Upgrading from R12.1.1 to R12.1.2

Hi,
I have the following configuration:
Oracle Enterprise Linux:5.3
EBS Version:R12.1.1
Database version:11.1.0.7
OracleAS 10g Forms and Reports:10.1.2.3.0
OracleAS 10g: 10.1.3.4.0
Please explain is it recommended to upgrade all Tech stack Components before upgrading from R12.1.1 to R12.1.2
I am upgrading from R12.1.1 to R12.1.2 without upgrading any tech stack components, as it requires minimum versions and R12.1.1 tech stack components are supporting those versions
Can i go ahead on production after applying it on test
will it create any problem, if i could upgrade tech stack components later, will it be a problem for me
Please explain...
Thanks,
Alig
Edited by: user12257829 on Aug 17, 2010 12:30 AM

Hi
Hussein
While Upgrading from R12.1.1 to R12.1.2 faced many errors(Applied 8502056 patch) and then applied 7303033
first adrelink failed.
1. An error occurred while relinking application programs.
Continue as if it were successful [No] : Yes
but i entered Yes to continue as my OS is OEL 5.3 binutil version is binutils-2.17.50.0.6-9.el5
as my system binutil is updated one but in the note at MOS 758831.1, binutils-2.17.50.0.6-6.0.1.el5.x86_64.rpm, this doesnt apply to my system as my binutil is updated one.
2. The following Oracle Forms objects did not generate successfully:
au resource OKLCSASD.pll
An error occurred while generating Oracle Forms library files.
Continue as if it were successful [No] : Yes
as i entered yes to continue with the patch and tried to compile OKLCSASD.pll thru adadmin and manully aslo but didnt succeed.
The patch is completed atlast, and a huge number of invalid objects where created ..
I tried to recompile thru admin,utlrp,adcompsc.sql & utl_recomp.recomp_parallel but unable to compile a single objects
How could i make sure that patch is applied successfully & recompileinvalid object
find below invalid objects
BIS_MEASURE_SECURITY_PVT
BIS_INDICATOR_REGION_PVT
BIS_TARGET_LEVEL_PVT
BIS_ACTUAL_PUB
ENG_ECO_PUB
BIS_PMF_REG_SERVICE_PVT
ENGECOBO
AS_SALES_LEAD_OPP_PVT
BISVIEWER_PMF
BIS_PMF_DEFINER_WRAPPER_PVT
IES_TELESALES_BP_PKG
OKL_REVERSE_CONTRACT_PVT
OKL_CONTRACT_PVT
OKL_AM_PARTIES_PVT_W
OKL_AM_CREATE_QUOTE_PVT_W
OKL_AM_REPURCHASE_ASSET_PVT_W
OKL_AM_RESTRUCTURE_QUOTE_PVT_W
OKL_AM_SEND_FULFILLMENT_PVT_W
OKL_SPLIT_ASSET_PVT_W
OKL_TRX_QUOTES_PUB
OKL_CONTRACT_REBOOK_PUB
OKL_AM_TERMNT_QUOTE_PUB
OKL_TXL_QUOTE_LINES_PUB
OKL_TRANSACTION_PUB
OKL_ACTIVATE_ASSET_PVT
OKL_GENERATE_ACCRUALS_PVT
OKL_ASSET_DETAILS_PVT
OKL_AM_ASSET_DISPOSE_PVT
OKL_ACTIVATE_IB_PVT
OKL_AM_PROCESS_ASSET_TRX_PVT
OKL_AM_QA_DATA_INTEGRITY_PVT
OKL_AM_PARTIES_PVT
OKL_AM_ASSET_RELOCATION_PVT
