ATP Check include in MRP and Exclude on Process order

Dear all,
We have a situation if we include reservations, deliveries and dependent requirements in ATP check in OPJJ, the system behaviour is that it includes all of them during MRP run. On process order level if we perform ATP check the system shows that all materials are available as it includes the dependent requirements and deliveries as well. we want to exclude dependent requirements and deliveries from ATP check on process order level so that it can only consider the quantities that are available in stock. and system will block the release of process order in case of short fall. as system includes dependent requirements and deliveries as well it always shows the msg that all material are available. Plz help and reply soon...... any suggestions or work arounds are always well come ..............

Hi
as i understand from ur question u dont want to considered dependent requrement and delivaries for
this go to t code OPJJ and do not select dependent requrement and delivaries tick.
after that go to t code OPJK and select material avalability as -03-No creation if material is missing
hope this will help u
regards
sachin

Similar Messages

  • Using Component scrap differently in MRP and in production/process orders

    Hello Gurus,
    We use Component scrap in our BOMs.
    MRP calculates the requirements including the scrap and that is fine. Is there a way that when we create production/process orders the components' required quantity will not include the scrap automatically? We don't want the components to be issued with the additional scrap, but rather issue the scrap by request only if required.
    Thanks

    Not possible.
    The SAP logic is tht procurement of RM and Production & consumption has to be in line. Functionally tht is ideal

  • CRM ATP Checking using R/3 & Immediate Delivery for Sales Order Type in R/3

    We use CRM 4.0 and R/3 6.4.
    I've configured CRM to do ATP Checking using R/3.  The ATP Checking works fine if I change the Sales Order Type in R/3 to NOT create a delivery immediately. 
    I'm trying to find out if the combination of turning on CRM ATP using R/3 and Create Delivery Immediately for a Sales Order in R/3 are supposed to work properly together.
    If anyone knows and or has this working, I'd like to know.
    Thanks.
    Donna

    Hi ,
    I am working with R/3 and I have the same problem.
    Complete delivery is flowing down from the customer master for all order.
    And then we have items on order which have different shipping point.
    They all fail in background delivery and give the error ' customer requested complete delivery'.
    Is there anyway to override this?
    Any help will be really appreciated.
    regards
    BgS

  • ATP check together with MRP

    Hi experts,
    Can ATP check runs together with MRP requirements? If yes, how to solve the issue below?
    Scenario: Finished product is required to transfer MRP requirements when creating sales orders. Meanwhile, ATP check runs.
    Issue: Due to strategy group 52, Consumption mode 1 & Bwd consumption period 45 (MRP 3), dates in shipping tab in sales orders can NOT be proposed, such as MAD. Delivery can NOT be created due to no MAD. (No schedule lines due for delivery up to the selected date Message no. VL248)
    If letting those three fields (strategy group, etc.) blank in MRP 3, dates in shipping tab in sales orders can be proposed. But MRP requirements cannot happen.

    Hi Weihua,
    We are facing the similar issue where we need to do ATP at storage location level. May I know how big is the enhancement you have done i.e: man day? and if possible, could you please point out to us where to enhance this?
    Thanks a lot,
    Ly

  • ATP Check for service parts and procurement scenario

    Dear Experts,
    We're testing CRM service scenario, focusing on the ATP check.
    After running the avaiability check for the service parts in the service order,
    is it posssible to determine the scenario automatically as follows?
    - when the necessary parts items are not available
    -> "Procurement" scenario will be used.
    The corresponding documents such as PO, PR or Reservation will be generated in ERP according to the setting "Define Logistics Scenario for the Procurement of Materials and Services".
    - when the necessary parts items are available in stock
    -> "Material withdrawal" scenario will be used. The items will be withdrawn at the service confirmation.
    From our understanding, the determination of the above scenario is controlled by the item type(ex.SRVP),
    so we expect that the system sets the appropriate item type depending on whether the item is available or not.
    Is there any possible solution for this?(i.e.standard customizing, BAdI etc....)
    Any advice would be higly appreciated.
    Best regards,
    F.T.

    Hi F.T,
    I have worked in Service Order Management Scenario, but not integration of Service Orders for ATP Check. But I found this Presentation which I hope might be somewhat helpful regarding the feasibility of the Business Scenario. You can have look at  the same and will be able to decide if this is the correct way forward or not.
    [Presentation|http://www.google.co.in/#hl=en&biw=1366&bih=548&q=ATPCheckforservicepartsandprocurementscenarioinSAPCRM+++&aq=f&aqi=&aql=&oq=&gs_rfai=&fp=a254323013e5943b]
    Hope this will help.
    Thanks,
    Samantak.

