Duration of project implementation for an orgn

duration of project implementation for an orgn?

Hi
It purely depends on The size of Client and Its Business process and The SAP Solution (e.g. SAP B1, MySAP SAP ECC etc)
Refer below link on sdn
project duration as per implementation phases
Typical Duration
Project preparation- 2 Months
Blue print - 3 months
Realization- 4 months
Fina preparation- 2 months
Golive
There is Hard & Fast rule that all project go exactly,This depends up on clients also and they should provide the information and depends up on them also
Message was edited by:
        SHESAGIRI.G

Similar Messages

  • Project duration as per implementation phases

    Divide project duration as per implementation phases?

    Dear Gopala Rao,
    It actually depends on various factors, such as :
    1. how many modules they want to implement.
    2. Team Size.
    3. Organizational Structure (Volume of data)
    4. Legacy System
    5. Business Complexity etc.
    There is no hard and fast rule that every project should be completed in a particular duration of time. Depending on the above factors, it may vary any where from 6 months to 18 months or so. (Approximately, it may be less than 6 months or more than 18 months in some exceptional cases).
    Usually it is divided into phases:
    1. Project Preparation : Project team, infrastructure, Software, Steering committe etc will be identified in this phase.
    2. Business Blue Print : Re-engineering of Business process and BBP sign off.
    3. Realization : Analysing Gap and Realization of possible customization and development effort
    4. Final Preparation and Go Live : Development and Configuration
    5. Post Go Live support : Support after go live
    You would allot specific time periods for each of these phases and will set milestones accordingly.
    or it could even be like :
    Project Start
    Analysis
    Design
    Design Freeze / Client Sign-off
    Construction
    Testing
    Implementation
    Project End
    Project Management Framework
    Post Close Review
    Training
    Change Management
    Refer following links for more info:
    http://en.wikipedia.org/wiki/SAP_Implementation
    http://www.sapfans.com/sapfans/asap/be_01_e.htm
    There are different flavors of project implementations.
    1. Template implementation - without much customization - based on a predefined rollout template
    2. CUstom rollout
    3. Ramp up rollout
    4. Enhancements to an existing implementation
    5. project recovery
    The project life cycle consists of [1] Project Charter,[2]Scope,[3] planning,[4]Execution,[5]Control and [6] closure.
    Charter tells you the purpose of the project,for example,to eliminate an expensive Transmission process by implementing EDI.
    Scope tells what all you will be doing in the project.In SAP,this is Blue printing.
    planning:Here you plan the capital Expenditure - capital budgeting,Expenses,Revenue,Resources and other elements that go in to the project.
    projectExecution : Actual execution of the planned activities
    Control:Here you steer the project towards the intended goals-variance analysis,cost Reduction,Value engineering,budget,standards,fast tracking,crashing,Resource allocation etc etc ,....all find a role here.Here Time,Cost and the other resources are controlled so as to complete the project in time and within the cost baselines.
    Testing also comes here-unit test,integration test,UAT........
    Closure:The project sign off takes place here.
    In the support Environment the "project" will cover a]incident management,b] problem management,c]change management,d]configuration management e] Release management and f] help desk.
    Reward points if it is helpful.
    Thanks and Regards,
    Naveen.

  • Project Plan for EAM analytics implementation.

    Hi Experts,
    My Boss has asked me to provide him the project plan for this EAM analytics implementation, showing how long will it take for the dashboards to be up with the correct data.
    Reason why he is asking this is because initial configuration has been done in BI Apps but  prima facie looks like the DATA on dashboards is not correct.
    Now he is worried as to how long will it take... and even i am not sure on this as I am new to this..( i m the only one configuring EAM Dashboards - ie only one resource )
    Any experiences or helpful advise for this kind of scenario that i can tell my boss or what should be my action plan.
    Thanks
    Ashish

    Any pointers?