OKL_AM_UTIL_PVT
OKL_AM_ASSET_RETURN_PVT
OKL_BLK_AST_UPD_PVT
OKL_CONTRACT_BOOK_PVT
OKL_KBK_APPROVALS_WF
OKL_COPY_ASSET_PVT
OKL_AM_CONSOLIDATED_QTE_PVT
OKL_AM_CREATE_QUOTE_PVT
OKL_AM_CALCULATE_QUOTE_PVT
OKL_CS_CREATE_QUOTE_PVT
OKL_CS_WF
OKL_CURE_CALC_PVT
OKL_EQUIPMENT_EXCHANGE_PVT
OKL_FUNDING_WF
OKL_INTEREST_CALC_PVT
OKL_LA_JE_PVT
OKL_CREATE_KLE_PVT
OKL_LCKBX_CSH_APP_PVT
OKL_LIKE_KIND_EXCHANGE_PVT
OKL_AM_BTCH_EXP_LEASE_LOAN_PVT
OKL_AM_LEASE_LOAN_TRMNT_PVT
OKL_AM_LOAN_TRMNT_PVT
OKL_LOSS_PROV_PVT
OKL_AM_LEASE_TRMNT_PVT
OKL_MASS_REBOOK_PVT
OKL_MISC_TRANS_PVT
OKL_QA_DATA_INTEGRITY
OKL_AM_QUOTES_WF
OKL_CONTRACT_REBOOK_PVT
OKL_CURE_RECON_PVT
OKL_RELEASE_PVT
OKL_REV_LOSS_PROV_PVT
OKL_AM_REPURCHASE_ASSET_PVT
OKL_AM_RESTRUCTURE_RENTS_PVT
OKL_AM_RESTRUCTURE_QUOTE_PVT
OKL_AM_RECYCLE_TRMNT_PVT
OKL_AM_PROCESS_RV_TRX_PVT
OKL_AM_RV_WRITEDOWN_PVT
OKL_AM_SEND_FULFILLMENT_PVT
OKL_LA_STREAM_PVT
OKL_SPLIT_CONTRACT_PVT
OKL_SPLIT_ASSET_PVT
OKL_AM_SV_WRITEDOWN_PVT
OKL_AM_AMORTIZE_PVT
OKL_TRANS_CONTRACTS_PVT
OKL_AM_TERMNT_QUOTE_PVT
OKL_CS_TRANSFER_ASSUMPTION_PVT
OKL_TRANSACTION_PVT
OKL_VARIABLE_INTEREST_PVT
OKL_GENERATE_ACCRUALS_PUB_W
OKL_VP_K_ARTICLE_PUB_W
OKL_AM_CONSOLIDATED_QTE_PUB_W
OKL_AM_CREATE_QUOTE_PUB_W
OKL_TRX_QUOTES_PUB_W
OKL_CONTRACT_REBOOK_PUB_W
OKL_AM_REPURCHASE_ASSET_PUB_W
OKL_AM_RESTRUCTURE_QUOTE_PUB_W
OKL_AM_SEND_FULFILLMENT_PUB_W
OKL_SPLIT_ASSET_PUB_W
OKL_TRX_ASSETS_PUB_W
OKL_TRX_CONTRACTS_PUB_W
OKL_TRANS_CONTRACTS_PUB_W
OKL_TXL_QUOTE_LINES_PUB_W
OKL_TRANSACTION_PUB_W
AST_UWQ_WRAPPER_PKG
OKL_AM_CNTRCT_LN_TRMNT_PVT
OKL_CS_PRINCIPAL_PAYDOWN_PVT
OKL_SERVICE_INTEGRATION_PVT
OKL_AM_TERMINATE_INV_AGMT_PVT
OKL_AM_TERMNT_INTERFACE_PVT
CSC_ACTION_ASSEMBLER_PVT_W
OKL_AM_SYSTEM_PARAMS_PUB
OKL_VENDOR_AGREEMENT_PUB
OKL_AM_INTEGRATION_PVT
OKL_PERIOD_SWEEP_PVT
OKL_SEC_AGREEMENT_PVT
OKL_VSS_WF
OKL_SSC_WF
OKL_AM_SYSTEM_PARAMS_PUB_W
WSH_IB_TXN_MATCH_PKG
WSH_RCV_CORR_RTV_TXN_PKG
WSH_IB_UI_RECON_GRP
OKL_AM_BAL_WRITEOFF_PVT
OKL_VP_SYNC_CR_PVT
OKL_CREDIT_LINE_WF
OKL_PROP_TAX_ADJ_PVT
OKL_PROCESS_PPD_PVT
OKL_LA_SALES_TAX_PVT
OKL_AM_TERMNT_VENDOR_PRG_PVT
OKL_AM_VENDOR_RES_SHARE_PVT
OKL_MULTIGAAP_ENGINE_PVT
one thing important while generating .pll/.fmb thru adadmin it asks for FND_INSTALL_PROCESSES & AD_DEFERRED_JOBS to be dropped, if we select to drop it will drop this tables and patch process will not continue if these tables were dropped and created for .pll/.fmb generation
How to avoid this  & to apply patch cleanly
Thanks,
Alig
Edited by: user12257829 on Aug 19, 2010 3:56 AM
Edited by: user12257829 on Aug 19, 2010 3:59 AM

Similar Messages

  • Is it really necessary to Upgrade from Oracle EBS R11i to R12?

