Assigning more than 1000 orders in one WBS
Hi Experts,
I have a requirement of assigning more than 1000 Orders to one WBS element. As per SAP note, a maximum of 1000 Orders can be asssigned to one WBS otherwise system performance may get affected. But as per the client requirement, either I should allow more than 1000 Orders or System should give an error message when the assignment crosses this limit... I checked for User exits (for Orders) and could not find any for this... any experience / suggestions ?
Thanks
Bala
Hi,
If more than 1000 orders has been assigned under one WBS then the system performance will get slow.Whenever you are retriving some data or reports for that WBS the system response will be slow.
If the client requirement is like that then you can create more than 1000 orders,
orelse you can break the WBS in SUb WBS & create many orders under different head.
You can cretae more than 1000 orders under one WBS.The system wont give any error message.
Regards,
Raj
Similar Messages
-
MRP, more than planned order in one purchase ru00E9quisition.
Hello, friends
I have a problem with the MRP system that, we want to collect or convert more than planned order into one purchase requisition.
Regards.Lamier,
Purchase requisitions typically are never seen by Suppliers. They are internal documents to be managed by people in your own company.
There are several ways to manage your business requirement. Many companies use purchasing scheduling agreements, and some companies will automatically send the schedules to the Vendor. Refer to http://help.sap.com/saphelp_erp60_sp/helpdata/en/75/ee0f7455c811d189900000e8322d00/frameset.htm Other companies will select all of the approved/released purchase requisitions and copy them into a single Purchase order, which is then transmitted to the vendor using standard methods. Review this and other tips in http://help.sap.com/saphelp_erp60_sp/helpdata/en/75/ee11d955c811d189900000e8322d00/frameset.htm
For businesses where standard ERP functionality is inadequate, It is also possible to create custom development that will meet any business requirement.
If you are unsatisfied with the standard functionality offerings available in SAP ERP, you should contact Walldorf. Alternatively, SAP generally listens to the larger user groups, such as ASUG here in the US. I imagine that Algeria also is covered by a similar group. If enough people in the user groups ask for the same functionality, SAP is more likely to place it into future offerings.
http://www.asug.com/
Best Regards,
DB49 -
How to assign more than one inter-company customer?
Hi
I'm new to Inter-company sales process. Recently I configured and tested the inter-company sales process in the system and is working perfectly.
My Question: How can we assign more than one customer as inter-company customers to a sales organisation? In the standard process we are only able to assign one customer at a time as inter-company customer. Could you guide why this is?Does any one ever got such a requirement in project?
Regards
SanjayDear Reazuddin,
This is my client requirement. (Detail Missing in the question:: 7 Companies, 4 sales organisations, 6 Plants/facilities.)( It is involved in a lot of intercomany transactions. It wants its customers from its sales territories to be able to place order from the sales org. under that territory.) I do not know why does SAP not allow us to assign more than one inter-company customer?
Regards
Sanjeev
Edited by: winhearts kr on Nov 22, 2010 4:14 AM -
Can I assign more than one Pricing procedures to the one vendor.
Hi Gurus,
Can I assign more than one Pricing procedures to the one vendor.
If possible, where it can assign &give the procedure.
My client requirement is :
Vendor supply the goods from two different countries. So, pricing procedure is different because taxes are differ in two countries and currency also differs.
If goods are supplying from country u2018Au2019 ,automatically pricing procedure for that country was trigger. How the system know , which pricing schema is required.
Give me solutionHi,
Extend your vendor to new purchase organisation. Assaign new pricing procedure to this Purchase organisation.
Use different Purchase organisation while creating POs for the same vendor procuring from different countries.
Regards,
Satya
Edited by: Penjarla Venkata Satyanarayana on Aug 28, 2008 4:21 PM
Edited by: Penjarla Venkata Satyanarayana on Aug 28, 2008 4:23 PM -
How can we assign more than one request group to a responsibility?
Hi
Can anyone tell me how we can assign more than one request group to a responsibility?
Thanks
SSHi SS,
Its not possible, rather you should create a combination of Requests/RequestSets and create a new Request Group.
Regards,
Kiran -
Can we assign more than one fieldgroup to a single event ?
