M61X0002

I'm using M61X0002 to have additional columns in MD04. How can I default them to be displayed every time I call MD04.
Now I always have to activate them by pushing the three buttons (for three columns)
TIA,
Edited by: Bernard Barth on Jan 27, 2010 9:34 PM
Now: I got an answer:
SAP has provided the related BAdI MD_ADD_COL_EZPS which enables that these columns are shown or hidden dynamically and controlled by the program or users instead of using the standard user exit M61X0002.
Edited by: Bernard Barth on Feb 26, 2010 9:36 AM

Hi,
The purpose of the User Exit M61X0002 is to program additional information in your own columns for the display of the MRP list (MD05) and the stock/requirements list (MD04).
Also check this below link:
http://forums.sdn.sap.com/thread.jspa?threadID=1903926
Regards,
Alok Tiwari

Similar Messages

  • Creation of Purchase Requisition with MRP - MD02

    Hello,
    I have created a sales order using one material with MRP. When I run MRP-transaction MD02 for this material, a purchase requisition is created.
    What we want is to block the creation of the purchase requisition when the sales order has delivery block (code 02). I have been trying to use this enhancements; setting break-points in all function modules, but when running MD02 is does not stop there:
    MEREQ001      Customers' Own Data in Purchase Requisi
    LMDR2001      User exits restr. profiles of opt. pur.ord.-based load bldg
    LMDZU001      User exits in additional planning                         
    M61X0001      User exits PP-MRP materials planning                      
    M61X0002      User Exits PP-MRP Material Requirements Planning Evaluation
    Do you know a way to do this or also change data in the purchase requisition created with MD02?
    Thanks and regards.

    Dear ,
    Are you very particualr to process the Sales Order demand when there is a delivery block ?
    To restrict that  one you can do the following steps :
    1.Goto Sales Order -VA02-Select the line item -Double Click -Select the Schedule line  tab -Set Sechedule line item categoery as CN instead of CP.If it is CP then it will processed through MRP
    2.Change the pricining date and make credit block for sales Order and do not release though VKM3 so it will not be tearted through MRP run  to have PR geneartion
    Hope this is clear
    regards
    JH

  • Add new field into result of the transaction MD4C

    i want more information into the result of MD4C
    example:
    delivery date of the purchase order and confirmation date of the purchase order and field USR06 of PRPS table and other field like
    moving average price VERPR of the table MBEW and other information from SAP table related to purchase order or WBS elements or Order
    thanks a lot for reply
    best regards
    Patrice

    User exits and BAdI's for MD4C
    Enhancement/ Business Add-in            Description
    Enhancement
    CO610001               User exits: Assembly processing
    M61X0001               User exits PP-MRP materials planning
    M61X0002               User Exits PP-MRP Material Requirements Planning Evaluations
    Business Add-in
    MD_MRP_RUN_PARALLEL         Add-Ins for parallel planning run of requirements planning
    MD_PIR_FLEX_CONS            BAdI for flexible planned ind. req. consumption/reduction
    MD_PLANNING_RESULT          BADI for Issuing Planning Result
    MD_PLANNING_SCENARIO          BAdI for Maintenance of Add. Parameters in Planning Scenario
    MD_PLDORD_BOMEX_CIF         BAdI: Deactivation of BOM Forced Explosion in CIF
    MD_PLDORD_CHANGE            BAdI for Changing Planned Orders
    MD_PLDORD_POST              BAdI: Update of Planned Orders
    MD_PLDORD_SCHEDULING          BAdI: Schedule Planned Orders
    MD_PLDORD_TIME_STAMP          BADI for publishing time stamp problems
    MD_PURREQ_CHANGE            BADI for changing purchase requisitions
    MD_PURREQ_POST              BADI for updating purchase requisitions
    MD_PURREQ_REL_STRAT         BAdI for Deactivating Release Strategy for MRP Purch. Reqs
    MD_STOCK_TRANSFER           BADI: Change the Requirement Date During Stock Transfer
    MD_SUBCONT_LOGIC            BADI: Determine Subcontracting Logic
    MD_ADD_COL_EZPS             BAdI: Extra Columns for Evaluation PP-MRP Reqmnts Planning
    MD_ADD_COL_OVERVIEW         BAdI: Display of Additional Columns in the Material Overview
    MD_ADD_ELEMENTS             BAdI for Adding Additional Requirements/Receipts
    MD_ALTERN_EXPLOSION         BAdI for Alternative Explosion of Planned Orders (IPPE)
    MD_CHANGE_CALENDAR          BAdI: Change Calendar for Range of Coverage Calculation
    MD_CHANGE_MRP_DATA          BAdI: Change Data when Importing MDPSX
    MD_DISPLAY_ELEMENT          BAdI for Changing Display of MRP Elements
    MD_EXT_SUP                  BAdI for Determining the Issuing Storage Location
    MD_INTERACT_PLANNING          BAdI for Deactivating Changeability of MRP Elements
    MD_LAST_LOT_EXACT           BAdI for Calculating Last Lot Exactly in Individual Segment
    MD_MODIFY_PRODVERS          BAdI for Modifying Production Version
    MD_MODIFY_SOURCE            BAdI for Modifying Source Determination in MRP
    MD_MRP_LIST          BADI for further processing of MRP list
    MD_MRP_PARAMETERS           BAdI: Change Planning Parameters

