I was doing Mass change in MM17 for Profit Center value. Old value need to change with new value.
I followed the below process:
1.Go to transation MM17
2.Select Variant name for Mass Change
3.Select MARA/MARC in the tab Tables & Execute
4.Input the materials & plants which under goes changes & Execute.
5.You will get two section of screens.In the top you can see New values with empty field.you can give the new value for Mass change. In the bottom you get the details of existing field for material/plant combination.
6.Click the icon called 'Carry out mass changes'.
7.Save and check the log for any errors.
The value of Profit center was changed & I checked in CDHDR & CDPOS tables.
Can any one of you give me the flow or tell the above process is correct.
Thanks in Advance
kavitha

Dear Kavitha,
The process expained by you very right.
Also for your information, you can also try  the Transaction MASS for the below objects Mass Processing
Objects Include,
BUS0015     Profit center
BUS1001     Materials (industry)
BUS1001001     Materials (retail)
BUS1133     Rental units
BUS2012     Purchase orders
BUS2032     Sales orders
BUS2104     Appropriation reqs
BUS2105     Purchase requisition
BUS3003     Purchasing info recs
BUS3006     G/L accounts
KNA1     Customers
LFA1     Vendors
Njoy SAP
-Saravanaganesh

Similar Messages

  • Mass change mm17

    Hi Experts,
    We are unable to change the commission group in Sales 2 view in material master using the Mass change code MM17.
    please suggest the solution (configuration/ settings) for this.
    Thanks a lot!
    sgskm

    I just did a test in my system and the provision group was updated without any issue thru MM17.
    Maybe you have a posting failure, check in SM13
    try to update any other other field together with the provision group, this way you can at least find out if it is just the provision group that cannot be updated or you are not able to update anything with MM17.
    if it does not work for any field, then search OSS notes, there might be a bug in the programs.
    try to update one record  directly in MM02 and see what happens.
    had you checked the application log despite of having a green light, maybe there is more info for you.

  • Mass change-mm17-marc-mfrgr

    Hi,
    Experts please check the following issue we are experiencing.
    We are trying to change/maintain one field marc-mfrgr through MM17, but the table is not getting updated.
    While we are doing the same through MM02 in purchasing view it is getting updated.
    After running MM17 following information log is comimg without any error message.
    Trying to create: 403897 T001 ____ ____ __________ ____ __ ___ ___
    The material cannot be maintained since no maintainable data transferred
    Trying to change: 403897 T001 ____ ____ __________ ____ __ ___ ___
    No changes made
    Please how the changes can be done through MM17.
    Regards

    Hi
    I feel the Purchasing view of material is not maintained properly for particular plant.
    Request you extend the material to concern plant using MM01 and then try mass changes.
    regards
    prasanna

  • Mass change of account assignment group in sales order

    Dear All.
    We have created a new Account assigement group and assigned revenue accounts to it.When the orders are registered this data will flow from the master data automatically.Where as in the open orders i need to make the changes manually.Is there a provision in std SAP to Mass change a filed in  sales order .Like we do in MM17 or XD99 .Kindly let me know.
    Thanks in advance .
    regards,
    K.Vivek

    Hi,
    Go to XD99,
    1. Select the table ie KNVV in the tables tab, select the fields tab and select the fields u would like to change for eg Acct assignment group
    2. Execute the report
    3. U will come to the screen where u can restrict the entries.
    Enter the criterion say
    Cust: Test 1
    Sales Org 8000
    Dist 08
    Div 08
    4. Again press execute
    5. Enter the new values you would like to have
    6. Now select columns of the new values and press carry out mass maintainence button in the new values area
    7. Press Save
    8. u will then receive a success message
    Best regards
    Mahesh

  • Mass change of material master

    Hi Experts,
    I have a query regarding mass change to be done in material master. I need to update one value in the Material group 4 field in sales org view 2 in MM02 transaction for nearly 300000 materials. One option i find is LSMW and the other i saw is transaction MM17. Please let me know how feasible is this MM17 transaction? Is it possible to upload all the 30000 materials through MM17 transaction in one go and update the field? Will there be any performance issue if MM17 transaction is used?
    Please give your suggestion.
    Thanks
    Dinakar

    Hi,
    Use MM17,
    Goto the Transaction code MM17 and in the table check the MVKE- sales org data for material
    and select the Fields tab and choose the field MVKE-MVGR4 and  execute
    Now enter all the materials in the next screen  for which you want to change  and execute
    In the next screen you can maintain the new values for the old
    Please check and revert
    thanks,
    santosh

  • Mass changes of Material Master field with different values

    Hi,
    How to change a field in Material Master for more than thousand materials. I think MM17 can only be used for mass changes of materials with same values. I need to upload different values for different materials. Is there any other way to do this.
    Thanks,
    K R Vishnu Kumar

    Hi Kumar.
    I think you have to use LSMW for mass updation for Material Master fields with different values.
    Regards,
    Rahul.

