TO_DATE('12/31/2007', 'mm/dd/yyyy') DATE_COL FROM DUAL)
SELECT DATE_COL,
TO_CHAR(DATE_COL, 'ww') W_IN_YEAR,
TO_CHAR(TRUNC(DATE_COL, 'month'), 'ww') W1_OF_MONTH,
TO_NUMBER(TO_CHAR(DATE_COL, 'ww')) -
TO_NUMBER(TO_CHAR(TRUNC(DATE_COL, 'month'), 'ww')) MY_WEEK,
TO_CHAR(DATE_COL, 'W') ORACLE_WEEK
FROM TAB
DATE_COL W_IN_YEAR W1_OF_MONTH MY_WEEK ORACLE_WEEK
01-DEC-2007 48 48 0 1
02-DEC-2007 48 48 0 1
03-DEC-2007 49 48 1 1
04-DEC-2007 49 48 1 1
05-DEC-2007 49 48 1 1
06-DEC-2007 49 48 1 1
07-DEC-2007 49 48 1 1
08-DEC-2007 49 48 1 2
09-DEC-2007 49 48 1 2
29-DEC-2007 52 48 4 5
30-DEC-2007 52 48 4 5
31-DEC-2007 53 48 5 5
12 rows selected
Similar Messages
-
Get week number for day from a list of days within a year..
I am beginning in ORACLE / SQL and wondering how I can use this query to work with a column of Dates that span over a number of years?
Ideally, I would like to use this script to add a number for the week of the year based on this.
Then when a new year begins to start over..
I am referencing an old thread..
TO_CHAR with dates to get week number issue
Here is what I have so far:
I keep getting an error stating "Bind Variable "p_date_beg" is NOT DECLARED"..
Thanks in advance for any help you can provide.
DECLARE
p_date_beg DATE;
BEGIN
SELECT RETRIEVAL_DATE
INTO P_DATE_BEG
FROM OBS_SELECT_LST12_SPG;
WITH TAB AS
(SELECT TO_DATE(TO_CHAR(:p_date_beg,'YYYYMM')||'01','YYYYMMDD') + LEVEL -1 DATE_COL
FROM DUAL
CONNECT BY LEVEL <=TO_NUMBER(TO_CHAR(LAST_DAY(:p_date_beg),'DD')))
SELECT DATE_COL, TO_CHAR(DATE_COL, 'FMDAY') DAY,
(CASE
WHEN TO_CHAR(TRUNC(DATE_COL, 'mm'),'FMDAY') = 'SUNDAY'
THEN TO_NUMBER(TO_CHAR(DATE_COL,'W'))
ELSE CEIL((TO_CHAR(SYSDATE, 'dd') + 1 - TO_CHAR(NEXT_DAY(TRUNC(SYSDATE, 'mm'), 'SUNDAY'), 'dd'))/7)
END) WEEK_NOB
END;hi, referring to this link about ISO week, http://www.epochconverter.com/date-and-time/weeknumbers-by-year.php, here is the code:
/* Formatted on 2012/06/13 06:32 (Formatter Plus v4.8.8) */
WITH t AS
(SELECT MIN (TO_DATE ('20120101', 'rrrrmmdd') + LEVEL - 1)
start_date,
1 week_th
FROM DUAL
WHERE TO_CHAR ( TRUNC (TO_DATE ('20120101', 'rrrrmmdd'), 'mm')
+ LEVEL
- 1,
'FMDAY'
) = 'MONDAY'
AND ( TO_DATE ('20120101', 'rrrrmmdd') + LEVEL - 1 <
TRUNC (NEXT_DAY (TO_DATE ('20120101', 'rrrrmmdd'),
'THU'
OR (TO_DATE ('20120101', 'rrrrmmdd') + LEVEL - 1
BETWEEN TRUNC (NEXT_DAY (TO_DATE ('20120101',
'rrrrmmdd'
'THU'
AND TRUNC (NEXT_DAY (TO_DATE ('20120101',
'rrrrmmdd'
'THU'
+ 7
CONNECT BY LEVEL < 15),
v AS
(SELECT t.start_date + 7 * (LEVEL - 1) start_date,
t.week_th + LEVEL - 1 week_th
FROM t
CONNECT BY LEVEL < 53),
u AS
(SELECT '20120501' dt
FROM DUAL
UNION ALL
SELECT '20120502'
FROM DUAL
UNION ALL
SELECT '20120503'
FROM DUAL
UNION ALL
SELECT '20120504'
FROM DUAL
UNION ALL
SELECT '20120505'
FROM DUAL
UNION ALL
SELECT '20120506'
FROM DUAL
UNION ALL
SELECT '20120507'
FROM DUAL
UNION ALL
SELECT '20120508'
FROM DUAL
UNION ALL
SELECT '20120509'
FROM DUAL)
SELECT *
FROM u, v
WHERE TO_DATE (u.dt, 'rrrrmmdd') BETWEEN v.start_date AND (v.start_date + 6);output:
DT START_DATE WEEK_TH
20120501 30/04/2012 18
20120502 30/04/2012 18