    Hi,
    Oracle Applications 11.0.3 (Oracle Financials) was implemented in our company and later in 2006 it was upgraded to 11.5.10 (with new implementation of Supply Chain Management Module - INV,OM and PO) and 2 months ago we upgraded it to 11.5.10.2+DB 11gR2.
    I've been recommending to upgrade to R12 but the Finance Users are reluctant for an upgrade and of the opinion that the R12 has many bugs and there will be issues after upgrade to R12.
    Once of the consultant is of the opinion that its better to re-implement R12 instead of Upgrade. He also tells me that R12 does not have sub-accounting and sub-ledger and trial balance reports in AP.Since I am not a Functional Consultant I could not comment on this.
    Please advice if there are any useful docs which address the upgrade to R12 issues which I can share with our consultant and users.
    I am currently going thru +Upgrade Advisor: Oracle E-Business Suite Financials and Projects Upgrade from 11.5.10.2 to 12.1.3 and 12.1.2 [ID 256.1]+
    Rgds,
    Thiru

    user1983888 wrote:
    Hi,
    Oracle Applications 11.0.3 (Oracle Financials) was implemented in our company and later in 2006 it was upgraded to 11.5.10 (with new implementation of Supply Chain Management Module - INV,OM and PO) and 2 months ago we upgraded it to 11.5.10.2+DB 11gR2.
    I've been recommending to upgrade to R12 but the Finance Users are reluctant for an upgrade and of the opinion that the R12 has many bugs and there will be issues after upgrade to R12.
    R12.1.x is a stable release that many customers (including Oracle themselves) have upgraded to.
    Once of the consultant is of the opinion that its better to re-implement R12 instead of Upgrade. He also tells me that R12 does not have sub-accounting and sub-ledger and trial balance reports in AP.Since I am not a Functional Consultant I could not comment on this.
    The Finance modules have been completely re-written and fucntionality had changed for the better. Re-implementation typically costs upto 3 times more than a upgrade. Re-implementation is not necessary if the business model and process have not changed. What are the consultants justifications for doing a re-implementation (other than making more money) ?
    Please advice if there are any useful docs which address the upgrade to R12 issues which I can share with our consultant and users.
    I am currently going thru +Upgrade Advisor: Oracle E-Business Suite Financials and Projects Upgrade from 11.5.10.2 to 12.1.3 and 12.1.2 [ID 256.1]+
    Pl see the Docs referenced in MOS Doc 850008.1 (Interesting Documents Concerning E-Business Suite 11i to R12 Upgrades)
    Rgds,
    ThiruHTH
    Srini

  • Upgrade from 11.5.9 to R12.1.1

    Hi,
    We have 11.5.9 CU2 with 9.2.0.7 database running on solaris 8, we would like this to be migrated and upgraded to 12.1.1 with 11.1.0.7 database on RHEL4. Could anyone confirm whether this approach is fine?
    1. Upgrade the source database on solaris 8 to 10.2.0.4
    2. Migrate the database from solaris 8 to RHEL4 by TDB/TTS or Exp/Imp
    3. Install R12.1.1 file system on RHEL4 using the upgrade option in rapid install
    4. Apply the R12.1.1 upgrade patch driver
    5. Upgrade the database to 11.0.7 on RHEL 4
    Thanks
    Murali

    Hi,
    1. Upgrade the source database on solaris 8 to 10.2.0.4
    2. Migrate the database from solaris 8 to RHEL4 by TDB/TTS or Exp/ImpCorrect.
    3. Install R12.1.1 file system on RHEL4 using the upgrade option in rapid install
    4. Apply the R12.1.1 upgrade patch driver
    5. Upgrade the database to 11.0.7 on RHEL 4Correct -- Refer to these documents for details.
    Note: 761570.1 - Database Preparation Guidelines for an E-Business Suite Release 12.1.1 Upgrade
    Note: 802875.1 - Interoperability Notes Oracle EBS Release 12.1 with Oracle Database 11gR1 (11.1.0)
    Regards,
    Hussein

  • Applimation Setup Reporter upgrade from Oracle eBS R11i to R12

    Hi,
    A prospective customer would like to carry out Applimation Setup Reporter upgrade when upgrading Oracle eBS from R11i to R12
    Would appreciate if one could share their experience and things to watch out when carrying out Applimation Setup Reporter upgrade.
    Best regards,
    Bratindra Dutta.

    Hello,
    this forum is dedicated for migrations from non-Oracle to Oracle databases, using the SQL Developer Migration Workbench.
    You can post your question in the eBS forum: https://forums.oracle.com/forums/category.jspa?categoryID=3
    But as the question is about an Applimation Setup Reporter upgrade you should also consult the vendor of that product.
    Regards
    Wolfgang

  • Upgrading from 11.5.9 to R12.1.3

    Hi ,
    i have searched forum and gone through many docs and links but still have not found the exact list of patches to be applied as a part of pre and post upgrade tasks .
    Oracle Applications Upgrade Guide Release 11i to 12.1.1 (Doc ID 1082375.1) . in this doc also i have not got the list of patches as post upgrade
    can anyone please help me with list of patches to be applied as part of pre n post upgrade tasks .
    Regards .