  • ATP check by valuation type and batches???

    Dear experts,
    I create a seles order, input one material and valuation type,  I can't fix the batche in sales order,the system give a message as following, so the ATP check is wrong.is there any solution to deal this issue?
    "Availability check for material 21-01 only occurs at plant level
    Message no. V1562
    Diagnosis
    You entered valuation type 9999999999999 for material 21-01 which is to be handled in batches without specifying a batch. Therefore, an availability check can only occur at plant level since it is not possible to determine all batches belonging to the valuation type. Usually, the plant stock level is higher than the stock level within a valuation type. Too much may be confirmed as a result.
    Procedure
    When you enter a batch number, the availability check occurs at batch level."
    Best regards
    Lance

    by myself

  • Can we run a finished good ATP check based on a full pallet at Sales order level

    Hi Folks,
    I have a requirement from business stating that "is it possible to run a finished good ATP check based (for ex.) on a full pallet when the alternative UOM is maintained in the material master for the finished goods.  For ex. 20 kg = 1 pallet".
    Now I know about the transactions POP1 & POF1 used in packing. But I want to know can we include the pallets & run an ATP check at SO level for the handling unit created altogether?
    Kindly suggest
    Thanks & regards
    Ashwin Vyas

    Hi Phanikumar,
    The customer has given a crude requirement as off now & asked to investigate. So i would like to explore the possible solutions.
    However, i would like to know is packing at SO level can be a solution to this requirement.
    Also, I agree with your comment that "In Normal--Availability can happen on BASE UNIT OF MEASURE", in addition to that here in this case the availability check is marked for the pallets in master data.
    Thanks
    Ashwin Vyas

  • How to include both items and service on Sales Orders

    Hello experts,
    I have a client who wants to include extra handling charges such as gift wrapping charges on their sales order in addition to regular items that is on the sales order.
    If I create the sales order as a Item/Service Type ='Service'. I can select the correct G/L account for this Sales Order. But if I create the sales order as a Item/Service Type ='Item', then I can only select items and not the sales order.
    The client wants to include both the items and service in the sales order. Is there a way to do this in SAP B1?
    Michael

    Hello Michael,
    I think you may create Service type items to include both by Item Type documents.
    Thanks,
    Gordon

  • Actual Costs and Activity Type - Process Order

    Hi,
    I'd like to know if there are any tables recorded with activity type and actual costs from process order.
    Thanks in advance.
    Osmar Tardivo.

    Osmar,
    Check table COEP

  • Planned qty. and value for process order (components wise)

    Hi Experts,
    I need to capture the planned qty. (requirement qty.) and planned value of the components of a process order for some profit report. Please suggest me from which table i can get these values. (In RESB only req. qty. is there.)
    Thanks
    Nitin kapoor

    COSP or MBEW would help get that info. But take help from your FI/Co colleague to understand the table better

  • Partial GR and GI for Process Orders

    Hello,
    I have a scenario where user want to do Partial GR and GI posting against process order using PI sheet and he can very well do this.
    I want to know which SAP table will store this data. I want to prepare report which will run everyday evening and get GR and GI postings done against process done.
    regards,
    Parshuram

    >
    parshuram manjrekar wrote:
    > Hello,
    >
    > I have a scenario where user want to do Partial GR and GI posting against process order using PI sheet and he can very well do this.
    >
    > I want to know which SAP table will store this data. I want to prepare report which will run everyday evening and get GR and GI postings done against process done.
    >
    > regards,
    > Parshuram
    Parshuram,
    You can use standard transaction MB51 for this purpose, which would give you all the material movements for an Order/orders.
    If you still need to develop a report then you need to use MSEG table to extract the data. Order details can be from AUFK/AFKO/ AFPO , planned GI quantities from RESB table
    Regards,
    Prasobh

  • Understanding Target Cost Version Differences for 0 and 1 for process order

    Our client need to understand the differences between our target cost versions that are utilized in calculating the process order CO03 cost analysis.  When should each target version be used and why do the variances change?  See example below.
    Target Version = 1       Target Cost Prelim Order Cost Estimate
    Version = 0          Target Cost for Prod Variances
    Can you please provide analysis and help me on this.
    I higly appreciate for your help.
    Thanks in advance.
    Seshadri

    I recommend that you post this in CO forum.