20120503 30/04/2012 18
20120504 30/04/2012 18
20120505 30/04/2012 18
20120506 30/04/2012 18
20120507 07/05/2012 19
20120508 07/05/2012 19
20120509 07/05/2012 19 -
Query to get Week number Pls help
I need to get week number of the current year in the format 2008-W47 ( this is for sysdate
when i try
select to_CHAR(sysdate,'YYYY'||'-IW')
FROM DUAL
i get 2008-47
but in the format 2008-W47
Help
sSQL> select to_CHAR(sysdate,'YYYY')||'-W'||to_char(sysdate,'IW') from dual
2 /
TO_CHAR(
2008-W47 -
Get week number for any given date
How to get a week number in Java?
/ ====================================================
Method: Get the desired Date format for the date
Developed By: Sandip Waghole [29-Jan-2010]
==================================================== /
public String getWeekNo(String strDate)
// input Date Format : M/dd/yyyy
int weekNo=0,i=0;
String strWeekNo=null;
int noOfDaysInTheYear=365;
int WEEK_STARTS_ON = 1; // Define the day on which week starts Sunday/Monday 1:Sunday 2:Monday
int firstDayNoInFirstWeekOfPresentYear=0; // Inititalize teh day on which week is starting in present year
int firstDayOfPresentYear=0; // Inititlize the 1st day of the present year whether Sunday/Monday/.....
int[] monthDaysArray = {31,28,31,30,31,30,31,31,30,31,30,31}; // Define array of the days as per months
int todaysDayNoInPresentYear=0;
int daysLateByFirstWeekStartedAfterYearStarted=0;
int intTemp=0;
//strDate="08/24/2000"; // For test purpose
StringTokenizer strDateTok = new StringTokenizer(strDate, "/ ");
int month = Integer.parseInt(strDateTok.nextToken());
int day= Integer.parseInt(strDateTok.nextToken());
int year = Integer.parseInt(strDateTok.nextToken());
GregorianCalendar cal = new GregorianCalendar();
// Check if present year is leap year
boolean boolIsLeapYear = cal.isLeapYear(year);
// If it is boolean year then add 1 to total days in the year & add one more day to february
if(boolIsLeapYear)
noOfDaysInTheYear=noOfDaysInTheYear+1;
monthDaysArray[1]=monthDaysArray[1]1;
// Find the 1st day of this year
Calendar calObj = new GregorianCalendar(year, Calendar.JANUARY, 1);
firstDayOfPresentYear = calObj.get(Calendar.DAY_OF_WEEK);
int intRemoveNoOfDaysFromWeek=0;
// # Find the day no of prsent day
for(i=0;i<month;i+) // get no of days till present year
intTemp = intTemp monthDaysArray;
todaysDayNoInPresentYear = intTemp - (monthDaysArray[month-1]-day);
if(firstDayOfPresentYear==6 || firstDayOfPresentYear==7) // If first Day is Friday or Saturday then it is week
// Identify the the day no on which 1st week of present year is starting
firstDayNoInFirstWeekOfPresentYear = 7 - firstDayOfPresentYear WEEK_STARTS_ON 1;
// Find delay in the 1st week start after r=the year start
daysLateByFirstWeekStartedAfterYearStarted = firstDayNoInFirstWeekOfPresentYear - 1;
// Now week is starting from Sunday
weekNo = (Integer)((todaysDayNoInPresentYear-daysLateByFirstWeekStartedAfterYearStarted)/7);
// Find the day no of today
intTemp = (todaysDayNoInPresentYear-daysLateByFirstWeekStartedAfterYearStarted) % 7;
if(intTemp > 0)
weekNo=weekNo+1;
else
