How to create a Purchase Requisition for a material component in WBS or NW?

Hello All,
I have created a project with the following structure:
Project Defination (Construction of Sub station)
      Main WBS
               Level 1 WBS
                         Level 2 WBS
                                   Network for level 2 WBS
                                                  Activity  (Procuring Material)
                                                             Material Component - MATXXX (Stock Item)
Now in the above structure i have a activity where in i am procuring all the materails required to construct a Substation.
So under this activity i have assigned all the materials which are needed to build Substaion.
After i change the status of the project to release, there  a reservation created for the quantity of the material which i have mentioned in the material component under the activity.
Now my querey is, how should i create a Purchase requisition for the reserved materail quantity in order to bring in the stock against the WBS / network / Project ?
Awaiting your reply.
Thanks and Regards,
Sudarshan.

Hi Sudarshan,
In your case you can run Me5J to check the list of PR created against your project.
Then Create PO and similarly you can check list of PO in Me2J.
Then followed by GR and check if any GR release exist in MIGO. Then once after doing GR you can check the Material in Stock which will move material from Unrestricted stock to Project Stock which you can check it in MMBE.
Then you can do the Good Issue in MIGO itself and run MIRO to complete the cycle.
Regards'
syed

Similar Messages

  • How to create a purchase requisition from the EP

    1. How to create a purchase requisition from the EP & What are the pre-requiste?

    Hi,
    You need to create a SAP transaction iview for purchase requisition transaction and link it to the role and to the user to view purchase requisition transaction.
    First you need to create a system in portal to link to the R/3 system. For creating system check this link.
    http://help.sap.com/bp_epv260/EP_EN/documentation/EP/N03_BB_InstallGuide_EN_US.doc
    For linking portal with R/3 and view the Purchase requisition check this link
    Configuring EP for connecting to SAP R/3
    Regards
    Arun

  • MRP creating additional purchase requisitions for the existing sales order

    Hi,
    We have scenario where we switch materials from POD material to ARP material. POD material is just like make to procurement which creates purchase requisition and purchase order upon saving the sales order. ARP (Auto replenishment) material creates purchase requisition based on sales order and re-order point while running MRP.
    When the material is POD title, it created purchase requisition and purchase order (example: 4500000110) while saving the sales order (example: 1000000010) for the quantity 10. After some time this material is switched to ARP and it has open sales order (1000000010) and purchase order (4500000110).
    We have special MRP run for ARP materials based on MRP type, which creates purchase requisition.. What is happening is when we run MRP; it is creating new purchase requisition for the old sales order (1000000010) for the quantity 10. But old sales order (1000000010) is already having purchase order (4500000110) to fulfill. So we donu2019t want to create new purchase requisition for the old sales orders. It should create purchase requisition only for new sales orders.
    Please advise
    Thanks in advance
    Srinivas

    Mangesh,
    If the components are Inhouse production then you can think of using collective orders by assigning special procurement key 52. If raw material exists then your requirement cannot be met..as i think your scenario is of assembly processing. The idea of assembly processing is that component materials will always be available and only assembly will be done based on Sale Order.
    Regards,
    Prasobh

  • Create another purchase order for a material ordered in full

    Hello friends,
    I have a little MM question for you.
    I've created a purchase requisition with a material A and quantity 100 UN
    I've then created a purchase order in reference to this PR.
    This PO has been released.
    Is it possible, in standard SAP, to create another purchase order in reference to the same purchase requisition for the same material and the same quantitiy ?
    How does SAP control that ? (customizing path ??)
    Regards,
    Bahia.

    Dear,
    Is it possible, in standard SAP, to create another purchase order in reference to the same purchase requisition for the same material and the same quantitiy ?  Yes it is possible in SAP
    How does SAP control that ? (customizing path ??): SAP controls in that way, when ever you create purchase requisition with a material A and quantity 100 UN...Now PO created and released...
    Now again if you try to create PO wrt PR, you can observe this time you will get all deatils in PO without quantity...reason behind that is, you have already released an order for full qty w.r.t. that PR...So this time qty field will be empty..You have to manually enter this field.
    Now the same you can see in the the PR status in ME53N Tcode.
    Regards
    Utsav

  • How to create a purchase order for a purchase requisition

    Dear Experts,
       Explain the steps for creating purchase order for a purchase requisition.
    and where can i find this purchase requisition field in PO creation.