Hi,
Can we assign more than one fieldgroup to an event ?
I want pick few fields from each tab and show all those fields in my own tab is it possible to do so ?
vishalHello Vishal,
To show together fields which belongs to different tabs (this is, in the same event), you could use Multigroup feature (Application Elements -> Tab Page Group -> Multigroup). This feature allows you to group several events (with different field groups associated in main layout table) in only one (the even which manages the tab).
Hope this point help you. -
More than 3 AR for one Sales Order in relationship map
Hello,
i would need some advice on the following: If you have more than 3 Invoice for one Sales order these are not shown seperately in the relationship map. SAP could reproduce the issue and refers to it as normal system procedure at the moment. They adviced me to post a thread here.Is there any way you could make the invoices be seen one by one.
SAP Version 8.81 PL 5
Thanks a lot for any advices on this topic
Vanessa
Edited by: Vanessa Schürer on Jan 16, 2012 2:45 PMWelcome to the forum.
If you have any suggestions you post them on sap's new idea collaboration page. You do bring up a good point and hopefully in 8.82 it will be resolved as the relationship map was not originally on the road map. Hopefully they can develop this feature. -
Assigning more than one G/L accounts to WRX
Hi!
I want to assign more than one G/L accounts to WRX, I knew that it can be done through general modification. I have defined like below:
Valuation General G/L accounts
Modification Modification
IN I01 240940000
IN I02 240940001
IN I03 240940002
IN I04 240940003
IN I05 240940004
IN I06 240940005
IN I07 240940006
IN I08 240940007
IN I09 240940008
IN I10 240940009
IN I11 240940010
But i don't know how to assign these general modification to valuation class/movement types based on which GR/IR account has to be selected.
please guide me..
points will be rewarded...
rameshDear Ramesh ,
For a Transaction WRX you have to link Valuation Maodifier , Valuation class & GL Account No.
Typical Assigning will be as below
CAcct Trans VG AG Vclass G/L Debit G/L Credit
INT WRX 0001 VBR 3000 400000 400000
If useful reward points,
Vivek Maitra
Edited by: VIVEK MAITRA on Dec 24, 2007 12:27 PM -
Purpose of assigning more than one budget to a project
Dear Members,
In Oracle Projects Costing module, system allows us to assign more than one budget to a particular project.
Can any one please tell me what is the real time requirement and the purpose of this functionality.
Many thanks in advance.
Best Regards.Hi
Different budget types may be related to different managerial processes.
Examples -
For contract project you may setup a budget type to represent the amounts presented and approved by the customer, and set another budget type for internal management, may be with more granular budget entry method.
Companies may set the initial budget of the project, and not allow to update that. The use another type to represent more recent update of the project forecast. Then compare the forecast to original budget.
There could be separate budgets to control parts of the project costs. Like using a budget only for controlling external expenses. On that you enter budget amount only for materials, outside processing and sub-contracting expenditure types.
Dina -
Can we assign more than one sales org to one company code ?
can we assign more than one sales org to one company code ?
or one as to one only ?
why sales org is assigned at company code level why not on plant level ?
regardsMultiple sales organizations can be assigned to company code.
Company code is the highest organizational unit and plant and sales organization are assigned to it.
In the logistics module, Plant is the highest entity in the MM module and Sales organization is the highest entity in SD module. Basically with this assignment of plant and sales org to company code all the financial accounts are updated.
Assigning of Sales org to company code and not to plant is the standard functionality that helps map most business processes.
Regards
AK
Reward points if helpful -
Assigning more than one sold to party
Hiiiii..
1) i would like to know whether we can assign more than one sold to party to a contact person.....?
regards,
sanjanaHi sanjana,
Yes, in CRM ofcourse you can assign more than one soldto parties to a contact person.
You jst need to maintain relationships.
But in R/3 the same is not possible.
Best Regards,
Pratik Pate.
Reward with points if it is of any use to you! -
Assigning more than one G/L account to transaction key WRX
Can any one tell me where we can create General Modification keys in MM-FI integration
As i need to assign more than one GL account for transaction key WRX (GR-IR)Clearing account.