weekNo=weekNo;
else
// 1st week is starting on 1st Of January
firstDayNoInFirstWeekOfPresentYear=firstDayOfPresentYear;
// Remove no. of days from the 1st week as week is starting from odd Sunday/Monday/Tuesday/Wednesday/Thursday
intRemoveNoOfDaysFromWeek = 7-firstDayOfPresentYear 1; // 1 added as include start day also
// So one week will be added in no. of weeks
weekNo = (Integer)((todaysDayNoInPresentYear-intRemoveNoOfDaysFromWeek)/7);
// Find the day no of today
intTemp = (todaysDayNoInPresentYear-intRemoveNoOfDaysFromWeek) % 7;
weekNo = weekNo +1; // As 1st weeks days are reduced from the todays day no in the year
if(intTemp > 0)
weekNo=weekNo+1;
else
weekNo=weekNo;
// Remove the no. of days from the week 1
strWeekNo=Integer.toString(weekNo);
return strWeekNo;
// Any issues please mail on [email protected] -
How to get week number from date
Hi,
please mention how to get the number of week from a particular date using fn module?Hi Debarshi,
Use FM <b>DATE_GET_WEEK</b>
Reward points if helpful.
Regards,
Hemant -
ABAP Get Week Number for a Given Date.
Hi All,
I want to calculate week number for given date.
SAP has provided function modules like DATE_GET_WEEK.. Etc are giving week number. taking default start day as Monday. But for my requirement is calculate week number based on start day as Sunday.
Please let me know if we have any custom logic ??
Thanks & Regards
Vasu YadavHi Vasu,
SAP standard functionality takes MONDAY as first day.
But if you want then you can change it to SUNDAY by implementing BADI CALENDAR_DEFINITION. Create a new implementation for method IF_CALENDAR_DEFINITION~GET_FIRST_DAY_OF_WEEK and assign value as SUNDAY.
Hope it solves your problem.
Thanks
Saurabh Kabra -
Calendar to get week number of current month
Hi All,
Description: Currently I am working on an application which require to calculate some data for current month from a database where I have the data of all the previous and current month of that year, I can take week number as criteria.
Help Required: I can find week of month or year using Calendar methods but how to find the first week on the current month only.
Lets suppose the current month is April so when I use, int weekofmonth = cal.get(cal.WEEK_OF_MONTH);
it will return me the number of present week however I want to get what would be the week number at the start of the month (April).
Hope I am able to describe my query properly.
Thanks in advance.
Amit/ ====================================================
Method: Get the desired Date format for the date
Developed By: Sandip Waghole [29-Jan-2010]
==================================================== /
public String getWeekNo(String strDate)
// input Date Format : M/dd/yyyy
int weekNo=0,i=0;
String strWeekNo=null;
int noOfDaysInTheYear=365;
int WEEK_STARTS_ON = 1; // Define the day on which week starts Sunday/Monday 1:Sunday 2:Monday
int firstDayNoInFirstWeekOfPresentYear=0; // Inititalize teh day on which week is starting in present year
int firstDayOfPresentYear=0; // Inititlize the 1st day of the present year whether Sunday/Monday/.....