  • View of rescheduling date in MD04

    Hallo,
    I would like to know whether there is a way to change the SAP standard view in the MD04 for rescheduling dates. The requirement is to see the date of the arrival of goods ignoring the goods receipt processing time.
    Currently I see in the column 'Rescheduling date' the calculated date for replenishment time + goods receipt processing time. Only if I click on exception message 015 I can see the actual arrival date.
    I would like to change that the other way round.
    Is there a way to do it?
    Thanks in advance for your help.
    Katrin

    There is no place to add the specfic fields in the evaluation list. The only options are user-exits.
    Solution 1:
    Please use customer exit M61X0002 to program company-specific additional information in your own columns for the display of the MRP list and the stock/requirements list.
    You can define that additional data fills each of up to three columns in the display of the individual lines and the period totals. The user uses pushbuttons to access this additional data in the lists.
    Solution 2:
    Function module LM61XU11 MD_STOCK_REQUIREMENTS_LIST_API includes the basic functions for setting up the MRP list and the stock/requirements list. Use this function module to program lists, which are exactly tailored to the requirements of your company.

  • Reg. User Exit for MD04 & MD05

    Hi All,
             The requirement is to put an Indicator 'R' in the <b>ROPInfo column</b> of transactions <b>MD04 & MD05</b> based on some criteria. Kindly guide is there any user exit using which I can update this ROPInfo Column? If not thru, user exit, is there any other way of doing the same?
    Thanks & Regards,
    Kiruhtika.M

    Hi
    New buttons to MD04/MD05 can be added in enhancement M61X0002 - User Exits PP-MRP Material Requirements Planning Evaluations, user-exit EXIT_SAPMM61R_001
    <b>Reward points</b>
    Regards

  • Analysis of rescheduling date

    Hi Experts,
    I am a buyer. i am facing problem in rescheduling cases.
    I want to analyze in mass the MRP dates and the reschedule dates with the exception messages.
    I tried Md06 but it does not give the comparison between the MRP dates and reschedule date.
    I wnat report in the following format:
    Material     Plant     Exception message         MRP date     Rescheduled date.
    Thanks,
    Sachin

    There is no place to add the specfic fields in the evaluation list. The only options are user-exits.
    Solution 1:
    Please use customer exit M61X0002 to program company-specific additional information in your own columns for the display of the MRP list and the stock/requirements list.
    You can define that additional data fills each of up to three columns in the display of the individual lines and the period totals. The user uses pushbuttons to access this additional data in the lists.
    Solution 2:
    Function module LM61XU11 MD_STOCK_REQUIREMENTS_LIST_API includes the basic functions for setting up the MRP list and the stock/requirements list. Use this function module to program lists, which are exactly tailored to the requirements of your company.

  • Screen exit for MD04

    Hi
    Anyone has implemented screen exit in MD04 then pls pass the exit name.
    Regards
    Shivram

    HI sen
    u can try for this
    ZXM61U03
    user exit M61X0002 (for transaction  MD04 )
    User Exit M61X0002 for the stock/requirements list (Transaction MD04) or the MRP list (Transaction MD05) has been activated.

  • How to get the rescheduling date in MD04?

