Hi,
I have created Work center Hierarchy, now want to see the cumulative capacity of subordinate work centers at Superior Work center level, but using cm01- std overview, i can't see.
Can anybody tell me , what-ever is missing?
with thanks,
Rasika
9869028103
HI Mangalraj,
Thanks for your reply. I had tried that , even though there is no cummulation done.
System is showing same error ,as 'There are no capacity requirements for the
selection and settings'.
what i have given input is Superior Work Center, Plant and Planner group.
I didn't mentioned the capacity at superior WC.
PLEASE HELP.
Rasika.
Similar Messages
-
Capacity cumulation in work center hierarchy
Hello
Does anyone uses workcenter hierarchies to cumulate capacity requirements ?
I've created a hierarchy but in the capacity evaluation transaction cm01,
the capacity requirements are not cumulated from the underlying work center.
Instead a capacity requirement of zero is shown on the hierarchy work center.
Is there any specifics to cumulate the capacity requirement to work center hierarchy header
Best regards
PascalHi,
In the transaction CM01, choose the pull-down menu Settings-> General. In the pop-up screen, under the "Herarchy" tab, select the check boxes "Cumulation of reqmts" and "Dyn. capacity cumulation", choose the "Hierarchy" and "Plant" and click on "Continue".
Now the "Available Capacity" will be as per hierarchy setup and Rem. avail cap = Reqmts-Available capacity.
Hope this solves the requirement.
-Thaila Shree -
Capacity planning for Work Center
I programmed time for a Work Center on internal activity, for 40 hr using 100% of one resource, the work center it has a capacity of 8 hr each day, the activity gets a duration of 5 days and I indicated that it has to begin the first day of the next month.
When I executed transaction CM01, I notice that the 40 hours are planned for the actual day and don´t respect the dates of the internal activity, I think it is a problem with the work center but do not find the error.
Any suggestion where to look for?
The data used for creating the Work Center on Capacities:
- Capacity Category : 002 Person
- Other formula: SAP008
The data used for capacity:
- Base unit of meas.:H
- Start: 08:00:00
- Finish: 17:00:00
- Capacity utilization: 100
- No. of indiv. cap.:1
- Unit: H
- Relevant to finite scheduling: active
- Can be used by several operations: active
- Long-term planning: active
The data used for creating the Work Center on Scheduling:
- Capacity Category: 002 Person
- Other formula: SAP004
- Work dimension: Time
- Work unit: H
Best Regards...Hi,
Please activate the capacity requirement in Capacity tab in CNR2.
Thanks.. -
Dear Gurus,
How can I use work center Hierarchy for Capacity Planning.
I have 5 Lathe machines. How can I use Work Center Hierarchy?
I also need Work Center Wise confirmation.
Please guide me. Also let me know how should I maintain data in work center as well as in routing.
Thanks in advance
RGCreate a new WC (in CR01) as category 0004. This will be the top level WC in your hierarchy. <BR sab="44">Create a hierarchy (in CR21). <BR sab="46">Add your 5 lathes and the newly created top level WC to the hierarchy (in CR22). This can be tricky: the WC you just created must be the top level, the other 5 must be under it. <BR sab="50">Pull the capacity data (in CM01) for the hierarchy: go to settings, hierarchy, check the cumulation of requirements and capacities and type the hierarchy name. <BR sab="54">Route things as before, to the original 5 lathes.
-
Profit Center Hierarchy Level in ABAP-HR
I am working on an ABAP-HR report related to Organisation management.
There is a requirement wherein I need to retrieve data from a Profit Center Hierarchy Level .Can u please advice me on this.
Thanks in advance,
Raja.Hi ,
(i_name is the entered profit center group name)
Get the internal name of the entered profit center hierarchy.
CALL FUNCTION 'G_SET_LIST_SELECT'
EXPORTING
SETCLASS = '0106'
SHORTNAME = I_NAME
KOKRS = 'MIT '
KTOPL = 'HEUS'
TABLES
MATCHING_SETS = T_SETLIST.
IF T_SETLIST[] IS INITIAL.
MESSAGE E002(SY) WITH 'Profit Center group does not exist'.
EXIT.
ELSE.
READ TABLE T_SETLIST INDEX 1.
ENDIF.
Get the entered profit center hierarchy info.
CALL FUNCTION 'G_SET_TREE_IMPORT'
EXPORTING
SETID = T_SETLIST-SETNAME
TABLES
SET_HIERARCHY = T_SETHIER
SET_VALUES = T_SETVALUES
EXCEPTIONS
SET_NOT_FOUND = 1
ILLEGAL_FIELD_REPLACEMENT = 2
ILLEGAL_TABLE_REPLACEMENT = 3
OTHERS = 4.
IF SY-SUBRC <> 0.
MESSAGE E002(SY) WITH 'Profit Center group does not exist'.
EXIT.
ENDIF.
or try one of these
FC_PRCTR_HIERARCHY
TXW_EXTRACT_CO_PCTR_HIERARCHY
Regards,
pankaj singh.