int[] monthDaysArray = {31,28,31,30,31,30,31,31,30,31,30,31}; // Define array of the days as per months
int todaysDayNoInPresentYear=0;
int daysLateByFirstWeekStartedAfterYearStarted=0;
int intTemp=0;
//strDate="08/24/2000"; // For test purpose
StringTokenizer strDateTok = new StringTokenizer(strDate, "/ ");
int month = Integer.parseInt(strDateTok.nextToken());
int day= Integer.parseInt(strDateTok.nextToken());
int year = Integer.parseInt(strDateTok.nextToken());
GregorianCalendar cal = new GregorianCalendar();
// Check if present year is leap year
boolean boolIsLeapYear = cal.isLeapYear(year);
// If it is boolean year then add 1 to total days in the year & add one more day to february
if(boolIsLeapYear)
noOfDaysInTheYear=noOfDaysInTheYear+1;
monthDaysArray[1]=monthDaysArray[1]1;
// Find the 1st day of this year
Calendar calObj = new GregorianCalendar(year, Calendar.JANUARY, 1);
firstDayOfPresentYear = calObj.get(Calendar.DAY_OF_WEEK);
int intRemoveNoOfDaysFromWeek=0;
// # Find the day no of prsent day
for(i=0;i<month;i+) // get no of days till present year
intTemp = intTemp monthDaysArray;
todaysDayNoInPresentYear = intTemp - (monthDaysArray[month-1]-day);
if(firstDayOfPresentYear==6 || firstDayOfPresentYear==7) // If first Day is Friday or Saturday then it is week
// Identify the the day no on which 1st week of present year is starting
firstDayNoInFirstWeekOfPresentYear = 7 - firstDayOfPresentYear WEEK_STARTS_ON 1;
// Find delay in the 1st week start after r=the year start
daysLateByFirstWeekStartedAfterYearStarted = firstDayNoInFirstWeekOfPresentYear - 1;
// Now week is starting from Sunday
weekNo = (Integer)((todaysDayNoInPresentYear-daysLateByFirstWeekStartedAfterYearStarted)/7);
// Find the day no of today
intTemp = (todaysDayNoInPresentYear-daysLateByFirstWeekStartedAfterYearStarted) % 7;
if(intTemp > 0)
weekNo=weekNo+1;
else
weekNo=weekNo;
else
// 1st week is starting on 1st Of January
firstDayNoInFirstWeekOfPresentYear=firstDayOfPresentYear;
// Remove no. of days from the 1st week as week is starting from odd Sunday/Monday/Tuesday/Wednesday/Thursday
intRemoveNoOfDaysFromWeek = 7-firstDayOfPresentYear 1; // 1 added as include start day also
// So one week will be added in no. of weeks
weekNo = (Integer)((todaysDayNoInPresentYear-intRemoveNoOfDaysFromWeek)/7);
// Find the day no of today
intTemp = (todaysDayNoInPresentYear-intRemoveNoOfDaysFromWeek) % 7;
weekNo = weekNo +1; // As 1st weeks days are reduced from the todays day no in the year
if(intTemp > 0)
weekNo=weekNo+1;
else
weekNo=weekNo;
// Remove the no. of days from the week 1
strWeekNo=Integer.toString(weekNo);
return strWeekNo;
// Any issues please mail on [email protected] or [email protected] -
How to get week number and day in my result?
hi experts, i have given the data is ID and DATE(yyyymmdd),i want to get output like ID,DATE,WEEKNO,YEAR,MONTH,DAY. how to get this output.
thanks & regards
vijayIn a routine transformation you can call function
DATE_GET_WEEK
to get the week number from the date.
To determ the others, use the substring
YEAR = DATE(4)
MONTH = DATE+4(2)
DAY = DATE+6(2) -
Project Portal, MSP_Portfolio_Analyzer, date dimension faulty week number
Hi,
I am working on a MDX query on the MSP_Portfolio_Analyzer cube of Project and I have problem that the date dimension contain wrong week number. For instance if I browse the dimension to 2013, quarter 3, month September it says day 1 is on Week 36. When I
use datepart function to return week number for 2013-09-01 I receive week 35 which is supposed to be correct.