  • Exception "not implemented for class oracle.jdbc.driver.T4CNumberAccessor"

    Hello I'm having some troubles dealing with 'java.sql.Date' I'm working with express edition database and I have three classes(different packages)
    1.Mapper
    2.Objects Class
    3.ConsoleTest
    I need to get an arraylist of objects, some of which contain dates, but when try to do it I get this exception
    "java.sql.SQLException: Invalid column type: getDate not implemented for class oracle.jdbc.driver.T4CNumberAccessor"
    Do you have any idea how I can implement the getDate method for this T4CNumberAccessor
    Here are the methods that I'm using
    1.Mapper
    public ArrayList<Object> getAllTaskAuctions(Connection con)
              ArrayList<Object> l1 = new ArrayList<Object>();
              String SQLString1 = "select * from taskauction natural join tasks";
    PreparedStatement statement=null;
    try
    //=== get taskauctions natural join tasks
    statement = con.prepareStatement(SQLString1);
    ResultSet rs = statement.executeQuery();
    while(rs.next())
    l1.add(new TaskAuction(rs.getInt(1), rs.getInt(2), rs.getInt(3),
    rs.getDate(4), rs.getDate(5), rs.getInt(6)));
    l1.add(new Task(rs.getInt(1), rs.getInt(2), rs.getString(3),
    rs.getString(4), rs.getString(5), rs.getString(6), rs.getInt(7)));
    catch (Exception exc)
    System.out.println("Fail in TaskAuctionMapper - getAllTaskAuctions");
    System.out.println(exc);
    return l1;
    2.ConsoleTest class
    Connection con;
         public Connection getConnection(){
              try{ 
         Class.forName("oracle.jdbc.driver.OracleDriver");
         con = DriverManager.getConnection(
         "jdbc:oracle:thin:@localhost:1521:XE", "Project", "123" );
         //username/password@[/]host[:port][service_name]
         catch (Exception e)
         {   System.out.println("fail in getConnection()");
         System.out.println(e); }
              return con;
         public static void main(String[] args) {
              ConsoleTest ct = new ConsoleTest();
              TaskAuctionMapper tam1 = new TaskAuctionMapper();
    ArrayList<Object> alt1 = tam1.getAllTaskAuctions(ct.getConnection());
    Iterator<Object> itr1 = alt1.iterator();
    while (itr1.hasNext())
    TaskAuction taskauct = (TaskAuction) itr1.next();
    //Problem, exception traced to TaskAuctionMapper
    System.out.println(
              "Task ID: " + taskauct.getTaskid()+ ", "+
              "StartDate: "+ taskauct.getStartdate()+", "+
              "User ID: " + taskauct.getUserid());
         }

    Found the answer, I shouldn't use integers as parameters of column index in the result set, but instead use String to mark the fields :)

  • Remaining Installs Available on Project Pro for Office 365

    Hello All, 
    I downloaded a demo version of Project Pro for Office 365 as I am looking to test/implement the software in my company. I have looked everywhere on the internet to solve my issue but I am unlucky, and therefore I am kindly asking your guidance on my issue.
    I am looking forward to install Project Pro, but I am only limited to install up to 5 users on my login. What is this limitation, and is there any way around it. My company setup is quite simple, I want to able to install 10 Project Pro for Office 365 licenses
    on 10 manager desktops, and I would like to link the primary account (1 licencse) to Project Online for portfolio management and other related PMO services.
    Am I doing it wrong? is there any other alternative to my situation? 
    We already have MS Project 2007 installed in the system, but we are looking to have more collaboration and sharing services between users. Any other PM offering from Microsoft is welcome.
    Thank you very much

    a3ilwan,
    This isn't really the best place to get an answer for your question. Those of us who respond on the forum are not Microsoft employees nor are we associated with Microsoft in any way. Therefore we neither have the knowledge nor the authority to answer licensing
    issues. You could start with the following link:
    http://www.microsoft.com/oem/en/licensing/sblicensing/pages/licensing_faq.aspx#fbid=moiaUWlZEtO?hashlink=faq8
    Johh

  • SAP implementation for the first time

    Hi,
    I'm still new to SAP and need to know a few things...
    Could someone help me with the answers of the following questions?
    1) What happens when a company goes through an SAP implementation for the first time.
    2) how the company goes into project mode to achieve success when implementing SAP.
    3) Project Members and what they do:
    Basis Analyst,
    Project Mgr,
    Security Analyst,
    Functional Analysts,
    Integration Manger,
    Technical Manager,
    ABAPers,
    etc.
    4) how the business gets involved to help project members get the help they need to implement SAP.
    Regards,
    Ashod