Message edited by pankaj singh -
Work Center Hierarchy and Routing
Hi,
I would like to know what exactly Work Center hierarchy mean?. Where is it used. In Routing, we maintain Sequence of operation along with workcenter where this operations are performed . Would like to know does work center hierarchy is linked to sequence maintained in Routing?. ThanksHi,
Any one can explain me the use of Workcenter Hierarchy?. In Routing, we maintain the sequence of operations. Does Routing and Workcenter Hierarchy has relation?. If Yes, what is the relation between these 2.
Thanks in advance -
Work Center Hierarchy and Capacity
Hello SAP friends,
Can someone please help me with the following scenario?
I have 3 Work Centers
MAQ00 - (Capacity 10:00 x 2)
MAQ01 - 8:00 -- 18:00 (Capacity 10:00)
MAQ02 - 8:00 -- 18:00 (Capacity 10:00)
I have a hierarchy
HICY01
MAQ00 - Root of hierarchy
|_ MAQ01
|_ MAQ02
Then, I have a routing
10 - PP01 - MAQ00 - 1H
20 - PP01 - MAQ00 - 2H
If I go to CM01 for Work Center MAQ00 I can see the capacity and requirement, where:
Capacity: 10:00 x 2
Requirement: 3:00
But if I go to transaction CM21 for Work Center MAQ00 the capacity and requirement is not correct. Can someone please help me with this?
Thanks in advance,
Adelmo SilvaHi,
CM01 will give the cumulative requirement as 3 hrs but CM21(Gradhical View) shows the individual spread of oprn. 10 and 20 as 1H and 2 H resp.
Does the above help you?
-Thaila Shree -
Regarding work center hierarchy
Hi all,
I have 2 work centers liked to a superior work center in a hirarchy.
Is it possible to do capacity planning at the superior work center level.
The scenario is like this - I will get planned order at a superior work center level. I will convert the planned order into 2 production orders with child work centers in respective order.
Now I want that, when I see the capacity overview for the superior work center, it should be full. That means I want to link the capacities of the child work centers to the parent work center.
Please let me know if it is possible ?
Regards,
YogeshHi,
Work center hierarchies are used in capacity planning to cumulate available capacity and capacity requirements. You can cumulate available capacities from subordinate work centers to a superior work center level in order to determine the total available capacity for the superior work center.
In your situation, I think you need to create two planned orders with the two work centers and after this you will be able to see the capacity requirements cumulated at the superior WC.
Regards
Datta -
Inspection time Capacity Updation in work center for skipped lots
Hi Guys,
I am using in process inspection type 03 along with DMR criteria at lot level i have defined the DMR rule and assigned it in routing header.DMR rule is inspection lot 1 in 5 will be inspected i.e when the inspection lot will be created and if there is no quality level exists it will first create the quality level with 1st inspection lot which will not be skipped lot and then it will skip next 4 lots and 5th will be inspected again.Quality level is updated during lot creation level.
what i am looking is when you have the skip inspection lot he capacity which has been planned for inspection for that work center should not be considered since there is no inspection done because of skipped inspection on that work center although it's the part of Routing/production process.
please let me know if any more inputs required.
your inputs/feedback is really appreciated
Regards
Ashutosh ShendeHi Krishna,
It is distributing unevenly because of the Int. Dist. key maintained for "Labour" capacity category.
Following are the available dist keys.
I think for your scenario, you should select SAP020
SAP000 Overall load for latest start date
SAP010 Overall load for earliest start date
SAP020 Equal distrib. earliest dates, fact.cal.
SAP030 Equal distrib. latest dates, fact. cal.
SAP040 Equal distrib. latest dates, discrete
SAP050 Equal distrib. earliest dates, oper.time
SAP060 Equal distr. latest dates, operat. time
SAP070 Overall load at latest finish date
Please let me know if this works for you.
Regards,
Abhay Kapase -
Capacity category in work center
Hi All,
please clarify me on this,
capacity category under scheduling tab in work center creation is showing as mandatory, but i do not want to maintain this field because iam not putting anything under capacity tab to avoid capacity planning.
is there anyway to take off it as mandatory under scheduling tab?Dear Sprint,
Goto OPFA and select the scheduling and click on influencing and mention the work center category in the field contents and
press enter and for the field capacity select the radio button for input or else display (remove it from the radio button mentioned
under required) and press enter and then save the data and now create a new work center for the changes made work
center category and revert back.
Regards
S Mangalraj -
FM for getting the capacity of given work center
Hi all ,
1) Is there any function module to get the capacity of the workcenter .
2) how to know the number of hours that work center works .
Please mention the field which represents the capacity .....
Regards
RajHi ,
You can use .
CHEeck out Transaction C0R4 .
Field is BEDID .That is Capacity Id in table KBED .
