Hi,
I have one background job with 5 variants associated with iy.
Now i want to remove 2 variant from that background job.
is it posible???
if yes then how to do that?
Thanks,

Hi.
Go to SM37, execute report to see it, click on modify, and change steps.
If you have problems, delete job, and create a new one.
Best regards.
Valter Oliveira.

Similar Messages

  • How to delete/deactivate a background job.

    Hi Gurus!
    Is there any way to delete a background job?
    I have a send job which sends email notifications to internet mails.
    I want to deactivate or completely delete the job.
    Please guide on what to do.
    I'll give points for answers.
    Regards,
    Vhong

    Hi,
    To delete the job, go to sm36, choose 'own jobs' and delete your job.
    As I experienced Selecting and deleting the job in sm37 does not delete the job, but just delete the scheduled or released job in database.
    P.S:
    It is kind of weird that, each time you schedule and save a job, it is scheduled in background. Even if you want to change the step definition and you save, you will see that the job is scheduled for the second time with the latest version. The last save does not cancel the previous job schedule. So you have to do it manually.
    Hope this helps
    Derya

  • Regarding Variants for Background jobs

    Hi Folks
    Can you please let me know the procedure how we can create the variants for Background jobs.
    Points are assured for correct answers.
    Regards,
    kumar

    Hi Sree Ram,
    Check this info.
    If you have any selection screen parameters for your program you need to enter the values for those fields in runtime. So, if you schedule your program in background to execute then there is no one to do this job. Here comes the concept of Variant.
    With variant you define what are the selection field values in the runtime. During runtime the program picks this values and runs the program.
    When you execute your program which has selection fields, you enter the values and then you click on 'GO TO ' tab and 'SAVE AS VARIANT'.
    When you schedule your program in background, give this variant also. Then it will run automatically.
    Hope this resolves your query.
    Reward all the helpful answers.
    Regards

  • Is it possible to delete a running background job programatically?

    Hi Gurus,
    is it possible to delete a running background job programatically? if yes how can we do that?
    Thanks in advance

    Or as sais by Sandeep you can use that fm.
    Before calling that select the required data from table TBTCO and pass to the fm.

  • How to trigger an existing background job in ABAP program?which fm?

    Hi experts,
        how to trigger an existing background job( defined in SM36 ) in ABAP program?which fm?
        seems that FM 'JOB_OPEN' / 'JOB_SUBMIT' / 'JOB_CLOSE' can only create a new job.

    Hi,
        now my requirement is that sap has generated one job automatically, and then i will have a job name
    'XXX'. and then i want to schedule the job in abap program,. which function module could i use ?
    my expected fm is that the system will trigger the job after i give the job name and start condition.
    i have tried job_open, but it seems just to create a new job. any advice ?

  • How to delete a Form Routine in Table Maintenance?

    Hello,
    Very Good Morning!
    How to delete a Form Routine in Table Maintenance?
    I had created a Form Routine at Environment>Modifcation>Events.
    I want to delete a Form Routine that I had created. Can any one please explain me the way I can delete it.
    Any suggestions are appreciated!
    Thanks & Regards
    Kittu

    Hello Rudra,
    Very Good morning!
    I am in Environment>Modification>Events.
    Here is had created a form routine ie...
    01   From_entry    Editor Icon
    In Editor Icon we will write the code.
    This will create a Include in the Function group.
    I had already comented that Include from the Function group. I can even delete it. But, I want to delete the Form Routine that I had created....
    01   From_entry    Editor Icon
    Can any one hepl me please...
    Thanks & Regards,
    Kittu

  • How to delete the SAP HR jobs in bulk

    Hi,
    I have created the jobs but now I want to delete them.
    Please let me know the following:
    How to delete the SAP HR jobs in bulk?
    Is there any programs/tcode to delete the jobs in bulk apart from LSMW?
    Thanks & Regards
    Manish

    Hi Manish,
    Please use report RHRHDL00.
    Regards,
    Dilek

  • Setting up archive delete functionalities using background job

    Hi,
    Through SARA transaction there we can set up a archive delete job by selecting the files, job timing details. Instead of this, we want to set up this functionality using a background job as per the variant and timing requirements.
    Is there any option to set up a background job of archive delete functionality by selecting the files through a program or function moduel. Please suggest me if anyone has done this in previous.
    Thanks,
    Siva

    Hello,
    Take a look at OSS note 205585 which describes how to schedule archive delete jobs indirectly using program RSARCHD.
    Hope this helps.
    Best Regards,
    Karin Tillotson

  • How to de-schedule a background job?

