Internal Requisition is in Incomplete status.

Dear All,
I created internal requisition and approved. even i approve it, still it is in incomplete status.
approval groups, assignments and document types are set properly.
do i need to check any setups in approving the requisition? plz suggest me.
Regards
RSM

thank you for the reply.
it is solved. The problem is Work Flows are not defaulted in the document types for the internal requisition.
Regards
RSM

Similar Messages

  • Setup to leave requisition for outside processing in 'Incomplete' status

    We are trying to implement outside processing, and the requisitions are automatically generated, but they are all in Approved status. Is there any setup/ profile option I can set to leave the requisitions in Incomplete status? Thanks

    I don't think it was using WF. When the work order was released, Oracle inserted the data immediately into the po_requisitions_interface_all and then launched the requisitions import program. But when it inserted the record, it inserted with the authorization_status as 'Approved'. So when the requisition import ran it created the requisition with approved status.
    There is a profile option INV: Minmax Reorder Approval that can control the status of the requisitions created using minmax. I thought there might be a profile option to control the status of requisitions created using outside processing, but seems like it does not exist.
    Another solution would be to create a trigger on the po_requisitions_interface_all table to set the status to 'Incomplete' for all requsiition lines. Since we have a policy to create requisitions iin ncomplete status by any automated processes it might work.
    Thanks for the ideas and feedback.

  • Resubmit a Requisition in 'Incomplete' Status from back end.

    I have a requirement wherein i need to restart the requisition approval which is in 'Incomplete' Status.
    The issue is that, if something changes to the AME rules when the requisition/requisitions are in flight , it caused the requisition workflow to complete and the status of the requisition goes to 'Incomplete'. I am trying to see if i fixed the AME and can resubmit the requisition/requisitions which were 'Incomplete'  using program from back end.
    Any help or pointer is appreciated.
    Thanks

    My Understanding is :
    PR with IN PROCESS status will convert to incomplete when you alter the AME.
    From Backend, you will again move the PR to original status (in process).
    Pl.confirm the same or rectify .

  • Purchase orders in Incomplete status though they are approved

    Hi,
    We have many purchase orders in Incomplete status though the respective requisitions are approved and once requisitions are approved PO's are auto created with suppliers having approved CPA
    Any help?
    Regards

    Our PO's are autocreated upon approval of requisitions.
    Errors were noticed in the POAPPRV workflow at the Activity = "Document Failed Correctness Check"
    Charge account is invalid
    Cause: The charge account that you entered is invalid.
    Action: Enter a valid charge account.
    on distribution 1 of shipment 1 of line 1
    Accrual account is invalid
    Cause: The accrual account that you entered or that was derived is invalid.
    Action: Enter a valid accrual account.
    on distribution 1 of shipment 1 of line 1
    Variance account is invalid
    Cause: The variance account that you entered or that was derived is invalid.
    Action: Enter a valid variance account.
    on distribution 1 of shipment 1 of line 1
    Found a few on metalink however they were for different error. (Buyer inactive and No ship to)
    POAPPRV Workflow Ending With Document Failed Correctness Check - Buyer is Inactive [ID 1476878.1]
    POAPPRV: Autocreated PO Fails Approval Correctness Check With Purchase Document Has No Ship-To Loca[Article ID 1512237.1]

  • How to cancel/close PO in "Incomplete" status

    In oracle purchasing,can i cancel/close/disable a PO which is now in Incomplete status? and how? The PO cannot be deleted due to audit purpose. Also, the po must be cancelled to free the requisition.
    Generally, approved pos are elligible for cancellation. Pls suggest what and how to do.