The format on one date from dimension is:
[Time].[Time].[Year].&[2013].&[3].&[9].&[36].&[2013-09-01T00:00:00]
The MDX query I am building is going to show forcast for capacity and worked hours, but I have problem when the week number is off compared with week number retrieved from now(). Any suggestion on how to solve this?
[Time].[Time].[Year].&[2013].&[3].&[9].&[36].&[2013-09-01T00:00:00]Hello,
This might help:
http://blogs.msdn.com/b/brismith/archive/2010/02/26/addressing-iso-8601-week-numbering-in-project-server-2007-and-2010.aspx
Paul
Paul Mather | Twitter |
http://pwmather.wordpress.com | CPS -
Get Week Number of Current Month
How can I get the week number of the current month (1-5)?
This is what I have tried and I'm not getting the expected
results.quote:
Originally posted by:
DJ5MD
Does your go 1-5 since it's only 30 days? Is that the
difference?
I think he was referring to your comment "How can I get the
week number of the current month (1-5)?". Some months can have 6
weeks so you should take that into account.
Both the function from cflib.org and his code should return 6
for 2007-09-30. -
How use locator with sax to get line number of an element?
dear friends,
it's clearly stated in subject. after trying for hours, i still couldn't figure out how to get line numbers. my class extends defaulthandler. please help.
ozgurhi
i am also struggling with same problem
someone plssssssss help.....
how can i use Locator to get line number of the XML document.
in my extended DefaultHandler class i have just implemented this,
public void setDocumentLocator(Locator location) {
lineNumber = location.getLineNumber();
but no help...
how to register my parser to the documnet locator events?
plzzzzzzz help...
-Soni -
How to get the week start date from ISO week number
Hi,
I have a table with the following stucture
Year error Week1 week2 week3 ......week53
2012 error1 2 4 2 1
2012 error2 3 0 1 1I was hoping to get something like select year, error, week1||'Week start date which is a monday of that week' , week2||'Week start date,again monday',....week53 from table
Any suggestions please?
Thanks,
SunHi, Sun,
To see when week N started, add 7 * (N - 1) days to the beginning of the year. (By definition, the beginning of the ISO year is the start of week 1 of the ISO year.)
To see when week 22 of the current year started:
SELECT TRUNC (SYSDATE, 'IYYY') + (7 * (22 - 1))
FROM dual
I hope this answers your question.
If not, post a little sample data (CREATE TABLE and INSERT statements, relevant columns only) for all the tables involved, and the results you want from that data.
Explain, using specific examples, how you get those results from that data.
Always say what version of Oracle you're using.
See the forum FAQ {message:id=9360002} -
Problem in getting week number
I am facing a problem regarding use of Calendar object.
I have used it to calculate Week_Of_The_Year where
the week day starts with Monday. (Mon - Sun)
Its working perfectly except the last week of this year i.e. 2004
where I want it to return fiscal week 53 , but instead its returning
1 (as because the January 1-2 ' 2005 lies in that specific week.)
and in the same manner its giving problem for the first week of the
next year i.e. 2005 .Its returning Fiscal week(FW) 2 for the
January 3-9 ' 2005 period where as I want it to return FW 1 for that
week.
here is the code snippet,
public int getWeekNumber(String dateString) {
Calendar cal = Calendar.getInstance();
java.util.Date dt = new java.util.Date(dateString);
cal.setTime(dt);
cal.setFirstDayOfWeek(Calendar.MONDAY);
int weekNumber = cal.get(Calendar.WEEK_OF_YEAR);
return weekNumber;
where as date string is in mm/dd/yyyy pattern.
Please, let me know if I could clearly explain the problem to you .
I am stuck with this problem with quite some time. If anybody can crack this
problem i will be grateful.
Thanks in advance.Haven't tried it, but have you tried playing with Calendar's setMinimalDaysInFirstWeek method? That is supposed to specify how many days must be in that first week of the year. You may need to read the Calendar API more closely.
-
Display ISO week number instead of date on x axis in Bar Chart
Hi,
I've created a simple SSRS report based on bar chart that shows several milestones. Everything works fine for me except I’m not able to convert the date into ISO week number format.
