hi,
I created delivery document with 20 delivery quantity at first. after that I want to create partially goods issue. for example i want to have 10 quantity in pick quantity and at first 10 quantity goods issue and save and another time goods issue the remained quantity. but I can not configure the system to do this.
thank you.

Lida,
As per standard SAP, you cant do partially picking. If you want to do partial elivery of item, change the quantity of the delivery item in the delivery and pick the full qty. for example :
Sales Order 10 Qty,
Delivery 5 qty
Picking 5Qty
This will be partial delivery,
Thanks,
Raja

Similar Messages

  • How to reverse goods issue for delivery note by using IDoc

    Hi all,
    I would like to reverse goods issue and picking request for delivery note by using inbound IDoc.
    I used message type SHPCON and IDoc type DEVLRY03 for posting goods issue in inbound processing and it's work but I couldn't find solution for posting reverse goods issue.
    Pls let me know which IDoc type or any ways for posting goods issue reversal and cancelling picking request.
    Thanks for your time.
    Su R.

    Hello,
              For this requirements we can actually follow two Approaches that I can think of. Here they are.
    Approach 1
             Little Complex Approach. What we can do is to make use of the Same Function Module (Posting Program) IDOC_INPUT_DELVRY to do the Delivery Updates (Except reversing the Goods Issue). During this,  we can make use of one of the Customer Functions available in the Enhancement V55K0001 and satisfy our Requirement.
    Approach 2
            We can actually code a Custom Posting Program (Function Module) in which the first part will take care of updating the Delivery & if the PGI is done, then we can make use of the Function Module BAPI_GOODSMVT_CANCEL to reverse the PGI.
            I think the later Approach is much easier rather than going for the Standard Function Module (Posting Program), Exits and find a place where we have to find another Enhancement Spot / Enhancement where we can call the above FM to Cancel the Goods Movement.
    Hope these inputs were helpful.
    Thanks and Regards,
    Venkat Phani Prasad Konduri

  • Automatic Goods issue when delivery document is save

    The users are missing to click the Post Goods issue after picking done. Is there a way where once the delivery doucment is saved, the stock will get reduced from the storage location without clicking Post Goods issue.

    hi
    i think it can be done in LT03 screen by putting the value "2" in adopt put quantity
    and save the transfer order pgi will be done automatically.
    the above applicable if u r using lean ware house functionality
    regards

  • Partial Goods Issue against a Delivery Document

    Dear Xperts,
    I am having a scenario regarding standard Stock Transport Process with Delivery(Material Movement 641).
    My requirement is, when I will create a Stock Transport Order the Delivery document will automatically be created at the same time.This can be achieved thru customization.
    But the problem is , the material quantity in the delivery document will be same as the order quantity in PO.My question is :
    1. Can the user change the quantity in delivery which is automatically got created at the time of PO creation.
    2. If yes, then for the remaining order quantities , shall the system will automatically create another delivery?
    3. If no, can we do partial goods issue against that delivery if total material is not available at sending plant?If yes , how to configure?
    Means , In delivery my material qty is 10, can I do Post Goods Issue of leass than 10 qty & create a proforma invoice against that delivery and do the P.G.I. and Billing again against that delivery?
    Plz advice.
    Regards,
    Soumick

    Hi
    As per your scenario you can do the PGI (post goods issue ) for partial quantity only if u required later for reaming quantity when ever stock is available that time you can do again PGI by using the same delivery no for reaming quantity but for this
    In PO you have unchecked the Delivery  completed indicator with   this when ever complete goods are coming then only PO will
    be close up to that PO will be in open Status
    Regards
    Balaraju

  • Check a UDF of batch number when I create Goods Issue or Delivery

    Hello,
    I manage my items with batch number and I want to block the creation of all  Goods Issue or Delivery in function of the value of a UDF (created the OIBT table).
    I think I can achieve this by using the stored procedure SBO_SP_TransactionNotification, but I never used it and I don't know if (and how) I can retrieve the selected batchnumbers of my documents.
    Is it possible to do so, or do you have any better suggestions???
    Thank You,
    Xavier.

    Hi Xavier,
    You can find some additional information about the SBO_SP_TransactionNotification stored procedure here:
    [https://www.sdn.sap.com/irj/scn/go/portal/prtroot/docs/library/uuid/e991e2b9-0901-0010-0395-ef5268b00aaf]
    The stored procedure only returns the following;
    - Object type
    - Transaction type
    - Num_of_cols_key (number of columns in the primary key of the object)
    - List_of_key_cols_tab_del (the list of the columns in the primary key)
    - List_of_cols_val_tab_del (the values of these columns)
    So the stored procedure doesn't directly return the information you want. You would have to link this with a DI application to access the document in question using the value of the primary key returned by the stored procedure. (Or through using an SQL query also using the primary key returned by the SP).
    Please note however, that SBO_SP_TransactionNotification is designed for notification purposes only. SAP can only support any issues arising out of use as a notification mechanism; the use of this stored procedure to block transactions or work as an authentication step are not supported. Please see SAP note 1011154 for more information.
    Regards,
    Niall