    Hi Ravi,
    Check out these documents:
    http://www.olemiss.edu/projects/sap/MM_Create_PO_with_Ref_to_a_PR.pdf
    http://www.sap.com/africa/services/education/pdf/Work_Instruction.pdf
    Regards,
    Chandra Sekhar

  • Not able to create the purchase requisition for the subcontracting process

    Dear Gurus,
    There is a process order with the component which is to be handled in the subcontracting .Earlier we are able to create the purchase requsition with the creation of the process order .But recently I am not able to do so .I am getting the "The value of the field Reservation/Purchase requsition as Never" .I have checked with the settings in the procurement type in the MRP2 view of the material master  which is "X" ,the validity of the outline agreement and contract  which is OK.Can you please help on this.

    Hi Venkata,
    Check this links:
    http://help.sap.com/saphelp_nw70/helpdata/EN/84/0cb892edfbc34290c1685132006662/content.htm
    http://help.sap.com/saphelp_nw70/helpdata/EN/58/54f9c1562d104c9465dabd816f3f24/frameset.htm
    http://help.sap.com/saphelp_nw70/helpdata/EN/f3/914f3445194d468f652d45494230b1/content.htm
    Which database and OS is your BW server on? Not all of them are supported for SQL server
    Hope this helps.
    Regards,
    Diego

  • Display purchase requisition for a material

    Hai...,
    can any one help me in developing a report to display purchase requisition based for perticular material number.
    tell me the tables and fields to  use..
    if possible sample code tooo....
    thanks in advance.

    Tables for Purchase Requsition.
    For Purchase Requisition
    EBAN Purchase Requisition
    EBKN Purchase Requisition Account Assignment
    EBUB - Index for Stock Transport Requisitions for Materi
    EINA - Purchasing Info Record: General Data
    EINE - Purchasing Info Record: Purchasing Organization D
    EIPA - Order Price History: Info Record
    EKAB - Release Documentation
    EKAN - Vendor Address: Purchasing Document
    EKBE - History per Purchasing Document
    EKBEH - Removed PO History Records
    EKBZ - History per Purchasing Document: Delivery Costs
    EKBZH - History per Purchasing Document: Delivery Costs
    EKEH - Scheduling Agreement Release Documentation
    EKEK - Header Data for Scheduling Agreement Releases
    EKES - Vendor Confirmations
    EKET - Scheduling Agreement Schedule Lines
    EKETH - Scheduling Agreement Schedules: History Tables
    EKKI - Purchasing Condition Index
    EKKN - Account Assignment in Purchasing Document
    EKKO - Purchasing Document Header
    EKPA - Partner Roles in Purchasing
    EKPB - "Material Provided" Item in Purchasing Document
    EKPO - Purchasing Document Item
    EKPV - Shipping-Specific Data on Stock Tfr. for Purch. D
    EKRS - ERS Procedure: Goods (Merchandise) Movements to b
    EKUB - Index for Stock Transport Orders for Material
    EORD - Purchasing Source List

  • Create auotmatic purchase order for non stock materials

    Hi,
    Please provide me information on how to create automtaic purchase order for non stock materials in MM system.
    Regards

    Hi,
    For automatic PO creation follow the steps.
    1) Material Master purchasing view tick automatic PO check box  (Material type NLAG)
    2) Vendor Master purchasing view tick automatic PO check box.
    3) Maintain Source list for Vendor & Material.
    4) Maintain Purchase Info Record.
    5) Create a Purchase Requisition.
    6) Use T.Code: ME59N & execute for PR for vendor, you will be able to create automatic PO.
    Note
    Ensure that Purchase Info Record should be there.
    If you have more than one vendor then fixes only one vendor in source list.
    During PR creation select source determination check box.
    SAM

  • How to create an inspection lot for each line item of the Purchase order?

    Hi,
    How to create an inspection lot for each line item of the Purchase order ?
    In detail if possible.

    Hi
       please check this
    [thread|Create Inspection Lot;

  • BAPI to create Purchase Requisition for selective BOM Material

    Dear Experts,
    I need ur help, Actually I am developing a module Pool prg to create Purchase Requisition for selective Bom Material .
    Actually, standard T.Code (ME21N) create PR for a multiple BOM Materia lwhich are used to create a prepared material. But my requirement is PR should be generate for selective BOM material .
    Multiple BOM Material is used to prepared a complete Material .
    I have checked a particular BOM Material, for this matrial Purchase Requisition should be genrate.
    Please suggest me the related code and Bapi which helps me .
    Thanks & Regards,
    Swapnika