There may be one valuation grouping code with different General modifications thereby we can assign more than one G/L account to WRX transaction key.
Example:
Valuation grouping code or valuation modification = IN
General Modifications: I01,I02,I03,I04..
General Ledger Accounts: 240940000,240940001,240940002,240940003
IN I01 240940000
IN I02 240940001
IN I03 240940002
IN I04 240940003
But , I am unable to find, where we can define these general modifications ( I01,I02,I03)....
If any one knew please let me know...
Ramesh BHi
Tcode: obyc, double clickon WRX event key, slect Rules ....you can find General Modification option>
REgards
ss
Assing the points if useful -
Problem with Assigning more than one value to GROUP dynamically
Hi,
I have a problem with assigning more than one value to GROUP varible dynamically.
I am able to assign only one value dynamically through Initialization block
I have even tried with the ROW-WISE initialization blocks..
using this query..
SELECT 'GROUP', G.GROUP_NAME
FROM GROUP_MAP G
WHERE G.USER_NAME = ':USER'
if GROUP_1, GROUP_2 are two groups to be associated,
through this, i'm getting " GROUP_1;GROUP_2 " into GROUP variable ( seen from Narative view )
And the properties and securities of this Groups are not inherited.
Please let me know if there is any other way to Populate the GROUP variable dynamically with more than one value.
Thank you.,Hi,
i finally got in this way..
i had created a function which takes USER_NAME as input and returns a string that contains the GROUP names with semicolon delimeted..
Though it is same as that of ROW-WISE initialization,
the properties of those groups are also being inherited..
Now, i can assign more than one groups and its properties to a user dynamically. -
Intercompany sale - how can i assign , more than 1 sales org of diff compan
Hi,
I have
comp1 - Sales org 1 - plant 1
comp2 - Sales org 2 - plant 2
comp3 - Sales org 3 - plant 3.
Now i want to do Intercompany sale of Sales org2 with plant 1 & Intercompany sale of sales org3 with plant 1.
For that how can i assign , more than 1 sales org of diff company codes to Plant1 ??
Does SAP allow to do intercompany sale for more than 1 diff sales orgs ??
Thanks for immediate response.
NitinHi nitin,
as per your scenario,
Company code 1 orders goods through its sales organization 1 from Plant 2 belonging to Company code 2.
It is imperative that both Plants 1 & 2 should have the material. In other words, the material is created for both the Plants 1 & 2 + their respective storage locations.
Sales Organizations and Plants are uniquely assigned to Company codes. It is not possible to assign either a plant or a sales organization to more than one company code.
Sales organizations and plants assigned to each other need not belong to the same company code.
In other terms,
a plant belonging to Company code 1 & assigned to Sales Organization 1 can also be assigned to Sales Organization 2 of Company Code 2.
CONFIGURATION SETTINGS
Assign Delivery Plant of the supplying company code to Sales Org + Distribution channel of the Ordering company code in the Enterprise Structure.
DEFINE ORDER TYPES FOR INTERCOMPNY BILLING:
Menu path: IMG/ SD/Billing/Intercompany Billing/Define Order Types for Intercompany billing
Assign Organizational units by Plant:
Menu Path: IMG/ SD/Billing/Intercompany Billing/Assign Organizational units by Plant.
Define Internal Customer Number By Sales Organization:
Menu Path: IMG/ SD / Billing/ Intercompany Billing/ Define Internal Customer Number By Sales Organization:
Creating / Showing Ordering Sales Organization as Internal Customer for Supplying Company code:
Transaction Code: XD01
The ordering sales organization is represented as Internal customer of Supplying company code.
We need to create customer master in Account Group - Sold to Party and maintain minimum required financial & Sales Area data.
This internal customer number has to be assigned to the ordering sales organization. Hence, the system automatically picks up this Internal customer number whenever there is Intercompany billing.
Thanks,
Raja -
COPA - Multiple Sales Order with one wbs element. COPA does not reference
COPA - Multiple Sales Order with one wbs element. COPA does not reference of reference of sales order.
Hi All
Currently we are in process of implementation of project related to Club Service for one of the client.