    Hi Manasi,
    There is alternate way to cancel the incomplete PO.
    You will not have the control option to cancel the PO if it is in incomplete status. You need to delete the PO only since the document is in preliminary level.
    Audit trial will track this number. Still if you want to cancel this PO in an incomplete stage then submit for approval and get it rejected from the first level approver
    itself and then you can cancel this PO.
    HTH
    Sanjay

  • Receiving Internal Requisition

    Hi,
    I am trying to receive the Internal Requisitions through the Receiving Open Interface (RCV_HEADERS_INTERFACE, RCV_TRANSACTIONS_INTERFACE and run Receiving Transaction Processor) and i could successfully receive the items into the receiving org inventory. But if its a serial controlled item, serial status still shows as 1 (Defined but not received) even after it got successfully received in to the inventory.
    Any helps on this please. I am on 11.5.10.2.
    Thanks,
    Genoo

    I would suggest you log a SR.
    Thanks,
    Hussein

  • Can't receive internal requisitions

    Hello,
    I have an issue receiving an internal requisition into a organization....i'll try to explain it with the next example....
    I have 3 organizations...A,B and C
    A, creates a internal requisition to B, but inside the internal requisition, it says to send the delivery to C....
    So the requisition is imported to OM and B processes the information updating the status line to 'INTERFACED'.....
    So when i log in to C and I try find the delivery number in the C organization it says there are no records that match your search criteria....
    my question here is....is it possible to do this? that company A creates a requisition to C????
    I would appreciate your help....

    i think its misuderstood...let me explain again pls....
    Organization A creates an internal requisition to B, so B import this requisition and creates the Order Sale....the information is processed but B is not going to send the # delivery to A to make the receipt, the # delivery is sent to a third organization, in this case letter C....
    So, when we sign in the C organization to make the reception, we got the message i mentioned......
    Is this possible??
    If it is, do you know what should i do to make the receipt in organization C....

  • ENCUMBRANCE ENTRIES FOR REQUISITION WITH PARTIAL RESERVE STATUS?

    Hi,
    On 11.5.10.2 in Production:
    When a Purchase Requisition (PR) is created with 2 distributions with 2
    different budget a/c and one account having sufficient funds and other one
    not having funds,
    Now reserved he PR which was showing the Budgetary control exception -
    Line 1 Distribution 1 fails funds check
    Line 1 Distribution 2 passes funds check
    In this case will that document is eligible to forward to the next manager for approval or will the document remains in “Incomplete” status.
    If that document is forward to the next manager for approval what was the reason behind that…?
    Please let me know..
    Regards,
    Kv.
    Edited by: Peter.Kv on Oct 25, 2009 9:34 PM

    Hi all,
    the problem was that the relation between plant and product was somehow mixed up. We created it new and now we can process the mesasges.
    But i have one more questions, which Monitoring Transactions i have for SRM (Abap/Portal)? When I was in Debug Mode i saw error Messages like:
    A     /SAPSRM/CH_SOA_MSG     84     Purchasing group for follow-on document missing
    A     BBP_PD     245     Purchasing group for follow-on document missing
    A     BBP_PD     246     Purchasing organization for follow-on document missing
    A     BBP_PD     249     Document type for determined backend system missing
    E     BBP_PC     13     No default value is defined
    E     BBP_PC     22     No tax data maintained
    E     BBP_PD     276     Back-end data could not be read
    E     BBP_PD     358     Select a location that is assigned to the plant chosen
    E     BBP_TAX     1     Tax code could not be determined
    E     BBP_TAX     13     Not possible to calculate tax
    But i only saw that in the monitoring? These Errors can happy every time and i need to see them.... can you please tell me, where i can have a look?

  • Can we combine Query for cancelled requisitions and query for internal requisitions without internal sales order into a single query

    Hi All,
    Greetings.
    I have two queries namely,
    1.Query for cancelled requisitions and
    2.Query for Internal Requisitions without Internal Sales Orders.
    I was on a task to combine those two queries..
    Can we do that? if so, please help me do that..
    Thanks in Advance,
    Bhaskar.

    Hi All,
    Greetings.
    I have two queries namely,
    1.Query for cancelled requisitions and
    2.Query for Internal Requisitions without Internal Sales Orders.
    I was on a task to combine those two queries..
    Can we do that? if so, please help me do that..
    Thanks in Advance,
    Bhaskar.

