Material Error in PO and Costing BOM

Hello,
Am having error when am using a certain material in creating production order error is "In-House production is not intended for material 50 status inactive Prod. : DSS only" this same material also encountered error in changing Costing BOM error is "material status Z4 inactive prod.: DSS only does not allow BOM maintenance". what thus this error mean and how could this material be used with this transaction?
Please guide and help me solve this.
Thanks and Regards,
JJ

Hello,
You will find the Material Status in Basic Data 1 View as well as in MRP1 View (apart from other places)..\
For this material, it Seems that the status restricts the Material is Mat. Cost Estimate Procedure as "B"
And Production Order Header also "B" (Error Message).
One thing I would recommend is please check why this status is put?
Whether some one is intentionally put this status for any business reason?
or Blocked this material altogether?
Regards,
Siva

Similar Messages

  • Production consumption variance w.r.t. Costing BOM

    Dear Sir / Madam,
    Our client is using BOM usage 1 as well as BOM usage 6 i.e., Production BOM and Costing BOM.
    Consumption of Raw materials and MRP happens based on the BOM usage 1.
    Costing of FG happens  using BOM usage 6.
    Users want to have a variance report between the actual raw materials consumed v/s the BOM components in the Costing BOM in value as well as quantity basis.
    If the costing BOM says 100 components and the production consumption happens for 110 components then the difference must be highlighted to them in the variance report.
    We have ML activated. Kindly help.

    Hi
    1. Create one more costing variant and valuation variant...
    The Qty Structure Control in this Costing Variant should refer to Costing BOM
    Also, assign this costing variant to Version 1...
    2. Run Cost estimate using this Costing Variant and save it in Planned Price 2 or 3 field
    3. Create Version 0 and Version 1 for target cost calculation (IMG > CO > Prod Csting > Cost Obj Contr > Prod cost  by order > Variance calculation)
    Version 0 will be based on Costing variant which releases Std Cost
    Version 1 will be based on Valuation variant which releases the cost to Planned Price Field
    Br, Ajay M

  • SAP report with sales (invoices) and cost of goods sold

    Is there standard SAP report that would show list of invoices, the materials sold, and the cost of goods sold (for how much they were bought)?

    Dear sapfan22222222
    If it is a one time activity, the please do the following.
    SE11 , put the table VBRK and execute (you may use selection criteria like DATE o BILLING DATE if there is any specific data which you are trying to extract.)
    VBRK-VBELN will give you the list of invoices.
    You can download the same into spreadsheet.
    Now copy the VBELN entries from the spreadsheet and put it in SE11 of VBRP as VBELN.
    VBRP-MATNR will give you the material sold.
    Download the same into 2nd spreadsheet
    your cost of goods sold will be coming in the pricing procedure against any condition type.
    So in VBRK which you have extracted earlier, you will find VBRK-KNUMV
    Put that KNUMV in KONV table (put KSCHL= your condition type which shows the cost of goods sold).
    Download that also as a spreadsheet.
    Now you may combine these 3 spreadsheet with the help of someone who is an expert in excel and get the required data.
    (BILLING NO FROM FIRST EXCEL , MATERIAL FROM 2ND EXCEL AND COST OF GOODS SOLD FROM 3RD EXCEL)
    Check and revert back.
    Thanks & Regards,
    Hegal K Charles

  • Costing - Multiple Production Versions and Recursive BoMs

    Hi All,
    We have a production and product costing scenario as follows:
    Production versions 10, 20 and 30. It takes all three versions to manufacture the finished material and there are no intermediate products in this scenario. 10 and 30 are to be costed and 30 is a recursive BoM with the input from version 10 also being the output. 10 is the main production step with components but 30 is a recursive BoM sometimes only with the output material as the input and sometimes with a more complete BoM but which includes the output material as an input component.
    The quantity input appears to be the same as quantity output for the recursive element.
    If anyone has come across this scenario and you can let me know what design principles you followed I would appreciate it.
    We are getting iteration error messages when costing production version 30 and even reducing the input quantity below 95% of the input as per the SAP documentation does not fix the error message.
    Any help you can give will be greatefully received.
    Thanks.
    Regards,
    Tim