    Please refer to these docs/links for the recommended patches (if no patches are mentioned in the upgrade docs as a post steps, then there is nothing to apply. However, consider applying the recommended patches for the modules you have).
    Database Preparation Guidelines for an E-Business Suite Release 12.1.1 Upgrade [ID 761570.1]
    Oracle Applications Current Patchset Comparison Utility - patchsets.sh [ID 139684.1]
    Latest E-Business Suite Applications Recommended Patch List [ID 123456.1]
    EBS: R12.1 Oracle Financials Recommended Patches [ID 954704.1]
    Oracle HRMS Product Family - Release 11i and Release 12 Information [ID 135266.1]
    MOS website > Patches & Updates > Recommended R12 Patches
    MOS website > Patches & Updates > Latest R12 Packs
    Oracle E-Business Suite Release 12.1.3 Now Available
    http://blogs.oracle.com/stevenChan/2010/08/ebs_1213_available.html
    Thanks,
    Hussein

  • After upgrade from 11.5.10 to R12.2.3, While terminating employee, i got the below error.

    APP-PER-51938: The system could not find the program unit being called. This could be because the application API pre-processor has not been run.
    Contact your system administrator quoting the following details: Error ORA-06508 in API Module PER_PERIODS_OF_SERVICE at hook after update.

    Thanks for the reply. But there is no Custom User Hook attached.  Moreover i checked all the user hooks are in Valid state.

  • Upgrade from 11i projects to r12 projects

    Can anyone provide me with a document on how to upgrade from existing 11i projects to R12 projects?
    Or if you let me know the pre-requisites that would be of great help me to me.

    You will need to follow the standard R12 upgrade process. You will first need to upgrade to 12.1.1 (http://download.oracle.com/docs/cd/B53825_03/current/acrobat/121upgrade.pdf), then apply the R12.1.3 patch (MOS Doc 1081434.1- Oracle Projects Release 12.1.3 Readme)
    MOS Doc 256.1 (Upgrade Advisor: Oracle E-Business Suite Financials and Projects Upgrade from 11.5.10.2 to 12.1.3 and 12.1.2) may also be relevant.
    HTH
    Srini

  • Steps to upgrade OBIA source EBS 11 to R12

    Hi,
    We have a specific requirement that our EBS source got upgraded from 11.5.10 to R12.
    Earlier OBIA Financial,HR Analytics is running successfully. Now we need to map it to R12 source.
    Can any one had done this already please suggest required steps.
    In my openion  changing folders in DAC to point to R12 adaptors and changing files with latest R12 data would work.
    Fyi..We haven't done any customizations in the OOB adaptor.
    Thanks in advance.
    Regards,
    Raj
    [email protected]

    You will need to install 11.2.0.4 into a new ORACLE_HOME, apply the latest 11.2.0.4 PSU patch to the new ORACLE_HOME (see MOS Doc 1454618.1) and then follow the steps in the Upgrade Guide
    http://docs.oracle.com/cd/E11882_01/server.112/e23633/upgrade.htm#UPGRD003
    see MOS Doc 1189783.1

  • Error - Upgrading from 12 0 4 to 12 0 6

    Hello:
    We are in the process of upgrading from 11 5 9 to R12.
    To be exact, we are upgrading from 12 0 4 to 12 0 6 on DB 10.2.0.4.
    The upgrade process errored on OMNDIAGMYGRATE.sql . Found an exact hit in Metalink (bug No 7115209).
    But no resolution found on the bug.
    Any idea ? Appreciate your help
    Thanks

    Looks like the bug is still open with no solution yet (11/21/08 03:22 am). Again, I would suggest you log a SR.

  • File- Export not working after upgrade from 11i to R12

    Hi,
    File -> Export not working after upgrade from 11i to R12.1.3 in few systems. Can you please let me know what could be the issue.
    If export record count more than 200 it is working fine in all the systems and if change the profile option "Export MIME type” value to ‘text/tab-separated-values’ from application/excel also it is wokring.
    Thanks and Regards,
    Jagadeesha