    Yergat wrote:
    Hi,
    > 1) What happens when a company goes through an SAP implementation for the first time.
    >
    SAP gets implemented
    > 2) how the company goes into project mode to achieve success when implementing SAP.
    Project mode is a state of anarchy between start and End, and being in the state for the longest period woud guarantee success....once you started, there should never be a end
    > 3) Project Members and what they do:
    > Basis Analyst,
    Analyses basic stuff
    > Project Mgr,
    He wrongly projects and manages filthily
    > etc.
    These are the most important ones, so always have them on board
    > 4) how the business gets involved to help project members get the help they need to implement SAP.
    > Regards,
    > Ashod
    When someone kicks on the back-side and we realize that we need to get onto Project mode - make no mistake my firend, it is the Business guys. the project guys need not worry, they will get this help for free

  • SAP Implementation for a building construction company

    Dear All ,
                   We are doing SAP implementation for a building construction Company .My client is responsible for building construction .What they do is initially some 10 members of this Company will create a society(Legal Entity)  .They are like promoters for company . They will put advertisement for buying of flats belonging to that society . Then some 20 members (outside) join this society by registering who are actual buyers of the Flats which society builds .
                   Then this society passes a resolution that my client will be the building contractor for flats . After that these 20 outside members will pay the full amount . After this Flats were built then these members will occupy flat ,then after some 4 -5 years of maintenance these 10 core members of society will hand over the society completely to secondary members and come out of the society .
                    Now how we will map this society in SAP  .One society can have more than one project going on . Somebody is suggesting to treat a society as a company code . But we have more than 250 societies . Is it viable . Shall we create plant for each project .
    Regards
    Abhijit Das

    Hi Abhijit,
    Suggestion by our PS consultant for your requirement is
    >>>I would suggest that in case of PS, consider society as Business area and each building as one Project and under project WBS and if any activities floor wise consider as networks.
    Oust side membersu2019 Account payables and receivables and downpayments will come under FICO.
    Regards,
    Uzair

  • SAP Implementation for a Real Estate Company

    Dear All ,
                 We are doing SAP implementation for a building construction Company .My client is responsible for building construction .What they do is initially some 10 members of this Company will create a society(Legal Entity) .They are like promoters for company . They will put advertisement for buying of flats belonging to that society . Then some 20 members (outside) join this society by registering who are actual buyers of the Flats which society builds .
                Then this society passes a resolution that my client will be the building contractor for flats . After that these 20 outside members will pay the full amount . After this Flats were built then these members will occupy flat ,then after some 4 -5 years of maintenance these 10 core members of society will hand over the society completely to secondary members and come out of the society .
    Now how we will map this society in SAP .One society can have more than one project going on . Somebody is suggesting to treat a society as a company code . But we have more than 250 societies . Is it viable . Shall we create plant for each project .
    Suggestions From SDN :I would suggest that in case of PS, consider society as Business area and each building as one Project and under project WBS and if any activities floor wise consider as networks
    Any Other Suggestions ?????
    Abhijit

    Hi,
    If you are using PS , then this is good approach.
    Also have a look at SAP Real Estate Management.
    http://www.sap.com/solutions/business-suite/erp/realestate/index.epx
    Regards,

  • In Primavera Risk Analysis, the MIN. ML, MAX columns is for imput the minimum impact, most likely impact , maximum impact duration of a risk or the remaining duration for MIN, ML and adding remaining duration with maximum impact for MAX?

    In Primavera Risk Analysis, the MIN. ML, MAX columns is for imput the minimum impact, most likely impact , maximum impact duration of a risk or the remaining duration for MIN, ML and adding remaining duration with maximum impact for MAX?

    You are welcome. I'm glad you got it back up.
    (1) You say you did the symbolic link. I will assume this is set correctly; it's very important that it is.
    (2) I don't know what you mean by "Been feeding the [email protected] for several weeks now, 700 emails each day at least." After the initial training period, SpamAssassin doesn't learn from mail it has already processed correctly. At this point, you only need to teach SpamAssassin when it is wrong. [email protected] should only be getting spam that is being passed as clean. Likewise, [email protected] should only be getting legitimate mail that is being flagged as junk. You are redirecting mail to both [email protected] and [email protected] ... right? SpamAssassin needs both.
    (3) Next, as I said before, you need to implement those "Frontline spam defense for Mac OS X Server." Once you have that done and issue "postfix reload" you can look at your SMTP log in Server Admin and watch as Postfix blocks one piece of junk mail after another. It's kind of cool.
    (4) Add some SARE rules:
    Visit http://www.rulesemporium.com/rules.htm and download the following rules:
    70sareadult.cf
    70saregenlsubj0.cf
    70sareheader0.cf
    70sarehtml0.cf
    70sareobfu0.cf
    70sareoem.cf
    70sarespoof.cf
    70sarestocks.cf
    70sareunsub.cf
    72sare_redirectpost
    Visit http://www.rulesemporium.com/other-rules.htm and download the following rules:
    backhair.cf
    bogus-virus-warnings.cf
    chickenpox.cf
    weeds.cf
    Copy these rules to /etc/mail/spamassassin/
    Then stop and restart mail services.
    There are other things you can do, and you'll find differing opinions about such things. In general, I think implementing the "Frontline spam defense for Mac OS X Server" and adding the SARE rules will help a lot. Good luck!