  • Good issue from delivery not possible due to credit block

    Hi gurus,
    Please help me on this issue.while doing PGI for the delivery i am getting the following error message."Good issue from delivery not possible due to credit block "The simple credit check is assigned for the sales document type.iam doing free of charge delivery.
    What are all the possible ways to get such error
    Regards
    Vis

    but system behavior is not set in transaction OVA8, means combination of risk categories and 03 is not set.
    I think you are checking the wrong risk category, please check once again the Risk category of the payer in FD32, what is it assigned and also check OVA8 with this risk category.
    If you find the above settings are correct as per your observation, try to create a fresh cycle so that you will get the correct results as per your settings in delivery.
    In your case what you are saying is correct, may be the risk category is changed recently this you can check the change log of the payer customer in FD32( if any change takes place).
    If possible try to past the screen shot of both.
    thanks,
    srinu.

  • How can I print ONLY the active document?

    Whenever I go to File/Print the darn PSE 9 program sends all of the working files in the bin to the printer. I've searched online for 2 hours now looking for an answer.
    I like to work with having several to many files in the 'bin' and prefer to only print the active file I'm currently working on without having to close the 'working files' before I can print. How can I print ONLY the active document or file in the project bin? Please help, I've upgraded from PSE 3 to PSE 9 and really like the updated features, but this one pain in the neck default is getting the best of me.

    Thanks for your help, that works nicely. It is good to have control of the printer again.

  • STO - JEX invoice getting created without Post goods issue of delivery

    Dear Experts,
                We have configured the "Stock Transport Purchase Order" process between 2 different plants within same company code. To satify the Indian legal process, after PGI issue we configured the process as "Proforma" invoice creation using Billing type ZJEX (Copy of JEX). And then Excise Invoice creation using J1IIN.
                      Now problem we are facing is, without "Post Goods Issue" of delivery ZNL also system is allowing to create the invoice using ZJEX type. We are using the standard NLN item category only. But our requirement is, without "Post goods issue" system should not allow to create the sales invoice.
    Can anybody give your suggestion on this issue.
    Thank u
    Regards,
    Nag

    Dear Experts,
            Thanks for your feedback. As per your suggestion i modified the copying requirement in to "034". But during invoice creation i am getting the message that "The item is not relevant for billing". So not successful.
    Can you please give suggestion to solve this issue
    Regards,
    Nag

  • Auto print of Goods Issue/Transfer Posting Documents by Movement type

    Hi,
    We have created two different output types to print the layout's of Goods Issue/Transfer Posting Documents.
    The requirement is to default the message in the document by movement type (key combination)
    Meaning if it is 201 it should populate GI output type
    If it is 313 it should populate TP output type.
    we do not have any standard key combination  (NACR) by movement type wise.
    Any alternative way of meeting this requirement?
    Thanks
    Regards
    Ram

    Hello Kevin,
    I donu2019t think it is necessary to use a user exit to keep the Material B (that is transferred from Material A) in the same bin.
    This can be controlled in the customizing: indicator Post to same bin, that can be set in the WM Movement type (V_T333-KZUAP) and in the Storage type (V_T3010-KZUAP).
    Now I donu2019t know your business process but I am surprised that Material B requires more space than Material A since it is u2018bornu2019 by means of a transfer posting and not a production or packing step that makes it bigger in terms of capacity required.
    A workaround for this could be to transfer (LT10) Material A first to a separate Storage type (with the Post to same bin-flag set) that has no Capacity check and after the 309 posting transfer it back into the warehouse with LT10.
    Success and thanks beforehand for any credits!
    Kind regards,
    Bart

  • Automating Goods issue during Delivery creation

    Hi all,
    We have a requirement to automate the Goods issue creation for certain type of orders when the Delivery is getting created. The orders that need to be automatically Goods issued during delivery creation are identified based on certain plants. These plants are linked to certain output type and in the output type routine is the standard program RVADEK01 with one additonal code for automating the Goods Issue creation.
    We have a custom table that holds the status of orders and there is a code in user exit userexit_save_document_prepare which changes the status of the order as closed when the goods issue is done.
    But when the delivery is saved, in this case when an automatic goods issue needs to happen, when the flow reaches this user exit, the output type code dosenot get executed and the Goods issue is not done and so the custom table will not be updated with the closed status. So we are in need to findout a place where we can update the status of the order in that table.
    The output type code is not executed even before the other user exit userexit_save_document. The output type code gets executed and goods issue is done after the this userexit_save_document when the COMMIT statement is executed in the subroutine BELEG_SICHEN_POST in the include FV50XF0B_BELEG_SICHERN.
    I need help in finding out if any user exit or badi is called after this commit statement, so that I can add my code to close the status of the order in my custom table. Just after this commit the Goods issue happens and the VBFA table gets updated with the 'R' records for goods issue.
    Please let me know if anyone has any idea on this. The ultimate goal is to find some place after the goods issue is done to update the status of the order as closed in the custom table we have.
    Thanks,
    Packia