    Enabled the FRD. Below are few last lines. Can you please let me know what i can in this log file contents.
    In Argument 1 - Type: String Value: global.frd_debug
    Executing GET_ITEM_PROPERTY/FIELD_CHARACTERISTIC Built-in:
    In Argument 0 - Type: Integer Value: 196613
    In Argument 1 - Type: Number Value: 54
    Out Argument 0 - Type: String Value: 12
    Executing COPY Built-in:
    In Argument 0 - Type: String Value: Entering app_menu.set_prop.
    In Argument 1 - Type: String Value: global.frd_debug
    Executing FIND_MENU_ITEM Built-in:
    In Argument 0 - Type: String Value: FILE.EXPORT
    Out Argument 0 - Type: Integer Value: 19
    Executing GET_MENU_ITEM_PROPERTY Built-in:
    In Argument 0 - Type: Integer Value: 19
    In Argument 1 - Type: Number Value: 79
    Out Argument 0 - Type: String Value: TRUE
    Executing COPY Built-in:
    In Argument 0 - Type: String Value: Completed app_menu.set_prop.
    In Argument 1 - Type: String Value: global.frd_debug
    Executing COPY Built-in:
    In Argument 0 - Type: String Value: Completed app_synch.menu_toolbar_sync. Event is WHEN-NEW-ITEM-INSTANCE.
    In Argument 1 - Type: String Value: global.frd_debug
    Executing NAME_IN Built-in:
    In Argument 0 - Type: String Value: GLOBAL.APP_CUSTOM_MODE
    Out Argument 0 - Type: String Value: NORMAL
    Executing NAME_IN Built-in:
    In Argument 0 - Type: String Value: GLOBAL.APP_CUSTOM_MODE
    Out Argument 0 - Type: String Value: NORMAL
    Executing COPY Built-in:
    In Argument 0 - Type: String Value: NULL
    In Argument 1 - Type: String Value: GLOBAL.OUT
    Executing USER_EXIT Built-in:
    In Argument 0 - Type: String Value: FND GETPROFILE NAME="UPK_RECORDING_ENABLED" FIELD="GLOBAL.OUT" N
    FNDCPVCM, 11, Built-In, Entry, 316509814, USER_EXIT
    FNDCPVCM, 11, Built-In, Exit, 316509814, USER_EXIT
    Executing NAME_IN Built-in:
    In Argument 0 - Type: String Value: GLOBAL.OUT
    Out Argument 0 - Type: String Value: N
    Executing NAME_IN Built-in:
    In Argument 0 - Type: String Value: system.current_form
    Out Argument 0 - Type: String Value: FNDCPVCM
    Executing NAME_IN Built-in:
    In Argument 0 - Type: String Value: system.current_block
    Out Argument 0 - Type: String Value: MASTER
    Executing NAME_IN Built-in:
    In Argument 0 - Type: String Value: system.current_form
    Out Argument 0 - Type: String Value: FNDCPVCM
    Executing NAME_IN Built-in:
    In Argument 0 - Type: String Value: system.current_block
    Out Argument 0 - Type: String Value: MASTER
    Executing GET_APPLICATION_PROPERTY Built-in:
    In Argument 0 - Type: Number Value: 75
    Out Argument 0 - Type: String Value: IHR40P
    Executing COPY Built-in:
    In Argument 0 - Type: String Value: Completed call_all_libraries. Event is WHEN-NEW-ITEM-INSTANCE.
    In Argument 1 - Type: String Value: global.frd_debug
    Executing COPY Built-in:
    In Argument 0 - Type: String Value: Completed app_standard.event. Event is WHEN-NEW-ITEM-INSTANCE.
    In Argument 1 - Type: String Value: global.frd_debug
    FNDCPVCM, 10, Prog Unit, Exit, 316509814, /FNDCPVCM-3/P45_30_DEC_201223_28_33
    FNDCPVCM, 9, Trigger, Exit, 316509814, WHEN-NEW-ITEM-INSTANCE
    FNDCPVCM, 8, Prog Unit, Exit, 316509814, /DMU-4/P8_30_DEC_201223_23_12
    # 15 - FNDCPVCM:MASTER.USER_CONCURRENT_QUEUE_NAME.1359399301498413820
    WINDOW FNDCPVCM PROGRESS_INDICATOR RESIZE 4198 1500 3
    # 16 - FNDCPVCM:MASTER.USER_CONCURRENT_QUEUE_NAME.1359399301512613925
    WINDOW FNDCPVCM PROGRESS_INDICATOR RESIZE 4198 1500 3

  • Business Folder Upgrade from 11i to R12

    Hi,
    We are upgrading from 11.5.10.2 to R12.
    In the process, we have to upgrade discoverer folder also.
    To undergo the change, we are testing one report from 11i to R12.
    The report has the business folder as po_vendors in 11i, which is taking data from PO_VENDORS table from PO schema.
    As the PO_VENDORS table is obselete in R12.
    We are trying to change the PO_VENDORS table to AP_SUPPLIERS table and we are changing schema from PO to AP.
    We were able to do that in Disco Admin, but when I run the report from Desktop, we are not able to get the data.
    Where in SQLInspector we can that the query is changed, one more interesting thing is when we run the query from backend for exact set of parameters, its returning data.
    Is there anything which we need to take care, are we doing anything wrong.
    Please help.
    Thanks,
    S