    Dear all,
         I have scheduled a background ABAP report titled ZHRWFIT19 at SM36 to trigger a workflow.
         Initially I scheduled this background job to 9 A.M.
         Later I changed to schedule this background job to 10 A.M at SM37.
         Now my workflow triggers twice i.e., at 9 A.M. once and 10 A.M once.
         I want it to start at 10 A.M. only.Though I changed the schedule time to 9 A.M. to 10 A.M, still my background job triggers the
         workflow at 9 A.M. and 10 A.M.
         How to de-schedule this background report at 9 A.M.?
         Please suggest for which I will be grateful forever.
    Thanks and regards,
    S.Suresh

    Dear Shastri,
             Thank you so much for your reply.
             As you have rightly pointed, I have 2 entries with same background job at SM37.That's why my workflow triggers twice.Now I want to permanently delete the background job entry at SM37 which triggers my workflow at 9 A.M.
            I couldn't delete this entry at SM37 permanently.Please suggest me how to permanently delete the entry that triggers the workflow at 9 A.M., for which I will grateful.
    Thanks and regards,
    S.Suresh

  • How do I run scheduled background job manually

    I have a cancelled background job that is givingh dumps. I have implemented corrections and now i want to run it manullay to check it. How do i do that. Please suggest

    Hi Bill,
    You mentioned that you've applied some correction..If you applied some notes that might have modified the standard code.
    In that case Go to SE38, Give the program name, choose "variant" > Display. Now select the variant (with which you got the message its not valid).  Go to "Variant" > "Adjust".
    Then try running the report with the variant. This should solve the variant issue.
    Thanks,
    Debasis.
    Edited by: Debasis Sahoo on Sep 24, 2008 11:55 PM

  • How to Cancel a ACTIVE background Job scheduled in SM37.

    Hi Friends,
    I have scheduled a Background job. The job is ACTIVE now. How can I cancel this job?
    Regards,
    Viji

    There is a last ditch method for jobs that don't get canceled for some reason or the other
    Go to SM50 - first try canceling the job from there
    If that doesn't work, note down the Process ID (PID) of the job
    Take direct OS access to your system (You would need your Basis person for this) and terminate the job
    If the server is Windows based, you can end it using the task manager and end that process id

  • How to delete adove  ( Form builder )

    dear,
    How to delete blank page in Adove dev. (t-code SFP ).
    regards,
    mukesh

    Hi,
      Open the Form in change mode. Go to the layout tab and open the Hierarchy view. You can create and delete pages here.
    PS:   Hieracrchy view can be selected from the Palettes Option
    Regards,
    Susanta

  • Variants for background jobs

    You need to schedule and automate batch jobs in an organisation. There will be multiple variants and multiple steps within same batch jobs. The variants are date dependent and needs to change every day. You need to automatically change the variants every day and schedule the jobs. Also check for the failures in the jobs. Apart from that Once the jobs in one server example : R/3 server ends the jobs in BW servers should be triggered automatically. Explain all steps with proper T codes and also provide a dry run example. Also provide all the table used for the variants purpose.
    Please help on this,thanks
    Narendra

    Hi Narendra,
    The background jobs are scheduled depending on the requirement with specific variants which are both date specific and even specific sometimes. These variants are created for the programs or reports which are run in the background job ,These variants are stored in VARID table for client specific variants and
    VARID_CI for client independent. For most of the times all these jobs are maintained in some job scheduling tools so that they automatically inform about job failures and processes can be automated.In our organisation we use UC4 for background job schedulign and it controls the process as you are looking for.
    Please award points accordingly
    With Regards,
    Junaid
    Message was edited by:
            muhammed junaid

  • How to delete the scheduled backup jobs

    Hi,
    I had scheduled differential (SOL 2000) backup every day as below.
    Enterprise manager --> select the <SID> --> Right Click --> Select all tasks --> Backup --> in this screen we have option to schedule the backup daily, monthly, weekly.
    Since the path which i set does not exists, its canceling every day.In ST04, log showing as canceled.
    Now, i don't want this differential backup daily. I want to cancel this.How can i cancel this scheduled job?
    Regards,
    Gayathry.

    Hi Gayathry,
    In that Enterprise manager, you can find Management --> SQL Server Agent --> Jobs
    Here you can observer your scheduled job if you want to delete this, you can delete.
    Nagendra.

  • How to pass layout variant in background job?

