Copying Task Fields to Resource Fields

Hi
I have a need to copy data from a task field to a resource field.  Basically I want to add the Project Name to every activity against each resource name in the Resource Usage View.  I have a piece of code from Jack Dahlgren that will copy Task
Field data to an Assignment Field but I need it to go in to a custom Resource Field, say Text1.
Any help/guidance would be appreciated as I am stuck.
Kind regards
Tony
TKHussar

Hi Tony,
According to the description, you were developing with Microsoft Project. I woud like to move it to
Project Customization and Programming forum.
The reason why we recommend posting appropriately is you will get the most qualified pool of respondents, and other partners who read the forums regularly can either share their knowledge or learn from your interaction with us.
Thanks for your understanding.
Regards & Fei
We are trying to better understand customer views on social support experience, so your participation in this interview project would be greatly appreciated if you have time. Thanks for helping make community forums a great place.
Click
HERE to participate the survey.

Similar Messages

  • Work Field In Resource Sheet

    The Work field in the Resource Sheet is calculated total hours for each resource based on the Duration in the Gantt chart. However, I have another field in the Gantt chart named Duration1 and I want Work field in the Resource Sheet to be calculated based
    on Duration1 not Duration. What formula can I use to customize Work field in Resource Sheet?

    Thanks guys! Since, there is no way to keep Duration different from the Actual Duration, I baselined Duration. Now, similarly, I would also like to baseline Work; however, baselined Work doesn't reflect
    input values of Work field. Also, just how Duration and Work data are different in my plan, Actual Duration and Actual Work may also differ. I was able to keep the Work values different from the Duration by changing the Duration task type.
    Is there a way to fix Actual Duration as well so that it's not same as Actual Work?
    Duration = allocated duration to complete the task [Task Type: Fixed Duration]
    Work = time it should take to complete the task [Different from Duration]
    Actual Duration = taken duration to complete the task
    Actual Work = time it took to complete the task
    Also, in Resource Sheet, is there a way to compare Baseline Work with Actual Work for
    each resource as well as Baseline Cost based on Baseline Work with Actual Cost based on Actual Work?
    This would allow us to work in the same plan while comparing the plan (by Start/Finish, Work in Gantt, Work in Resource Sheet, and Cost) before and after implementation. If not, then I guess we can have two copies of the plan (one for before implementation
    and the other for after) with Duration and Work where task type is fixed Duration.
    A few comment: 
    baselined Work doesn't reflect input values of Work field : when you
    save a baseline, the behavior is the same for all data copied in the baseline fields. The current value is stored is the corresponding baseline field. Ie when saving baseline n, work is copied in the baselinework n and duration is copied in the baselineduration
    n.
    Actual Work = time it took to complete the task
    : actual work is the effort and not the time it took to complete the task
    is there a way to compare Baseline Work with Actual Work for each resource :  if you split your screen and display the task form with work
    information, you'll see for each assignment work, actual work, baseline work, remaining work. Another way, if you need it timephased, is to use the resource or task usage views and add the baseline, actual and planned work (double clicking the right part of
    your screen).
    Hope this helps.
    Guillaume Rouyre - MBA, MCP, MCTS

  • How can I copy a number of like fields and paste to reduce form creation time?

    How can I copy a number of like fields and paste to reduce form creation time?

    Creating Form Fields by Ted Padova

  • Can I copy information from a metadata field to another  ?

    Hi,
    I would like to know if it's possible to copy information from metadata "city" field to "caption", for instance.

    exiftool

  • Use of Resource field on CK74N Additive Cost

    We would like to enter an outside vendor code (not in SAP, so can't be validated) into the Resource field of a CK74N and be able to then see that carried over into  the CK13N cost estimate display.  Does anyone know what Item category could be used for this?  Seems the Resource field has different uses based on the Item category.

    The various item categories and what they represent. If you are considering buying material from the outside vendor, <b>you may use M</b>.
    M (Material)  B (Base planning object)
    N (Service)  L (Subcontracting)
    E (Internal activity)  F (External activity)
    V (Variable item)  S (Total)
    I (Delivery costs)  A (Co-product)
    T (Text)  P (Process costs manually)
    G (Overhead - calculated automatically)
    X (Process costs - calculated automatically)

  • How to Map Proces form field with Resource form field?

    Hi,
    How to Map Proces form field with Resource form field while creating Process form in Form designer

    Are you talking about Provisioning ?
    then you do that in Data Flow under Process Defintion in OIM 10g
    In OIM 11g you use Request Dataset. In that you can directly map fields to process form.

  • Task Level Unique ID field.