  • [svn:fx-trunk] 12827: Removed the accessibility implementation for WindowAccImpl and WindowedApplicationAccImpl as they are likely not needed .

    Revision: 12827
    Revision: 12827
    Author:   [email protected]
    Date:     2009-12-10 19:03:29 -0800 (Thu, 10 Dec 2009)
    Log Message:
    Removed the accessibility implementation for WindowAccImpl and WindowedApplicationAccImpl as they are likely not needed.  In their current form they were preventing the accessibility of child components from being exposed.
    QE notes: none
    Doc notes: none
    Bugs: n/a
    Reviewer: Gordon
    Tests run: checkintests
    Is noteworthy for integration: no
    Removed Paths:
        flex/sdk/trunk/frameworks/projects/airspark/src/spark/accessibility/WindowAccImpl.as
        flex/sdk/trunk/frameworks/projects/airspark/src/spark/accessibility/WindowedApplicationAc cImpl.as

    Remember that Arch Arm is a different distribution, but we try to bend the rules and provide limited support for them.  This may or may not be unique to Arch Arm, so you might try asking on their forums as well.

  • Roll-out project implementation issue

    Dear colleagues,
    This issue might have already been turned up but couldn't find any related threads.
    We have created our template project, set up the structure, added project documentations (11MBs converted to PDF ), training materials, everything seems to be ok here.
    Now we have to create our first implementation project based on the template. Template is defined and is public (visible), Global Rollout Functionality is activated. The issue is, when we cretate the implementation project the structure is copied from the template, even the training materials can be seen in SOLAR02, but none of our blueprint documents are copied to the roll-out project.
    Have you ever faced such situation before? Do you have any clue where to find the root cause of this?
    thanks in advance for your replies
    Szabolcs
    Edited by: Szabolcs Dombó on Jul 17, 2008 1:26 PM

    Hi,
    Below mentioned is the details of using the SOLMAN for template rollout project. Hope this helps you.
    The process of setting up and using the template in projects involves two or more individual projects. The first project is referred as "Master Project".
    For Master project: Global Program Setup(Project Preparation)
    - Create a master project. this must be of project type template since this will allow the packaging of reuse elements.
    - Create the required number of templates(with in master project). At this stage, these templates are empty packages.
    - Select standard scenarios as a starting point to build business scenarios in the master project, in the same way as for a normal project.
    For Master project: Global Buisness Blueprint
    - Detail standard scenarios to customer specific solution structure
    - Assign template(s) at the scenario level of the customer specific solution structure
    - Set global attributes to determine global/standard/harmonised/local processes
    - Describe global business and technical requirement.
    ==========================================
    Reuse of template at local rollout site
    Project Preparation:
    - Create a local "rollout" project. This can be either an implemetation project type or can itself be a template project type if you may need to reuse sections of this project in its own right.
    - Select one or multiple templates and related scenarios in the scope tabbed page.
    Note: there is no direct relationship between the templates choosen here. In other words you can attach tempalte form multiple other "master" projects, which may have no other relationship to one another.
    Business Blueprint:
    - The contents of the templates which have been attached to the "roll-out" project appears as elements of the project structure.
    - Processes defined as global attributes with in the template area dopted wholesale with no changes.
    - Adapt harmonised and local processes to local specific requirement(such as enhance process scope).
    - Document local specific requirements of harmonised or local processes.
    - Add further local specific structure elements as required and document.
    Hope this help. Pls assign points.
    Rgds
    Manish