    Murali - Its possible to use multiple PV in sub contracting.
    Settings in ERP :
    1. In CFC9 activate the - Transfer multiple selection of PDS indicator. When you select this indicator, the system allows you to select several productions versions in the integration model; it also creates a Production Process Model (PPM) or Production Data Structure (PDS) for each production version in SAP SCM
    2. Assign the PV's to the subcontracting info record through -  Logistics  - Central Functions  - Supply Chain Planning Interface - Core Interface - Advanced Planner and Optimizer - Environment  - Data Transfer  -Assign Multiple Production Versions
    3. When you select the integration model parameters for PDS, you have selected PP/DS Subcontracting as the PDS Type value. Similarly, for PPM, you have selected Subcontracting PPM as the Type of PPM value.
    Subcontracting with multiple production versions is supported. However, the integration with an SAP ERP system requires at least SAP ERP 2005 with Enhancement Pack 03.
    Rgds
    Valavan

  • Sales BOM : Header item stock and cost

    Hello gurus,
    I'm very new for sales BOM and have one questions.
    We have material A and B (purchased from vendor).
    They will be assembled by 3PL company as C.
    Then we will sell C to the our customer.
    I want to set price/cost at the header item level.
    because we will sell material B free of charge.
    I've set C like below  
    1. Item category group. : ERLA
       Item category : TAQ
       Setting of A and B
        Item category group. : NORM
       Item category : TAE
    2. Then make BOM in tcode CS01 with C
        Material : C
        Plant: XXXX
        BOM Usage :5
        subitem : A, B
        Item category : N(Non-stock item)
    After then I tried to make a sales order
    with material C.
    I can get sub-items(A,B) successfully
    however system said there is no atp stock for C.
    How can I get stock of C from stock of A and B?
    And How can I set the cost of C with value of A+B?
    And How can I set the condition of C to calculate cost of C in header level?
    or can I set like
    price is determined in header level and cost is calculated in item level?
    Or please recommend nicer solution.
    Thank you very much.
    J.K.

    Hi Azam,
    It seems to me that you want to use Delivery Group for Sales BOM where If Mat A = Mat B + Mat C and Mat B Availability date is 20/07/2014 (DD/MM/YYYY) and Mat C availability is 25/07/2014 then Main line item should be confirmed with 25/07/2014.
    If any one sub Item is not available, then Any of the item from the Grouping should not be dispatched.
    If this is the requirement then, In Item Category (VOV7) for main Item update Create Delivery Group field with X and your requirement will be fulfilled.
    Do let us know the result after testing.
    Regards,
    MJ.

  • Material and cost center

    Hi,
    May I know where is material kept?
    As I understand, only when consumption of materail, it is debited to cost center. So before consume, the material is in inventory.
    I would like to know if in inventory, then it is not belong to any cost center? then why in profit center?
    thanks

    Newphama Calesta wrote:
    hi,
    > thanks.
    >
    > 1 Anyway, is it possible that we debit cost center when the material is consumed in the cost center?
    >
    > 2 What about direct labour cost? It is coming from the cost center where the worker is reported. so how can we relate direct labour and cost center?
    >
    >
    > 3
    > Sorry, I do not understand the statement in bold.
    > Need your help to explain a bit.
    >
    > Profit center is a responsibility area within an organisation which is required to show its own return on investment. For this purpose we require a balance sheet as well as profit and loss account for each profit center.
    >
    > thanks
    Hello
    1) Yes it is possible to debit cost center when the material is consumed in the cost center. An example of this is consumables which are consumed against cost centers with movement type 201. This is because these materials are not part of the BOM and pretty in nature.
    2) Whenever wages and salaries are booked the relevant cost centers are debited. Here the wages account is debited (so also cost center) and bank/wages payable account is credited. When we do actual production we charge direct labour to Manufacturing orders as an activity. This is only a CO entry where the cost center is credited and the manufacturing order is debited.
    3) Profit center is a responsibility area means the person who is managing the profit center is not only responsible for the profit but also responsible for the return on investment. Investment means total of current and fixed assets - liabilities. There may be two profit centers say A and B with investments of 1000 USD and 5000 USD. Both make a profit of 200 USD. So when we see the ROI then A is much better then B.
    So to find the total assets which includes stock, we need to maintain them profit center wise. This is the reason why the profit center field is available in material master.
    Hope this clarifies your doubt.
    Sangram