    Hi,
    We are using 3 views and a materialized view.
    Object names are
    1) AP_INVOICES
    2) AP_INVOICES_DISTRIBUTIONS
    3) AP_SUPPLIERS
    now when we change the views to base tables for e.g. AP_INVOICES to AP_INVOICES_ALL and AP_INVOICES_DISTRIBUTIONS to AP_INVOICES_DISTRIBUTIONS_ALL then our report is givng data.
    PFB the query.
    SELECT DISTINCT o215482.SEGMENT2 as E215623,o215482.SEGMENT2_DESCRIPTION as E215625,o215476.ATTRIBUTE5 as E216133,o215482.SEGMENT4 as E216142,o215482.SEGMENT1 as E216190,o215482.SEGMENT3 as E216208,o215482.SEGMENT3_DESCRIPTION as E216210,o215476.INVOICE_DATE as E216817,o215476.PAYMENT_STATUS_FLAG as E217125,o215473.PERIOD_NAME as E217133,o215487.VENDOR_NAME as E217379,o215487.SEGMENT1 as E217385,(SUBSTR(o215476.INVOICE_NUM,1,12)) as E217632,as215592_217133_OLD as as215592_217133_OLD,o215473.AMOUNT as E215705,NVL(o215476.INVOICE_AMOUNT,0) as E216800
    FROM APPS.AP_INVOICE_DISTRIBUTIONS o215473,
    APPS.AP_INVOICES o215476,
    APPS.JS_GL_CODE_COMBINATIONS_MV o215482,
    AP.AP_SUPPLIERS o215487,
    ( SELECT o215509.PERIOD_NAME AS as215592_217133_OLD_2, MAX(o215509.START_DATE) AS as215592_217133_OLD FROM ( SELECT gl.period_name ,gl.start_date ,gl.end_date ,gl.period_set_name FROM gl.gl_periods gl ) o215509 WHERE (o215509.PERIOD_SET_NAME = 'JS_GL_Calendar') GROUP BY o215509.PERIOD_NAME)
    WHERE ( (o215476.INVOICE_ID = o215473.INVOICE_ID)
    and (o215482.CODE_COMBINATION_ID = o215473.DIST_CODE_COMBINATION_ID)
    and (o215487.VENDOR_ID = o215476.VENDOR_ID)
    and (o215473.PERIOD_NAME = as215592_217133_OLD_2(+)))
    AND (o215482.SEGMENT6 LIKE :"Project Parameter 1")
    AND (o215482.SEGMENT5 LIKE :"Category Code Parameter 1")
    AND (o215482.SEGMENT4 LIKE :"Business Unit Parameter 1")
    AND (o215482.SEGMENT3 LIKE :"Cost Centre Parameter 1")
    AND (o215482.SEGMENT2 LIKE :"Account Parameter 1")
    AND (o215482.SEGMENT1 LIKE :"Company Parameter 1")
    AND (o215473.PERIOD_NAME LIKE :"Period Name Parameter 1")
    AND (o215487.SEGMENT1 LIKE :"Supplier Number Parameter 1")
    AND (o215476.CANCELLED_DATE IS NULL )
    AND ( ( UPPER(o215473.LINE_TYPE_LOOKUP_CODE) = UPPER('ITEM') OR UPPER(o215473.LINE_TYPE_LOOKUP_CODE) = UPPER('FREIGHT') ) )
    ORDER BY o215482.SEGMENT1 ASC , o215482.SEGMENT3 ASC , o215482.SEGMENT2 ASC , o215482.SEGMENT4 ASC , o215487.SEGMENT1 ASC , o215487.VENDOR_NAME ASC , (SUBSTR(o215476.INVOICE_NUM,1,12)) ASC ;
    Kindly help.
    Thanks,
    S

  • Inventory Module Upgrade from 11i to R12 - How to Copy Inventory Orgs.

    Hi All,
    We are working on R12 Upgrade project for Item Conversion.
    Requirement is to upgrade and bring all the Item setup and data from 11i to R12.
    As part of setup requirement, there are around 1900 Inventory Orgs in 11i instance. Please let me know what is the best approach / strategy to copy and bring over the 1900 Inventory Orgs.including the Master Org from 11i to R12.
    Your inputs will be highly appreciated.
    Thanks in Advance !
    Regards,
    Nityanand.

    Reporting Set of Books (MRC) in 11i is called as Alternate Currency Ledgers (ALC Ledger) in R12.
    After 11i upgrade, the reporting SOBs (MRCs) will be automatically changed to ALCs in R12.
    Some are primary and some are used as reportingI hope you are talking about MRCs.
    When we upgrade from 11i to r12, all the SOBs would be created as primary ledgers (as per oracle)If they are not MRCs and it is getting upgraded as primay ledger, you may create new ALC for your requirement.
    In that case you may need a datafix from Oracle to fix the old data.
    By
    Vamsi

  • EBS upgrade from 11i to R12 using Maintenance Wizard question

    I have installed Maintenance Wizard in development envrionment. I picked module to upgrade 11i to R12. When I am defining the node it not only picked up 11i nodes but required me to configure R12 nodes. So Do I have to to create upgrade file system(for R12) and then configured R12 nodes in Define nodes? My configuration is in In configuration at this time as I did not configured R12 nodes.
    Please help me resolve this issue.