    I need to create a report for buyers to show them the shortage of material. It will help them to determine how to reschedule the delivery of purchase orders. So, I need show the rescheduling date in MD04 on this report as the suggestion from MRP.
    So, would you please help to let me known how and where I can get the rescheduling date (MDEZ-UMDAT) displayed in stock/req list?
    Thanks a lot!

    Hi,
    With the User Exits it may be possible, check the feasibility..
    =============================================
    Programming of additional columns (Customer Exit)
    You can use Customer Exit M61X0002 to program up to three columns for the individual line display and the period totals. These columnscan be filled with additional data, which you can call in the lists using pushbuttons.
    Programming of customer-specific access to the lists (reports)
    By using reports RMMD07EX and RMMD07DB, you can program your own access to the collective display of the stock/requirements list.
    =============================================
    Regards,
    R.Brahmankar

  • Customizing MD04

    Hello,
    I would like to customize some new column in MD04 view.
    Does somebody can explain to me how to do that ?
    Thanks

    Hi,
    Goto:
    SPRO --> Production --> Material Requirements Planning --> Evaluation --> Configure MRP List / Stock/Requirements List.
    Read the documntation..
    =============================================================================
    Programming of additional columns (Customer Exit)
    You can use Customer Exit M61X0002 to program up to three columns for the individual line display and the period totals. These columns can be filled with additional data, which you can call in the lists using pushbuttons.
    =============================================================================
    Hope this helps..
    Regards,
    Siva

  • Compute formula for forecasting

    Hello,
    I want to compute the formula for reorder point in the system which includes min inventory + safety stock + daily consumption while doing forecasting for a material.
    The automatic reorder point type MRP is set for the material masters & forecasting is done for the same.
    But when the reorder point is computed through system , it does not match with the manually computed reorder point.
    Can anyone tell me any method to incorporate this manual formula into the system?
    Regards,
    Krutika

    Use this user exits, to deviate from Standard Formula.
    M61X0001  User exits PP-MRP materials planning
    M61X0002  User Exits PP-MRP Material Requirements Planning Evaluations
    You may also be required to to look into funtion modules of planning evaluations report. Check out this menu in IMG.
    SPRO > MM > Consumption-Based Planning > Evaluation > Reports, Function Modules: Program Customer-Specific Lists
    Thanks & regards
    Hameed Parvez

  • Any bapi avaialble to fetch component planned orders for header planned ord

    Hi Experts,
                     We have a req where we need to fetch component planned orders for  header planned order .
    In Detail :
      In MD4C tcode (select planned orders tab -> F8 ), when i pass the header planned order like 17474 .
      I get two component planned orders like 16276 16277 and corresponding materials like 12025185 , 12025189.
    We are using   BAPI_PLANNEDORDER_GET_DETAIL  to  fetch  component materials for a planned order .
    similarly any bapi or tables which have this data  to fetch component planned orders.
    Thanks in advance,
    Mani.

    Hope it would be helpful for you:
    Check these user exits.
    CO610001            User exits: Assembly processing                             
    M61X0001            User exits PP-MRP materials planning                        
    M61X0002            User Exits PP-MRP Material Requirements Planning Evaluations
    Thanks

Maybe you are looking for

  • Report export to csv - no data found in report

    Hi all, I've followed the steps to export my report to a csv file. In the Report Attributes, Report Export section I have: Enable CSV output: Yes           Separator: ,           Enclosed By: Link Label: Export Filename: Changes.xls But when I open i

  • "no picture" with streaming video

    Some websites, including Apple, won't give any streaming video (including the new apple ads) I get a black screen with "no video" Strangely enough, IE 5.2 works just fine, as does FireFox. I think this started happening after I updated Safari. Help!

  • Visual Administrator: Logon Failure

    Hi All, when i am trying to open go.bat file  its giving the error message "The system cannot find the path specified.Program terminated abnormally" in tolllanucher. please help me how can i resolve this? Regards Suresh

  • Java --   MS Word --   PDF

    Greetings !! I'm searching for the best way to interact with a Microsoft Word processed document exported in pdf format. The goal is to put some "tags", 'markers' into the Microsoft Word document (just as fields) and replace them in a java applicatio

  • Photoshop cs6 ne cesse de planter!

    Bonjour je viens à vous car j'ai besoin d'aide. Mon photoshop ne cesse de planter, ça tombe souvent lorsque j'enregistre et que je fais une manip' en même temps, mais parfois ça plante sans raison apparente c'est très handicapant. Avez-vous une idée