  • Creation of internal requisition in a B2B cycle

    Hi,
    I want to create an internal requisition in Purchasing instead of purchase order* in a B2B cycle.
    Can somebody share the setup details for this, or any workaround to do this ??
    If this thread is already available, Pls send me the link.
    Thanks in advance for spending your valuable time in read my thread.
    Rdx,
    J kannan
    Edited by: J Kannan on Mar 29, 2009 7:31 PM

    Hi,
    In the normal case, we will create Approved supplier list, Sourcing rule and assignment set with a BPA to create a BPR for every B2B sales order, that was created.
    In my case i want to create/auto generate an internal requisition instead of creating a BPR in the B2B cycle ( whch i mensioned above ).
    I need the setups/prerequisites to get the internal requisition when i raise a B2B sales order.
    Hope, you understood my requirement.
    Thanks,
    Rdx,
    J kannan

  • How to create a new sales order to internal requisition?

    Hi, All
    Need help!!!
    How to create a new sales order to internal requisition?
    The internal requisition has generated order sales but this has already been canceled, so I need to create a new sales order to the same internal requisition.
    How to release the internal requisition to re-create new sales order and after import in OM?
    please help me
    Thanks and regards
    Manuel,

    You cannot.
    Once a ISO is generated for an IR, the transferred_to_oe flag is set on that req.
    If the ISO was canceled, you should cancel the IR and create a new one.
    Hope this helps,
    Sandeep Gandhi

  • Automatic Creation Of Internal Requisition

    Hi
    I have a query related to creating of IR from Sales Order Line.
    Does Release 12 support automatic Creation Of Internal Requisition from Sales Order Line. If yes, does it work for both Models and Parts? Do we need sourcing rule to make IR ?
    Pls. share your views.
    Thanks,
    Rajeev

    Thanks Sandeep,
    I am looking for creating Internal Requisition from Sales Order Line , In 11.5.10.2 we cannot create IR automatically but can create Purchase Requisition(PR) in case of Back to Back Order. If we want to source the item internally from any other org then IR has to be created manually. Pls. let me know if I can create IR from SO Line and prerequisite setups.
    My understanding says that in order to create IR automatically we need to have sourcing rule , MAKE / BUY attribute as BUY for the item in the destination org , do we have to make Source Type as INVENTORY under General Planning Tab of Item Master to trigger IR for the item from SO Line < We are not using MRP / ASCP in our case>
    Please clarify.
    Regards,
    Rajeev
    +91 98868 32466

  • Payable Invoice has not created for internal requisition. ( R12.1.3)

    HI,
    This is an issue where i am facing for which the invoice has not created for the internal requisition, whereas the Receivables Transaction has created automatically for the same internal SO.
    Is there any way to find out the invoice, because i have again ran the Report "Create Inetrcompany AP invoice" and when i mchecked in the log it says 0 fetched invoice....
    Kindly help me out to solve this issue,
    Thanks in advance.
    Vijay

    Hi Vijay,
    Did you check in AP_INVOICES_INTERFACE table if there are some records with INVOICE_NUM like '%AR invoice number%'?
    If no records in the interface table - can you please, check by submitting the program without giving any input parameters?
    Regards,
    G V Ranjith

  • Drag and Drop Interaction - Incomplete status

    Hi
    I am in the process of testing out C8 to see if there are improvements from C7 regarding issues I had. I was impressed with the introduction of the D&D interaction but I had one concern with it and that was the captions that were available. I am able to have a success and failure caption like any other question but unfortunately I could not see anything for an incomplete status. When the user clicks submit I would like a message to appear to inform them that they must complete the question just like any other question.
    Does anyone have advice on how to do this?
    Thanks

    I suppose it is a validated D&D since you are talking about a question. If not everything is done, it is clearly a Failure, which means that you can use the Failure event to trigger a conditional advanced action that checks if all drag actions have been done that were expected. For that reason you'll have to track the drag actions, maybe by using the Object actions and a counter...
    Drag&Drop tips - Captivate blog

  • Internal Requisition Line not appears in receipts form

    Hi,
    I have created an internal req. with 3 lines. After that the internal requisition was approved. Then one of the lines was cancelled (line 1). After that the ohter 2 lines (line 2 and 3) where received in Receipts form.
    As I want to receive also Line 1, I have changed by data fix the CANCEL_FLAG from 'Y' to 'N'. So the problem is that when I go to receipts form, this line (line 1) did no appears.
    What happend? Should i have to run a process?
    Thanks,
    Facudno.

    Yes. I update the database table! Is there any other field that I nedd to update by database?

Maybe you are looking for