Concept of this project is - there is "X" company engaged in supporting the different shared services for their client e.g. Client IBM - Shared Support Services of IBM is
u2022 IDM
u2022 Software Installation
u2022 Help Desk
u2022 Maintenance
Co.. "X' is performing these services for IBM. So for Co. "X" - IBM is one engagement. Like this way Co. X is performing such activities for many companies e.g. microsoft, HP, ABN AMRO etc.
Objective - Get the consolidate report from COPA (Customer wise/services wise/sales order wise e.g. IBM/HelpDesk/10002/10).
We propose a solution to create a project for each engagement and with WBS element. Each WBS element of different services e.g.
Project IBM Inc. 100.100
WBS Element 100.100.IDM
WBS Element 100.100.SoftIns
WBS Element 100.100.HelpDesk
WBS Element 100.100.Maintainance
For this engagement (IBM), we are creating a sales order with line items (for services) and account assignment is WBS element. In a sales order, there may be two lines for one services. In a particular period, there are many such sales orders for this engagement... Milestone billing/period billing is used depending upon the services rendered.
Now Cost Object will be WBS Element. So cost and revenue will posted to WBS and from this it goes to COPA. In a month of May 2009 two - sales order is booked with three different line items with account assignment is WBS element.
Sales Order Line Item No.....Item Account Assignment Revenue
10000 100 IDM 100.100.IDM 1000
10000 200 HELPDESK 100.100.HelpDesk 2000
10000 100 Maintenance 100.100.Maintainance 3000
Another Sales order booked with two different line items
10000 100 IDM 100.100.IDM 3000
10000 200 HELPDESK 100.100.HelpDesk 4000
Cost will be booked directly against WBS element.
In sales order level, there is no profitability segment, as cost object is WBS element.
Billing, revenue will be posted directly to wbs element, from this revenue and cost of sales goes to COPA.
Now in COPA,
1.There is only one line for WBS element ex. 100.100.IDM with revenue 4000 (combing both the sales order)
2.There is only one line for WBS element ex. 100.100.HelpDesk with revenue 6000 (combing both the sales order)
3.There is only one line for WBS element ex. 100.100.Maintainance with revenue 4000
In above case 1 & 2 we will not have reference of sales order and sales order line item in COPA table. There is only one line for this. So we can not have reporting to sales order level.
Is there any way by this the reference of sales order and sales order line will come in COPA for case 1 & 2.
Please help in this issue.
Regards
Abhay Dev
Ph:- 91-22-67782229
Cell:- 91-9819175185Hi,
For these case (multiple materials with different characteristics); have you consider going to next level of WBS Elements. Meaning; lets say currently you are assigning WBS "Engineering (which is a level 2 WBS)" to all the items in SO. Instead under "Engineering" create 2 or 3 level 3 WBS Elements as E1, E2 etc and assign them 1:1 to your sales order line items. This would eliminate the exit as welll as complex development option. And also will let you get all the data in COPA and in turn you can pull to BW as well for reporting. Just a thought.
Regards
Sreekanth
Maybe you are looking for
-
Monitor Print Queue with java program
I'm plan to write a client/server based application which control the printing for every user. I've no idea how to start on the application. 1. Is it possible to monitor the print queue or print job using java application? 2. How does the server reac
-
How do I select then send Photos from photo stream to I Photo to edit? My photo ends up not transferring or is shown as black space with name below, without photo in I Photo. Any one have an answer?
-
Ugh! Please restore old Terminal.app focus-follows-mouse behavior!
The 10.4 and prior Terminal.app's focus-follows-mouse feature allowed one to type into the terminal by mousing over it even if the Terminal wasn't the currently focussed application. It didn't focus Terminal when you did this, but did direct keyboard
-
Check the frequency a report is run
Hello experts, I like to know if there is a way to find out how often a custom abap report is run and who the user is ? Is there anything in sap that i can use ? Any suggestions is appreciated and awarded. Thanks Joyce
-
Any function that can get me occurance of a particular char in a string?
Hi All, I want to calulate occurance of a semi colon in the following string , so i can achieve this using connect by but I am looking to use a function(preferably an oracle built in function) string : ';1;2;3;4;5;6;7;8;9;' Regards Rahul