  • SGT TrustSec Implementation for Wifi Clients

    Hello Experts,
    I am in ordering process of new equipments for a project where we need  Wireless-PCs connected to Cisco-APs---->Cisco WLC--->Cisco Switch-->>FW Gateway
    We also have Cisco ISE for AAA, and SGT assignment
    My question is:   To be able to assign/classify SGT for wireless-pcs and to further propagate the SGTs to the peer Switch and FW.    what exact WLC series I should get ?   I have chosen Cisco WLC-2500,  is that a correct ITEM ?
    Can you please also give me alittle details what really (Inline-SGT-Tagging) means. WLC-2500 does not support that feature, is that really needed for this project implementation ??
    Thanks for advices
    Waheed

    No it won't support Inline SGT tagging
    Cisco TrustSec Platform Support Matrix
    System Component
    Platform
    Solution Minimum Version
    Solution-Level Validated Version
    Security Group Tag (SGT) Classification
    SGT Exchange Protocol (SXP) Support and Version
    Inline SGT Tagging
    SGT Enforcement
    Cisco Wireless Controllers
    Cisco 5500 Series and 2500 Series; Cisco Wireless Services Module 2 (WiSM2); and Cisco Wireless LAN Controller Module for Integrated Services Routers G2 (WLCM2) (WLC 7500, 8500 and vWLC do not support Cisco TrustSec)
    Cisco AireOS 7.4
    Cisco AireOS 7.5.102
    Dynamic
    S v2
    No
    No
    http://www.cisco.com/c/en/us/solutions/enterprise-networks/trustsec/trustsec_matrix.html

  • Project plan for EP

    Dear All,
      I am very new to EP, we are planning to implement EP. Would anybody give a rough project plan for EP, Atleast any links. this is for 700 users.
    Thanks in advance
    chandrasekhar
    Message was edited by: chandrasekhar yadlapalli

    Chandra,
    Post your email and I can send you a project plan template. Additionally, you can get these templates and others from the EP ASAP links;
    https://media.sdn.sap.com/html/submitted_docs/Implementation_Roadmap_EP/Enterprise%20Portal/index.htm
    To download EP ASAP;
    https://service.sap.com/~sapidb/011000358700005875762004E
    The inner tab called 'Accelerators' are where the templates can be found.
    Regards,
    James

  • Project Plan for Collaboration Suite

    I need help on developing a project plan for implementation of Collaboration Suite9iAS. Does any one have any resources or can direct me to a location where I can see a sample project plan for a Collaboration Suite implementation. Any help would be greatly appreciated.
    Thank you,
    John

    Hi ,
    IT has five stages
    1. DESIGN PHASE
    2.DEVELOPMENT PHASE
    3.QUALITY PHASE
    4.TESTING OR TRAINING PHASE
    5.PRODUCTION AND SUPPORT OR GO LIVE
    each and every phase has different planning and functions and processes
    tommorow i will explain u in detail
    Hope this somewhat clears ur doubt
    Pls assign full points if answer is satisfied
    Regards ,
    Subash Balakrishann

  • ChaRM Maintenance Project & Implementation Project - How to select ?

    Hi,
    I am having an Interesting issue.
    I have defined two ChaRM Projects, One is Maintenance Project (ZCHARMIDES) & One is Implementation project (ZCHARM_NC).
    Implementation project (ZCHARM_NC) I defined today itself & Maintenance Project I am using for last 2 months.
    In both the projects I have same logical component.
    Now When I am creating a Change Request & authorizing it, it is generating Normal correction based on subject. But by default its taking Task list M000000001 which belongs to Maintenance Cycle, But I want to select Implementation Project, how to select this.
    My issue is why system is not asking me to select project ( Maintenance & Implementation) even though the logical component is same.
    I want to select Implementation Project  - I000000114 for checking Normal Corretion.
    Regards
    Praveen Khot(PK)

    Hi PK,
    It depends on the subject which you are selecting. A normal correction type in the subject field is related to the maintenance project. And hence, when you have only one maintenance project with that landscape, it automatically gets assigned to that maintenance project.
    In order to select the implementation project, your subject would look like Development (Implementation) (unless customized) and only then the follow on correction type would be the normal correction in the implementation project.
    Per the standard functionality of ChaRM, you will not be able to see the pop up to choose amongst one of the project types for a CR.
    Regards,
    Sneha Vyas.

Maybe you are looking for