BEDID is there in table AFKO or AFPO . -
Why ist Pool Capacity from PP work center automatically involved
Hi, All
i use PP work center to create a PM Order.
this PP work center has machine-, labor- and pool capacity. and I add "SAP008" into field "other fomula" for labor capacity in Tab capacities.
now after I create a PM Order, when I check CM50, I can see for this PP Work center also Pool Capacity involved.
Question:
1. where comes this Pool capacity, even though I didnot set any formula in field "other formula" for pool capacity in Tab capacities?
2. for creating PM Order, do I also need add "SAP008" into field "other fomula" for machine capacity in Tab capacities?
thanks®ardsHi Shrithar,
Do you means the time Profile in CM50.
when I check this time Profile, I see differant time interval, -Database read period
-Evalution period
-plannung period
-Dispatching of backlog
is it also influencing work center capacities?
thanks®ards -
Capacity evaluation in work center which has number of indivisual capacity.
Hi. guys.
Work Center(WC01) has 2 indivisual capacity.
and available capacity is 16H. (8H * 2)
I made capacity requirement(production order) with 26H.
Capacity evaluation displays the result as below.
Entries Rem.cap.reqs Avail.capacity R
Total 26 H 1,632 H
2009.10.09 0 H 16 H 0
2009.10.10 0 H 16 H 0
2009.10.11 8 H 16 H 50
2009.10.12 8 H 16 H 50
2009.10.13 8 H 16 H 50
2009.10.14 2 H 16 H 12
2009.10.15 0 H 16 H 0
I don't know why the requriment capacity is only 8H per day.
I think that the requirement capacity should be 16H per day.
can anyone explain the reason?Thanks.
But It's not what i want.
I'll explain my problem more detail
Work Center(WC01) - Available Capacity: 16H ( 8H * 2 (No. of Indivisual capacity))
Caracity Requirement - production order 1000001 (Start date: 10/10, Excution Time: 24H)
Capacity Evaluation (CM01) <NOW.>
Day Requirements AvailCap. CapLoad
2009.10.10 8.00 16.00 50%
2009.10.11 8.00 16.00 50%
2009.10.12 8.00 16.00 50%
So, I don't understand 'capacity load(%')
I want to product the material using two capcity
but capacity evaluation calcuate only one capacity now.
I think the below result is right.
Capacity Evaluation (CM01) <NOW.>
Day Requirements AvailCap. CapLoad
2009.10.10 16.00 16.00 100%
2009.10.11 8.00 8.00 50%
2009.10.12 0.00 0.00 0%
Is it impossible?? -
Capacity categories in work center
Dear PP gurus,
I have a work center where i have maintained 2 capacity categories in capacity tab screen. One m/c and other labour. Now when i assign this work center to a routing.....in the routing operation details screen, i see only the formula from the 1st capacity category showing up. How/Where can i see the formulas from the other capacity category, maintained in the work center?Hi,
For the capacity category say:Machine, in the "capacity header" in workcenter, you assign "no. of individual capacities" as 2. Also, you can create the capacities in CR11 and assign the same to the work center.
In routing you can just enable the check box "Required splitting" and assign no. of splits =2. you cannot assign the individual capacities you have created in CR11 in routing.
In Production order, in operation details, "Cap. reqmt assignment", you can assign those two individual capacities and assign qty to be processed in those capacities.
Hope this clarifies you..
-Thaila Shree -
Upload/ download Work Center Hierarchy
Hello All,
I need your help with this one. Therefore thanks in Advace:
Is there a way to download and upload work center hierarchies?
The idea ist to download a complex hierarchy to a file and then upload it to another system/ client.
Thanx
RafHi Daniele,
I just tried the way you suggested:
- RCRAPDX1 downloaded a txt to presentation server with data.
- changed only the plant in file.
- run RCRAPDX2
unfortunately result is that ths system try to maintain the work centers within the file,
(which are already maintained).
The hierarchy structure won't be maintained.
So what I look for is a manner to transport the complete hierarchy structure...
regards
raf
Maybe you are looking for
-
How do I get bookmark bar to match between all my devices?
My Safari bookmark bar is different on each of my device. Can I get them to match thru iCloud?
-
What is the name of Illustrator COM/DCOM Service?
Hi, I have installed Adobe Illustrator 6 on my PC (Windows XP Pro), have an issue in creating the application instance from the code that I deployed in my local IIS, but it works great in Visual Studio 2010. Per some suggestions on MS forums, I am tr
-
Hi I am having difficulty pairing my lumia 520 to other bluetooth devices. I can pair to them but they all loose the pairing after 3-4 seconds. has anyone else got the same problem?
-
Copy Standard Text into CRM_ORDERH
Hello, maybe anybody has an idea for my problem: I need an default text in a textscheme in the order-header. I can do this manually, I create a standard text within the textobject "TEXT" with SO10, and in the transaction I can copy the text with help
-
Any information of releasing E-business Suite R13 in near future?
Can any body give me information about releasing E-business Suite R13 in near future? Regards, Subir Paul India