Is there option to assign Production Version in MD62

Hi,
Can any one please help.
I have a HALB Material with 3 Production Versions (with the same Lot Size and Validity Dates)
While creating Planned Indipenmdent requirement (PIR). how can i specify what Production version to be used here and as well for MRP run.
Can any one please guide me.
Thanks and Regards
Khadeer

Hi,
Goto MD62
Execute the report
Goto Schedule line tab page
Fallow the menu path
Setting Production version
Enter the Production version required
Save
Check the PV where it is in green colour it should be active with valide date.
Regards,
R.Brahmankar
Edited by: R Brahmankar on Aug 2, 2008 4:34 PM

Similar Messages

  • How to add production Version  field in COOIS to selection options?

    Dear Experts,
    Need your suggestion for below issue raised by client.
    1) As per client, he was running COOIS with the selection option of a production version. But currently he is  not able to see this selection while executing a COOIS t-code.-----> Kindly guide me on its possibilities & necesary checks.
    2) If I want to correct it & want to add Production Version field in COOIS report what steps I should take?
    Need all your valuable guidence to resolve above issue.
    Thanks & Regards,
    Mehul

    Hello Vivek,
    Really thanks for your mail. Please see below comments-
    1) I checked the transaction COOIS & also told user to select Production Version after executing the report by giving Plant code & dates. But user asking for this field before execution.
    As per your suggestion I checked in Header level of first screen but its not showing me also.
    2)  I am using ECC6.0 version
    3) One finding from my side- This is I am checking only selecting Production Orders. But when I am selecting only Planned order then Production version can be seen in first screen under Repetitive Mfg. section.
    so kindly tell me why this not showing when Production order selected?
    Thanks in Advance for your help.
    Regards,
    Mehul

  • How to select the production versions for MTO?

    Hi PP Experts,
    In our scenario we have two production versions and also we are in MTO strategy. While creating the sales order is there any option to select the production version (i.e.) before planning for that corresponding sales order I have to choose the production versions.
    Example:
    Material u2013 A  -
    sale order u2013 666001 u2013Prod version - 0001
    Material u2013 A --- sale order u2013 666002 u2013 prod version - 0002
    How to map the above scenario?
    Thanks in advance.
    Regards,
    Vimal

    In our scenario we have two production versions and also we are in MTO strategy. While creating the sales order is there any option to select the production version (i.e.) before planning for that corresponding sales order I have to choose the production versions.
    If the Production version selection is based on Lot size means No problem.
    If both the Production version is same lot size, system will select the first PV only in MRP
    In STD SAP, we can't Give Production Version  in sale order level,
    If you want after MRP run , U can assign Production version in plan order or in production order Manually

  • Cannot select Product Version. Its greyed out ???

    Hi All,
           I have configured maitenance ooptimizer in sol man 4.0. but when i tried clicking the "Maintenance Optimizer" button under the "Change Management" -> "Support Package Stacks", I see every selection greyed out. I am not able to select any option (i.e Product Version, Priority, Short Text, and even the Back and Continue buttons are also greyed out).
        I have "SAP_MAINT_OPT_ADMIN" role under which the authorization objects CRM_ORD_PR and D_SOL_VSBL exist.
        I feel still there's some sort of authorization missing but not sure whats that.
       Can someone please reply to help me with this...
      Thanks
      Sourav

    Can I get some suggestions to the above question please.....

  • Production Version in Material Master

    Hi,
    I am having problems with this.
    I need to either change date on a production version or
    delete the product version.
    I have tried using a batch input sequence from my program both for changing the date
    and for deleting the production version and this all works well.
    Now this isn't good enough since there can be multiple production versions on a material
    and I don't know which line to change or delete in the batch run.
    Is there a good FM or BAPI to handle this?
    I don't want to change the MKAL table directly since there is a history table
    connected to this also (MKAL_AEND).
    What is the best approach?
    Rgds,
    /Fredrik.