  • Costing BOM and Mixed Costing

    A product which is manufactured in-house has more than one production version.  Each production version has its own BOM and Recipe.  To calculate a blended standard cost, we will use mixed costing functionality and assign ratio to each production version.  However we want to copy the BOM usage 1 (production) to BOM usage 6 (costing) and make changes only for costing purpose.
    Hence each production version will have a BOM for production and equivalent BOM for Costing as follows:
    Production Version/Procurement alternative
    BOM for Production
    BOM for Costing
    1
    Usage 1 / Alternative 1
    Usage 6 / Alternative 1
    2
    Usage 1 / Alternative 2
    Usage 6 / Alternative 2
    If a process order is created with Usage 1 /Alternative 1, how does the system know to compare actual cost with procurement alternative with Usage 6 / Alternative 1 for the purpose of variance calculation?
    Thank you,
    Siva

    Hi
    Welcome to SDN
    You dont have  option to specify the Valuation type in BOM i.e. in the BOM of B, you can only specify A as the Input material... You cant specify C1 or C2
    Hence, as a result, costing uses only the average price of C1 and C2 which is maintained in the Mat Master as a PLanned price
    MIxed Costing as well as Split Valuation for Material B makes no sense in this case....
    If you still want to have Mixed Costing & Splt Valuation in this case - You need to create one more material for Mat A i.e. Separate Mat codes for C1 and C2.. however, it will have its own challenges during MRP as to which material should be ordered, etc
    br, Ajay M

  • Reg. price maintenance in material master and Costing

    Dear Experts
    I have maintained price for material in material master and costing,but when I create PO price didn't come from anywhere. Pls help me.
    Thanks
    Rajakumar.k

    Dear Rajakumar,
    The values that are maintained in the material master in costing view is considered only for costing
    purpose.
    Say while doing the cost estimate for a material using CK40N,a costing variant will be used and say For
    Eg,PPC1,for this a valuation variant will be linked ,as per this valuation variant for costing purpose the
    first priority would have been given to the planned price in the material master in costing 2 view.
    So this value will be considered only for costing purpose.
    For procurement related things you have to maintain a purchase info record for a material + vendor
    combination in ME11 and a source list in ME01.
    In the purchase info record you can maintain a price for buying the material from that vendor.
    I hope this will clear your doubts.
    Check and revert back.
    Regards
    Mangalraj.S

  • How do i fetch workcenter ,cost center and cost elem using plant ,material

    Hi.
    i have plant and material in my sleection screen..
    how do i get corresponding workcenter,cost center and coste elements..
    i need to find total quanity(total hours per cost center) in terms of huors corresponding to each costcenter

    Start with VAPMA and then go to VBAP. You can use the information here to go to BSEG if necessary.
    Rob

  • Pricing and costing in MTO material

    Hi
    In Make to order production material  is it advisiable to maintain pricing condition record (PR00) in VK11.As at the time of creation of a sales order it is difficult to know the the excact requirement of the raw material and other cost.
    And also where to maintain the expected cost and actual cost for the MTO material and where to reconcile the differences. Can anyone tell me deatiled about the Pricing and costing related Issues in MTO.
    Thanks
    Debasish

    Hi,
    please go through this link..it may help u..
    http://help.sap.com/erp2005_ehp_03/helpdata/EN/dd/560126545a11d1a7020000e829fd11/frameset.htm
    regards...
    yogi..

  • Accounting 1 and Costing 1 View in Material Master

    Hi SAP Gurus,
    I noticed that we only have "Accounting" and "Costing" views activated in Material Master in our current SAP environment. I don't see "Accounting 1" and "Costing 1" views available. Could someone tell me how to activate these views?
    Thanks,
    Cassandra

    Check this path out for adding views to material type:
    Spro>Logistics-General>Material master>Basic Settings>Material types>Define attributes of material type, then click execute, then double click on material type you want to edit, here on right side you will see user departments, you need to get Accounting and costing view highlighted and click save
    In MM01, you need to extend the view for accounting 1 and costing 1. Enter your material number and click enter, here when you see views, select accounting 1 and costing 1, maintain data in the said views and save the material, your material will be extended to the said views.
    Edited by: Afshad Irani on Apr 22, 2010 10:56 PM

  • Profit center and cost center master data upload errors

    Hi Sapiens,
    Could you please guide me to resolve the below errors in profit center and cost cost center master data upload through LSMW. i am usinng recording method for upload and  getting below error while uploading the data from txt file.
    1. Valid from and to dates are not converting in DDMMYYYY format, which field type we have to use in field mapping?
    2. some of the fields data are overlapping when uploading the data.
    3. How to create validation for empty cells data.
    thank in advance.
    regards,
    jagadeesh.