    Dear Gurus,
    I have set layout variant as PARAMETERS in my program.
    The report will be executed successfully in front-end, but if I set it in background , it will pop up error msg: Program (IS_VARIANT-REPORT) not specified.
    But the alv function I have check...
    CALL FUNCTION 'REUSE_ALV_GRID_DISPLAY'
        EXPORTING
          I_BYPASSING_BUFFER       = 'X'
          I_CALLBACK_PROGRAM       = W_REPID
          I_GRID_TITLE             = V_GRID_TITLE
          I_CALLBACK_PF_STATUS_SET = 'SET_PF_STATUS'
    *      I_CALLBACK_USER_COMMAND  = 'FORM_USER_COMMAND'
    *      I_STRUCTURE_NAME         = 'ZSDS0005'
          I_SAVE                   = 'A'
          IS_LAYOUT                = I_LAYOUT
    *      IS_VARIANT               = STRU_DISVAR
          IS_VARIANT               = DEF_VARIANTE_F4
          IT_FIELDCAT              = I_FIELDCAT_ALV[]
          IT_SORT                  = XT_SORT[]
        TABLES
          T_OUTTAB                 = IT_OUT
        EXCEPTIONS
          PROGRAM_ERROR            = 1
          OTHERS                   = 2
    Jamie

    Thank you so much, but the sample code have one bug, and  I have already modified the code.
    The variant will be caught only after clicking F4 list, if there's already one default variant, system will ignore it.
    AT SELECTION-SCREEN.
    *  Validating selection screen fields
      PERFORM F_AT_SELECTION_SCREEN.
    *&      Form  f_at_selection_screen
    *       text
    *  -->  p1        text
    *  <--  p2        text
    FORM F_AT_SELECTION_SCREEN .
    * ALV Layout variant
      IF NOT P_VARI IS INITIAL.
        MOVE GX_VARIANT TO G_VARIANT.
        MOVE P_VARI          TO G_VARIANT-VARIANT.
        CALL FUNCTION 'REUSE_ALV_VARIANT_EXISTENCE'
          EXPORTING
            I_SAVE     = 'A'
          CHANGING
            CS_VARIANT = G_VARIANT.
        GX_VARIANT = G_VARIANT.
      ELSE.
        PERFORM F_INITIALIZE_VARIANT.
      ENDIF.
    ENDFORM.                    " f_at_selection_screen
    *&      Form  f_initialize_variant
    *       text
    *  -->  p1        text
    *  <--  p2        text
    FORM F_INITIALIZE_VARIANT .
    *  CLEAR DEF_VARIANTE_F4.
    *  gv_save           = 'X'.
      GX_VARIANT-REPORT = SY-REPID.
    *  DEF_VARIANTE      = DEF_VARIANTE_F4.
      CALL FUNCTION 'REUSE_ALV_VARIANT_DEFAULT_GET'
        EXPORTING
          I_SAVE     = G_SAVE
        CHANGING
          CS_VARIANT = GX_VARIANT
        EXCEPTIONS
          NOT_FOUND  = 2.
      IF SY-SUBRC = 0.
        P_VARI = GX_VARIANT-VARIANT.
      ENDIF.
    ENDFORM.                    " f_initialize_variant

Maybe you are looking for

  • Script won't work on newer Mac

    Last year, I wrote an Illustrator script (that pastes something into multiple files) for my coworker who works remotely. It worked fine. Recently, she upgraded her Mac to OS 10.8.5 (but still uses Illustator CS5) and now the script does nothing-- the

  • Image Stitches after exporting to PDF

    Hi guys, I have exported PDF documents from InDesign in virtually all standards and option configurations. The output would sometimes look good but upon closer inspection white lines would appear across images; these images are divided into (seemingl

  • Problem in starting rmid in a port different than the default one

    hi all, i am experiencing exceptions in running rmid in a port different than a default one. if i run rmiregistry 2000 rmid -J-Djava.security.policy=policy java -Djava.security.policy=policy -Djava.rmi.server.codebase=<mypath> -classpath <myclasspath

  • Can't set profile photo

    So I recently got a new skype account after losing my old login details. I decided to upload a pic of myself, and I discovered that this is impossible for some reason. I browse for the pic and click on it, and it just returns me to the screen with th

  • How do I remove aberation/halo from composited photos.

    I want to replace the sky in one photo with the sky from another photo. In Bridge I selected the photos and  load the photos into Photoshop layers.  This is Photoshop CC 2014 64-bit.  When they arrive in Photoshop, neither photo has any type of halo