    How can I use this to achieve what I want to do, either
    change the production version date or delete the production version?
    I have tried C223, but this is not good enough, nor is batch run in MM02.
    I can have multiple production versions and can not pick the correct line
    in batch run to change or delete.

  • Can we get Multiple production versions in APO

    Hi,
    Is there  a way to get multiple production versions into APO, as the info record( we are using) is what drive the creation of the PDS in APO from ECC
    Is there a way to find out how we can have multiple production versions in APO.
    Thanks
    Maddy

    Maddy,
    Standard functionality in APO is to support multiple production versions.
    Production Versions are a standard object in ECC.  They consist of a combination of a Bill of Materials, a Routing, and a few other bits of data.  For a given material/plant combination in ECC, there can be many Production Versions.
    Production Version - Repetitive Manufacturing (PP-REM) - SAP Library
    These Production Versions are integrated in standard CIF via either Production Process Model or Production Data Structure.
    Integration of Production Process Models - Integration of Master Data - SAP Library
    Integration of Production Data Structures Generated from R/3 Mas - Integration of Master Data - SAP Library
    Best Regards,
    DB49

  • There is already a transaction for the systems of this product version(MOPZ)

    Hello All,
    I am trying to configure maintenance optimizer in Solution Manager 7.0
    on Windows 2003 server and SQL 2005 server.
    I am configuring this for SAP CRM 2007 server.
    Created the server, database and system in SMSY
    Created Logical Component in TA code SMSY
    SM59 connection for SAP-OSS is OK.
    S-User is assigned to a User.
    Created a solution using TA code solution_manager.
    Defined the product version for the solution created in the TA code
    solution_manager.
    When creating a Maintenance Optimizer transaction, I select the
    product version and its logical component in the Plan Maintenance
    (Phase) and click on Continue to go to Select Files Phase, I get below
    warning:
    Information Procedure 8000000130 Saved
    Warning: Status was reset by system
    Warning: There is already a transaction for the systems of this
    product version
    I cannot get pass this phase.
    I have deleted and recreated the solution, carried out the same
    activity again but its giving the same Warning
    Warning: Status was reset by system
    Warning: There is already a transaction for the systems of this
    product version
    Any help will be appreciated???
    Regards,
    Satish.

    Hello Ragu,
    Thanks for your response.
    As of now, we do not have ChaRM in place. Secondly, we use a single customer number.
    I would like to let you know that in our landscape we have two CRM server, one ECC sever, one SOLMAN7.0 server.
    I tried to configure MOPZ for CRM, ECC, SOLMAN server to download the respective STACKS.
    I was successful in configuring CRM and SOLMAN.
    But  when I tried to configure in ECC, it failed due to RFC erros.
    So I deleted the transaction for the ECC system and deleted the system itself in Solution Manager.
    Reconfigured the Systems in "SMSY", RFC connections are correctly defined to configure MOPZ between SOLMAN7.0 and ECC6.0.
    When I start configuring the MOPZ, I cannot get pass the first phase and this is when I get an error: There is already a transaction for the systems of this product version.
    Please let me know if you need further information.
    Regards,
    Satish.

  • "Only assign one SAP NetWeaver product version to product system"

    Greetings,
    Somehow, after upgrading my PI system from NW 7.11 to NW 7.4, the SAP-XICONS component was left at the lower version. Everything else was upgraded and SUM didn't complain about this component. The component was present in the stack.xml file and the SCA was available. Yet somehow it was missed.
    Now I am unable to use SUM to update the component. There seems to be no way to get the LMDB to reflect the actual versions of this system and have Maintenance Optimizer function.
    After I assigned everything in the LMDB, the Verification Check says "Only assign one SAP NetWeaver product version to product system". And then MOPZ gives errors such as: "Wrong Netweaver product version found SAP NETWEAVER 7.4" and "Multiple Netweaver Product Version were found".
    However, if I remove the assignment of 7.11, MOPZ is still unable to calculate the queue. It even gives the same errors.
    How can I fix this? Is there some other way to generate the stack or get SUM to upgrade the component?