    Hello,
    In Project Pro you can add the task level field Inique ID to the view. I need to report this field on a report, and can't seem to find it in any of the Project Server 2010 database fields. Can anyone tell me the table or view and the database that I can
    find the task level Unique ID field for reporting? Thanks for your assistance! :)

    Have you anyway tried to query the "TaskIndex" from the Reporting DB?
    If you confirm that it isn't the task unique ID you're looking for, I'm afraid that the task unique ID is just meant to be seen in Project Pro for scheduling purpose and not reporting purpose. Thus it'll not be in the Reporting DB. 
    Eventhough it is neither documented nor documented, you might have a look to the draft DB.
    Hope this helps. 
    Guillaume Rouyre - MBA, MCP, MCTS

  • User defined fields in Resource object; Resource object form

    Hi,
    Can anyone tell me what is the purpose of having user defined fields for resource object and resource object form and how can we use those fields while requesting for target resource.
    Regards,
    Alabhya Goel

    Thanks for your reply!!!!!!!!!!
    I know about resource object form i am just asking what is the use of user define field in resource object form. How can we use it. Like when we create any user defined field in under User form those fields display on create user form but when we create any user defined field in resource object from those are not displayed in form.
    If anyone has used or worked on user defined fields in Resource Object or resource object form; please give me an overview over the same.
    Regards
    Alabhya Goel

  • Copy text from multiple fields to one field

    I would like to copy text from multiple fields into one field. Each of these smaller fields will only be allowed to have one character. The larger field will not be able to be edited.
    So far, I have thought of creating a naming heirarchy for these fields. I was going to then call upon the array of the parent and set the value of the parent to equal this array.
    var parent = this.getField("everything");
    var array = everything.getArray();
    var v;
    for(parent=0; parent<array.length; parent++)
    v = a + " " + v;               //Im guessing this line is incorrect
    parent.value = a;
    Any suggestions? or a better way of doing this.
    Thanks

    The code sample you provided is using AcroForm scripting and will not work in this form. There is another post similar to this one...have a look at this one it might help you out. It is doing the opposite of what you want but the concept of the loop and how each field is addressed inside ofthe loop is what you wil need.
    http://forums.adobe.com/message/2954517#2954517
    Paul

  • Field SNPLC is not an entry field for resource type 02

    While transferring resource, getting the error message below;
    Field SNPLC is not an entry field for resource type 02
    Message no. /SAPAPO/DMRES149
    Is that something to do with CFC9??
    Please help.

    Hi,
    You have defined the resource type as 2 ( single activity resource)  which is PPDS relevant but in the Planning parameters tab of the APO resource you have defined it as SNP relevant.( Not ticked the Not SNP relevant)
    Request you to make tick in the Not SNP relevant  field and then try Ciffing.
    Since SYSFAIL has happend request you to clear the failed Queues and then CIF it.
    Thanks,
    nandha

  • Copying all birthdates from custom field to regular addressbook field

    is there a way i can copy birthdates from a custom field to regular address book field?
    my current birthdates are not reflecting in iCal - and while there is are solutions to copying custom dates to ical, i would rather work on the solution to copy the custom date to regular birthdate.

    So, if you're sure all your custom dates are birthdays and you want to copy them all to the birthday field.
    First, open Address Book and from the File menu select Export, then +Address Book Archive...+ This saves a backup of your Address Book database in case you don't like the results of the script below.
    Then run this Applescript.
    -- Move all custom dates to birthdays
    -- John Maisey -- 21 June 2009 -- www.nhoj.co.uk
    tell application "Address Book"
    repeat with thisPerson in (people whose custom dates is not equal to {})
    tell thisPerson to set birth date to value of first custom date
    end repeat
    save addressbook
    end tell
    display dialog "All Address Book custom dates copied to birthdays."
    Best wishes
    John M

  • Copy Planning Plant to Sort field in Maintenance Plan

    Hi All,
    Is there any User Exit User exit is available to Copy Planning Plant to Sort field in Maintenance Plan.
    Regds
    Vinit

    I think it is not possibe as the sort field in maintenance plan is a customizing field. you can not enter any value in the sort field but you in SPRO first you have to maintain the values  for sort field.
    The sort field in order and notification, there you can copy the planning plant or anything else as they are manual input fields

  • DATE OF TASK  as an optional field

    Hai
    I want to make the field  DATE OF TASK  as an optional field ( basically itu2019s a mandatory field) for some reasons in IT19 monitoring of  tasks subtype 06 training period
    Plz let me know how to make this field optional?
    Plz give the steps in details
    Thanks

    Dear Siddharth
    Thank you for the reply, but not in ESS in R/3 only m trying, plz let me know clearly how to make it optional?

  • Copy Task Validation

    Hi,
    with this following scenario :
    Source data in version 100
    Target Data in version 200
    When i run copy task in version 200, is it possible to make a validation so it will appear error if a few tasks in version 100 have been run yet?
    Thanks in advance.

    Template... Do you mean some examples?
    I wrote some BAdIs. Each of them is individual, have different methods and parameters. Different structures and variables available. Some of them is reading the whole data package, some - just record by record, another ones - field by field of the same record...
    While accessing the BAdI class (in English) you may press F1 and get help with (not actually big, but enough for programming) explanations.

  • DSO - What key fields and data fields in dso

    Hi experts,
    I need to create a dso in between the cube and 2 data sources(2lis_11_vaitm, 2lis_12_vcscl) to stage the data. My question is: what key fields and data fields to choose for the dso? is there a standard dso to copy? please explain in detail the model to set up, whether to connect both the ds's to dso and then to cube or one ds to dso and the other to the cube. more details will help.

    Check this for standard DSO:
    http://help.sap.com/saphelp_nw04/helpdata/en/43/fcdc387f34384f94c3227baf3837a8/content.htm
    Thanks...
    Shambhu

Maybe you are looking for