    Hi
    when you are using LSMW for uploading PC & CC, simple way to correct the Error's WHILE RECORDING The First record, while Creating LSMW, B very care full while entering the details ,bez wht ever Fields your updating ..the same Fields get updated While LSMW Processed.
    As mentioned above update the vaild from and to date in wht ever format you want While recording, in the same format all the remaining records gets updated.. 
    Hope the suggections will Help you in solving your Issues.
    Thanks
    Goutam
    Edited by: Goutam78 on Apr 29, 2011 8:59 PM

  • Copy Material Codes, Costs, and Cost Code Distribution

    Has any one come up with way to copy material codes with their unit prices and cost code distributions from one project(or template) to another? When a user has a large inventory of material codes, it would be helpful to be able to copy, or import these to a new project.
    Thanks for any help.

    Forgot to mention that CMPlus will copy Materials from one project to another with the unit pricing of the current project HOWEVER, the cost distribution is tied to the contract that the material is associated with. If you are using materials with Daily Reports to track material not related to a contract then this will be all you need. IF you are using Materials in association with line items on a contract/PO then it will populate the selection list but you will need to perform more data entry to properly link to the contract.
    By performing this copy from one project to the other the capability to "Generate" materials from a contract or PO is no longer functional because the Material already exists as far a Contract Manager is concerned
    One more item to think about - materials can only be associated with one contract - that does not mean that a material can not be used on more than one contract.
    I am assuming that since you are asking this question that you have been using materials on your projects and understand the nuances and issues with the way CM handles Materials.

  • No Error Log generated in 'Costing' step in Costing Run (CK40N)

    In the Costing Run, when the 'Costing' step is run (after 'Material selection'  and 'BOM Explosion' steps), it gives a hard stop when it encounters the 1st error, instead of completing the 'Costing ' step and giving an Error Log with material information and nature of errors. This makes it very cumbersome to resolve all the errors.
    In the Costing Variant setting in config, the u2018Save Error Log' indicator has been checked.
    Please let me know if I am missing something.
    Venkat

    Hi Vimal,
    Your proposal does not resolve the issue. I found OSS Note 375901, which addresses this issue - see below
    :In Customizing for the costing variant (Transaction OKKN) in the tab "Misc.", you chose "Messages online" for the Error Management option.
    Solution
    Change the error management for the costing variant to
    "Log and Save Messages..."
    Many thanks for your inputs.
    Venkat

  • Cost Elements and Cost Centers in a service order

    Hello Finance Friends....
    I am inquiring about something that has been happening and I can not find the answer as to how.  I spoke with the finance consultant and he seems to think it is the valuation class being changed but the valuation class has not been changed at all....so here is my problem as I am at a lost...it is an intermittent problem....
    I have a service order for material to be repaired by the customer...lets say coming in for Ansi Calibration with repair.
    The technician will issue material to the service order for repair....if the technician does not end up using the material for repair he will reverse the goods issue and then the material goes back to stock...
    in my scenerio ....when the material is issued it is under GL account (cost elelment) 5XXXXXXX.  When the reversal was done it went to 6XXXXXXXX.  So when the DP90 transaction is done (billing request) it gives the error for cost center XXXX cost elelment 6XXXXXXX and can not complete the transaction DP90. The error is the Material combination for DP90....this works in others....these are just one offs that it is happening to and there seems to be no rhyme or reason to why it happens... I have tried reverse the transaction to put the material back to the service order and then manually reverse myself using the original GL account number it was issued on (5XXXXXX)...however when doing the DP90 it still reads the 6XXXXXXX cost element and cost center XXX.  Keep in mind that the valuation class or material type has not been changed.
    Where is the GL account and Cost center being derived from in the service order?  What can I check?
    Thanks in advance....

    Hi,
    Check in T030 table for OBYC assignments and TKA3A table for OKB9 settings.
    Also check account assignment tab of PO.
    Best Regards,
    Madhu