    The root cause was MOPZ marking the component incorrectly in the stack XML.
    The resolution was to use telnet to 5xx08 to manually deploy the SAP-XICONS archive.

  • Which SAP Product version to assign to a Logical Component in SMSY (SOLMAN)

    Dear SAP Colleagues,
    In our SAP environment, we do have 2 versions of ERP systems :
    1. CON - SIF - CDP systems are 'SAP ERP Central Component 5.0' product version.
    2. CDD - CDT - CDP systems are 'SAP ECC 6.0' product version.
    Question :
    When I want to assign these systems to a Z_LOGICAL_COMPONENTS, which product version do I have to choose ?
    Example for CON - SIF - CDP systems :
    1. They are 'SAP ERP Central Component 5.0' product version.
    2. In SMSY in our SOLMAN system, logical component are created using
        'SAP ECC 5.0' product version.
    Example for CDD - CDT - CDP systems :
    1. They are 'SAP ECC 6.0' product version.
    2. In SMSY in our SOLMAN system, logical component are created using
       'SAP ECC 6.0' product version.
    Question :
    What about 'SAP ERP 2004' and 'SAP ERP 6.0' product version ?
    In which case must I use this product version to assign CON-SIF-CPS
    or CDD-CDT-CDP to new Logical components ?
    Are they OSS Note or any matrix which give me the right product version to choose ?
    I have heard that 'SAP ECC x.x' product version should not used any longer ?
    Thanks
    Best regards
    P.C

    Hi,
    Read the following document, the mapping for systems and component versions is described in here:
    https://websmp202.sap-ag.de/~sapdownload/011000358700000074392009E/SP18_SolMan_Setup_Guide_V2.pdf
    For ECC 6.0 you should select ERP 6.0
    regards,
    Jaap

  • Is there a fade-out option in the new version of garageband? if so then how do you use it?

    is there a fade-out option in the newest version of garageband? if so then how do you use it?

    You are correct, although I didn't realize it was an add-on since it came in the standard download. Either way, the status shows "SmartPrintButton 1.0 (disabled)" with a warning sign that says "SmartPrintButton is incompatible with Firefox 28.0"
    Is this a recommended replacement for this Add-on? Or is the easiest fix for this issue to go back to an older version of Firefox?

  • I just dowload and pay the new LR6. I already have the LR 5.7 on my PC with OS 8.1 64bits - when I try to enter the serial number Adobe informs me that there are no eligible product available - the list doesn't include the LR6 version ?

    I already have the LR 5.7 on my PC with OS 8.1 64bits - when I try to enter the serial number Adobe informs me that there are no eligible product available - the list doesn't include the LR6 version ?

    thank you very much!
    everything's allright
    bye

  • Costing variant and production version

    We have two costing variants "C" (used to create current cost estimates) and "F" (Used to create Future cost estimate). All of the production versions in the system have a validity date of 9999. Is there a way to tell the system to use one production version when costing using Variant C and another version when costing is done using variant F.
    Or if that is not possibel than how do we use one production version in 2011 while recosting current standards and another production version in 2012. (Remember the production version that we are using currently in 2011 has a validity date of 9999)
    Regards

    Hi
    In your Costing Variant - You have a tab callled "Qty Structure Control".... Here you can specify BOM Determination and Routing Selection id.... i.e. If the BOM / Routing attached to the prod version can be assigned a specific BOM Determination Class and Routing Selection id, it can work
    OR ELSE
    While doing CK11N, you can manually specify the Prod Version in the "Qty Struct" Tab..... Create an LSMW for CK11N and you can do a mass costing like CK40N.... CK40N does not have this option of specifying Prod Version
    I would prefer 2nd option
    Br, Ajay M

  • Selecting New Production version while Splitting a Production Order

    Hi SAP Gurus,
    Is there any option of selecting a New Production Version for a split Production Order?
    I have a production Order with three operations 10.20 and 30. This production Order is curently using the Production Version 001. Now , i have split the production order at Operation 30 and want to select new production Version 002 for the same.
    Can you please let me know if this is possible?