  • Min/max MRP and double star planned order

    Hi,
        What does setting up materials for min/max mean ? Is it just some concept r does it involve some specific settings in the material master ? I know there are minimum and maximum lot sizing procedures available. Are these to be taken into account to set materials up for min/max ?
    What does a planned order with two stars in the MD04 screen mean?
    Thanks

    Dear,
    Single *** means order is Firmed and **** means Capacity planning has been done for the  planned order.
    There is "storage location" MRP with min max levels.
    Have a look at the fields on the MRP screens in the material master and you will see the settings you can choose from.
    There should be no need for any config as long as your basic MRP config is there.
    The normal MRP run will then try to maintain the correct stock level in that storage location and you use the special procurement keys on the material master to determine where the stock should come from to replenish that storage location.
    Go to TcodeOMIA  here you will find min max for your plant.
    Regards,
    R.Brahmankar

  • ATP check and Check against planning for a production order

    Hi
        When I create a production order for some orders it is ATP check and for some orders it is showing 2 in type avail check is check against planning in coois screen. Because of this orders are gettign released even though BOM material is out of stock.Can I know in which situations the orders will come under the second scenario. I always want the orders should be in ATP check
    regards,
    PradeepM.

    Hi,
    If you want only ATP check, then in MRP-3 view of the mtl master change the checking group to the same value as the one which you find to be following the ATP check.
    However before making this change do consult your colleagues in other domains, as this will impact all places where Av. check is done.
    Hope it clarifies.
    Regards,
    Vivek

  • ATP check on Sales order items not due for delivery?

    All,
    In our Sales order, we have a number of dummy material lines. Now, when I use the normal sales order ATP check button, SAP does nothing. However, we have a custom program that does an ATP check, and it returns a zero qty.
    My question is, how do we know if a material is due for delivery, before an ATP check is done? The only suggestion I have is to look at the schedule line, and see if there is a material movement behind it.
    Any other ideas?

    Mark
    This is a classic SD Professional's dilemma, though it manifests differently at different clients. Mostly customers crib about future requirements stopping current sales orders from being delivered or Scheduling agreements with future delivery dates 'stealing' stock from Sales orders.  Another manifestation is production orders usurping components from sales orders for spares and so on. ATP functionality in SAP is pulled in various directions by conflicting demands and it is difficult to satisfy everyone. Companies with chronic probelms often end up with negative ATP which is perhaps the most serious stage of the prognosis.
    Your solution lies in:
    1) Availability check control settings : Sales documents vs. deliveries  : For the delivery, don't include 'Sales Requirements'  and for the sales orders, do include 'Delivery Requirements and so on.
    2) Performing nightly rescheduling (V_V2) with Delivery priority and delivery date as key sort criteria. If the volumes are not high, you can try using manual confirmation via CO06.
    Take a look at this OSS note and the ones mentioned within:
    36520 - Availability check for delivery

Maybe you are looking for

  • Questions about Extended classic scenario

    Hi gurus, I'm working in SRM 5.0, ECS, backend ECC 6.0 (only one backend). Everytime a SC is being approved a SRM PO has be created. Then a copy of this PO  has to be created in ECC with document Type ATT and the same number of the SRM PO. I have two

  • Premiere Pro CS5.5 Quit Unexpectedly. Mac 10.10.2.

    Hey there, My Mac just started popping up with the "Premiere Pro CS5.5 Quit Unexpectedly" box.  Nothing has been done differently and the program has been working for years.  Any help? My Mac is a 2011 17" and currently has OSX Yosemite 10.10.2.

  • Multiclip editing + Panasonic HVX200

    Hello! I'm having some trouble trying to create a multiclip out of a footage from a Panasonic HVX200 HD camera... The thing is that the camera divides long clips into smaller ones... so to have the whole footage from a camera, i need to create a sequ

  • Why is my computer powering up automatically after shut-down?

    My Power Mac G4 has mysteriously started to power up in the middle of the night and I can't figure out why? I am on high speed cable hook up and don't recall changing strat up functions. Any advice?

  • CPROJECTS - How does the calculation take place ?

    Hi, I am wokring in cprojects. I have done the following entries <u><b>cost revenue rate - defined</b></u> amount costs - 50 US dollars /Hrs amount revenue 10 US dollars/Hrs different revenue - 1.0 US dollars / Hrs. <b><u>resource assigned and staffe