    Dear Siva,
    As informed yesterday I changed the language from DE to EN, to match the other shipping points settings in table V_TVST, this did not bring the solution.
    Please let me summarize, I am really desparate here:
    This is only IM related, Not WM.
    Picking lists are not printed for any Shipping Point from this warehouse, this is just a small subsidiary of my customer in Finland.
    Issue is not Aut. PGI.
    VP01SHP has not been configured for any shipping points, still there we do get the PR except for the new shipping point.
    In the deliveries of correct processed shipping points  I do not find any picking output type.
    Item category in new shipping is equal to Item category in already existing shipping points, so no need to config here.
    There is no picking block active.
    PR creation happens once I enter the pick qty in the delivery in VL02N. This is the part that we need to have automated.
    Can you please try to help me out?
    Tnx & regards,
    Chris

  • Issue in Delivery document Status update

    Hi ,
    We are facing serious issue in delivery document delta extraction via Delivery item Datasource (2LIS_12_VCITM). This leads to incorrect Pending logistic figures in stock and dispatch report. Details for the issue are as follows.
    Datasource used : 2LIS_12_VCITM
    Issue Description :
    The goods movement status flag (WBSTA) field from the ECC table VBUP is not correctly extracted by the standard deliveries item datasource (2LIS_12_VCITM) during delta loads.
    Steps taken to rectify the issue
    -     We have removed the commit work statement and applied in parallel update task in ECC. Include : ZSD_INCL_DEL_SAVE_FINS
    -     Setup tables for Delivery were filled in ECC.
    -     Historic data was deleted from the Delivery cube in  BW
    -     Data was pulled into PSA (Info package u2013 Full Update)  from where it was loaded to DSO in overwrite mode  (Historic data was not deleted from DSO)
    -     Data from DSO to delivery cube was loaded with DTP setting as Full Update.
    -     After complete data was updated in Cube the DTP setting were changed to Delta.
    -     Delta info package was scheduled  for the capturing the document changes from next load.
    -     Goods Movement status for all the documents created till this point was exactly similar to the status in ECC.
    -     The goods movement status flag (WBSTA) field from the ECC table VBUP is not correctly extracted by the standard deliveries item datasource (2LIS_12_VCITM) during delta loads.
    Example              :
                                    Delivery document no:  2131260470 is pulled with goods movement status u201CAu201D in firstly load (here BW Delivery status matches
                                        With ECC )
                                   Before next delta load status in ECC (WBSTA) changes to u201CCu201D (PGI Complete) along with updated u201CGoods Issue Dateu201D
                                   Extractor fails to capture the change in document ,thus status in BW remains as u201CAu201D with no date updated in u201CGoods Issue Dateu201D
                                       field.
    Steps for Reconstruction :
    1)     Check the value of Goods movement status and actual goods issue date fields in the PSA for the datasource 
    2LIS_12_VCITM in BW for the sample delivery mentioned in the attached file
    2)     Compare these values with the ones in the ECC table VBUP.
    Kindly help at the earliest.
    Regards,

    Hi,
       Could anyone please reply as its quite critical.
    many thanks in advance,
    regards
    pramod.

  • I have multiple documents how can I combine them into one document?

    I have multiple document files in Pages. How can I combine them into one document?

    Menu > View > Page Thumbnails > click on the thumbnails > Copy/Paste into thumbnails of other document
    Peter

  • How can I forward an e-mail document on adobe

    I want to know how can I forward a e-mail document from adobe and I saved the document called Princess Pink but cannot find it. two questions need answer

    Hi Ohtigers
    Is your document a PDF?
    Did you have it open in Reader or Acrobat Prod?
    Can you log into https://files.acrobat.com/ and search for your document?
    If your document is a PDF, you can open it in Adobe Reader and you can send the file using Adobe SendNow
    Select 'Tools' from the top bar
    In the right hand panel select 'Send Files'
    Click on  'Sign In' - you will be prompeted to enter your Adobe ID and password
    Enter an email address into the To field
    Option: Fille out the Subject and Message fields
    Select Send Link button

  • On my mac when i click on pages, a new document doesn't open instantly  but a window with my files open and then  have to click on the left bottom new document in order to open one. How can i have directly a new document when i click on pages icon

    On my mac when i click on pages, a new document doesn't open instantly  but a window with my files open and then  have to click on the left bottom < new document> in order to open one. How can i have directly a new document when i click on pages icon

    How to open an existing Pages document?
    Click Pages icon in the Dock to launch Pages.
    When Pages is open, click File menu in the  Pages menu bar.
    Select “Open”.
    When the select document  dialog box opens up, highlight/select the document and click “Open”
    at the bottom right corner of the dialog box.
    s
    https://support.apple.com/kb/PH15304?locale=en_US

  • How can I send more than one document on an email

    how can I send more than one document on one email

    Thank you but I understand that form of attaching a document. However when I select a document then click 'Share' I have the option of sending the document by email as a word or pages document or pdf, what I want to know is can I use this procedure to send more than one document per email and if I can how?

Maybe you are looking for