    Hi Sandeep,
       If you don't mind can you please let me know for what purpose you want to assign a new production version to production order after splitting at operation 30?
       To quickly recap, Production version is used if you have alternative BOM or alternative routings for a material. Based on Production Version that you have assigned in Material Master - MRP screen, your Routing and BOM details are selected.
        So how is this Production Version 002 different from Production Version 001 - is it in terms of routing or bom?
      With Best Regards,
    Srinivas

  • Product version not found

    Hi Experts,
    I am create Integration scenario while assigning the Product version i was face Product version not found error.
    I choose the different product version it is working. If you know solution please help me.
    Thanks & Regards,
    Veera.

    Hi ,
    Please check in the SLD once for the product version which you are trying to use.There might be the case that it had been deleted by someone.
    access  SLD from XI and check  if someone has deleted your software component from SLD
    Do a sld cache refresh. check for locks Integration Buileder -> administration->admin of locks and caches.
    Last  option restart the XI service and see if it starts working
    Regards,
    srinivas

  • How to create production version for multiple BOM & Routing ?

    If I have 3 BOMs ( A, B & C ) and 2 Routing ( 1 & 2 ) for material XYZ then how then production version will be created ? I feel that there will be 6 PVs.
    combination of A1, A2, B1, B2, C1 & C2. but some one told me that  I have to create duplicate routing of 1 & 2
    with number 3 & 4 and use it for bom B, and another duplicate Routing with number 5&6 and use it for BOM C.
    in this case my PV data will be like this A1, A2, B3, B4, C5, C6.
    Please guide me which way is correct. I feel that the first way is right, because in that case I have 2 routing in system, and in second way I have total 6 routings for that product. please guide me.

    Hi Archana
      If you are doing component allocation with routing ,
    routing for material 1  counter 1 you are choosing alternate Bom  1 or 2 for material.
    similarly for Material 1 counter 2 you are choosing alternate Bom 1 0r 2 according to your choice
    like this   3 routing groups will get created with each have 2 counters
    if you allocate similar kind of material in one group in material allocation tab & you are going for component allocation it will assign one material bom.
    second material bom will not get assigned to the operation.
    if you are not going assign the component at the routing level than you can follow first process.
    if you are planning to allocate components at routing level than you have to follow second process.
    If have any more doubt kindly revert back with your query.
    Thanks & Regards
    Sandeep Kumar Praharaj

Maybe you are looking for

  • The name of File when Saving New Keynote has "~" attached at the end

    When I do a save file in Keynote, the name of file has "~" attached at the end. It creates a new file so now I have two files which look like this: StolbaCh22.key StolbaCh22~.key Why is this happening? What am I doing wrong - can I delete either one

  • OSX 5.7 update display problems

    I have never had problems with updates before. With 10.5.7 I have an external display running with my macbook, (which was connected during the install), but since installing the update, I cannot correct the display. Now my macbook display has turned

  • Which 2nd hdd adaptor does T40 support?

    After looking through the Lenove support site and here, I found there are three ultrabay adapters for a 2nd HDD, 41U3148, 62p4554 and 40Y8725 62p4554 seems to be the officially recommended part for T40 series, and support IDE HDs, however now it's ea

  • Can we assign one Conc,Manager to any one instance of a RAC DB

    Hi All. Can we assign one concurrent request which is submitted by a particular Conc,Manager to any one instance of a RAC DB Thanks

  • Execute a Process when removing OIM Group ( Role )

    Hi All, I have a Provisioning Process for a resource object ( RO ). I have definied a Access Policy and attached it to OIM Group G1 and Resource Object RO. That means, when the OIM Group G1 is assingned to user U1 through "Group Membership" option, t