  • Create Material Master Views in mass-change

    Dear All,
    We have to add a additional view to the material master of some products.
    Is this possible to do as a mass change (ex. MM17) or have we to do it with transaction SCAT/ MASS?
    Do you know an other solution?
    Thank you.
    Best regards,
    Thomas

    Hi,
    Use
    LSMW using standard SAP provided RMDATIND program- check with ABAPer - You can extend all views or you can pick and choose selected views.
    or
    BDC scripts - If u have only 1/2 views extended use this.
    Mass change doesn't help.
    Hope this helps

  • Material Master Mass Change

    Hi Experts,
    PLease explain me abt the mass change of Material Master.. the detailed steps to be followed for the change
    I know the tcode MM17, please explain the process in that transaction

    You also have tcode MASS for more mass modification.
    Use object type BUS1001 and generate. Then you have to know the tables where the field you want to modify is.
    Pick the fields in their folder and generate again. Then in selection pick the materials or use other selection criteria. Generate again.
    In the upper side of the screen insert the data and click the button 'carry out a mass change'.
    Save and leave.
    Regards

  • MM17 (Mass upload)

    I want to upload the values to one of the fields in material master. I have 70,000 materials. Is this possible through MM17 (Mass upload) ?

    in MM17.
    you select your materials for a change.
    Then you enter the new value in the fields above and click the distribute button, this way all your selected materials will get this value as new value for the chosen field.
    alternative to a fix value in the field above your records you can click the formula button, this way you can create a small formula to calculate the new field value. E.g. you can add 1 to your maximum stock level,  means if you had 10 as maximum stock level then you will get 11, but if you had 1 then you will get 2...
    but this formula button allows you as well to add some ABAP coding.
    this way I can select on any other table and can then determine the new value based on your own  conditions.
    e.g. you lookup EORD table (source list) and if you find an entry there, then you write 111 in field X , if you dont find a source list, then you write 222 in field X.

  • Mass change of MAP

    I want to change moving avg price of say 500 materials, shall I use MM17 or any other option. Can u guide for the procedure using MM17. Also as standard price automatically gets updated in rhe system, shall I change rhe std price also if mat is maintained for moving avg price or it will be automaticaly updated? pls guide

    Hi,
    I dont think, MAP will be changed by MM17.
    You should create a LSMW of MR21 for mass change of MAP
    Regards,
    Amol

  • Mass change - Tcode MASS

    Hi,
    Would like to know if the fields/objects which i wanted to mass change is not found in transaction code MASS, is there any way i can INCLUDE or ADD into MASS?
    Thanks
    regards,
    JL

    hi
    R   U using mass maintenance -MM17,or MM14-for shedulled change
    zafina

  • Material Mass Change

    Hello,
    Can we do mass changes for material master. I need to delete some part of data in Sales text of the material,means i want to delete one text line out of 10 text lines. Is it possible or not.(may possible at mm17/MASS)
    Could you please explain step by step procedure.
    Thanks in advance,
    Govind.

    Hi
           XD99,MASS.,
    Thanks & Regards
    Narayana

  • Mass change in In house Production Time in Material master

    Hello Frinds,
    I am dooing mass change in Inhouse Production time in material master By using MM17
    field is MARC-DZEIT
    i am putting Material ,Plant & in house Production time & after execution it shows following MSG.
    No data meet the selection criteria
    Message no. M&107
    Where i m wrong weather my Varient is not created Properly  ,Pour some light on it ,if i m wrong tell me the way of dooing mass change in ECC6.0 ,LSMW & DBC is next Option ,i want to do it with MM17
    Regards ,
    Girish

    Dear Girish,
    Goto MM17--->click on Fields tab page,select the field MARC-DZEIT and then clcik on execute button.
    In the next screen,either input the material ,plant combination or else input the plant and click on
    execute button.
    Now enter the inhouse production time in the new values say 2 days,Either select the materials for
    which this new change has to be made or else select all the list of materials and click on mass change
    icon and check the results and save the datas.
    Regards
    Mangalraj.S

  • Reg: MASS CHANGE

    Hi
    We have uploaded 250No.of Materials  through BAPI.
    At that time we didn't select the plant.
    Now we would like to extend the material to a plant.At present the materials are not assigned to any particular plant.
    now i would like to do the mass change of materials in to the particular plant.
    pl give me the appropriate solution.
    Thanks
    pavan

    Hi
    Sorry for my input. I agree with manipal, you can not extend the material for plants in MM17. Try with LSMW in create mode for material master and extend it for the plants. This is better option.
    Ravi

  • Mass change of Reorder point at MRP area level

    Hi,
    I have another constraint.
    MM17 will mass change the reorder point at plant level.
    Is there any process to do mass change of reorder point for a particular MRP area level.
    Please suggest.
    Thanks in advance.

    Hi,
    When I am doing mass change of reorder point through MM17 tcode selecting MARC table,it will chnage at plant level and getting reflected in material master once I save changes.
    But I need it at storage location level.I tried to do this through MM17 tcode selecting MARD table,which will ask for storage location data(i.e storage location level).But after I save the changes,changes are not getting reflected in Display material-MRP1 view.
    Can anyone pls suggest why this is happening.
    Thanks in advance.

Maybe you are looking for

  • Ipod touch 4G

    A week ago it wouldn't sync, just sat there at step # - #. Then it would say it "couldn't be saved to computer". Update wouldn't work either. So I deleted iTunes, Bonjour, QuickTime, MobileMe, and backups in no special order.  After reinstalling it s

  • Date Format changes in EP.

    Dear All, In Adobe Interactive Form, I am using a field which is mapped to the Date Context Variable. In R3, it shows the date format as DD.MM.YYYY. But when I look from EP, it shows YYYY-MM-DD Why this validation ? How to solve this issue? I( am usi

  • Exam question

    Hi Friends, I am confused with one question of exam. The details of the question are given below: Question:    You have one order with 2 items and when the delivery is created, the system created 2      deliveries with one item one each delivery. Wha

  • Help w/ lab connetion

    setting up a lab again. here is what I have 2610 and 2501 rtrs 2912-xl and 2924-xl.. this may be a dump question. I am not able to ping from labsw2-2912 to other interfaces. am setting this lab wright or I am missing someting, the DCE and DTE connect

  • IDOC_INPUT_DELVRY

    Hi Gurus,     I am writing FM for idoc  inbound xi interface program. For this, i am getting delivery idoc which is already existed in ECC. Now i need to update few fields to the existing IDOC. Please update me your views. I am using IDOC_INPUT_DELVR