    My question is which database oracle_home we have to consider to upgrade R12? and What about another one oracle_home?
    When you run Rapid Install, provide the details of the already upgraded/installed 11.2.0.3 ORACLE_HOME.
    For 11gR1 ORACLE_HOME which is installed by Rapid Install, please see (How to upgrade Oracle E-Business Suite from 11i to 12.1.1 and keep the existing 10g Database? (Doc ID 1345020.1)).
    Thanks,
    Hussein

  • Upgrade from 11i to R12 - Custom Forms,Reports and Workflows

    Dear Community Friends,
    We are planning for upgrade from oracle apps 11.5.10.2 to R12.
    We have custom Forms,Form Libraries,Reports and Workflows.
    Kindly provide me for approach on how to migrate Custom form libraries,reports and Workflows.
    I beleive, this thread will exists as one shot point for custom forms,reports,workflow upgradation from 11i to r12 with detailed steps.
    I know that many links exists here in the forum for all the above objects mentioned,but still from all those i am able to get a clear picture for oracle forms but not for custom form libraries ,reports and workflows.
    Also,this post will provide a low level,practical picture of the steps for those who are in line with this.
    Links i have read for all these in our forum are:
    For Custom Forms,
    Re: Planning to upgrade from 11i to R12
    Re: Custom forms: After upgrading 11i to R12
    ofcourse,'n' number of links exists providing metalink notes also.
    Hussain,Helios and some others also has given many updates regd this.
    For custom workflow upgradation,
    Upgrade Workflow 11i to R12
    Workflow Upgrade
    Workflow Upgrade
    For reports,links mentioned the below metalink notes:
    Do Not Compile EBS R12 Reports Using rwconverter.sh or Reports Builder from IDS 10gR2 [ID 786794.1]
    Using the OracleAS 10.1.2 Forms and Reports Builders with Oracle Applications Release 12 [ID 444248.1]
    Per my understanding, after searching in many threads,i am here by summarising the practical low level steps for custom forms migration
    Please correct me,if i am wrong.
    1) Download the Forms(.fmb's) and all PLL's(all the PLL from resource folder in AU_TOP) into a Local Machine Folder
    2) Open the forms using Forms Developer 10G and connect to DB
    3) Compile by clicking compilein Forms Developer and then save it.
    4) Upload the Saved Forms(.fmb's) into the new R12 server(system) in the respective custom paths(paths similar to 11i Server)
    5) Compile all the forms using the command like below(example command is shown below or f60 gen commands or frmcmp.sh utility) in the respective custom form paths,
    this will generate the .fmx's.
    frmcmp_batch module=FORMNAME.fmb userid=apps/apps output_file=FORMNAME.fmx compile_all=yes
    Link for compiling forms: https://support.oracle.com/epmos/faces/ui/km/SearchDocDisplay.jspx?_afrLoop=359210362972527&type=DOCUMENT&id=1085928.1&displayIndex=3&_afrWindowMode=0&_adf.ctrl-state=c348xvwbg_98
    6) Open the form and check in R12 instance
    As per my understanding for custom form libraries,we can just copy paste the PLL's from 11i server to R12 server (Please correct me,if i am wrong)
    Can anyone please help me out in custom reports and custom workflows.Sorry that,i could not get a practical and clear picture for reports and also for workflow even after referring many threads and metalink notes mentioned.
    As for reports,some says that Developer Suite 10g can be used and .rdf can be used in R12.
    Some says that reports should be converted to XML published as reports does not exists in R12.
    So,i am not clear on this.
    Thanks,
    Ganesh
    [email protected]