    Hi
    you can Use BAPI   BAPI_REQUISITION_CREATE
    Hope Its  help You.
    Regards
    Ajit

  • Error while creating a Purchase Requisition T Code ME52N

    Dear Freinds,
    The users are trying to create the Purchase Requisition, however the system gives the error message that the GL Account xxxxxx cannot be used, as the comparison of the field selection strings are not comparable with the Account Assignment Category E. Message no. is ME045. How could we resolve this?
    Thanks for the help.
    Regards

    Dear,
    check the FSG for the GL Account 200010 and go to TCcode OBC4 and check the status of field 'Asset number / subnumber' and then go to TCode OME9 and select A and check the field status for field 'Asset number / subnumber'. Status at both areas are different hence system is not accpting. Make status identical.
    Regards,
    Sandip

  • Purchase requisitions for  raw materials

    Iam having multilevel BOM and when I do Sales order MRP then Iam getting planned order for Semi finished items but not getting Purchase requisitions for  raw materials.

    Hi,
    Planing File Entry :-
    The planning file is used to limit the scope of the planning run for the
    total planning run. For this purpose, all materials that have been
    assigned a valid MRP type are automatically entered in the planning
    file.
    System will check the Planing file entry only in the case of Total MRP (MD01) or Total MPS (MD40).
    While there is no need in the case of MD02,MD03,MD41,MD42,MD50.
    Now how this Planing File entry activates,
    - Once MRP is activated at Plant level (T.code OMDU)system automatically maintains entry in Planning file for all those materials which contains the Active MRP type.
    - So if materials which are created before this activation of MRP in that case you have to maintain this planing file entry manual.You can do this either by MD20 or by using Back Ground Jon OMD0.
    Regards,
    Dhaval

  • How to create an address code for PO delivery address?

    Hi Guys,
    How to create an address code for the delivery address in the purchase order? Please explain me with details.....
    Thanks
    Raja

    delivery adress records can be created with transaction MEAN.
    the number is purely internal.
    In ME21N you can then search by name (you will certainly not know the number)

  • How to create the Access sequence for the Vendor+material+plant combination

    Hi all
    Please let me know How to create the Access sequence for the Vendormaterialplant combination..
    Whats the use? What its effect in purhcase and taxe..
    brief me please

    Hi,
    you are asked to maintain the access sequence for the tax condition for which you are putting 7.5%.
    goto OBQ1 or img..financial accounting new...global settings.... taxes on sales and purchases ......basic settings.....
    find the tax condition type. see in it which access sequence is attached.
    if there is none then use JTAX used for taxes in India.
    or you can create the similar one for your.
    to create the same goto OBQ2.
    new entry or copy JTAX.
    and assign the access sequence to condition type.
    this will resolve your problem if you just need to assign the access sequence.
    regards,
    Adwait Bachuwar

  • How to create a account key for application type M ?

    Hi Guys,
    How to create a account key for application type M ? and link the same with
    Gl account.
    thanks.

    Hi
    Please create the account keys or transaction keys in
    SPRO-> IMG-> MM-> Purchasing-> Conditions-> Define Price Determination Process-> Define Transaction/Event Keys
    Thanks & Regards
    Kishore

Maybe you are looking for

  • Sharing multiple user accounts to AppleTV on one Mac

    I can't remember if I did this before with software 1.0/1.1, but I'm sure the possibility of having two concurrently active iTunes libraries on a single machine has been discussed as one way of separating out content. To do some more testing on softw

  • Budget Process (Linked the maintenance Order into Internal Order) in EAM

    Dear Experts, Scenario for Repair & Maintenance with only MM & FICO module live w.e.f. 2007 (PM not live) Process Managed thru Internal Order (Order Type: RPMT) Budget managed through Investment Management (IM); Budget is directly entered against the

  • Extended Transport Control

    I just implemented Extended Transport Control for my Transport Domain, which consists of DEV-100, DEV-111, QAS-200, QAS-220. Now, it asks me to set the 'target client' for all the transports that are already imported.Without setting the target client

  • Can't burn iso image

    I used to be able to burn an iso image from the context menu by clicking on 'Burn "*" to Disc...', inserting a disc and let it burn. Now when I try to burn an iso image by using the context menu a box pops up saying 'Are you sure you want to burn the

  • Why is this page displaying like this?

    I'm trying to convert this page so that the layout is based on server-side include files but since doing this the page is displaying incorrectly. What have i done wrong? http://www.milesfunerals.com/donations_2.php