I played around with different approaches. I was able to convert the date into an ISO week Format directly on the SQL Server. That
wasn't a problem.
But unfortunately I’m not able to display the week number on the horizontal axis in my Bar Chart. I tried both fields: TaskFinishDate and TaskFinishDateMS...
I would like to show the ISO week number instead of the date within the Bar Chart on the horizontal axis.
Any ideas/hints/help is really appreciated!
Thanks,
MikeHi Mike,
Per my understanding that you want to get the week number of the year based on the field "TaskFinishDate" which is datetime type and display the week number in the x-axis instead of the field "TaskFinishDate", right?
I have check the snapshot you have provided and it seems you have change the format of the datetime field in the x-axis like "dd.MM.YYYY", If you can't make the week number to display correctly in the x-axis, the issue can be caused by you haven't
change the format to Number in the category.
Details information below for you reference:
I assume you have use expression in the Label like below to convert the datatime TaskFinishDate in to ISO week number like below:
=DatePart(DateInterval.WeekOfYear,Fields!TaskFinishDate.Value)
or
=DatePart("ww",Fields!TaskFinishDate.Value)
Right click the X-axis and select the "Horizontal Axis Properties", then click the Number to change the format to "Number" as below:
Preview you will get the weeknumber display in the x-axis correctly.
If you still have any problem, please feel to ask.
Regards,
Vicky Liu
If you have any feedback on our support, please click
here.
Vicky Liu
TechNet Community Support -
How to calculate start date of the week based on week number ?
i need to get week number of the current date and based on that i need to calculate start date falling in the same week for last year.
Eg. today is 31st week of year and 31st july date. so what will be the date on the 31st week of last year. i need the start date of that week.
we can calculate the week number by select to_char(sysdate,'ww') from dual.
DO we have a single line query for that or will it require writing a pl/sql block ?you can try following query
it can be as inline but for more clean look and create it as select with include select
with t as
(select sysdate as dt from dual)
select to_char(prev_year_dt - to_char(prev_year_dt, 'D') + 1, 'DD.MM.YYYY') as start_of_week from (select
-- get day from prev year with the same week number
case
when to_number(to_char(add_months(dt, -12), 'WW')) > to_number(to_char(dt, 'WW')) then
dt - (to_number(to_char(add_months(dt, -12), 'WW')) - to_number(to_char(dt, 'WW'))) * 7
when to_number(to_char(add_months(dt, -12), 'WW')) < to_number(to_char(dt, 'WW')) then
dt + (to_number(to_char(dt, 'WW')) - to_number(to_char(add_months(dt, -12), 'WW'))) * 7
else
add_months(dt, -12)
end as prev_year_dt
from t) t1good luck
Sergii
'Monday' is not first day of week in 100% ;)
Edited by: Galbarad on Jul 30, 2012 11:00 PM
Maybe you are looking for
-
I am trying to watch a tv show that I purchased into I-tunes. I have the cable and it hooks to the TV okay. The TV shows the regular apple screen that looks like the universe screen - like when it boots up or is doing an upgrade on the OS. I can't
-
BlackBerry Desktop Software Is their a download for Mac desktop Os 10.5.8
Hi I was wondering if their is an archive within Blackberry where I could download a BlackBerry Desktop Software for my mac. I am useing 10.5.8, the new version is for 10.6 or higher. Regards Vintage Tec head 8088
-
Automatic creation of Warehouse No. data in the material master
Hi all, I want the automatic creation of Warehouse No. data in the material master record at the time of the first goods receipt is allowed. Similar to the way where we can do the same for Storage Location by clicking on Create SLoc. automatically i
-
Problem in Hiding the objects in Forms
Hi I have a requirement to use a standard Adobe form & Interface. In which i need some fields should be binded with custom objects and some should objects needs to be hidden form the form based upon the condition. I did the logic for the Hidden part
-
Document management for home use
Hello, I am going to / wanting to scan all documents (bills, insurance stuff, tax, ...) that I receive and want to archive it on my machine. For that I'm looking for some document management system suitable for home use. While I'm not afraid of some