    Per my understanding, after searching in many threads,i am here by summarising the practical low level steps for custom forms migration
    Please correct me,if i am wrong.
    1) Download the Forms(.fmb's) and all PLL's(all the PLL from resource folder in AU_TOP) into a Local Machine Folder
    2) Open the forms using Forms Developer 10G and connect to DB
    3) Compile by clicking compilein Forms Developer and then save it.
    4) Upload the Saved Forms(.fmb's) into the new R12 server(system) in the respective custom paths(paths similar to 11i Server)
    5) Compile all the forms using the command like below(example command is shown below or f60 gen commands or frmcmp.sh utility) in the respective custom form paths,
    this will generate the .fmx's.
    frmcmp_batch module=FORMNAME.fmb userid=apps/apps output_file=FORMNAME.fmx compile_all=yes
    Link for compiling forms: https://support.oracle.com/epmos/faces/ui/km/SearchDocDisplay.jspx?_afrLoop=359210362972527&type=DOCUMENT&id=1085928.1&displayIndex=3&_afrWindowMode=0&_adf.ctrl-state=c348xvwbg_98
    6) Open the form and check in R12 instance
    As per my understanding for custom form libraries,we can just copy paste the PLL's from 11i server to R12 server (Please correct me,if i am wrong)You are right, and the steps mentioned above should be sufficient.
    Can anyone please help me out in custom reports and custom workflows.Sorry that,i could not get a practical and clear picture for reports and also for workflow even after referring many threads and metalink notes mentioned.
    As for reports,some says that Developer Suite 10g can be used and .rdf can be used in R12.
    Some says that reports should be converted to XML published as reports does not exists in R12.
    So,i am not clear on this.You can still use RDF files in R12, and just follow the approach you mentioned above, and you do not have to migrate them to XML publisher (though it is recommended, but this can be done after the upgrade as an enhancement task).
    For custom workflow, you need also to do the same thing, open them using workflow builder and make sure they work in R12 (correct the code if required and save them again in R12 once they work properly).
    Thanks,
    Hussein

  • Upgrade from 11i to r12 application servers with Discoverer 10g

    Hello, one and all.
    I have recently upgraded from 11i to r12 Oracle financial application server, after much patching and testing we finally came to the Discoverer application server.
    Most workbooks open fine, however it seems that some of them (about 3%) reference columns that no longer exist in r12, for example, SET_Of_BOOKS_ID has become LEDGER_ID in r12 on the gl.gl_je_lines table.
    This causes any workbook that references that business area to return an error 'Database Error - ORA-00904: " O974567"."SET_OF_BOOKS_ID": invalid identifier.
    Well and good; I think that that's caused by the EUL not being refreshed after the upgrade, so I go to the Discoverer administrator and refresh the general ledger Business area. This unfortunately renames several objects inside the business area, including SET_OF_BOOKS_ID to LEDGER_ID, so instead of that error, we now get several 'Missing item or condition' errors until the workbook will not open at all with an 'Item dependency "" not found in the EUL.' error. This i assume is because the workbooks still reference the old items.
    I'm guessing that several Business areas and objects therein have been renamed since nearly none of the workbooks will open now. I have restored the EUL from a backup (imported all the *.eex files) however I was wondering if anyone had faced this issue.
    I apologize as I have very little understanding of Discoverer and this might be a simple fix, but I'm at this point willing to try anything for help.
    Thanks!

    user8612301 wrote:
    Hi Srini
    Srini,
    To understand your above reply,
    You say that
    1) If they are based on 11i Discoverer EUL and Folders then export EUL And WorkBooks and Import them
    into R12 Discoverer Environment..Refresh the EUL..So ORACLE will take care of the changes like 11i SOB vs R12 Ledegrs??Pl open a SR with Support on what to do with seeded EUL as part of this upgrade - I suspect you will need to import the R12 EUL as part of this upgrade.
    >
    2) If they are Custom SQL reports from 11i then just RECREATE them from SCRATCH..Correct - after you verify that they are changed to reflect the R12 data model
    >
    Am I right?
    thanks
    kp
    Edited by: user8612301 on Apr 20, 2011 8:57 AMSrini

  • Oracle E-Business Suit Upgrade from R12.0.6 +10.2.0.3 to R12.1.3 +11.2.0.2

    Dear Experts,
    Let me update you that one of our client is looking to upgrade their Oracle E-Business Suit Verion from R12.0.6 to R12.1.3. and database version from 10.2.0.3 to 11.2.0.2.
    Current all the financial and SCM modules are implemented on there production instance.
    We would like to know what are the pre and post upgrade activities needs to be performed ?
    What are the list of patches which needs to performed while doing an upgade from
    R12.0.6 to R12.1.1 - R12.1.3.
    Regards
    Mohammed.

    Please advise on the below approach....
    R12.1.1 to R12.1.3 upgrade high level steps
    Install upgrade / EBS Patch
    Pre-install R12.1     
    1. Setup hardware.     
    2. Install and setup OS.     
    Install R12.1.1     
    3. Install R12.1.1 (run Rapid Wiz)     
    Post –Install R12.1.     
    4. Upgrade Opatch in 10.1. home     
    5. Upgrade /patch OAS 10.1.2.3 (inc in R12.1.1)     
    6. Redeploye forms.ear     
    Pre-install R12.1.3     
    7. Upgrade OPatch in database home     
    8. Upgrade OPatch Database in 11.1.0.7     
    9. Upgrade OPatch in 10.1.3 Home     
    10. Upgrade /Patch OAS 10.1.3.4 to .5     
    11. Upgrade Java to 1.6_0_17 or lower     
    Install R12.1.3     
    12. Apply EBS R12.1.3 maintenance pack